Permit Application Status

PRCOM20251957


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20251957
Building Permit - Commercial
Issued
OLDHAM INVESTORS LLC
NEW COMMERCIAL
Q39 - NEW RESTAURANT CHANGED THE PERMIT FROM A SHELL BUILDING TO FULL COMMERCIAL AND ADDED THE INPSECTION FOR THE INTERIOR FINISH TO REMOVE CONFUSION DURING THE INSPECTION PROCESS. PLAN REVIEW FOR TH INTERIOR FINISH WERE COMPLETED UNDER PERMIT PRCOM20255090. Mike Weisenborn 12/31/2025 10:45 AM
05/12/2025
09/26/2025
11/19/2025
Locations
Contacts
CENTRIC CONSTRUCTION GROUP, Address:520 W PENNWAY STE 100, Phone:(816) 389-8300  
Nate Eubanks - Centric Construction, Phone:(816) 547-9160  
B & C MECHANICAL SERVICES LLC, Address:2008 E SPRUCE CIR STE B, Phone:(913) 681-0088  
TEAGUE ELECTRIC CONSTRUCTION LLC, Address:12425 W 92ND ST, Phone:(913) 529-4600  
WHATEVER IT TAKES ELECTRICAL CONTRACTORS LLC (WITEC), Address:9709 E 56TH STREET, Phone:(816) 743-0770  
BRR Architecture, Address:8131 Metcalf Ave, Phone:(913) 262-9095  
OLDHAM INVESTORS LLC, Address:1700 132ND ST STE 150  
Brad Wehde - Centric Construction, Address:520 W. Pennway St, Phone:(816) 389-8300  
Jared Sloniker, Address:19621 S 2600 Rd, Phone:(816) 542-7243  
Reviews
Review Type Outcome Est. Completion Date Completed
Sprinkler Plan Review Released for Construction 02/23/2026 02/23/2026
Craig Hill
Building Plan Review Approved 10/23/2025 10/23/2025
Joe Frogge
Final Development Plan
Resolved
10/23/2025

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational. 7/1/2025 - Acknowledged in letter.
Fire Plan Review Approved 10/23/2025 10/23/2025
Craig Hill
Licensed Contractors Approved 07/01/2025 08/15/2025
Joe Frogge
LC - MEP Subs
Resolved
08/15/2025

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 7/1/2025 - Acknowledged in letter.
Final Development Plan Review Approved 08/08/2025 07/31/2025
Grant White
Building Plan Review Rejected 07/01/2025 07/01/2025
Joe Frogge
Final Development Plan
Corrective Action Required
06/24/2025

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational. 7/1/2025 - Acknowledged in letter.
Planning - Screening of rooftop equipment
Resolved
07/01/2025

Unified Development Ordinance Article 8, Section 8.180.E Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. (parapet is not tall enough)
IBC 1803.1 General - geotech
Resolved
07/01/2025

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf. (2,400psf cited on sheet S001)
IPC 708.1 Cleanouts required
Resolved
07/01/2025

2018 IPC 708.1 Cleanouts Required. Cleanouts shall be provided for drainage piping in accordance with Sections 708.1.1 through 708.1.11. 2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access. Action required: Provide cleanouts to comply. 3 locations)
NEC Article 110.26 (C)(2) Large equipment
Resolved
07/01/2025

2017 NEC Article 110.26 (C)(3) Personnel Doors. Where equipment rated 800 A or more that contains overcurrent devices, switching devices, or control devices is installed and there is a personnel door(s) intended for entrance to and egress from the working space less than 25 feet from the nearest edge of the working space, the door(s) shall open in the direction of egress and be equipped with panic hardware. Action required: Provide panic device hardware at door 126 out of electrical room.
Fire Plan Review Approved 07/01/2025 06/30/2025
Craig Hill
Fire Plan Review Approved 05/27/2025 05/22/2025
Craig Hill
Construction documents for fire alarm systems
Corrective Action Required
05/22/2025

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Action Required: Provide deferred submittal for fire alarm system.
Construction documents - Fire protection systems
Corrective Action Required
05/22/2025

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action Required: Provide deferred submittal for fire protection system.
Building Plan Review Rejected 05/27/2025 05/22/2025
Joe Frogge
Final Development Plan
Corrective Action Required
05/22/2025

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational.
Planning - Screening of rooftop equipment
Corrective Action Required
05/22/2025

Unified Development Ordinance Article 8, Section 8.180.E Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. (parapet is not tall enough)
IBC 1803.1 General - geotech
Corrective Action Required
05/22/2025

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf. (2,400psf cited on sheet S001)
IPC 708.1 Cleanouts required
Corrective Action Required
05/22/2025

2018 IPC 708.1 Cleanouts Required. Cleanouts shall be provided for drainage piping in accordance with Sections 708.1.1 through 708.1.11. 2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access. Action required: Provide cleanouts to comply. 3 locations)
NEC Article 110.26 (C)(2) Large equipment
Corrective Action Required
05/22/2025

2017 NEC Article 110.26 (C)(3) Personnel Doors. Where equipment rated 800 A or more that contains overcurrent devices, switching devices, or control devices is installed and there is a personnel door(s) intended for entrance to and egress from the working space less than 25 feet from the nearest edge of the working space, the door(s) shall open in the direction of egress and be equipped with panic hardware. Action required: Provide panic device hardware at door 126 out of electrical room.
Licensed Contractors Rejected 05/27/2025 05/22/2025
Joe Frogge
LC - General Contractor
Resolved
05/23/2025

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Provide the name, email address & phone number for the on-site contact.
LC - MEP Subs
Corrective Action Required
05/22/2025

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Alarm Plan Review Pending
Craig Hill
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Commercial $8,000.00 $8,000.00 Paid 09/25/2025
Commercial Excise Tax Fee $34,963.50 $34,963.50 Paid 10/10/2025
Parks Impact Fee Non-Residential - Zone 4 $1,642.60 $1,642.60 Paid 09/25/2025
Right of Way Permit Fee $85.00 $85.00 Paid 09/23/2025
Site Grading Fee $252.56 $252.56 Paid 09/23/2025
Sanitary Sewer Insp Fees $540.60 $540.60 Paid 09/23/2025
Water Insp Fee $1,095.60 $1,095.60 Paid 09/23/2025
Paved Surface Inspection Fee $17,438.74 $17,438.74 Paid 09/23/2025
Storm Sewer Inspection Fee $2,969.40 $2,969.40 Paid 09/23/2025
Water Meter Fee $3,922.34 $3,922.34 Paid 10/10/2025
Water Tap Fee $27,200.00 $27,200.00 Paid 10/10/2025
Water Test Fee $200.00 $200.00 Paid 10/10/2025
Sanitary Sewer Development Fee $15,995.00 $15,995.00 Paid 10/10/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Alternate Protection Systems Inspection Pending
Water Service Inspection Pending
Above Ceiling Inspection Pending
Grading/Excavation/Fill Inspection Pending
Pavement-Proof Roll Pending
Pavement-Surface Pending
Install Street and Stop Signs Pending
Pavement-Aggregate Base Pending
Pavement-Stabilized Subgrade Pending
Foundation Inspection - Commercial Pending
Sanitary Sewer Construction Inspection Pending
Misc
Informational
11/24/2025
11-18-25 Dustin A, ran line from interceptor. Size of pipe does not match plans and sewer was falling backward
Erosion Control Inspection Pending
Misc
Informational
12/10/2025
10-30-25 Dustin A, Erosion control is in place and maintained. 12-10-25 Dustin A, Construction entrance needs to be reworked . Talked with Centric and they are going to rework it today and they new gravel coming
Light Pole Base Inspection Pending
Water Line - Construction Inspection Pending
Misc
Informational
01/08/2026
12-4-25 Dustin A, Bair working on fire line around building
Storm Sewer Construction Inspection Pending
Misc
Informational
01/12/2026
1-8-26 Dustin A, Bair working on storm, should tie in last of structure 102 to 103 this week 1-12-26 Dustin A, Bair working on storm
All Rough Inspection - Commercial Pending
Misc
Corrective Action Required
01/13/2026
Following areas inspected Exterior sheathing screw pattern
Hood/Duct Inspection Pending
Misc
Informational
02/23/2026
The following inspected -light test on shop welds (still need light test once connected) -Light test of welds in place. OK to wrap first layer -1st layer wrap
Sprinkler - Hydrostatic Test Pending
Sprinkler - Flow Test Pending
Gas Service Inspection - Commercial Pending
Misc
Corrective Action Required
02/24/2026
Underground gas line to fireplace installed in trench. Line has not been tested
Underground Electrical Inspection - Commercial Pending
Misc
Informational
02/26/2026
The following areas inspected and marked on plans in job trailer -conduit for 3 E most light poles -conduit for light poles and monument sign NW side of building -conduits from NE corner of building to 3 light poles along south side of parking lot, to SW light pole near traffic light, and to nearby monument sign; conduits to trash compactor and light pole adjacent ot fire hydrant near trash enclosure -bollard light conduit from east to south side of building, approx 1/2 side -secondary conduits to service location
Misc
Corrective Action Required
02/26/2026
2/26/26 -Conduit for remaining light poles (5) at SW lot, (3) at South adjacent lot
Water Line - Coliform Test 1 Pending
Footing Inspection - Commercial Pending
Misc
Informational
03/10/2026
Plans marked on site Following areas approved A-b/1 A/1-4 4/A-E E/4-2 1/c.1-d.1 A-ENorth side of Line 1 Complete perimeter footing. 3 interior footing pads 12 pad footings around building Exterior fireplace footings Perimeter footing stem walls Trash enclosure footings and pads First 4 feet of fire place Monument sign
Site Visit Pending
Misc
Informational
03/17/2026
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open 1-8-26 Dustin A, working on storm 1-14-26 Dustin A, Storm work and roof drains 1-30-26 Dustin A, No work for dev 2-2-26 Dustin A, Bair pouring flow fill on structures 2-6-26 Dustin A, Flow fill work 2-18-26 Dustin A, No site work going on at this time . 2-23-26 Dustin A, No site work today 3/4/26 PS Made site visit, contractor (Bair) spreading aggregate to building from construction entrance for telehandlers 3-11-26 Dustin A, No work on site , raining , Just building work being done 3-17-26 Dustin A, Building work
Electrical Service Inspection Pending 3/19/2026 3/19/2026
Footing Inspection - Commercial Partial 10/15/2025 10/15/2025 10/15/2025
Misc
Informational
10/15/2025
Following areas approved A-b/1 A/1-4 4/A-c.1
Footing Inspection - Commercial Partial 10/16/2025 10/16/2025 10/16/2025
Misc
Informational
10/15/2025
Plans marked on site Following areas approved A-b/1 A/1-4 4/A-E E/4-2
Erosion Control Inspection Partial 10/16/2025 10/16/2025 10/16/2025
Misc
Informational
10/16/2025
10-16-25 Dustin A, Erosion control is in place and there was a washout installed. They are getting me a swppp report
Footing Inspection - Commercial Partial 10/17/2025 10/17/2025 10/17/2025
Misc
Informational
10/16/2025
Plans marked on site Following areas approved A-b/1 A/1-4 4/A-E E/4-2 1/c.1-d.1 A-ENorth side of Line 1
Footing Inspection - Commercial Partial 10/21/2025 10/21/2025 10/21/2025
Misc
Informational
10/17/2025
Plans marked on site Following areas approved A-b/1 A/1-4 4/A-E E/4-2 1/c.1-d.1 A-ENorth side of Line 1 Complete perimeter footing. 3 interior footing pads
Footing Inspection - Commercial Partial 10/23/2025 10/23/2025
Misc
Informational
10/21/2025
Plans marked on site Following areas approved A-b/1 A/1-4 4/A-E E/4-2 1/c.1-d.1 A-ENorth side of Line 1 Complete perimeter footing. 3 interior footing pads 12 pad footings around building Exterior fireplace footings
Underslab Plumbing Inspection - Commercial Partial 10/28/2025 10/28/2025
Misc
Informational
10/28/2025
-Fireline entering into building and roughly 10’ out -stub out from foundation for grease interceptor -sanitary sewer stub out from foundation
Footing Inspection - Commercial Partial 10/28/2025 10/28/2025 10/28/2025
Misc
Informational
10/23/2025
Plans marked on site Following areas approved A-b/1 A/1-4 4/A-E E/4-2 1/c.1-d.1 A-ENorth side of Line 1 Complete perimeter footing. 3 interior footing pads 12 pad footings around building Exterior fireplace footings Perimeter footing stem walls
Water Line - Construction Inspection Partial 10/30/2025
Misc
Informational
10/30/2025
10-29-25 Dustin A, Fdc in stalled inside building and ran outside of footing ,
Site Visit Partial 10/27/2025 10/27/2025 10/31/2025
Misc
Informational
10/31/2025
10-27-25 Dustin A, No work for dev, crews working on pad site
Site Visit Partial 10/29/2025 10/29/2025 10/31/2025
Misc
Informational
10/31/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work
Erosion Control Inspection Partial 10/31/2025
Misc
Informational
10/31/2025
10-30-25 Dustin A, Erosion control is in place and maintained.
Footing Inspection - Commercial Partial 11/5/2025 11/5/2025 11/05/2025
Misc
Informational
10/28/2025
Plans marked on site Following areas approved A-b/1 A/1-4 4/A-E E/4-2 1/c.1-d.1 A-ENorth side of Line 1 Complete perimeter footing. 3 interior footing pads 12 pad footings around building Exterior fireplace footings Perimeter footing stem walls Trash enclosure footings and pads
Site Visit Partial 11/06/2025
Misc
Informational
10/31/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done
Site Visit Partial 11/07/2025
Misc
Informational
11/06/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer
Site Visit Partial 11/12/2025
Misc
Informational
11/07/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date .
Footing Inspection - Commercial Partial 11/12/2025 11/12/2025 11/12/2025
Misc
Informational
11/05/2025
Plans marked on site Following areas approved A-b/1 A/1-4 4/A-E E/4-2 1/c.1-d.1 A-ENorth side of Line 1 Complete perimeter footing. 3 interior footing pads 12 pad footings around building Exterior fireplace footings Perimeter footing stem walls Trash enclosure footings and pads First 4 feet of fire place
Misc
Resolved
11/12/2025
First 4 feet of fire place
Site Visit Partial 11/12/2025
Misc
Informational
11/12/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done
Site Visit Partial 11/13/2025
Misc
Informational
11/12/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor
Underslab Plumbing Inspection - Commercial Partial 11/18/2025 11/18/2025 11/18/2025
Misc
Informational
10/28/2025
-Fireline entering into building and roughly 10’ out -stub out from foundation for grease interceptor - Grease interceptor installed - Piping to and from interceptor across West side, (not connected to main) -sanitary sewer stub out from foundation
Sanitary Sewer Construction Inspection Failed 11/18/2025
Misc
Informational
11/18/2025
11-18-25 Dustin A, ran line from interceptor. Size of pipe does not match plans and sewer was falling backward
Site Visit Partial 11/20/2025
Misc
Informational
11/13/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water
Site Visit Partial 11/26/2025
Misc
Informational
11/20/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in
Water Line - Construction Inspection Partial 12/04/2025
Misc
Informational
12/04/2025
12-4-25 Dustin A, Bair working on fire line around building
Erosion Control Inspection Failed 12/10/2025 12/10/2025 12/10/2025
Misc
Informational
10/31/2025
10-30-25 Dustin A, Erosion control is in place and maintained. 12-10-25 Dustin A, Construction entrance needs to be reworked . Talked with Centric and they are going to rework it today and they new gravel coming
Site Visit Partial 12/15/2025
Misc
Informational
11/26/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm
Site Visit Partial 12/19/2025
Misc
Informational
12/15/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open
Underslab Plumbing Inspection - Commercial Partial 12/31/2025 12/31/2025
Misc
Informational
12/31/2025
THE FOLLOWING AREAS INSPECTED -MAIN TRUNK LINES FOR UNDERSLAB SEWER AND GREASE
Underslab Plumbing Inspection - Commercial Partial 2/19/2026 2/19/2026 12/31/2025
Misc
Informational
11/18/2025
-Fireline entering into building and roughly 10’ out -stub out from foundation for grease interceptor - Grease interceptor installed - Piping to and from interceptor across West side, (not connected to main) -sanitary sewer stub out from foundation
Underslab Plumbing Inspection - Commercial Passed 1/6/2026 1/6/2026 01/06/2026
Misc
Resolved
01/06/2026
THE FOLLOWING AREAS INSPECTED -MAIN TRUNK LINES FOR UNDERSLAB SEWER AND GREASE
Storm Sewer Construction Inspection Partial 01/08/2026
Misc
Informational
01/08/2026
1-8-26 Dustin A, Bair working on storm, should tie in last of structure 102 to 103 this week
Water Line - Construction Inspection Partial 01/08/2026
Misc
Corrective Action Required
01/08/2026
1-8-26 Dustin A, Fire line is in and vault is set. Waiting for Sapp to bore water line across the street. Service line will be installed after fire line is in and passed hydrostatic test
Sanitary Sewer Construction Inspection Partial 01/08/2026
Misc
Informational
01/08/2026
1-8-26 Dustin A, Sanitary sewer service is in to building. Need to confirm proper cleanouts ( every 100 ft run )
All Rough Inspection - Commercial Failed 1/9/2026 1/9/2026 01/09/2026
Misc
Corrective Action Required
01/09/2026
Exterior sheathing inspection only. Screw sheathing off to manufacture specifications
Storm Sewer Construction Inspection Partial 01/12/2026
Misc
Informational
01/08/2026
1-8-26 Dustin A, Bair working on storm, should tie in last of structure 102 to 103 this week 1-12-26 Dustin A, Bair working on storm
All Rough Inspection - Commercial Partial 1/13/2026 1/13/2026 01/13/2026
Misc
Corrective Action Required
01/09/2026
Following areas inspected Exterior sheathing screw pattern
Underslab Electrical Inspection - Commercial Passed 1/13/2026 1/13/2026 01/13/2026
Misc
Informational
01/13/2026
Site Visit Partial 01/30/2026
Misc
Informational
12/19/2025
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open 1-8-26 Dustin A, working on storm 1-14-26 Dustin A, Storm work and roof drains 1-30-26 Dustin A, No work for dev
Site Visit Partial 02/02/2026
Misc
Informational
01/30/2026
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open 1-8-26 Dustin A, working on storm 1-14-26 Dustin A, Storm work and roof drains 1-30-26 Dustin A, No work for dev 2-2-26 Dustin A, Bair pouring flow fill on structures
Site Visit Partial 02/06/2026
Misc
Informational
02/02/2026
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open 1-8-26 Dustin A, working on storm 1-14-26 Dustin A, Storm work and roof drains 1-30-26 Dustin A, No work for dev 2-2-26 Dustin A, Bair pouring flow fill on structures 2-6-26 Dustin A, Flow fill work
Hood/Duct Inspection Partial 2/9/2026 2/9/2026 02/09/2026
Misc
Informational
02/09/2026
The following inspected -light test on shop welds (still need light test once connected)
In-wall Inspection Partial 2/9/2026 2/9/2026 02/09/2026
Misc
Informational
02/09/2026
Following areas inspected -electrical room NE for of building okay to cover 8’ up
In-wall Inspection Partial 2/10/2026 2/10/2026 02/10/2026
Misc
Informational
02/09/2026
Following areas inspected -electrical room NE for of building okay to cover 8’ up -walls behind coolers (3) okay to cover
Site Visit Partial 02/18/2026
Misc
Informational
02/06/2026
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open 1-8-26 Dustin A, working on storm 1-14-26 Dustin A, Storm work and roof drains 1-30-26 Dustin A, No work for dev 2-2-26 Dustin A, Bair pouring flow fill on structures 2-6-26 Dustin A, Flow fill work 2-18-26 Dustin A, No site work going on at this time .
Hood/Duct Inspection Partial 2/19/2026 2/19/2026 02/19/2026
Misc
Informational
02/09/2026
The following inspected -light test on shop welds (still need light test once connected) -Light test of welds in place. OK to wrap first layer
Piers/Caissons Inspection - Commercial Partial 2/20/2026 2/20/2026 02/20/2026
Misc
Informational
02/20/2026
Following areas inspected (6) light poles bases on the south,SE, and E side of building
Hood/Duct Inspection Partial 2/23/2026 2/23/2026 02/23/2026
Misc
Informational
02/19/2026
The following inspected -light test on shop welds (still need light test once connected) -Light test of welds in place. OK to wrap first layer -1st layer wrap
Site Visit Partial 02/23/2026
Misc
Informational
02/18/2026
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open 1-8-26 Dustin A, working on storm 1-14-26 Dustin A, Storm work and roof drains 1-30-26 Dustin A, No work for dev 2-2-26 Dustin A, Bair pouring flow fill on structures 2-6-26 Dustin A, Flow fill work 2-18-26 Dustin A, No site work going on at this time . 2-23-26 Dustin A, No site work today
Underground Electrical Inspection - Commercial Partial 2/24/2026 2/24/2026 02/24/2026
Misc
Informational
02/24/2026
The following areas inspected and marked on plans in job trailer -conduit for 3 E most light poles -conduit for light poles and monument sign NW side of building
Underground Electrical Inspection - Commercial Partial 2/24/2026 2/24/2026 02/24/2026
Misc
Informational
02/24/2026
The following areas inspected and marked on plans in job trailer -conduit for 3 E most light poles -conduit for light poles and monument sign NW side of building -conduits from NE corner of building to 3 light poles along south side of parking lot and to near monument sign; conduits to trash compactor and light pole adjacent ot fire hydrant near trash enclosure
Gas Service Inspection - Commercial Failed 2/24/2026 02/24/2026
Misc
Corrective Action Required
02/24/2026
Underground gas line to fireplace installed in trench. Line has not been tested
Piers/Caissons Inspection - Commercial Partial 2/25/2026 2/25/2026 02/25/2026
Misc
Informational
02/20/2026
Following areas inspected (6) light poles bases on the south,SE, and E side of building; 4 light poles piers on the west side of building
Underground Electrical Inspection - Commercial Partial 2/25/2026 02/25/2026
Misc
Informational
02/24/2026
The following areas inspected and marked on plans in job trailer -conduit for 3 E most light poles -conduit for light poles and monument sign NW side of building -conduits from NE corner of building to 3 light poles along south side of parking lot, to SW light pole near traffic light, and to nearby monument sign; conduits to trash compactor and light pole adjacent ot fire hydrant near trash enclosure -bollard light conduit from east to south side of building, approx 1/2 side -secondary conduits to service location
Site Visit Partial 02/26/2026
Misc
Informational
02/23/2026
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open 1-8-26 Dustin A, working on storm 1-14-26 Dustin A, Storm work and roof drains 1-30-26 Dustin A, No work for dev 2-2-26 Dustin A, Bair pouring flow fill on structures 2-6-26 Dustin A, Flow fill work 2-18-26 Dustin A, No site work going on at this time . 2-23-26 Dustin A, No site work today
Underground Electrical Inspection - Commercial Partial 2/26/2026 2/26/2026 02/26/2026
Misc
Informational
02/25/2026
The following areas inspected and marked on plans in job trailer -conduit for 3 E most light poles -conduit for light poles and monument sign NW side of building -conduits from NE corner of building to 3 light poles along south side of parking lot, to SW light pole near traffic light, and to nearby monument sign; conduits to trash compactor and light pole adjacent ot fire hydrant near trash enclosure -bollard light conduit from east to south side of building, approx 1/2 side -secondary conduits to service location
Misc
Corrective Action Required
02/26/2026
2/26/26 -Conduit for remaining light poles (5) at SW lot, (3) at South adjacent lot
Piers/Caissons Inspection - Commercial Partial 2/27/2026 2/27/2026 02/27/2026
Misc
Informational
02/25/2026
Following areas inspected (6) light poles bases on the south,SE, and E side of building; 4 light poles piers on the west side of building; 3 light pole bases on the NW side of building; 3 light pole bases across street to S
Water Line - Hydrostatic Test Passed 3/2/2026 3/2/2026 03/02/2026
Misc
Informational
03/02/2026
3/2/26 PS Observed contractor (Bair) perform hydrostatic test at fire line from vault to interior riser. Testing passed, held 200 psi for 2 hours.
Site Visit Partial 3/4/2026 3/4/2026 03/04/2026
Misc
Informational
02/26/2026
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open 1-8-26 Dustin A, working on storm 1-14-26 Dustin A, Storm work and roof drains 1-30-26 Dustin A, No work for dev 2-2-26 Dustin A, Bair pouring flow fill on structures 2-6-26 Dustin A, Flow fill work 2-18-26 Dustin A, No site work going on at this time . 2-23-26 Dustin A, No site work today 3/4/26 PS Made site visit, contractor (Bair) spreading aggregate to building from construction entrance for telehandlers
In-wall Inspection Failed 3/5/2026 3/5/2026 03/05/2026
Misc
Resolved
03/05/2026
Following areas inspected -electrical room NE for of building okay to cover 8’ up -walls behind coolers (3) okay to cover
Misc
Corrective Action Required
03/05/2026
-provide protection for plumbing throughout where closer than 1 1/4” to face of framing 305 IPC -complete electrical at server area
In-wall Inspection Passed 3/6/2026 3/6/2026 03/06/2026
Misc
Resolved
03/06/2026
-provide protection for plumbing throughout where closer than 1 1/4” to face of framing 305 IPC -complete electrical at server area
Footing Inspection - Commercial Partial 3/10/2026 3/10/2026 03/10/2026
Misc
Informational
11/12/2025
Plans marked on site Following areas approved A-b/1 A/1-4 4/A-E E/4-2 1/c.1-d.1 A-ENorth side of Line 1 Complete perimeter footing. 3 interior footing pads 12 pad footings around building Exterior fireplace footings Perimeter footing stem walls Trash enclosure footings and pads First 4 feet of fire place Monument sign
Site Visit Partial 03/11/2026
Misc
Informational
03/04/2026
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open 1-8-26 Dustin A, working on storm 1-14-26 Dustin A, Storm work and roof drains 1-30-26 Dustin A, No work for dev 2-2-26 Dustin A, Bair pouring flow fill on structures 2-6-26 Dustin A, Flow fill work 2-18-26 Dustin A, No site work going on at this time . 2-23-26 Dustin A, No site work today 3/4/26 PS Made site visit, contractor (Bair) spreading aggregate to building from construction entrance for telehandlers 3-11-26 Dustin A, No work on site , raining , Just building work being done
Piers/Caissons Inspection - Commercial Passed 3/13/2026 3/13/2026 03/13/2026
Misc
Informational
02/27/2026
Following areas inspected (6) light poles bases on the south,SE, and E side of building; 4 light poles piers on the west side of building; 3 light pole bases on the NW side of building; 3 light pole bases across street to S 1light pole base NE corner of building
Site Visit Partial 03/17/2026
Misc
Informational
03/11/2026
10-27-25 Dustin A, No work for dev, crews working on pad site 10-29-25 Dustin A, Rain off and on , pad site work 11-5-25 Dustin A, No work for Dev being done 11-7-25 Dustin A, Bair is on site doing some utility work. Needed to break concrete out to get to sewer 11-10-25 Dustin A, Bair onsite doing sewer work. They attached to the sewer stub which is not released yet . They unhooked from stub and will need to come back at a later date . 11-12-25 Dustin A, Sewer work being done 11-13-25 Dustin A, Installing grease interceptor 11-20-25 Dustin A, bair working on locating water 11-25-25 Dustin A, no work being done for development. Working on a solution for the water tie in 12-15-25 Dustin A, Bair on site working on storm 12-19-25 Dustin A, Just building work being done today , Storm on north side has been dug up and cut open 1-8-26 Dustin A, working on storm 1-14-26 Dustin A, Storm work and roof drains 1-30-26 Dustin A, No work for dev 2-2-26 Dustin A, Bair pouring flow fill on structures 2-6-26 Dustin A, Flow fill work 2-18-26 Dustin A, No site work going on at this time . 2-23-26 Dustin A, No site work today 3/4/26 PS Made site visit, contractor (Bair) spreading aggregate to building from construction entrance for telehandlers 3-11-26 Dustin A, No work on site , raining , Just building work being done 3-17-26 Dustin A, Building work
Documents & Images
Date Uploaded File Type Document Name
05/12/2025 Application Form APPLICATION
05/12/2025 Plans Q39 SHELL ARCH OTP SNS
05/13/2025 Plans Q39 SHELL LS COMBINED DRAWING SET
05/14/2025 Letter License Tax Bill
05/23/2025 Letter DS P/R Corrections Document
06/24/2025 Engineer Report/Study Q39 LS GEOTECHNICAL REPORT
06/24/2025 Letter Q39 LS SHELL ADD 1 NARRATIVE
06/24/2025 Letter Q39 LS SHELL CODE RESPONSE
06/24/2025 Plans Q39 SHELL LS ADDENDUM 1 COMBINED DRAWING SET
09/23/2025 Receipt Receipt for transaction:2025-007306
09/25/2025 Receipt Receipt for transaction:2025-007361
09/26/2025 Letter DS Building Permit
10/10/2025 Receipt Receipt for transaction: 2025-007680
10/15/2025 Letter INSPECTION SUMMARY
10/16/2025 Letter INSPECTION SUMMARY
10/16/2025 Letter INSPECTION SUMMARY
10/16/2025 Letter Q39 LS SHELL ADD 2 NARRATIVE
10/16/2025 Plans Q39 SHELL LS ADDENDUM 2 COMBINED DRAWING SET
10/17/2025 Letter INSPECTION SUMMARY
10/21/2025 Letter INSPECTION SUMMARY
10/23/2025 Letter INSPECTION SUMMARY
10/23/2025 Approved Plans Approved construction plans
10/28/2025 Letter INSPECTION SUMMARY
10/28/2025 Letter INSPECTION SUMMARY
07/31/2025 Approved Plans Approved FDP_Q39_Oldham Village_PL2025102_7.31.2025
10/30/2025 Letter INSPECTION SUMMARY
10/30/2025 Approved Plans Approved plans_Q39_Oldham Village_PL2025102_10.30.2025
10/31/2025 Letter INSPECTION SUMMARY
10/31/2025 Letter INSPECTION SUMMARY
10/31/2025 Letter INSPECTION SUMMARY
10/31/2025 Engineer Report/Study Q39 in Lees Summit SWPPP report 10-30-25
11/05/2025 Letter INSPECTION SUMMARY
11/06/2025 Letter INSPECTION SUMMARY
11/07/2025 Letter INSPECTION SUMMARY
11/12/2025 Letter INSPECTION SUMMARY
11/12/2025 Letter INSPECTION SUMMARY
11/12/2025 Letter INSPECTION SUMMARY
11/13/2025 Letter INSPECTION SUMMARY
11/18/2025 Letter INSPECTION SUMMARY
11/18/2025 Letter INSPECTION SUMMARY
11/18/2025 Letter INSPECTION SUMMARY
11/20/2025 Letter INSPECTION SUMMARY
11/26/2025 Letter INSPECTION SUMMARY
12/04/2025 Letter INSPECTION SUMMARY
12/10/2025 Letter INSPECTION SUMMARY
12/10/2025 Letter INSPECTION SUMMARY
12/15/2025 Letter INSPECTION SUMMARY
12/15/2025 Letter INSPECTION SUMMARY
12/19/2025 Letter INSPECTION SUMMARY
12/16/2025 Approved Plans Approved construction plans - Tenant Space
12/31/2025 Letter INSPECTION SUMMARY
12/31/2025 Letter INSPECTION SUMMARY
01/06/2026 Letter INSPECTION SUMMARY
01/08/2026 Letter INSPECTION SUMMARY
01/08/2026 Letter INSPECTION SUMMARY
01/08/2026 Letter INSPECTION SUMMARY
01/09/2026 Letter INSPECTION SUMMARY
01/12/2026 Letter INSPECTION SUMMARY
01/13/2026 Letter INSPECTION SUMMARY
01/13/2026 Letter INSPECTION SUMMARY
01/30/2026 Letter INSPECTION SUMMARY
02/02/2026 Letter INSPECTION SUMMARY
02/06/2026 Plans Alliance FP Q 39 DRAW PE STAMPED
02/06/2026 Alliance FP Q39 CALCS PACKAGE PE STAMPED
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/10/2026 Letter INSPECTION SUMMARY
02/18/2026 Letter INSPECTION SUMMARY
02/19/2026 Letter INSPECTION SUMMARY
02/20/2026 Approved Plans Approved E003
02/20/2026 Letter INSPECTION SUMMARY
02/23/2026 Letter INSPECTION SUMMARY
02/23/2026 Letter INSPECTION SUMMARY
02/23/2026 Alliance FP Q 39 DRAW PE STAMPED RFC
02/24/2026 Letter INSPECTION SUMMARY
02/24/2026 Letter INSPECTION SUMMARY
02/24/2026 Letter INSPECTION SUMMARY
02/25/2026 Letter INSPECTION SUMMARY
02/25/2026 Letter INSPECTION SUMMARY
02/26/2026 Letter INSPECTION SUMMARY
02/26/2026 Letter INSPECTION SUMMARY
02/27/2026 Letter INSPECTION SUMMARY
03/02/2026 Letter INSPECTION SUMMARY
03/02/2026 Plans 2026-03-02-Water Line RFI_revision PL2025102
03/04/2026 Letter INSPECTION SUMMARY
03/05/2026 Letter INSPECTION SUMMARY
03/06/2026 Letter INSPECTION SUMMARY
03/10/2026 Letter INSPECTION SUMMARY
03/11/2026 Letter INSPECTION SUMMARY
03/13/2026 Letter INSPECTION SUMMARY
03/17/2026 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home