Planning Application Status

PL2022384




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2022384
I 470 Business and Technology Center - Lot 7
Commercial Final Development Plan
Commercial Final Development Plan
Withdrawn
11/01/2022
MARION RIDGE SAFETY STORAGE LLC
Applicant withdrew the application as the lot is being sold to a different user. Mike Weisenborn 02/21/2024 3:44 PM
Locations
Contacts
MARION RIDGE SAFETY STORAGE LLC, Address:1120 NW EAGLE RIDGE BLVD  
WARD DEVELOPMENT & INVESTMENT, Address:1101 C NW PAMELA BLVD, Phone:(816) 918-6416  
MIDWEST ARCHITECTS, Address:1120 NW EAGLE RIDGE BLVD, Phone:(816) 229-8115  
Reviews
Review Type Outcome Est. Completion Date Completed
Planning Review No Comments 12/28/2023 12/28/2023
Shannon McGuire
Traffic Review Corrections 12/28/2023 12/21/2023
Erin Ralovo
Corrective Action Required
12/21/2023

The change in layout is not acceptable. There is no access to the properties on the north and south and the new access point does not match the access to the other side of McBaine. The location of the dumpster is likely to cause access issues as well and there does not appear to be sufficient room to turn a fire truck around on site.
Corrective Action Required
12/21/2023

The radii at the entrance should be 35 Ft. Please revise.
Engineering Review No Comments 12/28/2023 12/19/2023
Sue Pyles, P.E.
Planning Review No Comments 06/29/2023 06/28/2023
Mike Weisenborn
Engineering Review No Comments 06/29/2023 06/22/2023
Sue Pyles, P.E.
Planning Review No Comments 01/25/2023 01/26/2023
Shannon McGuire
Engineering Review Approved with Conditions 01/25/2023 01/25/2023
Sue Pyles, P.E.
DE C&O #11 Pavement Thickness
Corrective Action Required
01/25/2023

Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
DE Contact Field Eng. Inspector
Corrective Action Required
01/25/2023

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
DE Engineers Estimate
Corrective Action Required
01/25/2023

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), sanitary sewer development fee, and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $22,494.45
DE Future Repair Work
Corrective Action Required
01/25/2023

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
Traffic Review No Comments 01/25/2023 01/18/2023
Mike Weisenborn
Fire Review Approved with Conditions 01/25/2023 01/18/2023
Mike Weisenborn
Code Statement
Corrective Action Required
01/18/2023

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Building Codes Review No Comments 01/25/2023 01/18/2023
Mike Weisenborn
Engineering Review Corrections 12/30/2022 12/30/2022
Sue Pyles, P.E.
Corrective Action Required
12/30/2022

Please include specific design details for the ADA-accessible ramps at the entrance.
Corrective Action Required
12/30/2022

Add the City’s standard details for Driveway and Curb & Gutter.
Corrective Action Required
12/30/2022

Please update the ESC details to the current versions.
Corrective Action Required
12/30/2022

Add an item on the estimate for ADA ramps.
Corrective Action Required
12/30/2022

Include the storm sewer Line 2 quantities in the estimate.
Planning Review Corrections 12/30/2022 12/30/2022
Shannon McGuire
Corrective Action Required
12/30/2022

Please call out a temporary asphalt curb along where the driveway meets the north property line.
Corrective Action Required
12/30/2022

Planning Comments #6 & #7 from the Applicant letter dated November 30, 2022 were not addressed with the resubmittal. #6 - All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. The proposed parapet walls do not meet this requirement. (Updated architectural plans were not received with the latest resubmittal) #7 - Please provide the manufacturer’s specification sheets for proposed mechanical equipment to be used. (This includes roof top mounted equipment)
Building Codes Review No Comments 12/30/2022 12/21/2022
Mike Weisenborn
Traffic Review No Comments 12/30/2022 12/21/2022
Mike Weisenborn
Fire Review Approved with Conditions 12/30/2022 12/21/2022
Mike Weisenborn
Code Statement
Corrective Action Required
12/21/2022

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Planning Review Corrections 11/29/2022 11/30/2022
Shannon McGuire
Corrective Action Required
11/30/2022

C100 & C200 – Please update the vicinity map (w/aerial) to reflect the correct boundaries of the proposed project. Update the project boundaries throughout the plan set as needed.
Corrective Action Required
11/30/2022

Please show the building setback lines from streets with dimensions.
Corrective Action Required
11/30/2022

Please label the width of the proposed parking stalls.
Corrective Action Required
11/30/2022

Please show the location of all oil and/or gas wells within the subject property. If none are present, please add a note stating such and cite your source of information.
Corrective Action Required
11/30/2022

Please provide information on the propose parking light poles to include the height.
Corrective Action Required
11/30/2022

All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. The proposed parapet walls do not meet this requirement.
Corrective Action Required
11/30/2022

Please provide the manufacturer’s specification sheets for proposed mechanical equipment to be used.
Corrective Action Required
11/30/2022

Please add the Floor Area Ratio (FAR) to the site data on sheet C200.
Corrective Action Required
11/30/2022

The shared driveways need to be extended to the north property line. Temporary asphalt curbs may be used in areas to be expanded only as shown and approved on the development plan.
Corrective Action Required
11/30/2022

CG-1 concrete curbing required around all parking areas and access drives in office, commercial and industrial districts. Please show the required curbing adjacent to the building.
Corrective Action Required
11/30/2022

Accessible parking spaces shall have an adjacent aisle 5 feet wide, and one in every 8 accessible spaces (but no less than one) shall be adjacent to an aisle 8 feet wide and the space shall be clearly marked with a sign indicating that the space is “van accessible.” Please label the widths of the ADA aisles.
Corrective Action Required
11/30/2022

All accessible parking shall comply with the requirements of the federal Americans with Disabilities Act.
Corrective Action Required
11/30/2022

For any property within two miles of the airport, a Form 7460 shall be completed and submitted to the FAA, and comments received back prior to any construction.
Corrective Action Required
11/30/2022

Screening to a height of two and one-half feet must be provided along the edge of the parking lot or loading area closest to and parallel to the street. A driveway to the parking lot or loading area may interrupt the screening. See Sec. 8.820 for screening options.
Engineering Review Corrections 11/29/2022 11/29/2022
Sue Pyles, P.E.
Corrective Action Required
11/29/2022

General: • Please submit an Engineer's Estimate of Probable Construction Costs. • Please submit the SWPPP and a copy of the MDNR Land Disturbance Permit.
Corrective Action Required
11/29/2022

Sheet C200: • Clearly show and label easements on this sheet and throughout the plan set. • Plan Note 7 does not appear to be used. Please clarify. • Utility Note 2 is misworded. All stormwater will be gathered in the private system and then connect to the public system at the existing curb inlet. Please revise.
Corrective Action Required
11/29/2022

Sheet C201: Only ornamental trees are allowed within public easements. Please revise as needed.
Corrective Action Required
11/29/2022

Sheet C210: • Use City standard details where possible. • All ADA-accessible ramps must have a specific detail associated with them. The specific details of these features must include, at a minimum, the design details specified in Section 5304.8 of the Design and Construction Manual. Elevation call-outs, although required, are not sufficient. Other design details specified in this section are required, including slope call-outs which comply with the criteria listed in Table LS-5, and section views specified in 5304.8.
Corrective Action Required
11/29/2022

Sheet C301: Please add additional erosion and sediment controls at the existing end section.
Corrective Action Required
11/29/2022

Sheet C400: • Please revise this sheet to match the rest of the plan set. All storm sewer upstream of the existing public curb inlet will be private. • Remove the partial Line 1 Profile.
Corrective Action Required
11/29/2022

Sheet C402: • Please revise the storm sewer system to meet the requirements as shown in Section 5604.5 for drops across structures. • Please revise the storm sewer numbering to be by line rather than numbering by both line and structure type.
Corrective Action Required
11/29/2022

Sheet C700: Please include the material and size of the domestic, irrigation and fire lines.
Traffic Review No Comments 11/29/2022 11/28/2022
Brad Cooley, P.E., RSPI
Building Codes Review No Comments 11/29/2022 11/23/2022
Joe Frogge
Fire Review Approved with Conditions 11/29/2022 11/22/2022
Jim Eden
Code Statement
Corrective Action Required
11/30/2022

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $725.00 $725.00 Paid 12/28/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
11/01/2022 Application Form Final Dev Plan App and Affidavit
11/30/2022 Letter Applicant Letter - FDP (DFDP)
12/21/2022 Engineer Report/Study SWPPP
12/21/2022 Activity Document I-470 LOTS 6a AND 7-MDNR-LAND PERMIT-EXP-2-27
12/21/2022 Engineers Estimate COST ESTIMATE-12-14-22
12/21/2022 Letter COMMENT LETTER-12-14-22
12/28/2022 Receipt Receipt for transaction: 2022-009666
12/30/2022 Letter Applicant Letter - FDP (DFDP)
01/18/2023 Letter Plan Review Response Letter to Planning 23_01_11
01/25/2023 Activity Document Fees I470 Bus and Tech Center Lot 7 FDP
01/26/2023 Letter Applicant Letter - FDP (DFDP)
01/26/2023 Approved Plans APPROVED 2701 NE McBaine Dr FDP
02/07/2023 3rd Party Permit/Approval 7460 Clearance letter_571031263
06/22/2023 Letter Owner Revision Narrative Letter 23_06_22
06/28/2023 Letter Applicant Letter - FDP (DFDP)
06/28/2023 Approved Plans APPROVED FDP REVISED 6.22.2023
07/19/2023 Plans I-470 B AND T CENTER LOT 7- REV SITE PLAN-7-18-23
12/19/2023 Letter 23_12_19 Site Design Revisions Narrative
12/19/2023 Plans I-470 B&T INDUSTRIAL CENTER -LOT 7-2nd SUB SET-12-12-23
01/02/2024 Letter Applicant Letter - FDP (DFDP)
02/21/2024 Email Projec Cancelation Email
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home