Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
12/13/2024
|
12/12/2024
|
|
Sue Pyles, P.E.
|
|
DE Commercial Detention Basin
Corrective Action Required
The applicant shall submit and the City shall accept an “As-built / As-graded” detention basin plan and BMP O&M Manual prior to issuance of any occupancy permit for the proposed development.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $500,471.55
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Building Codes Review
|
Approved with Conditions
|
12/13/2024
|
12/11/2024
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Architectural plans are not part of this process. We will review them after the building permit submission.
Action required: Comment is informational.
9/20/2024 - acknowledged in letter
|
|
Miscellaneous Correction
Provide retaining wall designs.
9/20/2024 - Unable to locate in submittal.
|
|
Miscellaneous Correction
Specify type/size of all water service connections.
9/20/2024 - Type of connection not provided.
|
|
Miscellaneous Correction
Specify locations, types, size, etc. for water meters.
**
Notes:
- Meters larger than 2" require custom designed pits.
- Water meter detail shown is for maximum 2" meter.
- Water Department dictates size and material of all piping from main to 10' past meter.
9/20/2024 - Water pipe from main to meter and then minimum 10' past meter is required to be 2"
|
|
|
Fire Review
|
Approved with Conditions
|
12/13/2024
|
12/09/2024
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Water Supply
Corrective Action Required
IFC 507.1 - An approved water supply capable of supplying the required fire flow for fire protection shall be provided to premises upon which facilities, buildings or portions of buildings are hereafter constructed or moved into or within the jurisdiction.
Confirm construction type. The fire model must provide the needed fire flow required by IFC Table B105.1(2), with 50% reduction for a sprinkler system for either a VA or VB building? Calculated on the largest building at 79, 582 sq. ft.
12/9/2025- V-A Construction acknowledged along with 2,500GPM fire flow.
|
|
|
Engineering Review
|
Corrections
|
11/19/2024
|
11/18/2024
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Sanitary sewer service line connection to an existing main must be made with a cut-in wye. Please label the connections for Buildings 1, 3, and 5 accordingly.
|
|
Corrective Action Required
As shown, the detention basin extends into the public easement located to the west. Moving the proposed water main removed that issue, but the basin still encroaches into the public easement around the sanitary sewer main.
|
|
Corrective Action Required
The ESC plans don’t include a sediment basin. This site would seem to need one to adequately control sediment leaving the site. We typically see the detention basin being used as a temporary sediment basin since it’s normally located in the lowest area. Please either add or explain. If added, be sure to include all appropriate standard details.
|
|
Corrective Action Required
Please remove City Standard Details GEN-5, GEN-6, and SAN-4 as they aren’t used in this project.
|
|
Corrective Action Required
Please add all City Standard Water Details.
|
|
Corrective Action Required
Provide a backfill detail.
|
|
|
Planning Review
|
No Comments
|
11/12/2024
|
11/13/2024
|
|
Adair Bright
|
|
|
Fire Review
|
Corrections
|
11/12/2024
|
11/07/2024
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Water Supply
Corrective Action Required
IFC 507.1 - An approved water supply capable of supplying the required fire flow for fire protection shall be provided to premises upon which facilities, buildings or portions of buildings are hereafter constructed or moved into or within the jurisdiction.
Confirm construction type. The fire model must provide the needed fire flow required by IFC Table B105.1(2), with 50% reduction for a sprinkler system for either a VA or VB building? Calculated on the largest building at 79, 582 sq. ft.
|
|
|
Building Codes Review
|
Corrections
|
11/12/2024
|
11/05/2024
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Architectural plans are not part of this process. We will review them after the building permit submission.
Action required: Comment is informational.
9/20/2024 - acknowledged in letter
|
|
Miscellaneous Correction
Corrective Action Required
Provide retaining wall designs.
9/20/2024 - Unable to locate in submittal.
|
|
Miscellaneous Correction
Corrective Action Required
Specify type/size of all water service connections.
9/20/2024 - Type of connection not provided.
|
|
Miscellaneous Correction
Corrective Action Required
Specify locations, types, size, etc. for water meters.
**
Notes:
- Meters larger than 2" require custom designed pits.
- Water meter detail shown is for maximum 2" meter.
- Water Department dictates size and material of all piping from main to 10' past meter.
9/20/2024 - Water pipe from main to meter and then minimum 10' past meter is required to be 2"
|
|
|
Planning Review
|
Corrections
|
10/01/2024
|
10/01/2024
|
|
Adair Bright
|
|
Corrective Action Required
Sheet C02 - remove the boundary of the previously vacated right-of-way.
|
|
Corrective Action Required
Sheet C04 - update the spelling of "ratio" and change "proposed zoning" to "existing zoning."
|
|
Corrective Action Required
Sheets C11, C12, and C13 - Provide setbacks to the parking lot from the applicable property lines.
|
|
Corrective Action Required
Sheet C13 - setback for building 7 should be measured to the closest point.
|
|
Corrective Action Required
Update the landscaping count - the open yard area includes the detention area for the tree requirement.
The latest revisions updated the count for shrubs but not for trees.
|
|
Corrective Action Required
Sheet L1.00 - provide greater contrast between the tree symbols and the lawn so staff can confirm the landscaping requirements are being met.
|
|
Corrective Action Required
The total percentage of open space needs to be stated. If it is already on the plan set, please let me know where.
|
|
Corrective Action Required
Photometric - confirm the concrete base/pedestal height.
|
|
Corrective Action Required
Photometric - show the perimeter area (100-ft. inset from the property lines).
|
|
Corrective Action Required
Sheet C06 - there is a building setback line called out at 18.9', but then the dimensioned setback is at 20.1' and they appear to be at the same location. Remove any unnecessary dimensions and verify setbacks.
|
|
Corrective Action Required
Provide setbacks to the buildings as well as the balconies.
|
|
Corrective Action Required
Many of the parking stall dimensions include the curb and gutter which we do not allow per Section 8.620 (https://library.municode.com/mo/lee's_summit/codes/unified_development_ordinance?nodeId=ART8SIST_DIVIIPA_S8.620PALODE). The project was previously approved a modification to allow 157 compact spaces, any additional spaces that do not meet the required 9' in width by 19' in length must either be removed or the site needs to be adjust to meet that requirement without including any of the curb.
|
|
|
Engineering Review
|
Corrections
|
10/01/2024
|
10/01/2024
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
General:
• These comments are in addition to, or sometimes a repeat of, our phone discussion last week.
• Please note that complete review of the grading and storm sewer system has not been completed. This will be done when the plans are more legible.
• Please include a roof drain plan and profiles for all pipes greater than 6” diameter.
|
|
Corrective Action Required
Sheet C03: As previously requested:
• As discussed, please look to ways to make the plans easier to read. As is, many sheets are very difficult to read.
• Please refer to Development Services, 816-969-1200, and not Public Works in Layout & Paving Note 6.
• Please refer to City of Lee's Summit and not Board of Public Utilities in Site Utility Note 6.
• Please refer to Design and Construction Manual and not Technical Provisions & Standard Drawings for Roads and Sewers in General Note 1 and Erosion Control Notes 1 & 2.
|
|
Corrective Action Required
Sheet C04:
• Please make a “typical” label for the proposed public water and sanitary sewer mains and refer to them as public and by others, or similar. There can just be 1 or 2 labels shown as typical.
• Please coordinate the proposed public sanitary layout with different sheets in this plan set so they all show the same information.
• Please show construction of the drive approaches and associated ADA ramps with this plan set.
• There appears to be missing linework on the fire line to the proposed hydrant just east of Bldg. 1.
• The City requires water meters to be located in grass rather than paved areas, including sidewalk. All meter locations seem to be shown in paved areas. Please revise.
• The public sanitary sewer shall terminate at Lot 3. Any line upstream of that will be private.
• As stated in the previous comment letter, sanitary sewer service lines can’t connect directly to MHs. Please revise as needed.
• As discussed, the detention basin must not extend into any public easement. Please revise.
• Please clarify existing easements, proposed easements, and easements to be vacated. This may be done on a separate document.
|
|
Corrective Action Required
Sheet C10: Please dimension the distance from the 100-yr WSE to the property line on this sheet and all other appropriate sheets.
|
|
Corrective Action Required
Sheet C14: Pavement design is a requirement of plan approval. An alternate pavement design after permit issuance can be requested. Depending on the change, a waiver from the City Engineer may be required.
|
|
Corrective Action Required
Sheet C21:
• It would appear that rip-rap or other energy dissipation will be necessary at the end sections entering the detention basins. Please evaluate and revise as accordingly.
• It appears that the water will pond at the end sections. Please evaluate and revise as necessary.
|
|
Corrective Action Required
Sheets C25-C28:
• The City’s design requirements for ADA-accessible ramps is 1.5% maximum cross-slope and 7.5% maximum longitudinal slope. This allows a construction tolerance. Please revise as needed.
• Please ensure all crosswalk slopes are visible.
|
|
Corrective Action Required
Sheet C31: Please review all of the structure and drainage area callouts. Some are missing, some are incorrect. Please revise as necessary.
|
|
Corrective Action Required
Sheets C33-C35:
• Please include the design HGL in Profile view.
• Please include the station in the 2End callout in Plan view.
• Please extend the Plan view to include Structure 2I.
• Please include information for the FES and Structure 2E in Profile view.
• The drop thru Structure 3A does not meet the minimum 0.5’ drop required.
|
|
Corrective Action Required
Sheet C36:
• Show and label the limits of the emergency spillway.
• As discussed, the detention basin must not extend into any public easement. Please revise.
|
|
Corrective Action Required
Sheet C37: Provide pipe profiles for the 8” water line.
|
|
Corrective Action Required
Sheets C53-C55:
• Provide a backfill detail.
• Only include standard details that pertain to the work included in this plan set.
|
|
|
Traffic Review
|
No Comments
|
10/01/2024
|
09/27/2024
|
|
Erin Ralovo
|
|
|
Building Codes Review
|
Corrections
|
09/24/2024
|
09/20/2024
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Architectural plans are not part of this process. We will review them after the building permit submission.
Action required: Comment is informational.
9/20/2024 - acknowledged in letter
|
|
Miscellaneous Correction
Corrective Action Required
Provide retaining wall designs.
9/20/2024 - Unable to locate in submittal.
|
|
Miscellaneous Correction
Corrective Action Required
Specify type/size of all water service connections.
9/20/2024 - Type of connection not provided.
|
|
Miscellaneous Correction
Corrective Action Required
Specify locations, types, size, etc. for water meters.
**
Notes:
- Meters larger than 2" require custom designed pits.
- Water meter detail shown is for maximum 2" meter.
- Water Department dictates size and material of all piping from main to 10' past meter.
9/20/2024 - Water pipe from main to meter and then minimum 10' past meter is required to be 2"
|
|
Miscellaneous Correction
Specify size and material for all waste services to buildings.
|
|
Miscellaneous Correction
Provide cleanouts near where the waste piping exits each building.
|
|
|
Fire Review
|
Corrections
|
09/24/2024
|
09/18/2024
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
FDC
Corrective Action Required
IFC 903.3.7 - Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official.
Locate FDC outside the fenced area and within 100 feet of a hydrant (near the location of where the fire main enters the building would work).
|
|
Water Supply
Corrective Action Required
IFC 507.1 - An approved water supply capable of supplying the required fire flow for fire protection shall be provided to premises upon which facilities, buildings or portions of buildings are hereafter constructed or moved into or within the jurisdiction.
Work with Water Utilities to provide a water model and confirm that adequate fire flow is provided based on construction type and square footage per IFC Table B105.1(2). Local amendment allows for only a 50% reduction in fire flow for a sprinkler system.
Provide information for fire flow.
|
|
Miscellaneous Correction
Vertical combustible construction is not allowed until hydrants and a base of asphalt for access roads and parking lots are in place.
|
|
Fire Lanes - Marking
IFC 503.3 - Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Mark alaong the west entrances. Acknowledged
|
|
Misc.
Corrective Action Required
Show fire lane turning movement in front of Building 6.
|
|
Miscellaneous Correction
All hydrant mains shall be 6". (Meet City design standards)
|
|
|
Engineering Review
|
Corrections
|
09/03/2024
|
09/04/2024
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
General:
• Submit an Engineer's Estimate of Probable Construction Costs.
• Submit the SWPPP and a copy of the MDNR Land Disturbance Permit.
• Please review the plans for clarity. There are many line weights, labels, text overlapping, and text box masking of information that make portions of the plans unreadable. There is also extraneous information that is crowding the page. For instance, there is survey information and shading that doesn’t need to be on every sheet. It all makes the plans very hard to read.
• Show and label all existing sidewalks, including widths.
|
|
Corrective Action Required
Sheet C01: Please show location of all oil/gas wells, or indicate none are present, and cite the source.
|
|
Corrective Action Required
Sheet C02: The vacated Sloan Street ROW is shown, but isn’t an existing condition.
|
|
Corrective Action Required
Sheet C03:
• Please replace Layout & Paving Note 5 with “The contractor shall contact the City’s Development Services Engineering Inspection to schedule an inspection coordination meeting with a Field Engineering Inspector prior to any land disturbance work at (816) 969-1200.”
• Do the Wetland Notes apply to this project? If not, please remove.
• Please revise Grading Note 5, and Site Utility Notes 6 & 17 to reference the correct location.
• Grading Note 8 and Earthwork Note 8 contradict each other. Please coordinate.
• Grading Note 10 and General Note 11 are incorrect. All work within the right-of-way associated with this project is included in the site permit. It would not require a separate permit.
• Please revise Site Utility Note 14, 8” and larger does not require ductile iron pipe. Please see Design and Construction manual Section 3901.B.1. C900 is preferred over DIP.
• The Design and Construction Manual has separation requirements, but does not always require a change in pipe material. Please note that the City does not prefer the use of DIP in general.
• Please refer to the Design and Construction Manual as the reference specification for Lee’s Summit in General Note 1 and Erosion Control Notes 1 & 2.
• Please revise “2012” to “2018” in General Note 20.
• Please revise “Public Works” with “Development services” in Erosion Control Note 21.
|
|
Corrective Action Required
Sheet C04:
• Please show and label existing and proposed utility easements on this sheet and throughout the plan set.
• Please clearly delineate public utilities not included in this plan set vs private utilities which are included on this sheet and throughout the plan set.
• Please include a legend that includes all shading and hatching on this sheet and throughout the plan set as necessary.
|
|
Corrective Action Required
Sheet C05: Please remove the vacated Sloan Street right-of-way from this sheet and throughout the plan set.
|
|
Corrective Action Required
Sheet C10: Please show and label the 100-year WSE and dimension to adjacent buildings and property lines.
|
|
Corrective Action Required
Sheet C14:
• Please reference KCMMB for both concrete and asphalt in the pavement sections.
• Please note that pavement sections are required to be included within the plan set. All pavement design must meet or exceed City requirements.
• Please show the entrance approaches as concrete.
|
|
Corrective Action Required
Sheets C25-C28: Please provide some sort of call-out or method to locate each of the ramps. A complete review will be done once that is provided.
|
|
Corrective Action Required
Sheets C33-C35:
• The City’s compacted fill requirement extends to 18” above the top of pipe. It’s fine to require more than the City does, just wanted you to be aware.
• Please label structure 1G in Plan view.
• Structures 3A, 5A, 5B require 0.5’ drop. Please revise.
• Please move the detention basin outlet structure information to a separate Detention Basin sheet. Include the plan view of the basin, as well as a Profile for the outlet pipe. Include the basin volume required as well as the volume as designed. On Plan view, include the emergency spillway location, elevation, and length.
|
|
Corrective Action Required
Sheet C36:
• Please label water meter sizes. Water meters are not combined in the backflow vault.
• Please clarify, are there water meters for each building or one main meter?
• Service connections to the public main can only be made with a wye connection, not a connection to a MH. Please revise as needed.
|
|
Corrective Action Required
Sheets C39-C47:
• The method of draining the backflow vault sump shall be shown. This can be accomplished by daylighting with a small diameter pipe or connecting to a storm structure. Each option could be done with or without a sump pump, depending on grades. Please evaluate and revise as appropriate.
• Provide sanitary sewer service line flowline elevation at buildings.
|
|
|
Traffic Review
|
Corrections
|
09/03/2024
|
09/03/2024
|
|
Erin Ralovo
|
|
Corrective Action Required
Grading plans show a marked crosswalk across the driveways, however they are not shown anywhere else on the site plans. Staff does not feel a marked crosswalk is needed and they should be removed.
|
|
|
Planning Review
|
Corrections
|
09/03/2024
|
09/03/2024
|
|
Adair Bright
|
|
Corrective Action Required
The landscaping open yard requirements shall include the detention area; therefore, you will be required to increase the amount of plantings.
|
|
Corrective Action Required
On Sheet C04, include the adjacent property information.
|
|
Corrective Action Required
Provide a retaining wall detail and a fence detail for the dog park.
|
|
Corrective Action Required
Provide a setbacks to the parking lot from all applicable property lines.
|
|
Corrective Action Required
Identify, label, and dimension sight triangles.
|
|
Corrective Action Required
The monument sign will require a separate sign permit and review - just a heads up.
|
|
Corrective Action Required
|
|
Corrective Action Required
The photometric plan shall include footcandle measurements over the entire property.
|
|
Corrective Action Required
On the photometric plan - please confirm the height to the top of the light fixture from grade.
|
|
Corrective Action Required
The elevations shall include a dashed line indicating the height of the roof-mounted equipment.
|
|
Corrective Action Required
Confirm that in areas where the roof/parapet height varies the roof-mounted equipment will be screen on all sides.
|
|
|
Building Codes Review
|
Corrections
|
09/03/2024
|
08/29/2024
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Architectural plans are not part of this process. We will review them after the building permit submission.
Action required: Comment is informational.
|
|
Miscellaneous Correction
Corrective Action Required
Provide retaining wall designs.
|
|
Miscellaneous Correction
Corrective Action Required
Specify type/size of all water service connections.
|
|
Miscellaneous Correction
Corrective Action Required
Specify locations, types, size, etc. for water meters.
**
Notes:
- Meters larger than 2" require custom designed pits.
- Water meter detail shown is for maximum 2" meter.
- Water Department dictates size and material of all piping from main to 10' past meter.
|
|
Miscellaneous Correction
Corrective Action Required
Specify size and material for all waste services to buildings.
|
|
Miscellaneous Correction
Corrective Action Required
Provide cleanouts near where the waste piping exits each building.
|
|
|
Fire Review
|
Corrections
|
09/03/2024
|
08/21/2024
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
FDC
Corrective Action Required
IFC 903.3.7 - Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official.
FDC not shown on the clubhouse.
|
|
Water Supply
Corrective Action Required
IFC 507.1 - An approved water supply capable of supplying the required fire flow for fire protection shall be provided to premises upon which facilities, buildings or portions of buildings are hereafter constructed or moved into or within the jurisdiction.
Work with Water Utilities to provide a water model and confirm that adequate fire flow is provided based on construction type and square footage per IFC Table B105.1(2). Local amendment allows for only a 50% reduction in fire flow for a sprinkler system.
|
|
Miscellaneous Correction
Vertical combustible construction is not allowed until hydrants and a base of asphalt for access roads and parking lots are in place.
|
|
Fire Lanes - Marking
Corrective Action Required
IFC 503.3 - Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Mark along the west entrances
|
|
Misc.
Corrective Action Required
Show fire lane turning movement in front of Building
|
|
Miscellaneous Correction
Corrective Action Required
All hydrant mains shall be 6". (Meet City design standards)
|
|
|