Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
08/03/2022
|
08/03/2022
|
|
Gene Williams, P.E.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included for two (2) water meters, a 1 inch and a 3/4 inch meter. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $17,126.38
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Building Codes Review
|
No Comments
|
08/03/2022
|
07/27/2022
|
|
Mike Weisenborn
|
|
|
Traffic Review
|
No Comments
|
08/03/2022
|
07/27/2022
|
|
Mike Weisenborn
|
|
|
Fire Review
|
Approved with Conditions
|
08/03/2022
|
07/27/2022
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Planning Review
|
Approved with Conditions
|
08/03/2022
|
07/27/2022
|
|
Mike Weisenborn
|
|
Miscellaneous Correction
Corrective Action Required
PHOTOMETRIC PLAN. Wallpacks shall incorporate full 90-degree cut-offs to direct the light downward and so the light source is not visibile from off the property.
|
|
|
Engineering Review
|
Corrections
|
07/25/2022
|
07/25/2022
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Cost estimate should be sufficiiently broken-down into line items, and although it is close to being acceptable, "utilities" needs to be broken down according to water and sanitary sewer. Please revise as appropriate.
|
|
Corrective Action Required
The cost estimate was missing the following items: 1) backflow vault, 2) water lines, 3) valves, 4) tees, bends, fittings, 5) ADA-accessible ramps, 6) sanitary wye and connections, 7) 6 inch aggregate base for pavement, 8) final restoration including sodding, seeding, fertilizer, and mulch/topsooil.
|
|
|
Planning Review
|
Approved with Conditions
|
07/25/2022
|
07/18/2022
|
|
Mike Weisenborn
|
|
Miscellaneous Correction
Corrective Action Required
PHOTOMETRIC PLAN. Wallpacks shall incorporate full 90-degree cut-offs to direct the light downward and so the light source is not visibile from off the property.
|
|
|
Fire Review
|
Approved with Conditions
|
07/25/2022
|
07/18/2022
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Traffic Review
|
No Comments
|
07/25/2022
|
07/18/2022
|
|
Mike Weisenborn
|
|
|
Building Codes Review
|
No Comments
|
07/25/2022
|
07/18/2022
|
|
Mike Weisenborn
|
|
|
Fire Review
|
Approved with Conditions
|
07/13/2022
|
07/13/2022
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Planning Review
|
Approved with Conditions
|
07/13/2022
|
07/13/2022
|
|
Hector Soto Jr.
|
|
Corrective Action Required
PHOTOMETRIC PLAN. Wallpacks shall incorporate full 90-degree cut-offs to direct the light downward and so the light source is not visibile from off the property.
|
|
|
Engineering Review
|
Corrections
|
07/13/2022
|
07/13/2022
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Engineer's Estimate of Probable Construction Costs was missing the geogrid specified in the design. Please ensure the geogrid is calculated a minimum 1 foot beyond the back of curb.
|
|
|
Traffic Review
|
No Comments
|
07/13/2022
|
07/12/2022
|
|
Brad Cooley, P.E., RSPI
|
|
|
Building Codes Review
|
No Comments
|
07/13/2022
|
07/07/2022
|
|
Joe Frogge
|
|
|
Engineering Review
|
Corrections
|
06/30/2022
|
06/30/2022
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Please refer to previous applicant letter. Asphaltic concrete section does not meet the Unified Development Ordinance (UDO) in terms of the chemically-stabilized subgrade or geogrid requirement. In addition, there is no specification for heavy duty asphaltic concrete in areas where emergency vehicles or heavy truck traffic will utilize. Please see the UDO for specific requirements.
|
|
Corrective Action Required
The response to comments letter from the applicant references another "response to comments" letter from Kaw Valley Engineering. No such letter was received, so certain aspects of the review could not be performed. Please submit the Kaw Valley response to comments letter.
|
|
|
Traffic Review
|
No Comments
|
06/30/2022
|
06/28/2022
|
|
Brad Cooley, P.E., RSPI
|
|
|
Fire Review
|
Approved with Conditions
|
06/30/2022
|
06/27/2022
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Planning Review
|
Approved with Conditions
|
06/30/2022
|
06/27/2022
|
|
Hector Soto Jr.
|
|
Corrective Action Required
PHOTOMETRIC PLAN. Wallpacks shall incorporate full 90-degree cut-offs to direct the light downward and so the light source is not visibile from off the property.
|
|
|
Building Codes Review
|
No Comments
|
06/30/2022
|
06/23/2022
|
|
Joe Frogge
|
|
|
Planning Review
|
Corrections
|
06/07/2022
|
06/07/2022
|
|
Hector Soto Jr.
|
|
Corrective Action Required
VICINITY MAP. The map on Sheet G0.0 calls out the wrong property as the project site. The correct site is the abutting lot to the north. Revise.
|
|
Corrective Action Required
LAND USE SCHEDULE. On the FDP Cover Sheet prepared by Kaw Valley Engineering, revise the listed number of "Required Stalls" (shown as 0) on the Land Use Schedule to match the Parking Summary table above it (shown as 9).
|
|
Corrective Action Required
DETAIL SHEET (SHEET C700).
- The pavement design details for both asphalt and P.C. concrete don't meet the minimum design standards under UDO Section 8.620.F.
- Add a note or dimension the accessible parking sign detail to indicate that the sign shall mounted a minimum 60" above finished grade, measured to the bottom of the sign.
|
|
Corrective Action Required
DIMENSION PLAN (SHEET C300). Dimension the driveways into and out of the site, as well as the drive aisles into and out of the parking lot area. Also dimension the distance between the parking lot improvements and the adjacent property lines.
|
|
Corrective Action Required
TRASH ENCLOSURE. To comply with the requirements of UDO Section 8.620F.1.c, the concrete approach in front of the trash enclosure shall be a minimum 30' in length, measured from the enclosure opening.
|
|
Corrective Action Required
LANDSCAPE PLAN. There is a typo in the calculated minimum number of street trees for the site. The Landscape Worksheet indicates that 37 trees are required, as opposed to the correct number of 7.
|
|
Corrective Action Required
BUILDING ELEVATIONS.
- The cooler is shown to be clad in vinyl. The use of vinyl on commercial development can only be approved by the Planning Commission and City Council through a public hearing process as part of a preliminary development plan. The public hearing process takes approximately 3 months from the time of application submittal. See UDO Section 8.170.A for the list of approved exterior materials for use in the commercial zoning districts.
- It appears on the exterior elevation for the back of the building that roof-mounted mechanical equipment will be in full view from the back and sides of the proposed building. In order to comply with the requirements of the City, RTUs shall be fully screened from view by raising the building parapet walls to a height at least equal to the height of the RTUs. Individual metal screening systems are not allowed on new construction projects. When revising the parapet wall heights, please take into account that the RTUs will sit on curbs and thus will sit taller than the manufactured height of the equipment.
- Label the color(s) of the two canopies.
|
|
Corrective Action Required
PHOTOMETRIC PLAN. The detail of the wall pack fixture on Sheet SU1.2 does not meet the design requirements of the UDO. Wall packs shall have full 90-degree shields so that the light is directted down and the light source is not visible from off the property.
|
|
Corrective Action Required
SIGNAGE.
- Signage shall be submitted and approved under separate cover through submittal of a sign permit application. As a single-tenant, stand-alone building, a total of 3 wall signs are allowed by right. The Seven Brew signs shown on the front and two sides can be approved administratively. The three additional chevrons and "Drive Thru Coffee" signs may only be approved under separate application by the Planning Commission. Should the "Drive Thru Coffee" copy be removed and only leave the chevrons with no text on the building to provide wayfinding, they would not be considered signs.
- Show the location of any free-standing signage and/or menu boards and order boxes proposed for the site to review for any conflicts with public utility lines, easements, right-of-way, etc.
|
|
|
Engineering Review
|
Corrections
|
06/07/2022
|
06/07/2022
|
|
Mike Weisenborn
|
|
Corrective Action Required
General:
1. Provide a stormwater memo stating how the stormwater will be managed.
2. The square footage of the building is inconsistent throughout the plan set and geotechnical report. Please clarify.
3. Submit and Engineer’s Estimate of Probable Construction Costs.
4. Include the following notes:
- “All construction shall follow the City of Lee's Summit Design and Construction Manual as adopted by Ordinance 5813. Where discrepancies exist between these plans and the Design and Construction Manual, the Design and Construction Manual shall prevail."
- “The contractor shall contact the City’s Development Services Engineering Inspection to schedule a pre-construction meeting with a Field Engineering Inspector prior to any land disturbance work at (816) 969-1200.”
|
|
Corrective Action Required
G0.0 Cover Sheet:
1. The wrong parcel is shown as the project site on the vicinity map. Please correct.
|
|
Corrective Action Required
FDP:
1. Review and revise total floor area.
2. Include proposed impervious area.
|
|
Corrective Action Required
C200 Site Plan:
1. All ADA-accessible ramps and ADA-accessible ways must have a specific detail associated with them. Please show the locations of these features, and provide a call-out on the plan view with a specific reference to the sheet number and detail number.
2. Concrete pad must extend a minimum of 30’ out from trash enclosure. Please review and revise.
|
|
Corrective Action Required
C300 Dimension Plan:
Dimension south entrance, the lane through the parking area and between the building and property lines.
|
|
Corrective Action Required
C400 Grading Plan:
1. Is there a retaining wall around the back of the building? If so, it needs to be called out with top and bottom elevations.
2. Proposed grading needs to be resolved to meet existing.
|
|
Corrective Action Required
C500 Utility Plan:
1. Water meter cannot be located in a paved area. Please relocate.
2. Are there two existing water service lines? Please clarify.
3. Continue the utility easement across the property to show if it will be impacted with the proposed building plan.
4. Where is note 29 on the plan and where are the irrigation plans?
5. Show utilities being crossed on the storm profile.
6. Please show the hydraulic grade line for the design storm on the profile view of the storm system.
7. The minimum allowable drop through manhole A-2 is 0.5’. Please review and revise.
|
|
Corrective Action Required
C600 Erosion Control Plan:
1. Max downslope runs for silt fence is 100’. Show silt fence tiebacks where appropriate.
2. What is reason for not making the silt fence continuous around the northwest corner? Review and revise if appropriate.
|
|
Corrective Action Required
C700 Detail Sheet:
1. Curb and gutter details need to match Lee’s Summit details. Please review and revise.
2. Pavement details must meet requirements found in section 8.620 of the UDO. Please review and revise.
3. Sidewalk design needs to match Lee’s Summit details. Please review and revise.
4. Include commercial driveway and curb inlet details that meet City of Lee’s Summit requirements.
5. The curb and gutter detail or pavement detail must show that the aggregate base and compaction of native subgrade extends a minimum of one (1) foot beyond the back of curb.
|
|
Corrective Action Required
SU1.1 Site Utilities Plan:
1. Change “Springfield” to “Lee’s Summit” in General Note 3.
|
|
Corrective Action Required
Geotechnical Report:
1. Correct the address.
2. Building size and finish floor elevation do not match those shown in the plan set.
|
|
|
Fire Review
|
Approved with Conditions
|
06/07/2022
|
06/07/2022
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Traffic Review
|
No Comments
|
06/07/2022
|
06/07/2022
|
|
Brad Cooley, P.E., RSPI
|
|
|
Building Codes Review
|
No Comments
|
06/07/2022
|
06/03/2022
|
|
Joe Frogge
|
|
|