Review Type |
Outcome |
Est. Completion Date |
Completed |
Final Development Plan Review
|
Approved
|
10/26/2022
|
05/23/2022
|
|
Mike Weisenborn
|
|
|
Fire Plan Review
|
Approved
|
05/17/2022
|
05/12/2022
|
|
Jim Eden
|
|
Address numbers required
identification 2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm).
Action required- Provide tenant space identification o the front and rear doors.
|
|
Portable fire extinguishers - general
2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Action required- Provide a minimum of one 2A:10B:C fire extinguishers in each space. Verified at inspection.
|
|
Duct smoke detectors
2018 IFC 907.3.1 Duct smoke detectors. Smoke detectors installed in ducts shall be listed for the air velocity, temperature and humidity present in the duct. Duct smoke detectors shall be connected to the building's fire alarm control unit when a fire alarm system is rquired by Section 907.2. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location and shall perform the intended fire safety function in accordance with theis code and the International Mechanical Code. Duct smoke detectors shall not be used as a substitute for required open area detection.
Action required- Provide remote annunciation/test/reset switches for the duct detectors.
|
|
Miscellaneous Correction
Drawing A20 with information on the fire area separation wall was not provided.
|
|
|
Building Plan Review
|
Rejected
|
05/17/2022
|
05/12/2022
|
|
Joe Frogge
|
|
Final Development Plan
The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan.
Action required: Comment is for informational purposes.
5/12/2022 - not addressed
|
|
Engineered truss package
Corrective Action Required
Copies of the engineered truss package were not provided at the time of permit application.
Action required: Comment is for informational purposes. Package deferred per application form. Roof will not be inspected prior to receipt and approval of truss package.
5/12/2022 - not addressed
|
|
Miscellaneous Correction
Incomplete information.
Provide the following:
- Complete construction details for fire rated wall assembly. Must include nail/screw patterns and penetration designs.
- Light pole base detail. (Elec & Civil both defer to Structural but not found in S-series design)
|
|
IPC 708.1 Cleanouts required
2018 IPC 708.1 Cleanouts Required. Cleanouts shall be provided for drainage piping in accordance with Sections 708.1.1 through 708.1.11.
2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access.
Action required: Provide cleanouts near where waste piping exits foundation.
|
|
|
Licensed Contractors
|
Rejected
|
05/17/2022
|
05/12/2022
|
|
Joe Frogge
|
|
LC - General Contractor
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances.
Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address & phone number for the on-site contact which is where inspection reports will be sent.
5/12/2022 - not addressed
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
5/12/2022 - not addressed
|
|
|
Fire Plan Review
|
Rejected
|
04/26/2022
|
04/20/2022
|
|
Jim Eden
|
|
Address numbers required
Corrective Action Required
identification 2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm).
Action required- Provide tenant space identification o the front and rear doors.
|
|
Portable fire extinguishers - general
Corrective Action Required
2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Action required- Provide a minimum of one 2A:10B:C fire extinguishers in each space. Verified at inspection.
|
|
Duct smoke detectors
Corrective Action Required
2018 IFC 907.3.1 Duct smoke detectors. Smoke detectors installed in ducts shall be listed for the air velocity, temperature and humidity present in the duct. Duct smoke detectors shall be connected to the building's fire alarm control unit when a fire alarm system is rquired by Section 907.2. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location and shall perform the intended fire safety function in accordance with theis code and the International Mechanical Code. Duct smoke detectors shall not be used as a substitute for required open area detection.
Action required- Provide remote annunciation/test/reset switches for the duct detectors.
|
|
Miscellaneous Correction
Corrective Action Required
Drawing A20 with information on the fire area separation wall was not provided.
|
|
|
Building Plan Review
|
Rejected
|
04/26/2022
|
04/14/2022
|
|
Joe Frogge
|
|
Final Development Plan
Corrective Action Required
The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan.
Action required: Comment is for informational purposes.
|
|
Engineered truss package
Corrective Action Required
Copies of the engineered truss package were not provided at the time of permit application.
Action required: Comment is for informational purposes. Package deferred per application form. Roof will not be inspected prior to receipt and approval of truss package.
|
|
Miscellaneous Correction
Corrective Action Required
Incomplete information.
Provide the following:
- Complete construction details for fire rated wall assembly. Must include nail/screw patterns and penetration designs.
- Light pole base detail. (Elec & Civil both defer to Structural but not found in S-series design)
|
|
IPC 708.1 Cleanouts required
Corrective Action Required
2018 IPC 708.1 Cleanouts Required. Cleanouts shall be provided for drainage piping in accordance with Sections 708.1.1 through 708.1.11.
2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access.
Action required: Provide cleanouts near where waste piping exits foundation.
|
|
|
Licensed Contractors
|
Rejected
|
04/26/2022
|
04/14/2022
|
|
Joe Frogge
|
|
LC - General Contractor
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances.
Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address & phone number for the on-site contact which is where inspection reports will be sent.
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
|
|
|