Summary
PRRES20192753
Building Permit - Residential
Certificate of Occupancy
SILVERSTONE DEVELOPMENT LLC
NEW SINGLE FAMILY
NEW HOUSE - PARTIAL FINISHED BASEMENT - COVERED DECK
09/25/2019
10/18/2019
10/19/2020
Locations
Contacts
SILVERSTONE DEVELOPMENT LLC, Address:PO BOX 346  
NICK ZVACEK CONSTRUCTION LLC, Address:1009 INDUSTRIAL DR, Phone:(816) 213-7204  
COMFORT SYSTEMS HTG/CLG, Address:128 W Markey Rd, Phone:(816) 322-1013  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
CENTURY PLUMBING, Address:14001 CENTURY LN, Phone:(816) 765-6066  
JEFF.BOEHM@ZVACEKCONSTRUCTION.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 09/27/2019 10/08/2019
Kim Brennan
Deck location
Corrective Action Required
09/25/2019

Deck location, with dimensions to property lines must be provided on the plot plan. Please show deck as being covered on the plot plan
Right-of-way
Corrective Action Required
09/25/2019

The right-of-way with dimensions must be provided on the plot plan.
As-graded plot plan
Corrective Action Required
09/25/2019

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy.
Residential Plan Review Approved 09/27/2019 09/25/2019
Kim Brennan
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee New Single Family $1,244.74 $1,244.74 Paid 10/18/2019
8331507-Sewer Connection Fee $600.00 $600.00 Paid 10/18/2019
Water Tap Fee $3,477.00 $3,477.00 Paid 10/18/2019
Water Meter Fee $425.02 $425.02 Paid 10/18/2019
Right of Way Permit Fee $80.00 $80.00 Paid 10/18/2019
Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 10/18/2019
Outstanding Fees Amount Paid Owing Date Paid


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Residential Failed 10/28/2019 10/28/2019
DCM5 ESC INSP DENIED
Corrective Action Required
10/28/2019
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION.
Footing Inspection - Residential Not Ready 10/28/2019 10/28/2019 at 1:50 PM 10/28/2019
Misc
Corrective Action Required
10/28/2019
**EROSION CONTROL NOT INSTALLED PER CITY REQUIREMENT. INSPECTION DENIED AND A NOT-READY FEE IS ASSESSED
Footing Inspection - Residential Passed 10/29/2019 10/29/2019 at 3:05 PM 10/29/2019
Misc
Corrective Action Required
10/28/2019
**EROSION CONTROL NOT INSTALLED PER CITY REQUIREMENT. INSPECTION DENIED AND A NOT-READY FEE IS ASSESSED
Foundation Inspection - Residential Passed 11/18/2019 11/18/2019 at 10:50 AM 11/18/2019
Sewer Service Inspection - R Passed 11/26/2019 11/26/2019 at 1:35 PM 11/26/2019
Water Service Inspection - R Passed 12/3/2019 (10:45) 12/3/2019 at 11:10 AM 12/03/2019
Underslab Plumbing Inspection - Residential Passed 12/6/2019 at 9:50 AM 12/06/2019
Piers/Caissons Inspection - Residential Failed 1/16/2020 1/16/2020 at 9:00 AM 01/16/2020
Misc
Corrective Action Required
01/16/2020
PIERS MUST BE MIN 36" DEEP BELOW GRADE
Piers/Caissons Inspection - Residential Passed 2/6/2020 at 2:05 PM 02/06/2020
Misc
Corrective Action Required
01/16/2020
PIERS MUST BE MIN 36" DEEP BELOW GRADE
Electrical Service Inspection Passed 2/28/2020 2/28/2020 02/28/2020
Gas Service Inspection - Residential Failed 2/28/2020 2/28/2020 02/28/2020
Misc
Corrective Action Required
02/28/2020
-Complete gas line to fireplace and provide min 10 psi pressure.
All Rough Inspection - Residential Failed 2/28/2020 2/28/2020 at 8:20 AM 02/28/2020
Misc
Corrective Action Required
02/28/2020
FRAMING: -Garage portal brace walls-install straps on the inner sides of the brace per code -Install collar ties above garage -Install full stud support for joist at master closet/garage return air wall -Fb fireplace space from roof -Security blocking for rear exterior doors -Install 3-studs support for ceiling beam at 2nd fl bathroom wall -Toe nail joists to sill and top plates in basement -Anchor sill plates at rear basement walls per code -Provide solid blocking under point loads to I beam below (at laundry rm sink wall) PLUMBING: -Protect water lines at master bathroom tub MECHANICAL: -Install fireplace -Pan off return air from soffit above door of basement bedroom **OK TO INSULATE
All Rough Inspection - Residential Passed 3/5/2020 3/5/2020 03/05/2020
Misc
Resolved
03/05/2020
FRAMING: -Garage portal brace walls-install straps on the inner sides of the brace per code -Install collar ties above garage -Install full stud support for joist at master closet/garage return air wall -Fb fireplace space from roof -Security blocking for rear exterior doors -Install 3-studs support for ceiling beam at 2nd fl bathroom wall -Toe nail joists to sill and top plates in basement -Anchor sill plates at rear basement walls per code -Provide solid blocking under point loads to I beam below (at laundry rm sink wall) PLUMBING: -Protect water lines at master bathroom tub MECHANICAL: -Install fireplace -Pan off return air from soffit above door of basement bedroom **OK TO INSULATE
Gas Service Inspection - Residential Passed 3/5/2020 3/5/2020 03/05/2020
Misc
Resolved
03/05/2020
-Complete gas line to fireplace and provide min 10 psi pressure.
Driveway Inspection Passed 4/2/2020 4/2/2020 04/08/2020
Misc
Informational
04/08/2020
On Wednesday, 4-08-2020. I visually inspected the finish of the driveway. It met standards and passes inspection
Occupancy Inspection - Codes Residential Failed 9/16/2020 9/16/2020 09/16/2020
Misc
Corrective Action Required
09/16/2020
**NO ACCESS TO HOUSE. THE BUILDER FAILED TO PROVIDE LOCKBOX CODE. CALLED 3 TIMES BUT NOT ANSWERED
Erosion Control Inspection Residential Passed 09/16/2020
DCM5 ESC INSP DENIED
Resolved
09/16/2020
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION.
Occupancy Inspection - Codes Residential Failed 9/17/2020 9/17/2020 09/16/2020
Misc
Corrective Action Required
09/16/2020
-Sidewalk not approved on record -As-graded plot plan is required prior to sodding -Final grade, sod, downspout and sump pump extensions -Make sure that the sewer tracer wire and port are installed and available at grade level. Find the sewer tracer wire and install port accordingly. FYI: I will pull out the tracer wire to check if it’s real -Install tamper-proof caps at AC valves -Install lag screws for deck ledger board every 16” -Install box extensions for switch & receptacle boxes recessed more than 1/4” behind wet bar backsplash -The fixed wet bar island counts as a wall space; therefore, at least one receptacle is required -Secure pex water line behind bar and also the lawn irrigation pex line -Remove all foundation wall metal ties
Occupancy Inspection - Codes Residential Temporary C of O 9/17/2020 9/17/2020 09/17/2020
Misc
Corrective Action Required
09/16/2020
-Final grade, sod, downspout and sump pump extensions -Install lag screws for deck ledger board every 16” **Install spacer, then lag the ledger board through the spacer; lag every 16" on center
Sidewalk Inspection Passed 9/18/2020 9/18/2020 09/17/2020
Misc
Informational
04/08/2020
On Wednesday, 4-08-2020. I completed a field inspection of the sidewalk. A large pile of dirt was in the front of the yard and need to be removed. The contractor did not complete all the sidewalk because the walk would be damaged when removal is completed. I will return at a later date and inspect the final sidewalk when it’s completed.
Misc
Informational
09/17/2020
9/17/20 Thursday Sidewalk- passed final inspection.
Plot Plan Inspection Passed 10/19/2020 10/19/2020
Occupancy Inspection - Codes Residential Full C of O 10/19/2020 10/19/2020
Misc
Resolved
10/19/2020
-Sidewalk not approved on record -As-graded plot plan is required prior to sodding -Final grade, sod, downspout and sump pump extensions -Install lag screws for deck ledger board every 16” **Install spacer, then lag the ledger board through the spacer; lag every 16" on center
Documents & Images
Date Uploaded File Type Document Name
09/25/2019 Letter Codes Residential Plan Review
10/18/2019 Receipt Receipt for transaction: 2019-006873
10/18/2019 Letter DS Building Permit
10/18/2019 Plot Plan DOC101819-001
10/28/2019 Letter INSPECTION SUMMARY
10/28/2019 Letter INSPECTION SUMMARY
10/29/2019 Letter INSPECTION SUMMARY
11/18/2019 Letter INSPECTION SUMMARY
11/26/2019 Letter INSPECTION SUMMARY
12/03/2019 Letter INSPECTION SUMMARY
12/06/2019 Letter INSPECTION SUMMARY
01/16/2020 Letter INSPECTION SUMMARY
02/06/2020 Letter INSPECTION SUMMARY
02/28/2020 Letter INSPECTION SUMMARY
02/28/2020 Letter INSPECTION SUMMARY
02/28/2020 Letter INSPECTION SUMMARY
03/05/2020 Letter INSPECTION SUMMARY
03/05/2020 Letter INSPECTION SUMMARY
09/16/2020 Letter INSPECTION SUMMARY
09/16/2020 Letter INSPECTION SUMMARY
09/16/2020 Letter INSPECTION SUMMARY
09/17/2020 Letter Codes Temporary Certificate of Occupancy
09/17/2020 Letter INSPECTION SUMMARY
10/16/2020 Plot Plan As Graded Plot Plan
10/19/2020 Letter INSPECTION SUMMARY
10/19/2020 Letter Field Certificate of Occupancy
10/19/2020 Letter Codes Final Certificate of Occupancy
10/19/2020 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home