Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Piers/Caissons Inspection - Commercial
|
Pending
|
|
|
|
Erosion Control Inspection
|
Pending
|
|
|
|
|
PW-Devices for Erosion and Sediment Control
Corrective Action Required
|
All Rough Inspection - Commercial
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Pending
|
10/9/2025
|
10/9/2025
|
|
|
Misc
Corrective Action Required
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
4/23/2025
|
4/23/2025
|
04/23/2025
|
|
Misc
|
Footing Inspection - Commercial
|
Passed
|
4/24/2025
|
4/24/2025
|
04/24/2025
|
|
Misc
|
Footing Inspection - Commercial
|
Passed
|
|
|
04/28/2025
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
5/5/2025
|
5/5/2025
|
05/05/2025
|
|
PW-Devices for Erosion and Sediment Control
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Failed
|
5/13/2025
|
5/13/2025
|
05/13/2025
|
|
Misc
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Passed
|
5/16/2025
|
5/16/2025
|
05/16/2025
|
|
Misc
|
Rated Assembly Inspection
|
Failed
|
6/30/2025
|
6/30/2025
|
06/30/2025
|
|
Misc
Corrective Action Required
|
Sewer Service Inspection
|
Passed
|
7/18/2025
|
7/18/2025
|
07/18/2025
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Failed
|
7/24/2025
|
7/24/2025
|
07/24/2025
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Failed
|
7/31/2025
|
7/31/2025
|
07/31/2025
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Not Ready
|
8/20/2025
|
8/20/2025
|
08/20/2025
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Failed
|
8/25/2025
|
8/25/2025
|
08/25/2025
|
|
Misc
Corrective Action Required
|
Water Service Inspection
|
Passed
|
|
|
08/25/2025
|
|
Misc
|
All Rough Inspection - Commercial
|
Not Ready
|
8/27/2025
|
8/27/2025
|
08/27/2025
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Failed
|
8/29/2025
|
8/29/2025
|
08/29/2025
|
|
Misc
Corrective Action Required
|
Electrical Service Inspection
|
Failed
|
8/29/2025
|
8/29/2025
|
08/29/2025
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Not Ready
|
9/2/2025
|
9/2/2025
|
09/02/2025
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
9/3/2025
|
9/3/2025
|
09/03/2025
|
|
Misc
Corrective Action Required
|
Electrical Service Inspection
|
Passed
|
9/18/2025
|
9/18/2025
|
09/18/2025
|
|
Misc
|
Rated Assembly Inspection
|
Failed
|
9/26/2025
|
9/26/2025
|
09/26/2025
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Not Ready
|
9/29/2025
|
9/29/2025
|
09/29/2025
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/2/2025
|
10/2/2025
|
10/02/2025
|
|
Misc
Corrective Action Required
|
|
Misc
|