Fire Plan Review
|
Approved with Conditions
|
03/18/2021
|
03/11/2021
|
|
Michael Weissenbach
|
|
Misc
(Action Required)
Provide a code analysis for this project. Please specify what the space is going to be used for.
3/03/21
Provide a code analysis and specify what the space is used for.
|
|
Address numbers required
Corrective Action Required
2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm).
(Verified At Inspection)
|
|
Portable fire extinguishers - conspicuous locations
Corrective Action Required
2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel.
(Verified At Inspection)
Provide one 2A10BC Fire Extinguisher
|
|
|
Building Plan Review
|
Approved
|
03/18/2021
|
03/11/2021
|
|
Joe Frogge
|
|
Code analysis required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Provide the following:
- code analysis (3/3/21 - not found in resubmittal)
- label use of each room (3/3/21 - not found in resubmittal)
|
|
|
Licensed Contractors
|
Approved
|
03/11/2021
|
03/11/2021
|
|
Joe Frogge
|
|
|
Fire Plan Review
|
Rejected
|
03/10/2021
|
03/03/2021
|
|
Michael Weissenbach
|
|
Misc
Corrective Action Required
(Action Required)
Provide a code analysis for this project. Please specify what the space is going to be used for.
3/03/21
Provide a code analysis and specify what the space is used for.
|
|
|
Building Plan Review
|
Rejected
|
03/10/2021
|
03/03/2021
|
|
Joe Frogge
|
|
Code analysis required
Corrective Action Required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Provide the following:
- code analysis (3/3/21 - not found in resubmittal)
- label use of each room (3/3/21 - not found in resubmittal)
|
|
Misc
A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Action required: Comment is for informational purposes.
|
|
|
Licensed Contractors
|
Approved
|
03/03/2021
|
03/03/2021
|
|
Joe Frogge
|
|
LC - MEP Subs
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. (Midwest Heating and Air & Intrepid Electric are not currently licensed here)
|
|
|
Licensed Contractors
|
Rejected
|
03/05/2021
|
03/01/2021
|
|
Joe Frogge
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. (Midwest Heating and Air & Intrepid Electric are not currently licensed here)
|
|
|
Building Plan Review
|
Rejected
|
03/05/2021
|
03/01/2021
|
|
Joe Frogge
|
|
Code analysis required
Corrective Action Required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Provide the following:
- code analysis
- label use of each room
|
|
Misc
Corrective Action Required
A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Action required: Comment is for informational purposes.
|
|
|
Fire Plan Review
|
Rejected
|
03/05/2021
|
02/23/2021
|
|
Michael Weissenbach
|
|
Misc
Corrective Action Required
(Action Required)
Provide a code analysis for this project. Please specify what the space is going to be used for.
|
|
|