Permit Application Status

PRCOM20233582


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20233582
Building Permit - Commercial
Certificate of Occupancy
150 HIGHWAY LEES SUMMIT LLC
NEW COMMERCIAL
NEW BUILDING FOR EARLY DAYCARE
07/24/2023
12/08/2023
01/31/2024
09/04/2024
Locations
Contacts
150 HIGHWAY LEES SUMMIT LLC, Address:7217 W 110TH ST  
BCCM Construction Group, Inc., Address:100 E. 7th St. Suite 201, Phone:(816) 659-9115 Ext:210  
OVERLAND PARK MECHANICAL CO LLC, Address:16088 FOSTER, Phone:(913) 814-8200  
BART'S ELECTRIC COMPANY INC, Address:7103 STEWART RD, Phone:(816) 421-0007  
QUESTEC MECHANICAL INC, Address:1390 E BOONE INDUSTRIAL DR, SUITE 260, Phone:(573) 875-0260  
Jarmel Kizel Architects and Engineers, Address:42 Okner Pkwy, Phone:(973) 994-9669  
Alpha Omega Geotech Inc, Address:1701 State Ave  
Bob Alexander - BCCM Construction, Phone:(816) 985-2000  
Reviews
Review Type Outcome Est. Completion Date Completed
Alarm Plan Review Released for Construction 06/04/2024 06/03/2024
Jim Eden
Alarms connected to automatic sprinkler system
Corrective Action Required
06/03/2024

2018 IFC 903.4.2- Alarms. Approved audible and visual devices shall be connected to every automatic sprinkler system. Such sprinkler water-flow alarm devices shall be activated by water flow equivalent to the flow of a single sprinkler of the smallest orifice size installed in the system. Listed alarm notification devices shall be provided on the exterior and interior of the building in an approved location. Where a fire alarm system is installed, actuation of the automatic sprinkler system shall actuate the building fire alarm system. Plans received 5/21/2024.
Miscellaneous Correction
Corrective Action Required
06/03/2024

Remove the exterior notification appliances. Place one exterior horn/strobe over the FDC to indicate waterflow only. Verified at inspection.
Installation acceptance testing
Corrective Action Required
06/03/2024

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule testing.
Miscellaneous Correction
Corrective Action Required
06/03/2024

Relocate the Knox box from the front door to 6' AFF over the FDC. Verified at inpection.
Building Plan Review Approved with Conditions 08/28/2023 11/30/2023
Joe Frogge
Final Development Plan
Resolved
10/30/2023

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational. 8/22/23 - acknowledged in letter
Miscellaneous Correction
Corrective Action Required
08/21/2023

A one-time impact fee in the form of a license tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process. Action required: Comment is for informational purposes. In this case the fee will be $67,897.50 8/22/23 - acknowledged in letter
Health Dept Review
Resolved
09/28/2023

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 797-7162. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is informational. 8/22/23 - acknowledged in letter
Health Dept Inspection
Resolved
09/28/2023

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 797-7162. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is informational. 8/22/23 - acknowledged in letter
IBC 1704.2 Special Inspections
Resolved
08/29/2023

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections. 8/22/23 - acknowledged in letter
IPC 403.1 Minimum number of fixtures
Resolved
08/22/2023

2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code. Action required: Facility required to have at least 1 bathtub or shower.
Engineered truss package
Corrective Action Required
08/21/2023

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide roof truss package or request deferral. 8/22/23 - deferred per request
Final Development Plan Review Approved 11/27/2023 11/27/2023
Scott Ready
Arborwalk West - The Learning Experience. ***Do not issue any type of permit until CID is presented to/and approved by Council; per David Bushek, this project is an exception and may proceed upon permit issuance***
Licensed Contractors Approved 08/28/2023 09/19/2023
Joe Frogge
LC - General Contractor
Resolved
09/19/2023

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and an email address & phone number for the on-site contact which is where inspection reports will be sent. 8/22/23 - acknowledged in letter
LC - MEP Subs
Resolved
09/19/2023

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 8/22/23 - acknowledged in letter
Special Inspections Review Approved 08/29/2023
Joe Frogge
Fire Plan Review Approved with Conditions 08/28/2023 08/22/2023
Joe Frogge
Key boxes for non-standardized fire service elevator keys
Corrective Action Required
08/21/2023

2018 IFC 506.1.2 Key boxes for non-standardized fire service elevator keys. Key boxes provided for non-standardized fire service elevator keys shall comply with Section 506.1 and 506.2 or as approved by the fire code official. Locate the Knox box 6' AFF over the FDC. Verified at inspection. Order the box from Knoxbox.com.
Construction documents for fire alarm systems
Corrective Action Required
08/21/2023

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.4 Provide shop drawings for review and approval.
Construction documents - Fire protection systems
Corrective Action Required
08/21/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Provide shop drawings for review and approval.
Miscellaneous Correction
Corrective Action Required
08/21/2023

The top pf the private fire hydrant shall be painted silver. Verified at inspection.
Fire Plan Review Approved with Conditions 08/07/2023 08/03/2023
Jim Eden
Key boxes for non-standardized fire service elevator keys
Corrective Action Required
08/03/2023

2018 IFC 506.1.2 Key boxes for non-standardized fire service elevator keys. Key boxes provided for non-standardized fire service elevator keys shall comply with Section 506.1 and 506.2 or as approved by the fire code official. Locate the Knox box 6' AFF over the FDC. Verified at inspection. Order the box from Knoxbox.com.
Construction documents for fire alarm systems
Corrective Action Required
08/03/2023

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.4 Provide shop drawings for review and approval.
Construction documents - Fire protection systems
Corrective Action Required
08/03/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Provide shop drawings for review and approval.
Miscellaneous Correction
Corrective Action Required
08/03/2023

The top pf the private fire hydrant shall be painted silver. Verified at inspection.
Building Plan Review Rejected 08/07/2023 08/03/2023
Joe Frogge
Final Development Plan
Corrective Action Required
08/03/2023

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational.
Miscellaneous Correction
Corrective Action Required
08/03/2023

A one-time impact fee in the form of a license tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process. Action required: Comment is for informational purposes. In this case the fee will be $67,897.50
Health Dept Review
Corrective Action Required
08/03/2023

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 797-7162. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is informational.
Health Dept Inspection
Corrective Action Required
08/03/2023

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 797-7162. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is informational.
IBC 1704.2 Special Inspections
Corrective Action Required
08/03/2023

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections.
IPC 403.1 Minimum number of fixtures
Corrective Action Required
08/03/2023

2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code. Action required: Facility required to have at least 1 bathtub or shower.
Engineered truss package
Corrective Action Required
08/03/2023

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide roof truss package or request deferral.
Licensed Contractors Rejected 08/03/2023
Joe Frogge
LC - General Contractor
Corrective Action Required
08/03/2023

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and an email address & phone number for the on-site contact which is where inspection reports will be sent.
LC - MEP Subs
Corrective Action Required
08/03/2023

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Commercial $11,148.58 $11,148.58 Paid 09/28/2023
7232302-Commercial License Tax Fee $67,897.50 $67,897.50 Paid 08/09/2024
91100C8-Sanitary Sewer Insp Fees $558.45 $558.45 Paid 12/05/2023
91100C9-Water Insp Fee $1,325.70 $1,325.70 Paid 12/05/2023
9110068-Storm Fee $6,294.48 $6,294.48 Paid 12/05/2023
9110081-Paved Surface Inspection Fee $6,642.62 $6,642.62 Paid 12/05/2023
9110071-Site Grading Fee $2,028.42 $2,028.42 Paid 12/05/2023
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 12/05/2023
8331401-Water Tap Fee $35,100.00 $35,100.00 Paid 12/05/2023
8350015-Water Meter Fee $4,377.17 $4,377.17 Paid 12/05/2023
8331507-Sanitary Sewer Development Fee $14,401.00 $14,401.00 Paid 12/05/2023
9110072-Water Test Fee $400.00 $400.00 Paid 12/05/2023
9110069-After Hours Inspections (Public Works)(Per Hour) $200.00 $200.00 Paid 08/09/2024
9110069-After Hours Inspections (Public Works)(Per Hour) $150.00 $150.00 Paid 08/09/2024
9110078-Temporary Occupancy Fee $50.00 $0.00 Paid 08/19/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Partial 1/2/2024 1/2/2024 01/02/2024
Misc
Informational
01/02/2024
1-2-24 PS Erosion control crew on site installing silt fence at perimeter
Erosion Control Inspection Partial 1/4/2024 1/4/2024 01/04/2024
Misc
Informational
01/02/2024
1-2-24 PS Erosion control crew on site installing silt fence at perimeter 1-4-24 PS Eroison control silt fence installed at perimeter of project. Gravel delivered for construction entrance. Contractor mobilizing equipment on site and expects to begin mowing grass today
Site Visit Partial 1/11/2024 1/11/2024 01/11/2024
Misc
Informational
01/11/2024
1-11-24 PS No activity on site due to weather this week
Site Visit Partial 1/17/2024 1/17/2024 01/17/2024
Misc
Informational
01/11/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site
Erosion Control Inspection Partial 1/29/2024 1/29/2024 01/29/2024
Misc
Informational
01/04/2024
1-2-24 PS Erosion control crew on site installing silt fence at perimeter 1-4-24 PS Eroison control silt fence installed at perimeter of project. Gravel delivered for construction entrance. Contractor mobilizing equipment on site and expects to begin mowing grass today 1-29-24 PS Erosion control acceptable at time of inspection
Grading/Excavation/Fill Inspection Partial 2/1/2024 2/1/2024 02/01/2024
Misc
Informational
02/01/2024
2-1-24 PS Scraper on site grading site
Site Visit Partial 2/2/2024 2/2/2024 02/02/2024
Misc
Informational
01/17/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site
Grading/Excavation/Fill Inspection Partial 2/7/2024 2/7/2024 02/07/2024
Misc
Informational
02/07/2024
2-7-24 PS Scraper on site grading
Grading/Excavation/Fill Inspection Partial 2/8/2024 2/8/2024 02/08/2024
Misc
Informational
02/07/2024
2-1-24 PS Scraper on site grading site 2-8-24 PS crew grading and excavating for building pad
Grading/Excavation/Fill Inspection Partial 2/9/2024 2/9/2024 02/09/2024
Misc
Informational
02/08/2024
2-1-24 PS Scraper on site grading site 2-8-24 PS crew grading and excavating for building pad 2-9-24 PS Crew grading and excavating for building pad
Grading/Excavation/Fill Inspection Partial 2/13/2024 2/13/2024 02/13/2024
Misc
Informational
02/09/2024
2-1-24 PS Scraper on site grading site 2-8-24 PS crew grading and excavating for building pad 2-9-24 PS Crew grading and excavating for building pad 2-13-24 PS Crews grading site and working on building pad/footings
Grading/Excavation/Fill Inspection Partial 2/20/2024 2/20/2024 02/20/2024
Misc
Informational
02/13/2024
2-1-24 PS Scraper on site grading site 2-8-24 PS crew grading and excavating for building pad 2-9-24 PS Crew grading and excavating for building pad 2-13-24 PS Crews grading site and working on building pad/footings 2-20-24 PS Site crew working on site grading and building pad
Site Visit Partial 2/21/2024 2/21/2024 02/21/2024
Misc
Informational
02/02/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing
Erosion Control Inspection Failed 2/21/2024 2/21/2024 02/21/2024
Misc
Resolved
02/21/2024
1-2-24 PS Erosion control crew on site installing silt fence at perimeter 1-4-24 PS Eroison control silt fence installed at perimeter of project. Gravel delivered for construction entrance. Contractor mobilizing equipment on site and expects to begin mowing grass today 1-29-24 PS Erosion control acceptable at time of inspection
Misc
Corrective Action Required
02/21/2024
2-21-24 PS Provide erosion control protection at storm inlets as discussed on east side inlet at creek and on inlet on south end against 150 highway to protect from silt entering storm system. Provide silt fence around soils pile south end where new sanitary/storm being installed if it is expected to be there for longer duration that completion of sanitary and storm lines currently being installed.
Footing Inspection - Commercial Partial 2/21/2024 2/21/2024 02/21/2024
Misc
Informational
02/21/2024
Perimeter OK to pour Interior pads OK to pour Copper concrete encased electrode located on north wall east side
Foundation Inspection - Commercial Failed 2/26/2024 2/26/2024 02/26/2024
Misc
Corrective Action Required
02/26/2024
-Number of rebar in wall does not match plans. -provide clearance around rebar (rebar resting on forms in some areas)
Site Visit Partial 2/26/2024 2/26/2024 02/26/2024
Misc
Informational
02/21/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings
Foundation Inspection - Commercial Partial 2/27/2024 02/27/2024
Misc
Resolved
02/27/2024
-Number of rebar in wall does not match plans. -provide clearance around rebar (rebar resting on forms in some areas)
Misc
Informational
02/27/2024
Perimeter okay
Site Visit Partial 2/27/2024 2/27/2024 02/27/2024
Misc
Informational
02/26/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings
Site Visit Partial 2/29/2024 2/29/2024 02/29/2024
Misc
Informational
02/27/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings
Site Visit Partial 3/4/2024 3/4/2024 03/04/2024
Misc
Informational
02/29/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings
Site Visit Partial 3/5/2024 3/5/2024 03/05/2024
Misc
Informational
03/04/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab
Site Visit Partial 3/6/2024 3/6/2024 03/06/2024
Misc
Informational
03/05/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today
Erosion Control Inspection Failed 03/08/2024
Misc
Corrective Action Required
03/08/2024
2-21-24 PS Provide erosion control protection at storm inlets on east side inlet at creek and on inlet on south end against 150 highway to protect from silt entering storm system. Provide silt fence around soils pile south end where new sanitary/storm being installed if it is expected to be there for longer duration that completion of sanitary and storm lines currently being installed.
Misc
Resolved
03/08/2024
Site Visit Partial 3/12/2024 3/12/2024 03/12/2024
Misc
Informational
03/06/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical
Underslab Plumbing Inspection - Commercial Partial 3/12/2024 3/12/2024 03/12/2024
Misc
Informational
03/12/2024
03/12/24-underslab plumbing in building completed and pressure tested.
Underslab Electrical Inspection - Commercial Partial 3/12/2024 3/12/2024 03/12/2024
Misc
Informational
03/12/2024
03/12/24- under slab electrical in building okay to cover.
Water Line - Construction Inspection Partial 3/18/2024 3/18/2024 03/18/2024
Misc
Informational
03/18/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation.
Site Visit Partial 3/20/2024 3/20/2024 03/20/2024
Misc
Informational
03/12/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19
Water Line - Construction Inspection Partial 3/25/2024 3/25/2024 03/25/2024
Misc
Informational
03/18/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation. 3-25-24 PS Crew on site boring for 6" water line at Arboridge Dr crossing
Site Visit Partial 3/28/2024 3/28/2024 03/28/2024
Misc
Informational
03/20/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction
Water Line - Construction Inspection Partial 3/29/2024 3/29/2024 03/29/2024
Misc
Informational
03/25/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation. 3-25-24 PS Crew on site boring for 6" water line at Arboridge Dr crossing 3-29-24 PS Contractor excavating at NE corner of building to begin installing 6" fire line
Water Line - Construction Inspection Partial 3/29/2024 3/29/2024 03/29/2024
Misc
Informational
03/29/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation. 3-25-24 PS Crew on site boring for 6" water line at Arboridge Dr crossing 3-29-24 PS Contractor excavating at NE corner of building to begin installing 6" fire line. PM Contractor installed 6" fire line from building to tee for private fire hydrant
Water Line - Construction Inspection Partial 4/1/2024 4/1/2024 04/01/2024
Misc
Informational
03/29/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation. 3-25-24 PS Crew on site boring for 6" water line at Arboridge Dr crossing 3-29-24 PS Contractor excavating at NE corner of building to begin installing 6" fire line. PM Contractor installed 6" fire line from building to tee for private fire hydrant 4-1-24 PS Contractor set private hydrant with line to hydran from tee at 6" fire line
Site Visit Partial 4/2/2024 4/2/2024 04/02/2024
Misc
Informational
03/28/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today
Storm Sewer Construction Inspection Partial 4/4/2024 4/4/2024 04/04/2024
Misc
Informational
04/04/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c
Storm Sewer Construction Inspection Partial 4/5/2024 4/5/2024 04/05/2024
Misc
Informational
04/04/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting
Storm Sewer Construction Inspection Partial 4/10/2024 4/10/2024 04/10/2024
Misc
Informational
04/05/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85
Storm Sewer Construction Inspection Partial 4/11/2024 4/11/2024 04/11/2024
Misc
Informational
04/10/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85 4-11-24 PS Contractor set storm box C-1 at STA 0+79.45 and HDPE to box
Storm Sewer Construction Inspection Partial 4/16/2024 4/16/2024 04/16/2024
Misc
Informational
04/11/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85 4-11-24 PS Contractor set storm box C-1 at STA 0+79.45 and HDPE to box 4-16-24 PS Contractor excavating for private storm line A
Rough Framing Inspection - Commercial Partial 4/17/2024 04/17/2024
THE FOLLOWING AREAS ARE APPROVED
Informational
04/17/2024
exterior walls sheathing
Storm Sewer Construction Inspection Partial 4/17/2024 4/17/2024 04/17/2024
Misc
Informational
04/16/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85 4-11-24 PS Contractor set storm box C-1 at STA 0+79.45 and HDPE to box 4-16-24 PS Contractor excavating for private storm line A 4-17-24 PS Contractor placing aggregate and cutting back existing corrugated storm pipe from private road crossing for clean connection to junction with new HDPE storm line at line A, STA 5+38.27
Storm Sewer Construction Inspection Partial 4/19/2024 4/19/2024 04/19/2024
Misc
Informational
04/17/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85 4-11-24 PS Contractor set storm box C-1 at STA 0+79.45 and HDPE to box 4-16-24 PS Contractor excavating for private storm line A 4-17-24 PS Contractor placing aggregate and cutting back existing corrugated storm pipe from private road crossing for clean connection to junction with new HDPE storm line at line A, STA 5+38.27 4-19-24 PS Contractor installing storm, connection made at junction for HDPE to existing corrugated storm with HDPE set to approx 5+00
Site Visit Partial 4/22/2024 04/22/2024
Misc
Informational
04/02/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today
Misc
Informational
04/22/2024
4-22-24 Dustin A, Contractor working on private water, Digging footings for vault.
Water Line - Construction Inspection Partial 4/23/2024 4/23/2024 04/23/2024
Misc
Informational
04/01/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation. 3-25-24 PS Crew on site boring for 6" water line at Arboridge Dr crossing 3-29-24 PS Contractor excavating at NE corner of building to begin installing 6" fire line. PM Contractor installed 6" fire line from building to tee for private fire hydrant 4-1-24 PS Contractor set private hydrant with line to hydran from tee at 6" fire line 4-23-24 PS Contractor set backflow vault for 6" fire line and currently setting backflow
Erosion Control Inspection Partial 4/23/2024 4/23/2024 04/23/2024
Misc
Corrective Action Required
03/08/2024
4-23-24 PS Provide erosion control, re establish silt fence along arborridge drive where silt fence was removed for new storm ilte at corner of 150 highway. Provide erosion control at slop in same area to prevent erosion from soil pile at top of slope. Maintain gravel filter at construction entrance. Gravel embedded in soil allowing for vehicles to bring mud onto arboridge drive during rain events
Water Line - Construction Inspection Partial 4/24/2024 4/24/2024 04/24/2024
Misc
Informational
04/23/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation. 3-25-24 PS Crew on site boring for 6" water line at Arboridge Dr crossing 3-29-24 PS Contractor excavating at NE corner of building to begin installing 6" fire line. PM Contractor installed 6" fire line from building to tee for private fire hydrant 4-1-24 PS Contractor set private hydrant with line to hydran from tee at 6" fire line 4-23-24 PS Contractor set backflow vault for 6" fire line and currently setting backflow 4-24-24 PS Backflow set with lines connected that supply to riser and arbor ridge dr bore. Collars poured at backflow vault and thrust block poured at 22 fitting on east side of vault
Underground Electrical Inspection - Commercial Partial 4/25/2024 4/25/2024 04/25/2024
Misc
Informational
04/25/2024
INSECTED TRENCH AND CONDUIT SOUTH OF BUILDING
Water Line - Hydrostatic Test Passed 4/25/2024 4/25/2024 04/25/2024
Misc
Informational
04/25/2024
4-25-24 PS Contractor performed hydrostatic test on water line. Test passed 200 psi for 2 hours
Water Line - Construction Inspection Partial 5/1/2024 5/1/2024 05/01/2024
Misc
Informational
04/24/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation. 3-25-24 PS Crew on site boring for 6" water line at Arboridge Dr crossing 3-29-24 PS Contractor excavating at NE corner of building to begin installing 6" fire line. PM Contractor installed 6" fire line from building to tee for private fire hydrant 4-1-24 PS Contractor set private hydrant with line to hydran from tee at 6" fire line 4-23-24 PS Contractor set backflow vault for 6" fire line and currently setting backflow 4-24-24 PS Backflow set with lines connected that supply to riser and arbor ridge dr bore. Collars poured at backflow vault and thrust block poured at 22 fitting on east side of vault 5-1-24 PS Contractor completed tie in at main for 6" water line, thrust blocked poured at tee with kickers poured at 90 and 45 degree turns on line
Erosion Control Inspection Partial 5/1/2024 5/1/2024 05/01/2024
Misc
Informational
05/01/2024
5-1-24 PS Erosion control acceptable
Underground Electrical Inspection - Commercial Failed 5/3/2024 5/3/2024 05/03/2024
Misc
Informational
04/25/2024
INSECTED TRENCH AND CONDUIT SOUTH OF BUILDING-Alex
Misc
Corrective Action Required
05/03/2024
All conduit underground to be minimum 18” and 24” under parking lot/drivable surfaces
Water Line - Construction Inspection Partial 5/6/2024 5/6/2024 05/06/2024
Misc
Informational
05/01/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation. 3-25-24 PS Crew on site boring for 6" water line at Arboridge Dr crossing 3-29-24 PS Contractor excavating at NE corner of building to begin installing 6" fire line. PM Contractor installed 6" fire line from building to tee for private fire hydrant 4-1-24 PS Contractor set private hydrant with line to hydran from tee at 6" fire line 4-23-24 PS Contractor set backflow vault for 6" fire line and currently setting backflow 4-24-24 PS Backflow set with lines connected that supply to riser and arbor ridge dr bore. Collars poured at backflow vault and thrust block poured at 22 fitting on east side of vault 5-1-24 PS Contractor completed tie in at main for 6" water line, thrust blocked poured at tee with kickers poured at 90 and 45 degree turns on line 5-6-24 PS Contractor backfilling main and private line at tie in. Contractor also flushing private water line for water sample testing tomorrow 5/7
Water Line - Coliform Test 1 Partial 5/7/2024 5/7/2024 05/07/2024
Misc
Informational
05/07/2024
5-7-24 PS First sample collected and delivered to keystone lab for testing
Rough Framing Inspection - Commercial Partial 5/7/2024 05/07/2024
THE FOLLOWING AREAS ARE APPROVED
Informational
04/17/2024
exterior walls sheathing interior walls truss hold downs and lateral bracing is to plans
Misc
Corrective Action Required
05/07/2024
-address over notched and cut studs in NW room -missing anchor bolts see NE corner of building and confirm throught
In-wall Inspection Passed 5/7/2024 5/7/2024 05/07/2024
Water Line - Coliform Test 2 Partial 5/8/2024 5/8/2024 05/08/2024
Misc
Informational
05/08/2024
5-8-24 PS Obtained water sample #2 and delivered to keystone lab for testing
Rough Framing Inspection - Commercial Failed 5/8/2024 5/8/2024 05/08/2024
THE FOLLOWING AREAS ARE APPROVED
Informational
05/07/2024
exterior walls sheathing interior walls truss hold downs and lateral bracing is to plans
Misc
Corrective Action Required
05/07/2024
-address over notched and cut studs in NW room (have engineer address)
Erosion Control Inspection Partial 5/9/2024 5/9/2024 05/09/2024
Misc
Informational
05/01/2024
5-1-24 PS Erosion control acceptable
Site Visit Partial 5/13/2024 05/13/2024
Misc
Informational
04/22/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today 5-13-24 Dustin A, No activity today
Misc
Informational
04/22/2024
4-22-24 Dustin A, Contractor working on private water, Digging footings for vault.
Storm Sewer Construction Inspection Partial 5/13/2024 05/13/2024
Misc
Informational
04/19/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85 4-11-24 PS Contractor set storm box C-1 at STA 0+79.45 and HDPE to box 4-16-24 PS Contractor excavating for private storm line A 4-17-24 PS Contractor placing aggregate and cutting back existing corrugated storm pipe from private road crossing for clean connection to junction with new HDPE storm line at line A, STA 5+38.27 4-19-24 PS Contractor installing storm, connection made at junction for HDPE to existing corrugated storm with HDPE set to approx 5+00 5-10-24 NS Contractor was planning on working on storm but from the time I was there they were just unloading materials.
Underground Electrical Inspection - Commercial Partial 5/13/2024 5/13/2024 05/13/2024
Misc
Informational
05/03/2024
INSECTED TRENCH AND CONDUIT SOUTH OF BUILDING 05/13/24- light pole conduit, and conduit on north side side of building
Misc
Resolved
05/13/2024
All conduit underground to be minimum 18” and 24” under parking lot/drivable surfaces
Water Line - Coliform Test 1 Passed 5/14/2024 5/14/2024 05/14/2024
Misc
Informational
05/07/2024
5-7-24 PS First sample collected and delivered to keystone lab for testing 5-14-24 PS Coliform test#1 passed
Water Line - Coliform Test 2 Passed 5/14/2024 5/14/2024 05/14/2024
Misc
Informational
05/14/2024
5-14-24 PS Coliform test #2 passed
Water Line - Construction Inspection Partial 5/14/2024 5/14/2024 05/14/2024
Misc
Informational
05/06/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation. 3-25-24 PS Crew on site boring for 6" water line at Arboridge Dr crossing 3-29-24 PS Contractor excavating at NE corner of building to begin installing 6" fire line. PM Contractor installed 6" fire line from building to tee for private fire hydrant 4-1-24 PS Contractor set private hydrant with line to hydran from tee at 6" fire line 4-23-24 PS Contractor set backflow vault for 6" fire line and currently setting backflow 4-24-24 PS Backflow set with lines connected that supply to riser and arbor ridge dr bore. Collars poured at backflow vault and thrust block poured at 22 fitting on east side of vault 5-1-24 PS Contractor completed tie in at main for 6" water line, thrust blocked poured at tee with kickers poured at 90 and 45 degree turns on line 5-6-24 PS Contractor backfilling main and private line at tie in. Contractor also flushing private water line for water sample testing tomorrow 5/7 5-14-24 PS Coliform samples from 5/7 and 5/7 passed test
Underground Electrical Inspection - Commercial Partial 5/14/2024 5/14/2024 05/14/2024
Misc
Informational
05/13/2024
INSECTED TRENCH AND CONDUIT NORTH OF BUILDING 05/13/24- light pole conduit, and conduit on north side side of building 05/14/24- partial conduit for monument sign
Storm Sewer Construction Inspection Partial 5/16/2024 5/16/2024 05/16/2024
Misc
Informational
05/13/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85 4-11-24 PS Contractor set storm box C-1 at STA 0+79.45 and HDPE to box 4-16-24 PS Contractor excavating for private storm line A 4-17-24 PS Contractor placing aggregate and cutting back existing corrugated storm pipe from private road crossing for clean connection to junction with new HDPE storm line at line A, STA 5+38.27 4-19-24 PS Contractor installing storm, connection made at junction for HDPE to existing corrugated storm with HDPE set to approx 5+00 5-10-24 NS Contractor was planning on working on storm but from the time I was there they were just unloading materials. 5-16-24 PS Contractor excavating for storm line A and A-4
Storm Sewer Construction Inspection Partial 5/17/2024 5/17/2024 05/17/2024
Misc
Informational
05/16/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85 4-11-24 PS Contractor set storm box C-1 at STA 0+79.45 and HDPE to box 4-16-24 PS Contractor excavating for private storm line A 4-17-24 PS Contractor placing aggregate and cutting back existing corrugated storm pipe from private road crossing for clean connection to junction with new HDPE storm line at line A, STA 5+38.27 4-19-24 PS Contractor installing storm, connection made at junction for HDPE to existing corrugated storm with HDPE set to approx 5+00 5-10-24 NS Contractor was planning on working on storm but from the time I was there they were just unloading materials. 5-16-24 PS Contractor excavating for storm line A and A-4 5-17-24 PS Contractor set inlet A-5 with HDPE on north side, contractor excavating from A-5 to A-4 public storm junction box
Storm Sewer Construction Inspection Partial 5/20/2024 5/20/2024 05/20/2024
Misc
Informational
05/17/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85 4-11-24 PS Contractor set storm box C-1 at STA 0+79.45 and HDPE to box 4-16-24 PS Contractor excavating for private storm line A 4-17-24 PS Contractor placing aggregate and cutting back existing corrugated storm pipe from private road crossing for clean connection to junction with new HDPE storm line at line A, STA 5+38.27 4-19-24 PS Contractor installing storm, connection made at junction for HDPE to existing corrugated storm with HDPE set to approx 5+00 5-10-24 NS Contractor was planning on working on storm but from the time I was there they were just unloading materials. 5-16-24 PS Contractor excavating for storm line A and A-4 5-17-24 PS Contractor set inlet A-5 with HDPE on north side, contractor excavating from A-5 to A-4 public storm junction box 5-20-24 PS Contractor set junction box A-4 with HDPE connection from A-5
Erosion Control Inspection Partial 5/20/2024 5/20/2024 05/20/2024
Misc
Informational
05/09/2024
5-1-24 PS Erosion control acceptable 5-20-24 PS re establish gravel filter at construction entrance (recently disturbed for storm construction) prevent mud tracking on Arboridge Dr, clean mud from street
Water Line - Coliform Test 2 Passed 5/14/2024 05/21/2024
Misc
Informational
05/08/2024
5-8-24 PS Obtained water sample #2 and delivered to keystone lab for testing
Storm Sewer Construction Inspection Partial 5/21/2024 5/21/2024 05/21/2024
Misc
Informational
05/20/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85 4-11-24 PS Contractor set storm box C-1 at STA 0+79.45 and HDPE to box 4-16-24 PS Contractor excavating for private storm line A 4-17-24 PS Contractor placing aggregate and cutting back existing corrugated storm pipe from private road crossing for clean connection to junction with new HDPE storm line at line A, STA 5+38.27 4-19-24 PS Contractor installing storm, connection made at junction for HDPE to existing corrugated storm with HDPE set to approx 5+00 5-10-24 NS Contractor was planning on working on storm but from the time I was there they were just unloading materials. 5-16-24 PS Contractor excavating for storm line A and A-4 5-17-24 PS Contractor set inlet A-5 with HDPE on north side, contractor excavating from A-5 to A-4 public storm junction box 5-20-24 PS Contractor set junction box A-4 with HDPE connection from A-5 5-21-24 PS Contractor poured collars/inverts at storm box A-5 and C-1, collar poured on northside of junction box A-4
Water Service Inspection Passed 5/23/2024 5/23/2024 05/23/2024
Pavement-Proof Roll Partial 6/3/2024 6/3/2024 06/03/2024
Misc
Informational
06/03/2024
5-31-24 PS Contractor performed proof roll of compacted subgrade prior to placement of geogrid and aggregate base at parking lot. Third party inspector was on site for test. There were couple of areas of concern but they have been addressed by contractor.
Pavement-Aggregate Base Partial 6/4/2024 6/4/2024 06/04/2024
Misc
Informational
06/04/2024
6-4-24 PS contractor installing geo grid on compacted subgrade, grid has appropriate lap between rolls
Pavement-Aggregate Base Partial 6/4/2024 6/4/2024 06/04/2024
Misc
Informational
06/04/2024
6-4-24 PS contractor installing geo grid on compacted subgrade, grid has appropriate lap between rolls P.M. geo grid installed through parking lot
Curb - Proof Roll Partial 6/5/2024 6/5/2024 06/05/2024
Misc
Informational
06/05/2024
6-5-24 PS Inspected proof roll for curb at parking lot, areas inspected approved for curb construction
Pavement-Proof Roll Partial 6/5/2024 6/5/2024 06/05/2024
Misc
Informational
06/03/2024
5-31-24 PS Contractor performed proof roll of compacted subgrade prior to placement of geogrid and aggregate base at parking lot. Third party inspector was on site for test. There were couple of areas of concern but they have been addressed by contractor. 6-5-24 PS Inspected proof roll for surface at parking lot, areas inspected approved for surface asphalt construction
Pavement-Aggregate Base Partial 6/5/2024 6/5/2024 06/05/2024
Misc
Informational
06/04/2024
6-4-24 PS contractor installing geo grid on compacted subgrade, grid has appropriate lap between rolls P.M. geo grid installed through parking lot 6-5-24 PS Base aggregate placed and compacted through parking lot
Pavement-Curb Construction Partial 6/6/2024 6/6/2024 06/07/2024
Misc
Informational
06/07/2024
6-6-24 PS Contractor poured and set curb along parking lot stall perimeter; white cure applied
Erosion Control Inspection Partial 6/7/2024 6/7/2024 06/07/2024
Misc
Informational
05/20/2024
5-1-24 PS Erosion control acceptable 5-20-24 PS re establish gravel filter at construction entrance (recently disturbed for storm construction) prevent mud tracking on Arboridge Dr, clean mud from street
Pavement-Curb Construction Partial 6/7/2024 6/7/2024 06/07/2024
Misc
Informational
06/07/2024
6-6-24 PS Contractor poured and set curb along parking lot stall perimeter; white cure applied 6-7-24 PS Contractor poured and set curb at remainder of curb along parking lot stall perimeter at islands
Pavement-Proof Roll Partial 6/11/2024 6/11/2024 06/11/2024
Misc
Informational
06/05/2024
5-31-24 PS Contractor performed proof roll of compacted subgrade prior to placement of geogrid and aggregate base at parking lot. Third party inspector was on site for test. There were couple of areas of concern but they have been addressed by contractor. 6-5-24 PS Inspected proof roll for surface at parking lot, areas inspected approved for surface asphalt construction 6-11-24 PS Inspected proof roll for surface at parking lot, this is same area inspected on 6-5. Rain over weekend required another proof roll. Areas inspected approved for surface construction
Pavement-Surface Partial 6/12/2024 6/12/2024 06/12/2024
Misc
Informational
06/12/2024
6-12-24 PS Contractor poured concrete pad in front of trash enclosure at lot
Erosion Control Inspection Partial 6/12/2024 6/12/2024 06/12/2024
Misc
Resolved
06/12/2024
5-1-24 PS Erosion control acceptable 5-20-24 PS re establish gravel filter at construction entrance (recently disturbed for storm construction) prevent mud tracking on Arboridge Dr, clean mud from street
Pavement-Surface Partial 6/13/2024 6/13/2024 06/13/2024
Misc
Informational
06/12/2024
6-12-24 PS Contractor poured concrete pad in front of trash enclosure at lot 6-13-24 PS Contractor laid base asphalt throughout parking lot stall portion of lot per plan
Pavement-Surface Partial 6/14/2024 6/14/2024 06/14/2024
Misc
Informational
06/13/2024
6-12-24 PS Contractor poured concrete pad in front of trash enclosure at lot 6-13-24 PS Contractor laid base asphalt throughout parking lot stall portion of lot per plan 6-14-24 PS Contractor laying surface layer asphalt throughout parking lot stall portion of lot
Pavement-Surface Partial 6/14/2024 6/14/2024 06/14/2024
Misc
Informational
06/14/2024
6-12-24 PS Contractor poured concrete pad in front of trash enclosure at lot 6-13-24 PS Contractor laid base asphalt throughout parking lot stall portion of lot per plan 6-14-24 PS Contractor laying surface layer asphalt throughout parking lot stall portion of lot. PM contractor completed surface layer asphalt at parking lot stall area of lot
Electrical Service Inspection Partial 6/14/2024 06/14/2024
Misc
Informational
06/14/2024
OK TO THE FIRST MEANS OF DISCONNECT. RELEASE TO EVERGY INSPECTIONS NOT DONE TO MULTI AND SUB PANNELS.
Pavement-Proof Roll Partial 6/19/2024 6/19/2024 06/19/2024
Misc
Informational
06/11/2024
5-31-24 PS Contractor performed proof roll of compacted subgrade prior to placement of geogrid and aggregate base at parking lot. Third party inspector was on site for test. There were couple of areas of concern but they have been addressed by contractor. 6-5-24 PS Inspected proof roll for surface at parking lot, areas inspected approved for surface asphalt construction 6-11-24 PS Inspected proof roll for surface at parking lot, this is same area inspected on 6-5. Rain over weekend required another proof roll. Areas inspected approved for surface construction 6-19-24 PS Inspected proof roll of compacted subgrade prior to placement of geogrid/aggregate at approach and road that connects to parking lot. Areas inspected approved for geogrid/aggregate placement
Pavement-Aggregate Base Partial 6/19/2024 6/19/2024 06/19/2024
Misc
Informational
06/05/2024
6-4-24 PS contractor installing geo grid on compacted subgrade, grid has appropriate lap between rolls P.M. geo grid installed through parking lot 6-5-24 PS Base aggregate placed and compacted through parking lot 6-19-24 PS contractor installed geo grid, placed aggregate and compacting at approach and road connecting to parking lot
Curb - Proof Roll Partial 6/20/2024 6/20/2024 06/20/2024
Misc
Informational
06/05/2024
6-5-24 PS Inspected proof roll for curb at parking lot, areas inspected approved for curb construction 6-20-24 PS Inspected proof roll for curb at parking lot road between lot and approach, areas inspected approved for curb construction
Pavement-Proof Roll Partial 6/20/2024 6/20/2024 06/20/2024
Misc
Informational
06/19/2024
5-31-24 PS Contractor performed proof roll of compacted subgrade prior to placement of geogrid and aggregate base at parking lot. Third party inspector was on site for test. There were couple of areas of concern but they have been addressed by contractor. 6-5-24 PS Inspected proof roll for surface at parking lot, areas inspected approved for surface asphalt construction 6-11-24 PS Inspected proof roll for surface at parking lot, this is same area inspected on 6-5. Rain over weekend required another proof roll. Areas inspected approved for surface construction 6-19-24 PS Inspected proof roll of compacted subgrade prior to placement of geogrid/aggregate at approach and road that connects to parking lot. Areas inspected approved for geogrid/aggregate placement 6-20-24 PS Inspected proof roll for asphalt surface at parking lot road between lot and approach, areas inspected approved for asphalt surface construction
Pavement-Curb Construction Partial 6/21/2024 6/21/2024 06/21/2024
Misc
Informational
06/07/2024
6-6-24 PS Contractor poured and set curb along parking lot stall perimeter; white cure applied 6-7-24 PS Contractor poured and set curb at remainder of curb along parking lot stall perimeter at islands 6-21-24 PS Crew setting forms for curb at parking lot and road that connects parking lot to approach curb.
Pavement-Curb Construction Partial 6/21/2024 6/21/2024 06/21/2024
Misc
Informational
06/21/2024
6-6-24 PS Contractor poured and set curb along parking lot stall perimeter; white cure applied 6-7-24 PS Contractor poured and set curb at remainder of curb along parking lot stall perimeter at islands 6-21-24 PS Crew setting forms for curb at parking lot and road that connects parking lot to approach curb. PM Crew poured curb at road that connects parking lot to approach
Sewer Service Inspection Partial 6/21/2024 6/21/2024 06/21/2024
Misc
Informational
06/21/2024
6-21-24 PS partial inspection, contractor installed 6" service line from building to cleanout on west side of lot.
Pavement-Surface Partial 6/25/2024 6/25/2024 06/25/2024
Misc
Informational
06/14/2024
6-12-24 PS Contractor poured concrete pad in front of trash enclosure at lot 6-13-24 PS Contractor laid base asphalt throughout parking lot stall portion of lot per plan 6-14-24 PS Contractor laying surface layer asphalt throughout parking lot stall portion of lot. PM contractor completed surface layer asphalt at parking lot stall area of lot 6-25-24 PS Contractor laying base asphalt at road that connects approach to parking lot
Sewer Service Inspection Partial 6/25/2024 6/25/2024 06/25/2024
Misc
Informational
06/21/2024
6-21-24 PS partial inspection, contractor installed 6" service line from building to cleanout on west side of lot. 6-25-24 Contractor completed sewer service line from building towards stub stopping two sticks before stub. Service line cannot connect to stub riser until public main testing is completed and passed
Pavement-Surface Partial 6/25/2024 6/25/2024 06/25/2024
Misc
Informational
06/25/2024
6-12-24 PS Contractor poured concrete pad in front of trash enclosure at lot 6-13-24 PS Contractor laid base asphalt throughout parking lot stall portion of lot per plan 6-14-24 PS Contractor laying surface layer asphalt throughout parking lot stall portion of lot. PM contractor completed surface layer asphalt at parking lot stall area of lot 6-25-24 PS Contractor laying base asphalt at road that connects approach to parking lot. PM Contractor completed surface asphalt at road that connects approach to parking lot
Site Visit Partial 6/27/2024 6/27/2024 06/27/2024
Misc
Informational
05/13/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today 5-13-24 Dustin A, No activity today
Misc
Informational
05/13/2024
4-22-24 Dustin A, Contractor working on private water, Digging footings for vault. 6-27-24 PS No inspections for development today
Site Visit Partial 6/28/2024 6/28/2024 06/28/2024
Misc
Informational
06/27/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today 5-13-24 Dustin A, No activity today
Misc
Informational
06/27/2024
4-22-24 Dustin A, Contractor working on private water, Digging footings for vault. 6-27-24 PS No inspections for development today 6-28-24 PS No inspections for development today
Above Ceiling Inspection Failed 7/1/2024 7/1/2024 07/01/2024
Misc
Corrective Action Required
07/01/2024
-complete and close all open electrical boxes throughout -fill missing knockouts in boxes -secure all wiring separately from grid supports. -secure all electrical with in 12” of all boxes. -max span for electrical between lighting fixtures 6’ (support where over spaned)
Erosion Control Inspection Failed 7/2/2024 7/2/2024 07/02/2024
Misc
Informational
07/02/2024
7-2-24 - Place gutter buddy at corner arboridge/150 to protect inlet - clean mud from streets and any mud build up at gutter buddies at storm inlets - clean mud that has washed across sidewalk at 150 from site. Add additional erosion control if grass buffer will not contain erosion
Above Ceiling Inspection Partial 7/3/2024 7/3/2024 07/03/2024
Misc
Corrective Action Required
07/01/2024
Still to inspect -hallway outside infant B room -staff toilet OKAY TO INSTALL CEILING TILE. LEAVE OUT WHERE STATED ABOVE
Site Visit Partial 7/3/2024 7/3/2024 07/03/2024
Misc
Informational
06/28/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today 5-13-24 Dustin A, No activity today
Misc
Informational
06/28/2024
4-22-24 Dustin A, Contractor working on private water, Digging footings for vault. 6-27-24 PS No inspections for development today 6-28-24 PS No inspections for development today 7-2-24 PS No inspections for development today
Site Visit Partial 7/9/2024 7/9/2024 07/09/2024
Misc
Informational
07/03/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today 5-13-24 Dustin A, No activity today
Misc
Informational
07/03/2024
4-22-24 Dustin A, Contractor working on private water, Digging footings for vault. 6-27-24 PS No inspections for development today 6-28-24 PS No inspections for development today 7-2-24 PS No inspections for development today 7-9-24 PS Bair grading for sidewalks and street widening at arboridge
Curb - Proof Roll Partial 7/11/2024 7/11/2024 07/11/2024
Misc
Informational
06/20/2024
6-5-24 PS Inspected proof roll for curb at parking lot, areas inspected approved for curb construction 6-20-24 PS Inspected proof roll for curb at parking lot road between lot and approach, areas inspected approved for curb construction 7-11-24 PS Inspected curb proof roll for approach, approved to proceed for approach pour
Pavement-Proof Roll Partial 7/11/2024 7/11/2024 07/11/2024
Misc
Informational
06/20/2024
5-31-24 PS Contractor performed proof roll of compacted subgrade prior to placement of geogrid and aggregate base at parking lot. Third party inspector was on site for test. There were couple of areas of concern but they have been addressed by contractor. 6-5-24 PS Inspected proof roll for surface at parking lot, areas inspected approved for surface asphalt construction 6-11-24 PS Inspected proof roll for surface at parking lot, this is same area inspected on 6-5. Rain over weekend required another proof roll. Areas inspected approved for surface construction 6-19-24 PS Inspected proof roll of compacted subgrade prior to placement of geogrid/aggregate at approach and road that connects to parking lot. Areas inspected approved for geogrid/aggregate placement 6-20-24 PS Inspected proof roll for asphalt surface at parking lot road between lot and approach, areas inspected approved for asphalt surface construction 7-11-24 PS Inspected proof roll for approach surface, approved to proceed with pour of approach
Pavement-Surface Partial 7/11/2024 7/11/2024 07/11/2024
Misc
Informational
06/25/2024
6-12-24 PS Contractor poured concrete pad in front of trash enclosure at lot 6-13-24 PS Contractor laid base asphalt throughout parking lot stall portion of lot per plan 6-14-24 PS Contractor laying surface layer asphalt throughout parking lot stall portion of lot. PM contractor completed surface layer asphalt at parking lot stall area of lot 6-25-24 PS Contractor laying base asphalt at road that connects approach to parking lot. PM Contractor completed surface asphalt at road that connects approach to parking lot 7-11-24 PS Contractor poured concrete for parking lot approach and curb
Sidewalk Inspection Partial 7/12/2024 7/12/2024 07/12/2024
Misc
Informational
07/12/2024
7-12-24 PS partial sidewalk inspection on public, north side of approach, forms in place and aggregate has been compacted, there is a comcast box within path of sidewalk that will need to be addressed as box not allowed in sidewalk. Contractor approved to pour partial
Sewer Service Inspection Partial 7/17/2024 7/17/2024 07/17/2024
Misc
Informational
06/25/2024
6-21-24 PS partial inspection, contractor installed 6" service line from building to cleanout on west side of lot. 6-25-24 Contractor completed sewer service line from building towards stub stopping two sticks before stub. Service line cannot connect to stub riser until public main testing is completed and passed 7-17-24 PS Bair excavating for completion on sanitary service line. Public main passed testing
Sanitary - Material Verification Passed 7/17/2024 7/17/2024 07/17/2024
Water Line - Construction Inspection Passed 7/17/2024 7/17/2024 07/17/2024
Misc
Informational
05/14/2024
3-15-24 DP. Adams crew with Bair was onsite today and installed the 6" fire riser under the foundation of the far West building shell today. They wrapped the ductile pipe and 90* fitting. They used tracer wire and poured concrete collars on both sides of foundation. 3-25-24 PS Crew on site boring for 6" water line at Arboridge Dr crossing 3-29-24 PS Contractor excavating at NE corner of building to begin installing 6" fire line. PM Contractor installed 6" fire line from building to tee for private fire hydrant 4-1-24 PS Contractor set private hydrant with line to hydran from tee at 6" fire line 4-23-24 PS Contractor set backflow vault for 6" fire line and currently setting backflow 4-24-24 PS Backflow set with lines connected that supply to riser and arbor ridge dr bore. Collars poured at backflow vault and thrust block poured at 22 fitting on east side of vault 5-1-24 PS Contractor completed tie in at main for 6" water line, thrust blocked poured at tee with kickers poured at 90 and 45 degree turns on line 5-6-24 PS Contractor backfilling main and private line at tie in. Contractor also flushing private water line for water sample testing tomorrow 5/7 5-14-24 PS Coliform samples from 5/7 and 5/7 passed test
Water Line - Hydrostatic Test Passed 7/17/2024 7/17/2024 07/17/2024
Water Line - Coliform Test 1 Passed 7/17/2024 7/17/2024 07/17/2024
Sewer Service Inspection Passed 7/18/2024 7/18/2024 07/18/2024
Misc
Informational
07/17/2024
6-21-24 PS partial inspection, contractor installed 6" service line from building to cleanout on west side of lot. 6-25-24 Contractor completed sewer service line from building towards stub stopping two sticks before stub. Service line cannot connect to stub riser until public main testing is completed and passed 7-17-24 PS Bair excavating for completion on sanitary service line. Public main passed testing 7-18-24 PS private service completed
Sidewalk Inspection Partial 7/18/2024 7/18/2024 07/18/2024
Misc
Informational
07/12/2024
7-12-24 PS partial sidewalk inspection on public, north side of approach, forms in place and aggregate has been compacted, there is a comcast box within path of sidewalk that will need to be addressed as box not allowed in sidewalk. Contractor approved to pour partial 7-18-24 PS Partial sidewalk inspection from south side approach stopping at temp construction entry, forms in place, aggregate compacted, approved to pour partial
Grading/Excavation/Fill Inspection Partial 7/22/2024 7/22/2024 07/22/2024
Misc
Informational
02/20/2024
2-1-24 PS Scraper on site grading site 2-8-24 PS crew grading and excavating for building pad 2-9-24 PS Crew grading and excavating for building pad 2-13-24 PS Crews grading site and working on building pad/footings 2-20-24 PS Site crew working on site grading and building pad 7-22-24 PS Bair grading site
Gas Service Inspection - Commercial Partial 7/25/2024 7/25/2024 07/25/2024
Misc
Corrective Action Required
07/25/2024
Okay to release to spire -Secure gas line at roof top supports -paint exterior gas line
Site Visit Partial 7/26/2024 7/26/2024 07/26/2024
Misc
Informational
07/09/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today 5-13-24 Dustin A, No activity today
Misc
Informational
07/09/2024
4-22-24 Dustin A, Contractor working on private water, Digging footings for vault. 6-27-24 PS No inspections for development today 6-28-24 PS No inspections for development today 7-2-24 PS No inspections for development today 7-9-24 PS Bair grading for sidewalks and street widening at arboridge 7-26-24 Dustin A, Dirt work being done along side 150
Sprinkler - Hydrostatic Test Passed 7/29/2024 07/29/2024
Sidewalk Inspection Partial 7/29/2024 7/29/2024 07/29/2024
Misc
Informational
07/18/2024
7-12-24 PS partial sidewalk inspection on public, north side of approach, forms in place and aggregate has been compacted, there is a comcast box within path of sidewalk that will need to be addressed as box not allowed in sidewalk. Contractor approved to pour partial 7-18-24 PS Partial sidewalk inspection from south side approach stopping at temp construction entry, forms in place, aggregate compacted, approved to pour partial 7-29-24 PS Partial sidewalk inspection public north side of approach at ADA ramp, comcast relocated box within sidewalk path, forms in place and aggregate compacted, approved to pour
Grading/Excavation/Fill Inspection Partial 8/1/2024 8/1/2024 08/01/2024
Misc
Informational
07/22/2024
2-1-24 PS Scraper on site grading site 2-8-24 PS crew grading and excavating for building pad 2-9-24 PS Crew grading and excavating for building pad 2-13-24 PS Crews grading site and working on building pad/footings 2-20-24 PS Site crew working on site grading and building pad 7-22-24 PS Bair grading site 8-1-24 PS Site grading and hauling soil piles off site
Erosion Control Inspection Failed 8/1/2024 8/1/2024 08/01/2024
Misc
Corrective Action Required
08/01/2024
- provide silt fence erosion control at south side of lot along 150, clean mud from sidewalk on 150 side - clean mud buildup at gutter buddies - clean all mud and construction debris from Arboridge Dr including construction materials in center island
Site Visit Partial 8/6/2024 8/6/2024 08/06/2024
Misc
Informational
07/26/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today 5-13-24 Dustin A, No activity today
Misc
Informational
07/26/2024
4-22-24 Dustin A, Contractor working on private water, Digging footings for vault. 6-27-24 PS No inspections for development today 6-28-24 PS No inspections for development today 7-2-24 PS No inspections for development today 7-9-24 PS Bair grading for sidewalks and street widening at arboridge 7-26-24 Dustin A, Dirt work being done along side 150 8-6-24 Dustin A, Sod crew working, prep work for the remainder of sidewalk to go in and light poles electrical being pulled
Sidewalk Inspection Partial 8/7/2024 8/7/2024 08/07/2024
Misc
Informational
07/29/2024
7-12-24 PS partial sidewalk inspection on public, north side of approach, forms in place and aggregate has been compacted, there is a comcast box within path of sidewalk that will need to be addressed as box not allowed in sidewalk. Contractor approved to pour partial 7-18-24 PS Partial sidewalk inspection from south side approach stopping at temp construction entry, forms in place, aggregate compacted, approved to pour partial 7-29-24 PS Partial sidewalk inspection public north side of approach at ADA ramp, comcast relocated box within sidewalk path, forms in place and aggregate compacted, approved to pour 8-7-24 Dustin A, Sw was called in for rest of sidewalk south from approach for the learning center going towards 150. Sw is formed and aggregate was compacted and slopes are in compliance. The aggregate was less then 1 inch thick in some areas and some areas was bare dirt. I talked to the contractor and they going to fix today and call me back to come look again.
Electrical Service Inspection Passed 8/7/2024 08/07/2024
Misc
Resolved
08/07/2024
Sidewalk Inspection Partial 8/7/2024 8/7/2024 08/07/2024
Misc
Informational
08/07/2024
7-12-24 PS partial sidewalk inspection on public, north side of approach, forms in place and aggregate has been compacted, there is a comcast box within path of sidewalk that will need to be addressed as box not allowed in sidewalk. Contractor approved to pour partial 7-18-24 PS Partial sidewalk inspection from south side approach stopping at temp construction entry, forms in place, aggregate compacted, approved to pour partial 7-29-24 PS Partial sidewalk inspection public north side of approach at ADA ramp, comcast relocated box within sidewalk path, forms in place and aggregate compacted, approved to pour 8-7-24 Dustin A, Sw was called in for rest of sidewalk south from approach for the learning center going towards 150. Sw is formed and aggregate was compacted and slopes are in compliance. The aggregate was less then 1 inch thick in some areas and some areas was bare dirt. I talked to the contractor and they going to fix today and call me back to come look again. 8-7-24 Dustin A, Contractor has dug out to get aggregate depth requirements. Rechecked slopes and aggregate compaction and both are to spec. Approved to pour
Occupancy Inspection - Planning Temporary C of O 8/9/2024 8/9/2024 08/08/2024
Corrective Action Required
08/08/2024
The parking lot lighting was not installed at the time of my inspection. Please install these per the approved plans.
Corrective Action Required
08/08/2024
Along the north property line (adjacent to the church driveway) there was a tree that was installed and appears to not have survived the transplanting processes. This is a required tree per the approved FDP landscaping plan. Please replace the tree with one that has not died.
Curb - Proof Roll Passed 8/9/2024 8/9/2024 08/09/2024
Misc
Informational
07/11/2024
6-5-24 PS Inspected proof roll for curb at parking lot, areas inspected approved for curb construction 6-20-24 PS Inspected proof roll for curb at parking lot road between lot and approach, areas inspected approved for curb construction 7-11-24 PS Inspected curb proof roll for approach, approved to proceed for approach pour
Pavement-Aggregate Base Passed 8/9/2024 8/9/2024 08/09/2024
Misc
Informational
06/19/2024
6-4-24 PS contractor installing geo grid on compacted subgrade, grid has appropriate lap between rolls P.M. geo grid installed through parking lot 6-5-24 PS Base aggregate placed and compacted through parking lot 6-19-24 PS contractor installed geo grid, placed aggregate and compacting at approach and road connecting to parking lot
Pavement-Curb Construction Passed 8/9/2024 8/9/2024 08/09/2024
Misc
Informational
06/21/2024
6-6-24 PS Contractor poured and set curb along parking lot stall perimeter; white cure applied 6-7-24 PS Contractor poured and set curb at remainder of curb along parking lot stall perimeter at islands 6-21-24 PS Crew setting forms for curb at parking lot and road that connects parking lot to approach curb. PM Crew poured curb at road that connects parking lot to approach
Pavement-Proof Roll Passed 8/9/2024 8/9/2024 08/09/2024
Misc
Informational
07/11/2024
5-31-24 PS Contractor performed proof roll of compacted subgrade prior to placement of geogrid and aggregate base at parking lot. Third party inspector was on site for test. There were couple of areas of concern but they have been addressed by contractor. 6-5-24 PS Inspected proof roll for surface at parking lot, areas inspected approved for surface asphalt construction 6-11-24 PS Inspected proof roll for surface at parking lot, this is same area inspected on 6-5. Rain over weekend required another proof roll. Areas inspected approved for surface construction 6-19-24 PS Inspected proof roll of compacted subgrade prior to placement of geogrid/aggregate at approach and road that connects to parking lot. Areas inspected approved for geogrid/aggregate placement 6-20-24 PS Inspected proof roll for asphalt surface at parking lot road between lot and approach, areas inspected approved for asphalt surface construction 7-11-24 PS Inspected proof roll for approach surface, approved to proceed with pour of approach
Pavement-Surface Passed 8/9/2024 8/9/2024 08/09/2024
Misc
Informational
07/11/2024
6-12-24 PS Contractor poured concrete pad in front of trash enclosure at lot 6-13-24 PS Contractor laid base asphalt throughout parking lot stall portion of lot per plan 6-14-24 PS Contractor laying surface layer asphalt throughout parking lot stall portion of lot. PM contractor completed surface layer asphalt at parking lot stall area of lot 6-25-24 PS Contractor laying base asphalt at road that connects approach to parking lot. PM Contractor completed surface asphalt at road that connects approach to parking lot 7-11-24 PS Contractor poured concrete for parking lot approach and curb
Sanitary Sewer Construction Inspection Passed 8/9/2024 8/9/2024 08/09/2024
Storm Sewer Construction Inspection Passed 8/9/2024 8/9/2024 08/09/2024
Misc
Informational
05/21/2024
4-4-24 PS Contractor excavating and placing storm line, nyloplast drain STA 4+82.80 moving towards 4+20.86 on storm line c 4-5-24 PS Contractor set storm line c nyloplast at C-7 STA 4+82.80, C-6 4+20.86, C-5 3+71.23, C-4 3+15.62 and set HDPE connecting 4-10-24 PS Contractor set nyloplast at line C, C-3, C-2 with HDPE to STA 0+85 4-11-24 PS Contractor set storm box C-1 at STA 0+79.45 and HDPE to box 4-16-24 PS Contractor excavating for private storm line A 4-17-24 PS Contractor placing aggregate and cutting back existing corrugated storm pipe from private road crossing for clean connection to junction with new HDPE storm line at line A, STA 5+38.27 4-19-24 PS Contractor installing storm, connection made at junction for HDPE to existing corrugated storm with HDPE set to approx 5+00 5-10-24 NS Contractor was planning on working on storm but from the time I was there they were just unloading materials. 5-16-24 PS Contractor excavating for storm line A and A-4 5-17-24 PS Contractor set inlet A-5 with HDPE on north side, contractor excavating from A-5 to A-4 public storm junction box 5-20-24 PS Contractor set junction box A-4 with HDPE connection from A-5 5-21-24 PS Contractor poured collars/inverts at storm box A-5 and C-1, collar poured on northside of junction box A-4
Water Line - Coliform Test 2 Passed 8/9/2024 8/9/2024 08/09/2024
Foundation Inspection - Commercial Passed 08/09/2024
Misc
Informational
02/27/2024
Perimeter okay
Underslab Electrical Inspection - Commercial Passed 08/09/2024
Misc
Informational
03/12/2024
03/12/24- under slab electrical in building okay to cover.
Underslab Plumbing Inspection - Commercial Passed 08/09/2024
Misc
Informational
03/12/2024
03/12/24-underslab plumbing in building completed and pressure tested.
Rough Framing Inspection - Commercial Passed 08/09/2024
THE FOLLOWING AREAS ARE APPROVED
Informational
05/08/2024
exterior walls sheathing interior walls truss hold downs and lateral bracing is to plans
Misc
Resolved
08/09/2024
-address over notched and cut studs in NW room (have engineer address)
Occupancy Inspection - Engineering Failed 8/9/2024 8/9/2024 08/09/2024
Misc
Corrective Action Required
08/09/2024
8-9-24 PS For TCO: - Modot approval required for removal of signal lights and turn lane on 150 from phase 1 of development until phase 2 Punch list items needed for C of O: - Vegetation required, 70% growth - complete all site grading - Mow grass/weeds along perimeter of 150 and provide erosion control, clean all mud from sidewalk along 150 and Arboridge Dr - Remove all dumpsters, porta johns, construction debris and trash, cones, net barricade, and sandbags along site, Arboridge Dr and center island at Arboridge - Fire Hydrant on Arboridge Dr that was relocated for road widening will need to be turned towards Arboidge Dr, C900 pipe for valve box will need to be cut to grade with top hat installed - Top head of private hydrant will need to be painted silver, not just the valve nut - New concrete installed at Arboridge on south side of approach has crack with separation that will need to be replaced. The section will need to be replaced joint to joint with monolithic curb to match existing Arboridge design - Chip out concrete and smooth inlet lip at storm box to prevent debris grabbing - Replace broken handle at backflow vault hatch lid, install ladder at backflow vault, pump out standing water and correct drainage issues so that vault will drain water - Cut off all metal lifting loops at box lids and grout lids
Sprinkler - Flow Test Passed 8/9/2024 08/09/2024
Alarm Test Passed 8/9/2024 08/09/2024
Occupancy Inspection - Fire Passed 8/9/2024 8/9/2024 08/09/2024
Occupancy Inspection - Planning Temporary C of O 08/09/2024
Corrective Action Required
08/09/2024
Along the north property line (adjacent to the church driveway) there was a tree that was installed and appears to not have survived the transplanting processes. This is a required tree per the approved FDP landscaping plan. Please replace the tree with one that has not died.
Occupancy Inspection - Codes Commercial Failed 8/9/2024 8/9/2024 08/09/2024
Misc
Corrective Action Required
08/09/2024
OKAY DELIVERIES AND PERMANENT FIXTURES -complete painting of gas line -outlets required in 25’ of RTU -label all RTU’s and fans -label hallways doors for electrical panels -GFCI protection for outlet near sink in SW most room -provide permanent address as discussed on site -address pending pier inspection -upload engineer report for trash enclosure footing -address all outstanding items from other department
Site Visit Partial 8/13/2024 8/13/2024 08/13/2024
Misc
Informational
08/06/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today 5-13-24 Dustin A, No activity today
Misc
Informational
08/06/2024
4-22-24 Dustin A, Contractor working on private water, Digging footings for vault. 6-27-24 PS No inspections for development today 6-28-24 PS No inspections for development today 7-2-24 PS No inspections for development today 7-9-24 PS Bair grading for sidewalks and street widening at arboridge 7-26-24 Dustin A, Dirt work being done along side 150 8-6-24 Dustin A, Sod crew working, prep work for the remainder of sidewalk to go in and light poles electrical being pulled 8-13-24 Dustin A, Nothing for us to look at, waiting on items on punch list to be corrected.
Site Visit Partial 8/14/2024 8/14/2024 08/14/2024
Misc
Informational
08/13/2024
1-11-24 PS No activity on site due to weather this week 1-17-24 PS No activity on site 2-2-24 PS No activity on site 2-21-24 PS Crews on site working on building footing 2-26-24 PS Crews on site working on building footings 2-27-24 PS Crew working on building footings 2-29-24 PS Crew working on building footings 3-4-24 PS Crew working on building footings 3-5-24 PS Made site visit, no inspections for development, plumbing contractor working on building underslab 3-6-24 PS No inspections for development today 3-12-24 PS No inspections for development, crews on site installing building underslab plumbing and electrical 3-20-24 PS No inspections for development today, crew poured building underslab yesterday 3/19 3-28-24 PS Crews on site working on building construction 4-2-24 PS No inspection for development today 5-13-24 Dustin A, No activity today
Misc
Informational
08/13/2024
4-22-24 Dustin A, Contractor working on private water, Digging footings for vault. 6-27-24 PS No inspections for development today 6-28-24 PS No inspections for development today 7-2-24 PS No inspections for development today 7-9-24 PS Bair grading for sidewalks and street widening at arboridge 7-26-24 Dustin A, Dirt work being done along side 150 8-6-24 Dustin A, Sod crew working, prep work for the remainder of sidewalk to go in and light poles electrical being pulled 8-13-24 Dustin A, Nothing for us to look at, waiting on items on punch list to be corrected. Talked with triston on erosion control and let him know sidewalk needed to be cleaned off
Erosion Control Inspection Failed 8/15/2024 8/15/2024 08/15/2024
Misc
Corrective Action Required
08/01/2024
8-15-24 PS Discussed erosion control with Brandon GC, overgrown vegetation addressed, lots have been hydro seeded, erosion control is being addressed within the next 2 business days for silt fence along 150 side and arboridge side. Silt fence required as grade is sloped towards sidewalk until vegetation is established. Sidewalk will be cleaned with silt fence install
Occupancy Inspection - Codes Commercial Ready for Temp CO 8/19/2024 08/19/2024
Misc
Corrective Action Required
08/09/2024
-outlets required in 25’ of RTU (outlets found not working) -address all outstanding items from other department
Occupancy Inspection - Engineering Temporary C of O 8/19/2024 8/19/2024 08/19/2024
Misc
Corrective Action Required
08/09/2024
8-19-24 PS Engineering approval for TCO, 30 day TCO Punch list items needed for C of O: - Vegetation required, 70% growth - complete all site grading - provide erosion control at 150 and arboridge, clean all mud from sidewalk along 150 and Arboridge Dr - Remove all dumpsters and construction debris - Fire Hydrant on Arboridge Dr that was relocated for road widening will need to be turned towards Arboidge Dr, C900 pipe for valve box will need to be cut to grade with top hat installed - Replace broken handle at backflow vault hatch lid - Cut off all metal lifting loops at box lids and grout lids
Occupancy Inspection - Engineering Temporary C of O 08/20/2024
Misc
Corrective Action Required
08/09/2024
8-9-24 PS For TCO: - Modot approval required for removal of signal lights and turn lane on 150 from phase 1 of development until phase 2 Punch list items needed for C of O: - Vegetation required, 70% growth - complete all site grading - Mow grass/weeds along perimeter of 150 and provide erosion control, clean all mud from sidewalk along 150 and Arboridge Dr - Remove all dumpsters, porta johns, construction debris and trash, cones, net barricade, and sandbags along site, Arboridge Dr and center island at Arboridge - Fire Hydrant on Arboridge Dr that was relocated for road widening will need to be turned towards Arboidge Dr, C900 pipe for valve box will need to be cut to grade with top hat installed - Top head of private hydrant will need to be painted silver, not just the valve nut - New concrete installed at Arboridge on south side of approach has crack with separation that will need to be replaced. The section will need to be replaced joint to joint with monolithic curb to match existing Arboridge design - Chip out concrete and smooth inlet lip at storm box to prevent debris grabbing - Replace broken handle at backflow vault hatch lid, install ladder at backflow vault, pump out standing water and correct drainage issues so that vault will drain water - Cut off all metal lifting loops at box lids and grout lids
Misc
Informational
08/23/2024
8-23-24 DP. Bair was onsite today working on the punch list items listed above. -They fixed the handle on the backflow vault hatch lid - They pumped the water out of the backflow vault -They installed a ladder in the backflow vault - Reddi Service was on site and performed the backflow test, which passed -They rotated 056-065, cut down the valve riser and installed a top hat -The dumpster and porta johns have been removed -They removed the gutter buddy and cleaned up the throat of the storm box across from the Holy Spirit Catholic Church Sign. - Grading on site has been completed. - The ESC company was onsite and completed Hydroseeding in the lot to the south of the Learning Experience building. - ESC measures have been installed around hydroseeded area
Erosion Control Inspection Partial 8/21/2024 8/21/2024 08/21/2024
Misc
Informational
08/21/2024
8-21-24 PS Contractor installed silt fence along south side of sit at 150 sidewalk and on east side of lot along arboridge.
Sidewalk Inspection Passed 8/28/2024 08/28/2024
Misc
Informational
08/07/2024
7-12-24 PS partial sidewalk inspection on public, north side of approach, forms in place and aggregate has been compacted, there is a comcast box within path of sidewalk that will need to be addressed as box not allowed in sidewalk. Contractor approved to pour partial 7-18-24 PS Partial sidewalk inspection from south side approach stopping at temp construction entry, forms in place, aggregate compacted, approved to pour partial 7-29-24 PS Partial sidewalk inspection public north side of approach at ADA ramp, comcast relocated box within sidewalk path, forms in place and aggregate compacted, approved to pour 8-7-24 Dustin A, Sw was called in for rest of sidewalk south from approach for the learning center going towards 150. Sw is formed and aggregate was compacted and slopes are in compliance. The aggregate was less then 1 inch thick in some areas and some areas was bare dirt. I talked to the contractor and they going to fix today and call me back to come look again. 8-7-24 Dustin A, Contractor has dug out to get aggregate depth requirements. Rechecked slopes and aggregate compaction and both are to spec. Approved to pour
Grading/Excavation/Fill Inspection Passed 8/28/2024 08/28/2024
Misc
Informational
08/01/2024
2-1-24 PS Scraper on site grading site 2-8-24 PS crew grading and excavating for building pad 2-9-24 PS Crew grading and excavating for building pad 2-13-24 PS Crews grading site and working on building pad/footings 2-20-24 PS Site crew working on site grading and building pad 7-22-24 PS Bair grading site 8-1-24 PS Site grading and hauling soil piles off site
ESC - (Vegetation/Ground Cover) Partial 8/28/2024 08/28/2024
Misc
Informational
08/28/2024
8-28-24 PS Contractor sodded Learning Experience lot, contractor hydro seeded the (2) adjoining lots. 70% vegetation growth required on seeded lots
Occupancy Inspection - Engineering Temporary C of O 8/28/2024 08/28/2024
Misc
Corrective Action Required
08/28/2024
Approved for TCO Punch list items needed for C of O: - Vegetation required, 70% growth required on seeded lots, maintain all erosion control methods until growth is established
Occupancy Inspection - Engineering Passed 9/4/2024 9/4/2024 09/04/2024
Misc
Corrective Action Required
08/28/2024
Approved for TCO Punch list items needed for C of O: - Vegetation required, 70% growth required on seeded lots, maintain all erosion control methods until growth is established 9-4-24 RH Approved for Final with Vegetation being completed. Will hold the public infrastructure permit open for the two lots to show 70% vegetation.
Occupancy Inspection - Planning Passed 9/4/2024 9/4/2024 09/04/2024
Above Ceiling Inspection Passed 09/04/2024
Misc
Resolved
09/04/2024
Still to inspect -hallway outside infant B room -staff toilet OKAY TO INSTALL CEILING TILE. LEAVE OUT WHERE STATED ABOVE
Gas Service Inspection - Commercial Passed 09/04/2024
Misc
Resolved
09/04/2024
Okay to release to spire -Secure gas line at roof top supports -paint exterior gas line
Underground Electrical Inspection - Commercial Passed 09/04/2024
Misc
Informational
05/14/2024
INSECTED TRENCH AND CONDUIT NORTH OF BUILDING 05/13/24- light pole conduit, and conduit on north side side of building 05/14/24- partial conduit for monument sign
Footing Inspection - Commercial Passed 09/04/2024
Misc
Informational
02/21/2024
Perimeter OK to pour Interior pads OK to pour Copper concrete encased electrode located on north wall east side
Piers/Caissons Inspection - Commercial Passed 09/04/2024
ESC - (Vegetation/Ground Cover) Passed 09/04/2024
Misc
Informational
08/28/2024
8-28-24 PS Contractor sodded Learning Experience lot, contractor hydro seeded the (2) adjoining lots. 70% vegetation growth required on seeded lots
Occupancy Inspection - Water Utilities Passed 8/9/2024 9/4/2024 09/04/2024
Occupancy Inspection - Codes Commercial Full C of O 9/4/2024 9/4/2024 09/04/2024
Misc
Resolved
09/04/2024
-outlets required in 25’ of RTU (outlets found not working) -address all outstanding items from other department
Documents & Images
Date Uploaded File Type Document Name
07/24/2023 Application Form APPLICATION
07/24/2023 Plans Civil Plans - Learning Experience Lee's Summit PERMIT 7-19-23
07/24/2023 Engineer Report/Study 220528 E Day Care Lee's Summit - Geotechnical Report
07/28/2023 Plans TLE Lee's Summit MO - permit set
08/04/2023 Letter DS P/R Corrections Document
08/21/2023 Letter August 17 - Building Plan Review
08/21/2023 Letter August 17 - Fire Plan Review
08/21/2023 Plans Revised Drawings
08/29/2023 Engineer Report/Study TLE Special Inspection Retention Letter
09/20/2023 Plans 00_ TLE Lees Summit - Combined
09/20/2023 Approved Plans Approve plan set
09/28/2023 Email health dept info
09/28/2023 Receipt Receipt for transaction: 2023-007389
10/30/2023 Letter License Tax Bill
11/27/2023 Approved Plans Approved FDP_11272023_Learning Experience_Arborwalk West
11/27/2023 Approved Plans Approved_Arborwalk West_Public Sanitary_11272023
11/27/2023 Approved Plans Approved_Arborwalk West_Public Street and Storm_11272023
12/05/2023 Receipt Receipt for transaction: 2023-008872
12/08/2023 Letter License Tax Bill
12/08/2023 Letter DS Building Permit
01/02/2024 Letter INSPECTION SUMMARY
01/04/2024 Letter INSPECTION SUMMARY
01/11/2024 Letter INSPECTION SUMMARY
01/17/2024 Letter INSPECTION SUMMARY
01/29/2024 Letter INSPECTION SUMMARY
02/01/2024 Letter INSPECTION SUMMARY
02/02/2024 Letter INSPECTION SUMMARY
02/07/2024 Letter INSPECTION SUMMARY
02/08/2024 Letter INSPECTION SUMMARY
02/09/2024 Letter INSPECTION SUMMARY
02/13/2024 Letter INSPECTION SUMMARY
02/20/2024 Letter INSPECTION SUMMARY
02/21/2024 Letter INSPECTION SUMMARY
02/21/2024 Letter INSPECTION SUMMARY
02/21/2024 Letter INSPECTION SUMMARY
02/26/2024 Letter INSPECTION SUMMARY
02/26/2024 Letter INSPECTION SUMMARY
02/27/2024 Letter INSPECTION SUMMARY
02/27/2024 Letter INSPECTION SUMMARY
02/29/2024 Letter INSPECTION SUMMARY
03/04/2024 Letter INSPECTION SUMMARY
03/05/2024 Letter INSPECTION SUMMARY
03/06/2024 Letter INSPECTION SUMMARY
03/08/2024 Letter INSPECTION SUMMARY
03/08/2024 Letter INSPECTION SUMMARY
03/12/2024 Letter INSPECTION SUMMARY
03/18/2024 Letter INSPECTION SUMMARY
03/20/2024 Letter INSPECTION SUMMARY
03/25/2024 Letter INSPECTION SUMMARY
03/28/2024 Letter INSPECTION SUMMARY
03/29/2024 Letter INSPECTION SUMMARY
03/29/2024 Letter INSPECTION SUMMARY
04/01/2024 Letter INSPECTION SUMMARY
04/02/2024 Letter INSPECTION SUMMARY
04/04/2024 Letter INSPECTION SUMMARY
04/05/2024 Letter INSPECTION SUMMARY
04/10/2024 Letter INSPECTION SUMMARY
04/11/2024 Letter INSPECTION SUMMARY
04/16/2024 Letter INSPECTION SUMMARY
04/17/2024 Letter INSPECTION SUMMARY
04/17/2024 Letter INSPECTION SUMMARY
04/19/2024 Letter INSPECTION SUMMARY
04/22/2024 Letter INSPECTION SUMMARY
04/23/2024 Letter INSPECTION SUMMARY
04/23/2024 Letter INSPECTION SUMMARY
04/24/2024 Letter INSPECTION SUMMARY
04/25/2024 Letter INSPECTION SUMMARY
04/25/2024 Letter INSPECTION SUMMARY
05/01/2024 Letter INSPECTION SUMMARY
05/01/2024 Letter INSPECTION SUMMARY
05/03/2024 Letter INSPECTION SUMMARY
05/03/2024 Letter INSPECTION SUMMARY
05/03/2024 Letter INSPECTION SUMMARY
05/06/2024 Letter INSPECTION SUMMARY
05/07/2024 Letter INSPECTION SUMMARY
05/08/2024 Letter INSPECTION SUMMARY
05/08/2024 Letter INSPECTION SUMMARY
05/08/2024 Letter INSPECTION SUMMARY
05/08/2024 Letter INSPECTION SUMMARY
05/08/2024 Letter INSPECTION SUMMARY
05/09/2024 Letter INSPECTION SUMMARY
05/13/2024 Letter INSPECTION SUMMARY
05/13/2024 Letter INSPECTION SUMMARY
05/13/2024 Letter INSPECTION SUMMARY
05/14/2024 Letter INSPECTION SUMMARY
05/14/2024 Letter INSPECTION SUMMARY
05/14/2024 Letter INSPECTION SUMMARY
05/14/2024 3HE0042_1 MB_Level_1_Simple 05 08 24 1635
05/14/2024 3HE0047_1 MB_Level_1_Simple 05 09 24 1646
05/14/2024 Letter INSPECTION SUMMARY
05/16/2024 Letter INSPECTION SUMMARY
05/17/2024 Letter INSPECTION SUMMARY
05/20/2024 Letter INSPECTION SUMMARY
05/20/2024 Letter INSPECTION SUMMARY
05/20/2024 Letter INSPECTION SUMMARY
05/21/2024 The Learning Experience-0000-Lees Summit-MO-FA-J02-0502024-FA-1 (36X48)-signed
05/21/2024 The Learning Experience-0000-Lees Summit-MO-FA-J02-05022024-SUBBOOK
05/21/2024 Letter INSPECTION SUMMARY
05/21/2024 Letter INSPECTION SUMMARY
05/23/2024 Letter INSPECTION SUMMARY
06/03/2024 Letter INSPECTION SUMMARY
06/03/2024 The Learning Experience-0000-Lees Summit-MO-FA-J02-0502024-FA-1 (36X48)-signed APPROVED
06/03/2024 Letter Fire (Alarm) Plan Review Notice
06/03/2024 Letter Fire (Alarm) Plan Review Notice
06/04/2024 Letter INSPECTION SUMMARY
06/04/2024 Letter INSPECTION SUMMARY
06/05/2024 Letter INSPECTION SUMMARY
06/05/2024 Letter INSPECTION SUMMARY
06/05/2024 Letter INSPECTION SUMMARY
06/05/2024 IMG_0108
06/07/2024 Letter INSPECTION SUMMARY
06/07/2024 Letter INSPECTION SUMMARY
06/07/2024 Letter INSPECTION SUMMARY
06/10/2024 3RD Party Insp Report RFI-#27--City-required-structural-approval_Response
06/11/2024 Letter INSPECTION SUMMARY
06/12/2024 Letter INSPECTION SUMMARY
06/12/2024 Letter INSPECTION SUMMARY
06/13/2024 Letter INSPECTION SUMMARY
06/13/2024 Letter INSPECTION SUMMARY
06/14/2024 Letter INSPECTION SUMMARY
06/14/2024 Letter INSPECTION SUMMARY
06/14/2024 Letter INSPECTION SUMMARY
06/19/2024 Letter INSPECTION SUMMARY
06/19/2024 Letter INSPECTION SUMMARY
06/20/2024 IMG_0122
06/20/2024 IMG_0126
06/20/2024 IMG_0123
06/20/2024 IMG_0124
06/20/2024 IMG_0125
06/20/2024 Letter INSPECTION SUMMARY
06/20/2024 Letter INSPECTION SUMMARY
06/21/2024 Letter INSPECTION SUMMARY
06/21/2024 Letter INSPECTION SUMMARY
06/21/2024 Letter INSPECTION SUMMARY
06/25/2024 Letter INSPECTION SUMMARY
06/25/2024 IMG_0127
06/25/2024 IMG_0128
06/25/2024 Letter INSPECTION SUMMARY
06/25/2024 Letter INSPECTION SUMMARY
06/27/2024 Letter INSPECTION SUMMARY
06/28/2024 Letter INSPECTION SUMMARY
07/01/2024 Letter INSPECTION SUMMARY
07/02/2024 Letter INSPECTION SUMMARY
07/03/2024 Letter INSPECTION SUMMARY
07/03/2024 Letter INSPECTION SUMMARY
07/09/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/12/2024 Letter INSPECTION SUMMARY
07/17/2024 Letter INSPECTION SUMMARY
07/17/2024 Letter INSPECTION SUMMARY
07/17/2024 Letter INSPECTION SUMMARY
07/17/2024 Letter INSPECTION SUMMARY
07/17/2024 Letter INSPECTION SUMMARY
07/17/2024 Letter INSPECTION SUMMARY
07/18/2024 Letter INSPECTION SUMMARY
07/18/2024 Letter INSPECTION SUMMARY
07/22/2024 Letter INSPECTION SUMMARY
07/26/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
08/01/2024 Letter INSPECTION SUMMARY
08/01/2024 Letter INSPECTION SUMMARY
08/06/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/08/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Receipt Receipt for transaction: 2024-006744
08/09/2024 Receipt Receipt for transaction: 2024-006745
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/13/2024 Letter INSPECTION SUMMARY
08/14/2024 Letter INSPECTION SUMMARY
08/15/2024 Light Pole Base Inspection Report
08/15/2024 2024-05-23 - 230502 - TLE - The Learning Experience - Reinforcing Steel Inspection (1)
08/15/2024 Letter INSPECTION SUMMARY
08/15/2024 Letter MoDOT Approval Memo_8.15.2024
08/16/2024 Engineer Report/Study Traffic Study Memo_Revised_Approved_08162024
08/16/2024 Letter MoDOT Approval Memo_Revised_08162024
08/19/2024 Letter INSPECTION SUMMARY
08/19/2024 Letter INSPECTION SUMMARY
08/19/2024 Certificate/License Codes Temporary Certificate of Occupancy
08/20/2024 Letter INSPECTION SUMMARY
08/21/2024 Letter INSPECTION SUMMARY
08/23/2024 Letter INSPECTION SUMMARY
08/26/2024 The Learning Experience BACKFLOW Test
08/28/2024 Letter INSPECTION SUMMARY
08/28/2024 Letter INSPECTION SUMMARY
08/28/2024 Letter INSPECTION SUMMARY
08/28/2024 Letter INSPECTION SUMMARY
09/03/2024 Certified_BacKflow_Testing_Inc_-_215503_1723813134__428da17b269949838a31506dd0d8cf2b[1]
09/04/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter Codes Final Certificate of Occupancy
09/04/2024 Letter Field Certificate of Occupancy
09/04/2024 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home