Permit Application Status

PRRES20200268


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20200268
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - FINISHED BASEMENT - COVERED DECK SUSPENDED STOOP
02/05/2020
02/24/2020
06/16/2021
Locations
Contacts
WYSS HOME BUILDING LLC, Address:PO BOX 6620, Phone:(816) 820-0142  
MIKE BRYANT HEATING & COOLING , Address:1711 E 123RD , Phone:(913) 441-7807  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
ROBERTSON PLUMBING LLC, Address:PO BOX 165, Phone:(816) 781-9340  
MCRWYSS@HOTMAIL.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Residential Plan Review Approved 02/07/2020 02/24/2020
Kim Brennan
05 Provide square footage of living area, garage area, unfinished basement
Corrective Action Required
02/05/2020

Provide square footage of living area, garage area, unfinished basement area, etc (IRC Section R304) Please provide square footage for unfinished basement
Misc
Corrective Action Required
02/05/2020

Please provide the address to the property on all pages of the drawings
10 Combustion air
Corrective Action Required
02/05/2020

Provide combustion air calculations and specify transfer air grilles for fuel burning appliances located in confined space(s). (IRC Chapter 17 and Section G2407)
Plot Plan Review Approved 02/07/2020 02/24/2020
Kim Brennan
Legal description
Corrective Action Required
02/06/2020

The legal description, including plat or phase number and lot number, and street address must be provided on the plot plan. Please add the street number
Spot elevations
Corrective Action Required
02/06/2020

Spot elevations and/or drainage flow arrows shall be provided throughout the lot. Please provide drainage flow arrows on the west side of the lot.
Basement opening elevations
Corrective Action Required
02/06/2020

Minimum Building Opening Elevation (MBOE) and location on structure must be provided on the plot plan.
Basement egress
Corrective Action Required
02/06/2020

Basement egress location(s) and elevation of the lowest adjacent grade must be provided on the plot plan.
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,398.40 $1,398.40 Paid 02/24/2020
8331507-Sewer Connection Fee $480.00 $480.00 Paid 02/24/2020
8331401-Water Tap Fee $3,477.00 $3,477.00 Paid 02/24/2020
8350015-Water Meter Fee $425.02 $425.02 Paid 02/24/2020
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 02/24/2020
7232302-Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 02/24/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Residential Failed 3/11/2020 03/11/2020
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
03/11/2020
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Footing Inspection - Residential Passed 3/11/2020 03/11/2020
Water Service Inspection - R Passed 5/1/2020 (2:15) 5/1/2020 05/01/2020
Sewer Service Inspection - R Partial 5/1/2020 (2:15) 5/1/2020 05/01/2020
Misc
Informational
05/01/2020
- 29' sewer house to midle ft yard -
Sewer Service Inspection - R Passed 5/4/2020 at 10:40 AM 05/04/2020
Misc
Informational
05/01/2020
- 29' sewer house to midle ft yard -
Underslab Plumbing Inspection - Residential Passed 5/5/2020 5/5/2020 at 8:20 AM 05/05/2020
Misc
Informational
05/05/2020
- UFER IN POCKET BEHIND GARAGE ABOVE FLOOR DRAIN -
Suspended Slab Inspection Passed 6/22/2020 (9:00) 6/22/2020 06/22/2020
Erosion Control Inspection Residential Failed 8/27/2020 8/27/2020 08/27/2020
DCM3 ESC REQUIRED 2 DAY
Resolved
08/27/2020
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
08/27/2020
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
08/27/2020
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
DCM2 ESC DEFICIENT INSTALLATION
Resolved
08/27/2020
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Gas Service Inspection - Residential Failed 8/27/2020 8/27/2020 08/27/2020
Misc
Corrective Action Required
08/27/2020
INSPECTION DENIED - POST ADDRESS - DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
All Rough Inspection - Residential Failed 8/28/2020 8/28/2020 08/28/2020
Misc
Corrective Action Required
08/28/2020
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Electrical Service Inspection Passed 9/2/2020 9/2/2020 09/02/2020
Gas Piping Inspection - Residential Failed 9/2/2020 9/2/2020 09/02/2020
Corrective Action Required
09/02/2020
- SECURE WARD FLEX AT FIREPLACE
Gas Service Inspection - Residential Failed 9/2/2020 9/2/2020 09/02/2020
Misc
Corrective Action Required
08/27/2020
- BOND GAS LINE
All Rough Inspection - Residential Failed 9/2/2020 9/2/2020 09/02/2020
Misc
Corrective Action Required
08/28/2020
•Joist hangers required at header and ceiling joist at garage door •Joist hanger required at ceiling joist connection to attic access in garage •Pan off top of cubbie shelf in mud •Secure ward flex at fireplace •Secure DWV 2” or less at mid point •Terminate NM (romex) at ceiling in living room, front entry •Fireblock DWV chase 1st floor bath at shower •Fireblock top DWV chase master vanity •Joist hanger required at ceiling joist to header connection master bedroom •Continuous 2x4 studs at foyer for load bearing walls •Bond gas line •Fireblock deadspace between rec room and bed hall in basement •Fireblock vertical to horizontal at all furred downs in basement •Anchor bolt required within 12” of plate break - basement
All Rough Inspection - Residential Failed 9/11/2020 09/11/2020
Misc
Corrective Action Required
09/02/2020
•Fireblock top of cubbie- main level shelving by stairs •Terminate NM (romex) at ceiling in living room, front entry •Continuous 2x4 studs at foyer for load bearing walls •Strap all DWV piping 2” or smaller at midpoint- basement •Anchor bolt required within 12” of plate break - basement, left of sub panel OK TO INSULATE DO NOT ROCK RE-INSPECTION REQUIRED
Gas Service Inspection - Residential Passed 9/11/2020 09/11/2020
Misc
Resolved
09/11/2020
- BOND GAS LINE
Gas Piping Inspection - Residential Passed 9/11/2020 09/11/2020
All Rough Inspection - Residential Passed 9/14/2020 9/14/2020 09/14/2020
Misc
Resolved
09/14/2020
Driveway Inspection Partial 1/13/2021 (P.M.) 1/13/2021 01/13/2021
Misc
Informational
01/13/2021
1-13-21 1:34PM The drive forms are set and the aggregate is compacted.
Occupancy Inspection - Codes Residential Failed 1/19/2021 1/19/2021 01/19/2021
Misc
Corrective Action Required
01/19/2021
-Only partial approval of drive approach, contact development services to resolve this issue -Seal exterior penetrations, at condensing unit & Intersystem bonding termination -Seal top and sides of condensing unit disconnect and exterior lighting exposed to the elements -Remove trash and construction debris interior/exterior -Remove excavation spoils from site -Final grade and sod -Provide as graded plot plan for review/approval -Remove debris from street and storm box inlet -Complete downspout installation -Downspouts and sump piping to discharge minimum 36 inches from foundation -Ensure building sewer tracer wire and box are accessible at grade -Complete 100W lighting fixture installation, rear of structure -Complete lighting fixture installation, rear man door -Complete deck guardrail installation -Deck beam/post connection per code -Provide proper three-ply deck beam bearing at connection to structure, north end -provide proper rim joist bearing at connection to structure, south end -Complete lighting fixture installation over front stoop -Provide handrail at garage/dwelling separation door stairs -Complete interior guardrail at stairs to basement -open side of basement stairs requires guardrail, basement level -complete low voltage installation -complete safety glazed shower door installation -Remove paint covers from smoke/carbon monoxide alarms -Provide water hammer arrestors at washing machine connections -Fireblock through floor penetration under range -complete kitchen hood installation -Identify circuit #12 in sub panel
Occupancy Inspection - Codes Residential Failed 1/21/2021 1/21/2021 01/21/2021
Misc
Corrective Action Required
01/19/2021
-Only partial approval of drive approach, contact development services to resolve this issue -Seal top and sides of condensing unit disconnect and exterior lighting exposed to the elements -Remove trash and construction debris interior/exterior -Remove excavation spoils from site -Final grade and sod -Provide as graded plot plan for review/approval -Remove debris from street and storm box inlet -Complete downspout installation -Downspouts and sump piping to discharge minimum 36 inches from foundation -Ensure building sewer tracer wire and box are accessible at grade -Complete deck guardrail installation -Deck beam/post connection per code -Provide proper three-ply deck beam bearing at connection to structure, north end -provide proper rim joist bearing at connection to structure, south end -Complete interior guardrail at stairs to basement -open side of basement stairs requires guardrail, basement level -complete low voltage installation -complete safety glazed shower door installation -Remove paint covers from smoke/carbon monoxide alarms -Provide water hammer arrestors at washing machine connections -Fireblock through floor penetration under range -complete kitchen hood installation
Driveway Inspection Passed 1/25/2021 01/29/2021
Misc
Informational
01/13/2021
1-13-21 1:34PM The drive forms are set and the aggregate is compacted.
Occupancy Inspection - Codes Residential Temporary C of O 5/24/2021 5/24/2021 05/24/2021
Misc
Corrective Action Required
01/21/2021
-Provide as graded plot plan for review/approval -Handrail at exterior basement walkout, wall to grade -Provide water hammer arrestors at washing machine connections (contactor to send info on installed arrestors) **OK FOR TCO - TCO EXPIRES 6/11/21**
Occupancy Inspection - Codes Residential Temporary C of O 6/11/2021 6/11/2021 06/11/2021
Misc
Corrective Action Required
05/24/2021
-Provide as graded plot plan for review/approval **OK FOR TCO - TCO EXPIRES 6/25/21**
Plot Plan Inspection Passed 6/16/2021 06/16/2021
Erosion Control Inspection Residential Passed 06/16/2021
DCM2 ESC DEFICIENT INSTALLATION
Resolved
06/16/2021
DCM2 ESC DEFICIENT INSTALLATION
Resolved
06/16/2021
Occupancy Inspection - Codes Residential Full C of O 6/16/2021 6/16/2021 06/16/2021
Misc
Resolved
06/16/2021
Documents & Images
Date Uploaded File Type Document Name
02/06/2020 Letter Codes Residential Plan Review
02/24/2020 Receipt Receipt for transaction: 2020-000779
02/24/2020 Letter DS Building Permit
02/26/2020 Plot Plan DOC022620-02262020114217
03/11/2020 Letter INSPECTION SUMMARY
05/01/2020 Letter INSPECTION SUMMARY
05/01/2020 Letter INSPECTION SUMMARY
05/04/2020 Letter INSPECTION SUMMARY
05/04/2020 Letter INSPECTION SUMMARY
05/05/2020 Letter INSPECTION SUMMARY
06/22/2020 Letter INSPECTION SUMMARY
08/27/2020 Letter INSPECTION SUMMARY
08/27/2020 Letter INSPECTION SUMMARY
08/28/2020 Letter INSPECTION SUMMARY
09/02/2020 Letter INSPECTION SUMMARY
09/02/2020 Letter INSPECTION SUMMARY
09/02/2020 Letter INSPECTION SUMMARY
09/02/2020 Letter INSPECTION SUMMARY
09/11/2020 Letter INSPECTION SUMMARY
09/11/2020 Letter INSPECTION SUMMARY
09/11/2020 Letter INSPECTION SUMMARY
09/11/2020 Letter INSPECTION SUMMARY
09/14/2020 Letter INSPECTION SUMMARY
01/13/2021 Letter INSPECTION SUMMARY
01/19/2021 Letter INSPECTION SUMMARY
01/21/2021 Letter INSPECTION SUMMARY
01/29/2021 Letter INSPECTION SUMMARY
05/18/2021 Letter Codes 10 Day Letter
05/24/2021 Letter Codes Temporary Certificate of Occupancy
06/11/2021 Letter Codes Temporary Certificate of Occupancy
06/15/2021 Plot Plan Approved As Graded Plot Plan
06/16/2021 Letter INSPECTION SUMMARY
06/16/2021 Letter INSPECTION SUMMARY
06/16/2021 Letter Field Certificate of Occupancy
06/16/2021 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home