Review Type |
Outcome |
Est. Completion Date |
Completed |
Planning Review
|
No Comments
|
04/28/2025
|
04/22/2025
|
|
Claire Byers
|
|
|
Engineering Review
|
Approved with Conditions
|
04/28/2025
|
04/22/2025
|
|
Susan Nelson, P.E.
|
|
DE C&O #01 Eng Plans – FDP/PDP
Corrective Action Required
All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final development plan. All public infrastructure must be substantially complete, prior to the issuance of any certificates of occupancy.
|
|
DE C&O #03 Eng & Insp Fees
Corrective Action Required
All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $2,350.41
|
|
|
Engineering Review
|
Corrections
|
04/04/2025
|
04/04/2025
|
|
Susan Nelson, P.E.
|
|
Corrective Action Required
Submit an Engineer's Estimate of Probable Construction Costs. The submitted estimate will not satisfy the requirements of the Unified Development Ordinance (Section 3.415) for the required documentation to calculate the Engineering Plan Review and Inspection Fee. This must be an itemized list of unit prices and quantities that includes all materials, labor, equipment and incidental work necessary to complete the entire project. Please resubmit an appropriate signed and sealed estimate.
|
|
Corrective Action Required
Submit signed and sealed plans that do not say Preliminary – Not For Construction.
|
|
Corrective Action Required
Add a note stating: “All construction shall follow the City of Lee's Summit Design and Construction Manual as adopted by Ordinance 5813. Where discrepancies exist between these plans and the Design and Construction Manual, the Design and Construction Manual shall prevail."
|
|
Corrective Action Required
Add a note stating: “The contractor shall contact the City’s Development Services Engineering Inspection to schedule a pre-construction meeting with a Field Engineering Inspector prior to any land disturbance work at (816) 969-1200.”
|
|
Corrective Action Required
Show existing utilities on the overall site plan. Address the plan for relocation of existing utility conflicts with the proposed and future building expansion.
|
|
Corrective Action Required
Please provide a graphic and notes showing the compacted aggregate base to be extended a minimum of 12 inches beyond the back of curb. The City standard detail does not show this, so provide either a standalone curb detail or add the curb detail to the typical pavement section.
|
|
|
Traffic Review
|
No Comments
|
04/04/2025
|
04/03/2025
|
|
Erin Ralovo
|
|
|
Building Codes Review
|
No Comments
|
04/04/2025
|
04/03/2025
|
|
Joe Frogge
|
|
|
Fire Review
|
Approved with Conditions
|
04/04/2025
|
04/03/2025
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Planning Review
|
Corrections
|
04/04/2025
|
03/26/2025
|
|
Claire Byers
|
|
Corrective Action Required
If northern parking expansion is part of this FDP approval scope, provide relocated light pole location(key note 3 of overall site plan sheet 01c101).
|
|
Corrective Action Required
Show where the 3 trees will be relocated as part of building expansion (key note 6 of sheet 01C101).
|
|
|