Review Type |
Outcome |
Est. Completion Date |
Completed |
Planning Review
|
No Comments
|
02/28/2023
|
02/27/2023
|
|
Hector Soto Jr.
|
|
|
Engineering Review
|
Approved with Conditions
|
03/14/2022
|
03/15/2022
|
|
Sue Pyles, P.E.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $70,102.52
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Building Codes Review
|
No Comments
|
03/14/2022
|
03/14/2022
|
|
Joe Frogge
|
|
Miscellaneous Correction
Utility Note #9 on sheet C4.0 shows option of copper or plastic tubing after water meter. Copper piping is required to be connected to meter and extend at least 10' towards building before transitioning to plastic. This will be verified during inspections.
|
|
|
Planning Review
|
No Comments
|
03/14/2022
|
03/14/2022
|
|
Jennifer Thompson
|
|
|
Traffic Review
|
No Comments
|
03/14/2022
|
03/14/2022
|
|
Brad Cooley, P.E., RSPI
|
|
|
Fire Review
|
Approved with Conditions
|
03/14/2022
|
03/13/2022
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
|
|
|
Engineering Review
|
Corrections
|
02/25/2022
|
02/25/2022
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
General:
• Submit an Engineer's Estimate of Probable Construction Costs.
• Show location of all oil/gas wells, or indicate none are present, and cite the source.
• Show and label the location and limits of the one percent annual chance flood, as set forth on the current FEMA maps, with reference to the panel number and effective date. Elevations shall be provided if shown on the FEMA map.
• Please add a note stating that "...all construction shall follow the City of Lee's Summit Design and Construction Manual as adopted by Ordinance 5813. Where discrepancies exist between these plans and the Design and Construction Manual, the Design and Construction Manual shall prevail."
• Please add a note stating: “The contractor shall contact the City’s Development Services Engineering Inspection to schedule a pre-construction meeting with a Field Engineering Inspector prior to any land disturbance work at (816) 969-1200.”
|
|
Corrective Action Required
Sheet C3.0: The proposed fire hydrant is noted as “by others” but is included in this plan set. Please revise label.
|
|
Corrective Action Required
Sheet C4.0:
• The wye connections and stub will be installed with the public sanitary sewer extensions. Please revise this plan set to show connection to the stubs.
• Waterline Sta. 2+14.90 shows a 45 degree bend, but it would appear to need a 90 degree bend. Please revise Plan and Profile views.
• The bend shown in the FH label differ between Plan and Profile labels. Please revise.
|
|
Corrective Action Required
Sheet C8.0:
• Include the following note on this and any other profile sheet applicable: “Compacted Fill shall be placed to a minimum 18” above the top of the pipe prior to installation.” Show and label the limits of the compacted fill placement in the Profile view. Use hatching for clarity.
• Structure B-1 requires a 0.5’ fall across the structure. Please revise.
|
|
Corrective Action Required
Please add trench and backfill detail.
|
|
|
Planning Review
|
Corrections
|
02/25/2022
|
02/25/2022
|
|
Jennifer Thompson
|
|
Corrective Action Required
All proposed signs require a sign permit to be submitted and approved prior to installation.
|
|
Corrective Action Required
The landscaping requirements haven't been met for all three lots.
|
|
Corrective Action Required
Provide the manufacturer's specifications for all exterior building lighting.
|
|
Corrective Action Required
Just a reminder the minor plat has not been recorded.
|
|
|
Building Codes Review
|
Approved with Conditions
|
02/25/2022
|
02/25/2022
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Utility Note #9 on sheet C4.0 shows option of copper or plastic tubing after water meter. Copper piping is required to be connected to meter and extend at least 10' towards building before transitioning to plastic. This will be verified during inspections.
|
|
|
Traffic Review
|
No Comments
|
02/25/2022
|
02/24/2022
|
|
Susan Barry, P.E.
|
|
|
Fire Review
|
Approved with Conditions
|
02/25/2022
|
02/11/2022
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
|
|
|