Review Type |
Outcome |
Est. Completion Date |
Completed |
Final Development Plan Review
|
Approved
|
05/27/2025
|
05/27/2025
|
|
Daniel Fernandez
|
|
|
Fire Plan Review
|
Approved
|
03/11/2025
|
03/10/2025
|
|
Joe Frogge
|
|
|
Building Plan Review
|
Rejected
|
03/11/2025
|
03/10/2025
|
|
Joe Frogge
|
|
Final Development Plan
The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan.
Action required: Comment is informational.
3/10/2025 - Acknowledged in letter.
|
|
License Tax - Payment
Corrective Action Required
A one-time impact fee in the form of a license tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process.
Action required: Comment is for informational purposes. After a credit for previous store, the fee will be $31,234.50.
|
|
Health Dept Review
Corrective Action Required
For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 797-7162. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit.
Action required: Comment is informational.
3/10/2025 - Acknowledged in letter.
|
|
Health Dept Inspection
Corrective Action Required
For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 797-7162. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit.
Action required: Comment is informational.
3/10/2025 - Acknowledged in letter.
|
|
SEC - CPTED
Code of Ordinances Section 8.330. CPTED Review Requirement.
All development applications shall be subject to CPTED review and recommendations. The application of CPTED concepts and strategies is site specific and the level of review shall be determined on a case by case basis. Some requests during development review will require mandatory compliance. Others will be strongly encouraged but compliance will be voluntary. Mandatory compliance elements will be addressed in Article 9 “Uses with Conditions”.
Section 8.340. CPTED Uses Specified The following uses have been classified as “Uses with Conditions” per Article 9 of this Chapter, having been determined with a tendency toward an increased risk of crime,. Specific conditions for such uses are found in Article 9 and shall be required to be met prior to receiving any zoning approval, business license or approval to occupy any commercial space.
1. Bank/Financial Services
2. Bank Drive-Thru Facility
3. Check Cashing and Payday Loan Business
4. Convenience Store (C-Store)
5. Financial Services with Drive-up Window or Drive-Thru Facility
6. Pawn Shop
7. Title Loan Business, if performing on site cash transactions with $500 or more in cash on hand
8. Unattended self-serve gas pumps
9. Unsecured Loan Business
10. Other similar uses shall meet the same standards as the above.
Action required: Provided drawing or report to verify compliance with items listed in CPTED regulations. In case of alternate methods or other valid reasonings you will need to file for a Code Modification Request (CMR) for each item. Form should be attached to email with plan review comments.
|
|
|
Licensed Contractors
|
Rejected
|
03/11/2025
|
03/10/2025
|
|
Joe Frogge
|
|
LC - General Contractor
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances.
Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and the name, email address & phone number for the on-site contact.
3/10/2025 - Acknowledged in letter.
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
3/10/2025 - Acknowledged in letter.
|
|
|
Fire Plan Review
|
Approved
|
12/27/2024
|
12/20/2024
|
|
Craig Hill
|
|
|
Building Plan Review
|
Rejected
|
12/27/2024
|
12/18/2024
|
|
Joe Frogge
|
|
Final Development Plan
Corrective Action Required
The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan.
Action required: Comment is informational.
|
|
License Tax - Payment
Corrective Action Required
A one-time impact fee in the form of a license tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process.
Action required: Comment is for informational purposes. After a credit for previous store, the fee will be $31,234.50.
|
|
Health Dept Review
Corrective Action Required
For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 797-7162. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit.
Action required: Comment is informational.
|
|
Health Dept Inspection
Corrective Action Required
For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 797-7162. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit.
Action required: Comment is informational.
|
|
SEC - CPTED
Corrective Action Required
Code of Ordinances Section 8.330. CPTED Review Requirement.
All development applications shall be subject to CPTED review and recommendations. The application of CPTED concepts and strategies is site specific and the level of review shall be determined on a case by case basis. Some requests during development review will require mandatory compliance. Others will be strongly encouraged but compliance will be voluntary. Mandatory compliance elements will be addressed in Article 9 “Uses with Conditions”.
Section 8.340. CPTED Uses Specified The following uses have been classified as “Uses with Conditions” per Article 9 of this Chapter, having been determined with a tendency toward an increased risk of crime,. Specific conditions for such uses are found in Article 9 and shall be required to be met prior to receiving any zoning approval, business license or approval to occupy any commercial space.
1. Bank/Financial Services
2. Bank Drive-Thru Facility
3. Check Cashing and Payday Loan Business
4. Convenience Store (C-Store)
5. Financial Services with Drive-up Window or Drive-Thru Facility
6. Pawn Shop
7. Title Loan Business, if performing on site cash transactions with $500 or more in cash on hand
8. Unattended self-serve gas pumps
9. Unsecured Loan Business
10. Other similar uses shall meet the same standards as the above.
Action required: Provided drawing or report to verify compliance with items listed in CPTED regulations. In case of alternate methods or other valid reasonings you will need to file for a Code Modification Request (CMR) for each item. Form should be attached to email with plan review comments.
|
|
|
Licensed Contractors
|
Rejected
|
12/27/2024
|
12/17/2024
|
|
Joe Frogge
|
|
LC - General Contractor
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances.
Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and the name, email address & phone number for the on-site contact.
3/10/2025 - Acknowledged in letter.
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
3/10/2025 - Acknowledged in letter.
|
|
|
Health Department Review
|
Pending
|
|
|
|
Joe Frogge
|
|
|