Summary
PRCOM20221430
Building Permit - Commercial
Voided
NEW SHELL BUILDING
NEW SHELL FOR FUTURE RESTAURANT AND MEDICAL OFFICE
04/12/2022
10/18/2022
07/12/2022
Locations
Contacts
  
  
  
  
  
CLARKITECTURE, Address:7701 E KELLOGG DR, STE 630, Phone:(316) 302-4472  
Reviews
Review Type Outcome Est. Completion Date Completed
Final Development Plan Review Approved 10/26/2022 05/23/2022
Mike Weisenborn
Fire Plan Review Approved 05/17/2022 05/12/2022
Jim Eden
Address numbers required
Informational
05/12/2022

identification 2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). Action required- Provide tenant space identification o the front and rear doors.
Portable fire extinguishers - general
Informational
05/12/2022

2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. Action required- Provide a minimum of one 2A:10B:C fire extinguishers in each space. Verified at inspection.
Duct smoke detectors
Resolved
05/12/2022

2018 IFC 907.3.1 Duct smoke detectors. Smoke detectors installed in ducts shall be listed for the air velocity, temperature and humidity present in the duct. Duct smoke detectors shall be connected to the building's fire alarm control unit when a fire alarm system is rquired by Section 907.2. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location and shall perform the intended fire safety function in accordance with theis code and the International Mechanical Code. Duct smoke detectors shall not be used as a substitute for required open area detection. Action required- Provide remote annunciation/test/reset switches for the duct detectors.
Miscellaneous Correction
Resolved
05/12/2022

Drawing A20 with information on the fire area separation wall was not provided.
Building Plan Review Rejected 05/17/2022 05/12/2022
Joe Frogge
Final Development Plan
Resolved
06/07/2022

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 5/12/2022 - not addressed
Engineered truss package
Corrective Action Required
05/10/2022

Copies of the engineered truss package were not provided at the time of permit application. Action required: Comment is for informational purposes. Package deferred per application form. Roof will not be inspected prior to receipt and approval of truss package. 5/12/2022 - not addressed
Miscellaneous Correction
Resolved
05/12/2022

Incomplete information. Provide the following: - Complete construction details for fire rated wall assembly. Must include nail/screw patterns and penetration designs. - Light pole base detail. (Elec & Civil both defer to Structural but not found in S-series design)
IPC 708.1 Cleanouts required
Resolved
05/12/2022

2018 IPC 708.1 Cleanouts Required. Cleanouts shall be provided for drainage piping in accordance with Sections 708.1.1 through 708.1.11. 2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access. Action required: Provide cleanouts near where waste piping exits foundation.
Licensed Contractors Rejected 05/17/2022 05/12/2022
Joe Frogge
LC - General Contractor
Corrective Action Required
05/10/2022

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address & phone number for the on-site contact which is where inspection reports will be sent. 5/12/2022 - not addressed
LC - MEP Subs
Corrective Action Required
05/10/2022

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 5/12/2022 - not addressed
Fire Plan Review Rejected 04/26/2022 04/20/2022
Jim Eden
Address numbers required
Corrective Action Required
04/20/2022

identification 2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). Action required- Provide tenant space identification o the front and rear doors.
Portable fire extinguishers - general
Corrective Action Required
04/20/2022

2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. Action required- Provide a minimum of one 2A:10B:C fire extinguishers in each space. Verified at inspection.
Duct smoke detectors
Corrective Action Required
04/20/2022

2018 IFC 907.3.1 Duct smoke detectors. Smoke detectors installed in ducts shall be listed for the air velocity, temperature and humidity present in the duct. Duct smoke detectors shall be connected to the building's fire alarm control unit when a fire alarm system is rquired by Section 907.2. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location and shall perform the intended fire safety function in accordance with theis code and the International Mechanical Code. Duct smoke detectors shall not be used as a substitute for required open area detection. Action required- Provide remote annunciation/test/reset switches for the duct detectors.
Miscellaneous Correction
Corrective Action Required
04/20/2022

Drawing A20 with information on the fire area separation wall was not provided.
Building Plan Review Rejected 04/26/2022 04/14/2022
Joe Frogge
Final Development Plan
Corrective Action Required
04/14/2022

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Engineered truss package
Corrective Action Required
04/14/2022

Copies of the engineered truss package were not provided at the time of permit application. Action required: Comment is for informational purposes. Package deferred per application form. Roof will not be inspected prior to receipt and approval of truss package.
Miscellaneous Correction
Corrective Action Required
04/14/2022

Incomplete information. Provide the following: - Complete construction details for fire rated wall assembly. Must include nail/screw patterns and penetration designs. - Light pole base detail. (Elec & Civil both defer to Structural but not found in S-series design)
IPC 708.1 Cleanouts required
Corrective Action Required
04/14/2022

2018 IPC 708.1 Cleanouts Required. Cleanouts shall be provided for drainage piping in accordance with Sections 708.1.1 through 708.1.11. 2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access. Action required: Provide cleanouts near where waste piping exits foundation.
Licensed Contractors Rejected 04/26/2022 04/14/2022
Joe Frogge
LC - General Contractor
Corrective Action Required
04/14/2022

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address & phone number for the on-site contact which is where inspection reports will be sent.
LC - MEP Subs
Corrective Action Required
04/14/2022

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Inspections

There are no inspections for this permit application.

Documents & Images
Date Uploaded File Type Document Name
04/12/2022 Application Form Commercial Permit Application (original)_FLAT
04/12/2022 Plans ARCH PLANS 2022-04-12
04/12/2022 Plans CIVIL PLANS 2022-04-01
04/12/2022 Plans COVER SHEET 2022-04-12
04/12/2022 Plans ELEC PLANS 2022-04-08
04/12/2022 Plans MECH PLANS 2022-04-08
04/12/2022 Plans STRUCT PLANS 2022-04-05
04/12/2022 Engineer Report/Study 2220068 - Covenant Shell Building Structural Calculations
04/12/2022 Engineer Report/Study 22-5193 Summit Orchards Lot 4E Geotech Report
04/21/2022 Letter DS P/R Corrections Document
04/27/2022 Letter Fire Building Plan Review
05/06/2022 Drawing COVER SHEET 2022-05-05
05/06/2022 Plans ELEC PLANS 2022-05-05
05/06/2022 Plans MECH PLANS 2022-04-25
05/06/2022 Plans STRUCT PLANS 2022-04-29
05/06/2022 Plans ARCH PLANS 2022-05-05
05/13/2022 Letter DS P_R Corrections Document WITH RESPONSES
05/13/2022 Approved Plans Approved Building Plans
07/12/2022 RE_ 400 NW Chipman Rd
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home