Review Type |
Outcome |
Est. Completion Date |
Completed |
Planning Review
|
Approved with Conditions
|
04/07/2021
|
04/07/2021
|
|
Jennifer Thompson
|
|
Corrective Action Required
The overall replatting of the Paragon Star development remains to be completed. Additional discussion is needed whether or not a building permit could be issued for this project prior to the plats being recorded.
|
|
|
Engineering Review
|
Approved with Conditions
|
04/07/2021
|
04/06/2021
|
|
Sue Pyles, P.E.
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $81,092.00
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Building Codes Review
|
No Comments
|
04/07/2021
|
03/31/2021
|
|
Mike Weisenborn
|
|
|
Traffic Review
|
No Comments
|
04/07/2021
|
03/31/2021
|
|
Mike Weisenborn
|
|
|
Fire Review
|
Approved with Conditions
|
04/07/2021
|
03/31/2021
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Traffic Review
|
No Comments
|
03/30/2021
|
03/30/2021
|
|
Mike Weisenborn
|
|
|
Planning Review
|
Corrections
|
03/30/2021
|
03/30/2021
|
|
Jennifer Thompson
|
|
Corrective Action Required
The UDO requires trash enclosure areas to be improved with a Portland cement concrete pad and a Portland cement concrete approach 30 feet in length, measured from the enclosure opening. I apologize, I overlooked this on first submittal review.
|
|
Corrective Action Required
The overall replatting of the Paragon Star development remains to be completed. The plats are scheduled for Planning Commission on April 8, 2021. Additional discussion is needed whether or not a building permit could be issued for this project prior to the plats being recorded.
|
|
|
Engineering Review
|
Corrections
|
03/30/2021
|
03/30/2021
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Submit an Engineer's Estimate of Probable Construction Costs.
|
|
|
Fire Review
|
Approved with Conditions
|
03/30/2021
|
03/26/2021
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Building Codes Review
|
No Comments
|
03/30/2021
|
03/23/2021
|
|
Joe Frogge
|
|
|
Planning Review
|
Corrections
|
12/18/2020
|
12/18/2020
|
|
Jennifer Thompson
|
|
Corrective Action Required
CG-1 curbing is required around the entire parking/drive aisle areas. It's noted there is no curbing shown on the south portion of the site. Please revise.
|
|
Corrective Action Required
The Unified Development Ordinance requires all roof top units to be screened via a parapet wall. The proposed perforated metal screening would require a modification to the ordinance. Please revise the elevations.
|
|
Corrective Action Required
The overall replatting of the Paragon Star development remains to be completed.
|
|
|
Engineering Review
|
Corrections
|
12/18/2020
|
12/17/2020
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
The FDP boundary shown on Sheet C001 doesn’t match the extent of the proposed work included in the plan set. Please rectify.
|
|
Corrective Action Required
There are so many hatchings and shadings used it is difficult to differentiate between what they are all showing. This is especially true when grading, elevations, dimensions, or anything else specific is added to the mix. Please more clearly show the information and make sure all hatching is used is included in the Legend.
|
|
Corrective Action Required
Please label the proposed retaining wall to clearly indicate it is not included in this project.
|
|
Corrective Action Required
Include water meter size.
|
|
Corrective Action Required
The pipe lengths shown in Water Line Construction Notes W1 and W4 appear incorrect. Please verify and revise as needed.
|
|
Corrective Action Required
Please remove the Modular Block Retaining Wall detail. If a FH is added, please include the appropriate standard detail.
|
|
|
Traffic Review
|
No Comments
|
12/18/2020
|
12/17/2020
|
|
Michael Park
|
|
|
Fire Review
|
Corrections
|
12/18/2020
|
12/15/2020
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
FDC
Corrective Action Required
IFC 903.3.7 - Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official.
Action required- Show the location of the FDC and provide a hydrant within 100 feet.
|
|
|
Building Codes Review
|
No Comments
|
12/18/2020
|
12/10/2020
|
|
Joe Frogge
|
|
|