Summary


PRSUBDSUBD20200801
Public Infrastructure
Final Acceptance
DEVELOPMENT COMPLETE
Install required sanitary and water for minor plat.
03/30/2020
03/31/2020
03/16/2021
Locations
Contacts
CAPITAL CONSTRUCTION SERVICES LLC, Address:2642 NE HAGAN RD, Phone:(816) 875-0018  
DOUG ROTHFUSS, Address:2642 NE HAGAN RD, Phone:(816) 875-0018  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 03/30/2020 03/30/2020
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $565.26 $565.26 Paid 03/31/2020
91100C9-Water Insp Fee $238.53 $238.53 Paid 03/31/2020
9110072-Water Test Fee $200.00 $200.00 Paid 03/31/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary - Material Verification Passed 4/7/2020 04/08/2020
Misc
Informational
04/08/2020
All the materials seem to be acceptable and are on the approved product list.
Sanitary Sewer Construction Inspection Partial 4/8/2020 04/08/2020
Misc
Informational
04/08/2020
The contractors dug up and expososed the stub coming out of the existing MH. It had about a 2ft stick of pipe coming out of the existing boot. After taking some shots with the laser they were able to determine that the angle the new pipe was coming gout of the existing boot would line up with the new MH that is to be installed. They started with a new stick of pipe coming out of the MH. They are laying 8" sanitary pipe going toward the new MH. The contractors have installed the wyes for 2 service lines, they will be coming back to install the service line, tracer wire, etc.
Sanitary Sewer Construction Inspection Partial 4/8/2020 04/08/2020
Misc
Informational
04/08/2020
The dept of the existing MH was about 4ft deeper than it was shown on the plans. The fall was 4.05%, I spoke with Kent and he was good with the engineer just showing the sanitary line will be deeper than originally designed. The depth of the line will no exceed 15ft. so we will just show all the changes on the as-builds. The changes will also need to be shown for the 3 service lines.
Sanitary Sewer Construction Inspection Partial 4/9/2020 04/09/2020
Misc
Informational
04/09/2020
The contractor is continuing to install the 8" sewer main. They are currently installing the 3rd service line with a wye. The bottom cone of the MH wil most likely be installed this afternoon after the service line. The contractor said they will install the trench check for the service line when they install the inverts.
Misc
Informational
04/09/2020
The contractor is continuing to install the 8" sewer main. They are currently installing the 3rd service line with a wye. The bottom cone of the MH wil most likely be installed this afternoon after the service line. The contractor said they will install the trench check for the service line when they install the inverts.
Misc
Informational
04/09/2020
The contractor is continuing to install the 8" sewer main. They are currently installing the 3rd service line with a wye. The bottom cone of the MH wil most likely be installed this afternoon after the service line. The contractor said they will install the trench check for the service line when they install the inverts.
Sanitary Sewer Construction Inspection Passed 4/14/2020 04/23/2020
Misc
Informational
04/13/2020
The contractor has finished install
Misc
Informational
04/23/2020
The contractor use a pre poured invert, the water dept. took a look and said it was ok this time. I let them know we do not use them. They backfilled the MH and the 30 day starts now for the video inspection. The constructin has been completed.
Sanitary Sewer - Camera Test Passed 5/14/2020 06/19/2020
Misc
Informational
04/23/2020
Misc
Corrective Action Required
06/19/2020
They had to put grout around the pipes going into the MH. They have completed the job.
Erosion Control Inspection Passed 06/19/2020
Sanitary Sewer - Air Test Passed 06/19/2020
Sanitary Sewer - Mandrel Passed 06/19/2020
Sanitary Sewer - Vacuum Passed 06/19/2020
Sanitary Sewer - Invert Passed 06/19/2020
Grading/Excavation/Fill Inspection Passed 06/19/2020
Water - Material Verification Passed 06/19/2020
Water Line - Hydrostatic Test Passed 06/19/2020
Water Line - Coliform Test 1 Passed 06/19/2020
Water Line - Coliform Test 2 Passed 06/19/2020
Water Line - Valve Passed 4/14/2020 06/19/2020
Water Line - Fire Hydrant Passed 06/19/2020
Water Line - Thrust Restraint Passed 06/19/2020
Water Line - Construction Taps Removed Passed 06/19/2020
Water Line - Construction Inspection Passed 06/19/2020
Water - Material Verification Passed 06/19/2020
Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home