Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
No Comments
|
11/27/2024
|
11/25/2024
|
|
Susan Nelson, P.E.
|
|
DE C&O #01 Eng Plans – FDP/PDP
Corrective Action Required
All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final development plan. All public infrastructure must be substantially complete, prior to the issuance of any certificates of occupancy.
|
|
DE C&O #03 Eng & Insp Fees
Corrective Action Required
All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $29,897.17
|
|
|
Planning Review
|
No Comments
|
11/27/2024
|
11/25/2024
|
|
Hector Soto Jr.
|
|
|
Engineering Review
|
Approved with Conditions
|
09/18/2024
|
09/13/2024
|
|
Susan Nelson, P.E.
|
|
DE C&O #01 Eng Plans – FDP/PDP
Corrective Action Required
All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final development plan. All public infrastructure must be substantially complete, prior to the issuance of any certificates of occupancy.
|
|
DE C&O #03 Eng & Insp Fees
Corrective Action Required
All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $29,897.17
|
|
|
Planning Review
|
No Comments
|
09/18/2024
|
09/11/2024
|
|
Mike Weisenborn
|
|
|
Traffic Review
|
No Comments
|
09/18/2024
|
09/11/2024
|
|
Mike Weisenborn
|
|
|
Building Codes Review
|
Approved with Conditions
|
09/18/2024
|
09/11/2024
|
|
Mike Weisenborn
|
|
Miscellaneous Correction
Corrective Action Required
Architectural design package used as a reference but has not been evaluated for compliance.
|
|
|
Fire Review
|
Approved with Conditions
|
09/18/2024
|
09/11/2024
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Engineering Review
|
Corrections
|
08/19/2024
|
08/13/2024
|
|
Sue Pyles, P.E.
|
|
|
Building Codes Review
|
Approved with Conditions
|
08/19/2024
|
08/12/2024
|
|
Mike Weisenborn
|
|
Miscellaneous Correction
Corrective Action Required
Architectural design package used as a reference but has not been evaluated for compliance.
|
|
|
Fire Review
|
Approved with Conditions
|
08/19/2024
|
08/12/2024
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Traffic Review
|
No Comments
|
08/19/2024
|
08/12/2024
|
|
Mike Weisenborn
|
|
|
Planning Review
|
No Comments
|
08/19/2024
|
08/12/2024
|
|
Mike Weisenborn
|
|
|
Planning Review
|
No Comments
|
06/27/2024
|
06/27/2024
|
|
Hector Soto Jr.
|
|
|
Engineering Review
|
Corrections
|
06/27/2024
|
06/25/2024
|
|
Susan Nelson, P.E.
|
|
Corrective Action Required
The submitted estimate will not satisfy the requirements of the Unified Development Ordinance (Section 3.415) for the required documentation to calculate the Engineering Plan Review and Inspection Fee. This must be an itemized list of unit prices and quantities that includes all materials, labor, equipment and incidental work necessary to complete the entire project. Please resubmit an appropriate signed and sealed estimate.
|
|
|
Traffic Review
|
No Comments
|
06/27/2024
|
06/20/2024
|
|
Mike Weisenborn
|
|
|
Building Codes Review
|
Approved with Conditions
|
06/27/2024
|
06/20/2024
|
|
Mike Weisenborn
|
|
Miscellaneous Correction
Corrective Action Required
Architectural design package used as a reference but has not been evaluated for compliance.
|
|
|
Fire Review
|
Approved with Conditions
|
06/27/2024
|
06/20/2024
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Traffic Review
|
No Comments
|
05/29/2024
|
05/28/2024
|
|
Erin Ralovo
|
|
|
Fire Review
|
Approved with Conditions
|
05/29/2024
|
05/28/2024
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Engineering Review
|
Corrections
|
05/29/2024
|
05/24/2024
|
|
Susan Nelson, P.E.
|
|
Corrective Action Required
The submitted estimate will not satisfy the requirements of the Unified Development Ordinance (Section 3.415) for the required documentation to calculate the Engineering Plan Review and Inspection Fee. This must be an itemized list of unit prices and quantities that includes all materials, labor, equipment and incidental work necessary to complete the entire project. Please resubmit the signed and sealed estimate.
|
|
Corrective Action Required
Sheet C001 Paving Note 22 has a typographical error in the callout for the KCMMB concrete material.
|
|
|
Planning Review
|
Corrections
|
05/29/2024
|
05/21/2024
|
|
Hector Soto Jr.
|
|
Corrective Action Required
MECHANICAL SCREENING. Sheets A201 (Exterior Elevations) and A506 (Electric Panel Details) appear to show that the proposed parapets are of adequate height to comply with the City ordinance requiring all RTUs to be fully screened from view on all sides via the use of parapets extended to a height at least equal to the heights of the units being screened. Please confirm that the depicted height and screening takes into account any additional height added to the units from any curb or like structure on which the RTUs will sit.
The response from Kimley-Horn to the previously made comment above is to see the response from Rogue Architects dated May 4, 2024. No such response has been received/uploaded into our system as part of the subject application.
|
|
Corrective Action Required
CROSS ACCESS AND CROSS PARKING. Fill in the blank dates and missing recording information (i.e. the instrument #) in the Cross Access and Cross Parking Note provided on Sheet C200.
|
|
|
Building Codes Review
|
Approved with Conditions
|
05/29/2024
|
05/21/2024
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Architectural design package used as a reference but has not been evaluated for compliance.
|
|
Miscellaneous Correction
Provide complete light pole base detail. (noted as ref: structural but not found in submittals.)
|
|
|
Engineering Review
|
Corrections
|
04/26/2024
|
04/26/2024
|
|
Susan Nelson, P.E.
|
|
Corrective Action Required
Submit an Engineer's Estimate of Probable Construction Costs.
|
|
Corrective Action Required
Submit the SWPPP and a copy of the MDNR Land Disturbance Permit.
|
|
Corrective Action Required
Please be advised that there are updated plans for the public sanitary sewer extension. The public sanitary sewer and associated sewer easement extend further into this lot than shown. The manhole and lateral stub locations have changed to accommodate the appropriate connection to the public sanitary sewer. Revise your development plans accordingly.
|
|
Corrective Action Required
Label the existing sanitary sewer manholes with the City naming convention. The last sanitary sewer manhole in the public sanitary sewer extension into this lot is designated as MH 22-148.
|
|
Corrective Action Required
Revise the service connection to the existing sanitary sewer stub. All building sewer stubs shall be SDR 26 (minimum) PVC and use of a saddle connection is not allowed.
|
|
Corrective Action Required
Show the existing 12-inch water main along Chipman Rd. and along Ward Rd. Direct connection to the 12-inch water main along Ward Rd. would eliminate two bends used in the proposed configuration.
|
|
Corrective Action Required
Show the size and location of water main connection and water meter (LS 6901 L. Water Meters). The water meter shall be located in the R/W or easement within 1 foot of the R/W or easement line, whichever is farthest. Note on the plans that the building service line connection to the water main is made by a corporation stop.
|
|
Corrective Action Required
Soft type “K” copper service line (diameter in accordance with the City standard details) shall extend a minimum of 10 feet beyond the meter well (between the meter and the private customer) (LS 6901 K. Service Lines).
|
|
Corrective Action Required
Please be advised that there are updated development plans for the adjacent lot to the west. Revise your development plans accordingly.
|
|
Corrective Action Required
Add a note stating: “The contractor shall contact the City’s Development Services Engineering Inspection to schedule a pre-construction meeting with a Field Engineering Inspector prior to any land disturbance work at (816) 969-1200.”
|
|
Corrective Action Required
Provide a drainage map that shows the intent to drain everything to the existing curb inlet. Add calculations to the plans that show that the existing storm system is sized correctly.
|
|
Corrective Action Required
Show pavement sections and add the following notes to the plans regarding paving per Section 2200 of the City Design and Construction Manual.
- All asphalt materials shall conform to the KCMMB ASPHALT MATERIAL SPECIFICATION, current edition.
- All concrete materials for paving curb and gutter, sidewalks, paths, commercial driveways and other pavements in the right of way shall conform to the KCMMB specifications.
|
|
Corrective Action Required
Please provide a graphic and notes showing the aggregate base to be extended a minimum of 12 inches beyond the back of curb. The City standard detail does not show this, so provide either a standalone curb detail or add the curb detail to the typical pavement section.
|
|
Corrective Action Required
Provide a complete plan for the ADA-accessible ramps. Ensure all elevation callouts, running slope callouts, and cross-slope points for construction of ADA-accessible ramps and sidewalks. Also, include details of the sidewalk through the new driveways. Site specific information is required on the ADA plans. Specific elevations, slopes, etc. for each location. Include all ADA facilities for access to the building. Add sidewalk along Chipman Rd. to connect to the sidewalk added with the adjacent development project to the west.
|
|
Corrective Action Required
Please verify and note, if necessary, that only ornamental trees and shrubs may be planted within any easements.
|
|
|
Planning Review
|
Corrections
|
04/26/2024
|
04/26/2024
|
|
Hector Soto Jr.
|
|
Corrective Action Required
LOT INFORMATION. Label all the property line dimensions for the future Lot 10F configuration. The overall site plan on Sheet C200 lists some property line dimensions for the current Lot 10C configuration.
|
|
Corrective Action Required
STREETS. Label the NW Chipman Rd centerline in order to indicate that the R/W dimension provided on Sheet C200 is not for the entire width of R/W.
|
|
Corrective Action Required
SIDEWALKS. Construction of a 5' sidewalk is required along the entire NW Chipman Rd frontage of the subject site as shown on the plat.
|
|
Corrective Action Required
MECHANICAL SCREENING. Sheets A201 (Exterior Elevations) and A506 (Electric Panel Details) appear to show that the proposed parapets are of adquate height to comply with the City ordinance requiring all RTUs to be fully screened from view on all sides via the use of parapets extended to a height at least equal to the heights of the units being screened. Please confirm that the depicted height and screening takes into account any additional height added to the units from any curb or like structure on which the RTUs will sit.
|
|
Corrective Action Required
TRASH ENCLOSURE. The Portland cement concrete trash enclosure approach shown on the plans has a length of approximately 15'-9" from the enclosure opening. To comply with City ordinance, trash enclosure areas shall be improved with a Portland cement concrete pad and a Portland cement concrete approach 30 feet in length, measured from the enclosure opening. The pad and approach shall be improved with a minimum six inches of full depth unreinforced Portland cement concrete constructed on a sub-grade of four inches of granular base course.
|
|
Corrective Action Required
PARKING LOT PAVEMENT. The Fire Access Road Note on Sheet C200 states that all fire access lanes shall be heavy duty asphalt capable of supporting 75,000 pound loads. However, the legend on the same page indicates the use of light duty asphalt over the whole site. The only asphalt pavement section composition listed under the Pavement Notes on Sheet C201 is that for a light duty option of 1.5" surface course over 4" base course. Heavy duty is 1.5" surface course over 5" base course.
|
|
Corrective Action Required
PARKING LOT BOUNDARY. Temporary asphalt curbing shall be provided along the western boundary of the parking lot where it will be extended in the future to connect to the abutting lot at the time said pad site is developed. Revise the plans accordingly. However, staff will coordinate on the need and timing of actually constructing said temporary asphalt curbing depending on the progress and timing of the development of the abutting pad site.
|
|
Corrective Action Required
SIGNS. As noted on the plans, signs are reviewed and approved under separate cover via a sign permit application. FYI, this site is subject to the signage standards for the Summit Orchards West development established by the developer and approved by the City Council that limits tenants under 5,000 sq. ft. to one (1) wall sign per facade (but no more than 3); a maximum 4' letter/logo height and allowable sign area not to exceed 10% of the facade on which the signs are mounted. Monument signs are limited to one (1) per lot, 12' maximum height, 72 sq. ft. sign face and 96 sq. ft. overall structure area (inclusive of sign face).
|
|
Corrective Action Required
CROSS ACCESS AND CROSS PARKING. Add a note to the plans regarding the cross access and cross parking rights and obligations established via the plat that affect the subject lot.
|
|
|
Traffic Review
|
Corrections
|
04/26/2024
|
04/24/2024
|
|
Erin Ralovo
|
|
Corrective Action Required
Sidewalk is required along Chipman Road.
|
|
Corrective Action Required
Staff would like to see a pedestrian way similar to that shown on the Andy's site leading up from the sidewalk, or a shared facility on the boundary.
|
|
|
Fire Review
|
Corrections
|
04/26/2024
|
04/24/2024
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Action required- Fire department access lane shall be capable of supporting 75,000-pounds. Plans call out light asphalt.
|
|
|
Building Codes Review
|
Corrections
|
04/26/2024
|
04/19/2024
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Architectural design package used as a reference but has not been evaluated for compliance.
|
|
Miscellaneous Correction
Corrective Action Required
Provide complete light pole base detail. (noted as ref: structural but not found in submittals.)
|
|
|