Permit Application Status

PRSUBD20210481


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20210481
Public Infrastructure
Final Acceptance
GALE COMMUNITIES INC
DEVELOPMENT COMPLETE
The Ridge at Winterset Summit subdivision
02/03/2021
04/29/2021
01/10/2025
08/07/2023
Locations
Contacts
GALE COMMUNITIES INC, Address:400 SW LONGVIEW BLVD STE 105  
REORGANIZED SCHOOL DIST NO 7, Address:600 SE MILLER ST  
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
REDFORD CONSTRUCTION INC, Address:PO BOX 1065, Phone:(816) 540-2030  
SKELSEY KEVIN R & MOLLY E, Address:2720 SW GRAY LANE  
CUNDIFF JON D & VICKY L, Address:701 SW WINTERWALK LN  
DAVIS TOM & MARY, Address:178 SW ROOSEVELT RDG  
PACE FRANK & KRISTINE, Address:2408 SW WINTERCREEK CT  
VEACH BRETT & ALISON, Address:185 SW WINTER RD  
WINTERSET COMMUNITY ASSOCIATION INC, Address:2505 SW WINTERCREEK DR  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 02/03/2021 04/29/2021
Dawn Bell
Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Insp Fees $1,690.70 $1,690.70 Paid 02/09/2021
Storm Sewer Inspection Fee $321.06 $321.06 Paid 02/09/2021
Paved Surface Inspection Fee $2,160.87 $2,160.87 Paid 02/09/2021
Site Grading Fee $1,366.89 $1,366.89 Paid 02/09/2021
Right of Way Permit Fee $80.00 $80.00 Paid 02/09/2021
Water Insp Fee $883.43 $883.43 Paid 02/09/2021
Water Test Fee $400.00 $400.00 Paid 02/09/2021
Outstanding Fees Amount Paid Owing Date Paid
After Hours Inspections (Public Works)(Per Hour) $150.00 $0.00 $150.00 Not Paid
After Hours Inspections (Public Works)(Per Hour) $25.00 $0.00 $25.00 Not Paid
After Hours Inspections (Public Works)(Per Hour) $125.00 $0.00 $125.00 Not Paid


$300.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary - Material Verification Partial 5/3/2021 05/03/2021
Misc
Informational
05/03/2021
Manholes were manufactured by Barbour Concrete with ML-13-NCR steps. Sanitary pipes for the main line are 8 inch SDR 26 were manufactured by Sanderson Pipe. Sanitary pipes for the service laterals are 4 inch SDR 26 manufactured by Sanderson Pipe. Manhole casting are 1502A manufactured by EJ USA and have the correct stamping on the lids. RP 5-3-21
Site Visit Partial 5/3/2021 5/3/2021 05/03/2021
Misc
Informational
05/03/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Sanitary Sewer Construction Inspection Partial 5/4/2021 5/4/2021 05/04/2021
Misc
Informational
05/04/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Site Visit Partial 5/4/2021 5/4/2021 05/04/2021
Misc
Informational
05/03/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/04/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Sanitary Sewer Construction Inspection Partial 5/5/2021 5/5/2021 05/05/2021
Misc
Informational
05/05/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Site Visit Partial 5/5/2021 5/5/2021 05/05/2021
Misc
Informational
05/04/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/04/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/05/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Sanitary Sewer Construction Inspection Partial 5/6/2021 5/6/2021 05/07/2021
Misc
Informational
05/07/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Site Visit Partial 5/6/2021 5/6/2021 05/07/2021
Misc
Informational
05/05/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/05/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/05/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/07/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Sanitary Sewer Construction Inspection Partial 5/7/2021 5/7/2021 05/07/2021
Misc
Informational
05/07/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/07/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Site Visit Partial 5/7/2021 5/7/2021 05/07/2021
Misc
Informational
05/07/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/07/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/07/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/07/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/07/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Sanitary Sewer Construction Inspection Partial 5/10/2021 5/10/2021 05/11/2021
Misc
Informational
05/07/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/07/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/11/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Site Visit Partial 5/10/2021 5/10/2021 05/11/2021
Misc
Informational
05/07/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/07/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/07/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/07/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/07/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/11/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Sanitary - Material Verification Passed 5/4/2021 5/4/2021 05/11/2021
Misc
Informational
05/03/2021
Manholes were manufactured by Barbour Concrete with ML-13-NCR steps. Sanitary pipes for the main line are 8 inch SDR 26 were manufactured by Sanderson Pipe. Sanitary pipes for the service laterals are 4 inch SDR 26 manufactured by Sanderson Pipe. Manhole casting are 1502A manufactured by EJ USA and have the correct stamping on the lids. RP 5-3-21
Water - Material Verification Partial 5/11/2021 5/11/2021 05/11/2021
Misc
Informational
05/11/2021
Only materials delivered so far is 8 inch C-900 water pipe from Sanderson. RP 5-11-21
Storm - Material Verification Partial 5/11/2021 5/11/2021 05/11/2021
Misc
Informational
05/11/2021
Only materials delivered so far is 15 inch 6500 storm pipe from ADS and a 15 inch ESSGV 15 end section from Contech. RP 5-11-21
Sanitary Sewer Construction Inspection Partial 5/11/2021 5/11/2021 05/11/2021
Misc
Informational
05/11/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/11/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/11/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/11/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. RP 5-11-21
Site Visit Partial 5/11/2021 5/11/2021 05/11/2021
Misc
Informational
05/11/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/11/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/11/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/11/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/11/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/11/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/11/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Sanitary Sewer Construction Inspection Partial 5/12/2021 5/12/2021 05/12/2021
Misc
Informational
05/11/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/11/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/11/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/11/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. RP 5-11-21
Misc
Informational
05/12/2021
They ran into harder rock today. They laid 7 sticks of sanitary pipe. RP 5-12-21
Site Visit Partial 5/12/2021 5/12/2021 05/12/2021
Misc
Informational
05/11/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/11/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/11/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/11/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/11/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/11/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/11/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
05/12/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Sanitary Sewer Construction Inspection Partial 5/13/2021 5/13/2021 05/13/2021
Misc
Informational
05/12/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/12/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/12/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/12/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. RP 5-11-21
Misc
Informational
05/12/2021
They ran into harder rock today. They laid 7 sticks of sanitary pipe. RP 5-12-21
Misc
Informational
05/13/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. RP 5-13-21
Site Visit Partial 5/13/2021 5/13/2021 05/13/2021
Misc
Informational
05/12/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/12/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/12/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/12/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/12/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/12/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/12/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
05/12/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
05/13/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Sanitary Sewer Construction Inspection Partial 5/14/2021 5/14/2021 05/14/2021
Misc
Informational
05/13/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/13/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/13/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/13/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. RP 5-11-21
Misc
Informational
05/13/2021
They ran into harder rock today. They laid 7 sticks of sanitary pipe. RP 5-12-21
Misc
Informational
05/13/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. RP 5-13-21
Misc
Informational
05/14/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Site Visit Partial 5/14/2021 5/14/2021 05/14/2021
Misc
Informational
05/13/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/13/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/13/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/13/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/13/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/13/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/13/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
05/13/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
05/13/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
05/14/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Storm - Material Verification Passed 5/18/2021 5/18/2021 05/18/2021
Misc
Informational
05/11/2021
Only materials delivered so far is 15 inch 6500 storm pipe from ADS and a 15 inch ESSGV 15 end section from Contech. RP 5-11-21
Misc
Informational
05/18/2021
Curb structures 1-3 and 1-2 were manufactured by Barbour Concrete. They used ML-13-NCR steps for the structures. Lids have the correct stamping on them. RP 5-18-21
Storm Sewer Construction Inspection Partial 5/19/2021 5/19/2021 05/24/2021
Misc
Informational
05/24/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Site Visit Partial 5/19/2021 5/19/2021 05/24/2021
Misc
Informational
05/14/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/14/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/14/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/14/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/14/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/14/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/14/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
05/14/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
05/14/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
05/14/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
05/24/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Site Visit Partial 5/24/2021 5/24/2021 05/24/2021
Misc
Informational
05/24/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/24/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/24/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/24/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/24/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/24/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/24/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
05/24/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
05/24/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
05/24/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
05/24/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
05/24/2021
Tenax LBO 302 geo grid was delivered for construction of roadway. RP 5-24-21
Site Visit Partial 5/25/2021 5/25/2021 05/25/2021
Misc
Informational
05/24/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/24/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/24/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/24/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/24/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/24/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/24/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
05/24/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
05/24/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
05/24/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
05/24/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
05/24/2021
Tenax LBO 302 geo grid was delivered for construction of roadway. RP 5-24-21
Misc
Informational
05/25/2021
Randy Spalding has started grading the roadway. RP 5-25-21
Site Visit Partial 5/26/2021 5/26/2021 05/26/2021
Misc
Informational
05/25/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/25/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/25/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/25/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/25/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/25/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/25/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
05/25/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
05/25/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
05/25/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
05/25/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
05/25/2021
Tenax LBO 302 geo grid was delivered for construction of roadway. RP 5-24-21
Misc
Informational
05/25/2021
Randy Spalding has started grading the roadway. RP 5-25-21
Misc
Informational
05/26/2021
KC Testing was on site taking compaction testing for the sanitary line and laterals in the roadway. RP 5-26-21
Site Visit Partial 6/7/2021 6/7/2021 06/07/2021
Misc
Informational
05/26/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
05/26/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
05/26/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/26/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
05/26/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/26/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/26/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
05/26/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
05/26/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
05/26/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
05/26/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
05/26/2021
Tenax LBO 302 geo grid was delivered for construction of roadway. RP 5-24-21
Misc
Informational
05/26/2021
Randy Spalding has started grading the roadway. RP 5-25-21
Misc
Informational
05/26/2021
KC Testing was on site taking compaction testing for the sanitary line and laterals in the roadway. RP 5-26-21
Misc
Informational
06/07/2021
Met with Steven and Ryan from the Water camera crew to determine if they would be able to access the whole line after testing is completed. They informed me that it shouldn’t be any issue. RP 6-7-21
Sanitary Sewer - Air Test Passed 7/7/2021 7/7/2021 07/07/2021
Misc
Informational
07/07/2021
Air gauge was calibrated 4/21. All sanitary lines held 4psi for the required time. RP 7-7-21
Sanitary Sewer - Mandrel Passed 7/7/2021 7/7/2021 07/07/2021
Misc
Informational
07/07/2021
They had the correct size mandrel and it passed through out all sanitary lines. RP 7-7-21
Sanitary Sewer - Vacuum Passed 7/7/2021 7/7/2021 07/07/2021
Misc
Informational
07/07/2021
Vacuum gauge was calibrated on 4/21. All manholes held over 9psi for the required time. Manholes still needs excess mastic removed before camera testing. RP 7-7-21
Site Visit Partial 7/13/2021 7/13/2021 07/13/2021
Misc
Informational
06/07/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
06/07/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
06/07/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
06/07/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
06/07/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
06/07/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
06/07/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
06/07/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
06/07/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
06/07/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
06/07/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
06/07/2021
Tenax LBO 302 geo grid was delivered for construction of roadway. RP 5-24-21
Misc
Informational
06/07/2021
Randy Spalding has started grading the roadway. RP 5-25-21
Misc
Informational
06/07/2021
KC Testing was on site taking compaction testing for the sanitary line and laterals in the roadway. RP 5-26-21
Misc
Informational
06/07/2021
Met with Steven and Ryan from the Water camera crew to determine if they would be able to access the whole line after testing is completed. They informed me that it shouldn’t be any issue. RP 6-7-21
Misc
Informational
07/13/2021
Camera crew was on site doing video inspections. RP 7-13-21
Site Visit Partial 7/23/2021 7/23/2021 07/23/2021
Misc
Informational
07/13/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
07/13/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
07/13/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
07/13/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
07/13/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
07/13/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
07/13/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
07/13/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
07/13/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
07/13/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
07/13/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
07/13/2021
Tenax LBO 302 geo grid was delivered for construction of roadway. RP 5-24-21
Misc
Informational
07/13/2021
Randy Spalding has started grading the roadway. RP 5-25-21
Misc
Informational
07/13/2021
KC Testing was on site taking compaction testing for the sanitary line and laterals in the roadway. RP 5-26-21
Misc
Informational
07/13/2021
Met with Steven and Ryan from the Water camera crew to determine if they would be able to access the whole line after testing is completed. They informed me that it shouldn’t be any issue. RP 6-7-21
Misc
Informational
07/13/2021
Camera crew was on site doing video inspections. RP 7-13-21
Misc
Informational
07/23/2021
Spalding cut roadway down to grade. They rolled out Tenax 302 geo grid and covered it with 10 inches of APWA Type 5 rock. RP 7-23-21
Pavement-Stabilized Subgrade Partial 7/23/2021 7/23/2021 07/23/2021
Misc
Informational
07/23/2021
Spalding cut roadway down to grade. They rolled out Tenax 302 geo grid and covered it with 10 inches of APWA Type 5 rock. RP 7-23-21
Pavement-Proof Roll Partial 8/16/2021 8/16/2021 08/16/2021
Misc
Informational
08/16/2021
Randy Spalding had a tandem dump truck with a 19.22 ton load. The curb line passed the proof roll. RP 8-16-21
Pavement-Curb Construction Partial 8/17/2021 8/17/2021 08/17/2021
Misc
Informational
08/17/2021
Turner & Michael formed and poured 400 feet of curbing and center median. They used 57 cubic yards of 4K KCMMB mix from Show Me Ready Mix. They formed and poured 1 curb inlet and will have to come back for the other one since the lid was busted and removed. They used white cure on all the concrete. RP 8-17-21
Site Visit Partial 9/7/2021 9/7/2021 09/07/2021
Misc
Informational
07/23/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
07/23/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
07/23/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
07/23/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
07/23/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
07/23/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
07/23/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
07/23/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
07/23/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
07/23/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
07/23/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
07/23/2021
Tenax LBO 302 geo grid was delivered for construction of roadway. RP 5-24-21
Misc
Informational
07/23/2021
Randy Spalding has started grading the roadway. RP 5-25-21
Misc
Informational
07/23/2021
KC Testing was on site taking compaction testing for the sanitary line and laterals in the roadway. RP 5-26-21
Misc
Informational
07/23/2021
Met with Steven and Ryan from the Water camera crew to determine if they would be able to access the whole line after testing is completed. They informed me that it shouldn’t be any issue. RP 6-7-21
Misc
Informational
07/23/2021
Camera crew was on site doing video inspections. RP 7-13-21
Misc
Informational
07/23/2021
Spalding cut roadway down to grade. They rolled out Tenax 302 geo grid and covered it with 10 inches of APWA Type 5 rock. RP 7-23-21
Misc
Informational
09/07/2021
Met with Cutter Gale on site. The last curb inlet has been formed and poured, but many sections of curbing still need to be grouted. Once grouted, they are ready to proceed with asphalt. RP 9-7-21
Pavement-Curb Construction Partial 9/9/2021 9/9/2021 09/09/2021
Misc
Informational
08/17/2021
Turner & Michael formed and poured 400 feet of curbing and center median. They used 57 cubic yards of 4K KCMMB mix from Show Me Ready Mix. They formed and poured 1 curb inlet and will have to come back for the other one since the lid was busted and removed. They used white cure on all the concrete. RP 8-17-21
Misc
Informational
09/09/2021
Turner & Michael grouted all the openings in the curbs and replaced the panels that were broken. RP 9-9-21
Pavement-Proof Roll Passed 9/13/2021 9/13/2021 09/13/2021
Misc
Informational
08/16/2021
Randy Spalding had a tandem dump truck with a 19.22 ton load. The curb line passed the proof roll. RP 8-16-21
Misc
Informational
09/13/2021
They had a tandem dump truck with a 20.6 ton load. No issues with the proof roll. RP 9-13-21
Pavement-Surface Partial 9/14/2021 9/14/2021 09/14/2021
Misc
Informational
09/14/2021
Newland Paving got 2 loads of APWA Type 5R down for base before the asphalt plant went down. RP 9-14-21
Pavement-Surface Partial 9/15/2021 9/15/2021 09/15/2021
Misc
Informational
09/14/2021
Newland Paving got 2 loads of APWA Type 5R down for base before the asphalt plant went down. RP 9-14-21
Misc
Informational
09/15/2021
Newland Paving laid 332 tons of APWA Type 5-1R for the base. We waited until the temps reached 140 degrees. Then they laid 222 tons of APWA Type 5-01 for the surface. JM Fahey was on site doing compaction testing for the base and surface. RP 9-15-21
Water Line - Construction Inspection Partial 9/24/2021 09/24/2021
Misc
Informational
09/24/2021
Redford connected to the existing valve and installed a fire hydrant, it is 3ft off back of curb, I checked with water and that is okay. They are planning on laying the pipe and installing all the bends and then pouring thrust blocks when they are finished. They have several bends to be installed.
Water - Material Verification Failed 9/27/2021 9/27/2021 09/28/2021
Misc
Informational
05/11/2021
Only materials delivered so far is 8 inch C-900 water pipe from Sanderson. RP 5-11-21
Misc
Corrective Action Required
09/28/2021
Fire hydrants have the wrong fitting at the base. Jarrod had the supplier send of the spec sheet concerning the fitting. Forwarded this on to water, who promptly rejected the fitting as not meeting our spec. I notified the contractor with Water’s findings. RP 9-28-21
Water - Material Verification Passed 9/28/2021 9/28/2021 09/29/2021
Misc
Informational
09/28/2021
Only materials delivered so far is 8 inch C-900 water pipe from Sanderson. RP 5-11-21
Misc
Corrective Action Required
09/28/2021
Fire hydrants have the wrong fitting at the base. Jarrod had the supplier send of the spec sheet concerning the fitting. Forwarded this on to water, who promptly rejected the fitting as not meeting our spec. I notified the contractor with Water’s findings. RP 9-28-21
Misc
Informational
09/29/2021
Water department agreed to let them use the Mueller fire hydrants with the white boot on the bottom. RP 9-29-21
Water Line - Construction Inspection Partial 9/28/2021 9/28/2021 09/29/2021
Misc
Informational
09/24/2021
Redford connected to the existing valve and installed a fire hydrant, it is 3ft off back of curb, I checked with water and that is okay. They are planning on laying the pipe and installing all the bends and then pouring thrust blocks when they are finished. They have several bends to be installed.
Misc
Informational
09/29/2021
Redford connected the last fire hydrant to the end of the water line. RP 9-29-21
Water Line - Hydrostatic Test Passed 10/1/2021 10/1/2021 10/01/2021
Misc
Informational
10/01/2021
Water line held over 160 psi for 2 hours. RP 10-1-21
Water Line - Coliform Test 1 Partial 10/1/2021 10/1/2021 10/01/2021
Misc
Informational
10/01/2021
Chlorinated the water line. Has to sit until 10AM Saturday. RP 10-1-21
Site Visit Partial 11/2/2021 9/14/2021 11/02/2021
Misc
Informational
09/07/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
09/07/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
09/07/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
09/07/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
09/07/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
09/07/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
09/07/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
09/07/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
09/07/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
09/07/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
09/07/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
09/07/2021
Tenax LBO 302 geo grid was delivered for construction of roadway. RP 5-24-21
Misc
Informational
09/07/2021
Randy Spalding has started grading the roadway. RP 5-25-21
Misc
Informational
09/07/2021
KC Testing was on site taking compaction testing for the sanitary line and laterals in the roadway. RP 5-26-21
Misc
Informational
09/07/2021
Met with Steven and Ryan from the Water camera crew to determine if they would be able to access the whole line after testing is completed. They informed me that it shouldn’t be any issue. RP 6-7-21
Misc
Informational
09/07/2021
Camera crew was on site doing video inspections. RP 7-13-21
Misc
Informational
09/07/2021
Spalding cut roadway down to grade. They rolled out Tenax 302 geo grid and covered it with 10 inches of APWA Type 5 rock. RP 7-23-21
Misc
Informational
09/07/2021
Met with Cutter Gale on site. The last curb inlet has been formed and poured, but many sections of curbing still need to be grouted. Once grouted, they are ready to proceed with asphalt. RP 9-7-21
Misc
Informational
11/02/2021
Jarrod’s crew cut down the new valve risers to grade. The existing valve riser is not their responsibility. RP 11-2-21
Water Line - Coliform Test 1 Passed 10/2/2021 10/2/2021 11/06/2021
Misc
Informational
11/06/2021
Diana pulled samples and delivered to Keystone Laboratories for testing. They passed their first Bac T testing. RP 11-1-21
Water Line - Coliform Test 2 Passed 11/1/2021 11/1/2021 11/06/2021
Misc
Informational
11/06/2021
Diana pulled second Bac T samples and delivered them to Keystone Laboratories for testing. They also passed testing. RP 11-1-21
Pavement-Aggregate Base Passed 11/06/2021
Sanitary Sewer Construction Inspection Passed 11/06/2021
Misc
Informational
05/14/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
05/14/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
05/14/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
05/14/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. RP 5-11-21
Misc
Informational
05/14/2021
They ran into harder rock today. They laid 7 sticks of sanitary pipe. RP 5-12-21
Misc
Informational
05/14/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. RP 5-13-21
Misc
Informational
05/14/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
11/06/2021
Sanitary line has been installed and passed physical and camera testing. 11-1-21
Storm Sewer Construction Inspection Passed 11/06/2021
Misc
Informational
05/24/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
11/06/2021
Storm and rip rap at the end section have been installed. 11-1-21
Water Line - Construction Inspection Passed 11/06/2021
Misc
Informational
09/29/2021
Redford connected to the existing valve and installed a fire hydrant, it is 3ft off back of curb, I checked with water and that is okay. They are planning on laying the pipe and installing all the bends and then pouring thrust blocks when they are finished. They have several bends to be installed.
Misc
Informational
09/29/2021
Redford connected the last fire hydrant to the end of the water line. RP 9-29-21
Misc
Informational
11/06/2021
Water line has been installed and passed all required testing. 11-1-21
Water - Material Verification Passed 11/06/2021
Misc
Informational
09/28/2021
Only materials delivered so far is 8 inch C-900 water pipe from Sanderson. RP 5-11-21
Misc
Corrective Action Required
09/28/2021
Fire hydrants have the wrong fitting at the base. Jarrod had the supplier send of the spec sheet concerning the fitting. Forwarded this on to water, who promptly rejected the fitting as not meeting our spec. I notified the contractor with Water’s findings. RP 9-28-21
Misc
Informational
11/06/2021
Water approved the fire hydrant for this project. RP 11-1-21
Water - Material Verification Passed 11/06/2021
Misc
Informational
11/06/2021
Water materials were correct or approved by the Water Dept. RP 11-1-21
Sidewalk Inspection Failed 11/29/2021
Misc
Corrective Action Required
11/29/2021
Someone saw cut the existing curbing at the wrong locations and replaced it with the same curbing and ADA ramp. They needed a depressed curb with the ADA ramp. This could of been avoided if they would of called in a pre-inspection. Curbing and ramp need to be removed and replaced. RP 11-29-21
Sidewalk Inspection Partial 12/3/2021 12/3/2021 12/03/2021
Misc
Corrective Action Required
11/29/2021
Someone saw cut the existing curbing at the wrong locations and replaced it with the same curbing and ADA ramp. They needed a depressed curb with the ADA ramp. This could of been avoided if they would of called in a pre-inspection. Curbing and ramp need to be removed and replaced. RP 11-29-21
Misc
Corrective Action Required
12/03/2021
Curbing needs to be removed joint to joint. ADA ramp can be altered to match roadway slope and turning space. RP 12-3-21
Sidewalk Inspection Partial 12/10/2021 12/10/2021 12/13/2021
Misc
Corrective Action Required
12/03/2021
Someone saw cut the existing curbing at the wrong locations and replaced it with the same curbing and ADA ramp. They needed a depressed curb with the ADA ramp. This could of been avoided if they would of called in a pre-inspection. Curbing and ramp need to be removed and replaced. RP 11-29-21
Misc
Corrective Action Required
12/03/2021
Curbing needs to be removed joint to joint. ADA ramp can be altered to match roadway slope and turning space. RP 12-3-21
Sidewalk Inspection Partial 12/13/2021 12/13/2021 12/15/2021
Misc
Corrective Action Required
12/13/2021
Someone saw cut the existing curbing at the wrong locations and replaced it with the same curbing and ADA ramp. They needed a depressed curb with the ADA ramp. This could of been avoided if they would of called in a pre-inspection. Curbing and ramp need to be removed and replaced. RP 11-29-21
Misc
Corrective Action Required
12/13/2021
Curbing needs to be removed joint to joint. ADA ramp can be altered to match roadway slope and turning space. RP 12-3-21
Misc
Informational
12/15/2021
Curbing was removed joint to joint. Forms were placed and aggregate was present and compacted. RP 12-15-21
Sidewalk Inspection Passed 12/22/2021 12/22/2021 12/23/2021
Misc
Corrective Action Required
12/15/2021
Someone saw cut the existing curbing at the wrong locations and replaced it with the same curbing and ADA ramp. They needed a depressed curb with the ADA ramp. This could of been avoided if they would of called in a pre-inspection. Curbing and ramp need to be removed and replaced. RP 11-29-21
Misc
Corrective Action Required
12/15/2021
Curbing needs to be removed joint to joint. ADA ramp can be altered to match roadway slope and turning space. RP 12-3-21
Misc
Informational
12/15/2021
Curbing was removed joint to joint. Forms were placed and aggregate was present and compacted. RP 12-15-21
Misc
Informational
12/23/2021
Finished sidewalk meets LS and ADA specs. RP 12-22-21
Master Drainage As-built Inspection Passed 1/10/2022 01/07/2022
Misc
Informational
01/07/2022
MDP is acceptable and closely matches what is in the field. RP 1-7-22
Record Drawing Review Passed 2/2/2022 02/02/2022
Misc
Informational
02/02/2022
All record drawings appear to be correct in the field and have been cleared by Gene too.
Site Visit Partial 2/14/2022 2/14/2022 02/14/2022
Misc
Informational
11/02/2021
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
11/02/2021
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
11/02/2021
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
11/02/2021
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
11/02/2021
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
11/02/2021
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
11/02/2021
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
11/02/2021
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
11/02/2021
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
11/02/2021
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
11/02/2021
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
11/02/2021
Tenax LBO 302 geo grid was delivered for construction of roadway. RP 5-24-21
Misc
Informational
11/02/2021
Randy Spalding has started grading the roadway. RP 5-25-21
Misc
Informational
11/02/2021
KC Testing was on site taking compaction testing for the sanitary line and laterals in the roadway. RP 5-26-21
Misc
Informational
11/02/2021
Met with Steven and Ryan from the Water camera crew to determine if they would be able to access the whole line after testing is completed. They informed me that it shouldn’t be any issue. RP 6-7-21
Misc
Informational
11/02/2021
Camera crew was on site doing video inspections. RP 7-13-21
Misc
Informational
11/02/2021
Spalding cut roadway down to grade. They rolled out Tenax 302 geo grid and covered it with 10 inches of APWA Type 5 rock. RP 7-23-21
Misc
Informational
11/02/2021
Met with Cutter Gale on site. The last curb inlet has been formed and poured, but many sections of curbing still need to be grouted. Once grouted, they are ready to proceed with asphalt. RP 9-7-21
Misc
Informational
11/02/2021
Jarrod’s crew cut down the new valve risers to grade. The existing valve riser is not their responsibility. RP 11-2-21
Misc
Corrective Action Required
02/14/2022
Forms need to be removed from the sidewalk and curbing. Once removed, they can finish their backfilling. RP 2-14-22
Site Visit Partial 2/17/2022 2/17/2022 02/24/2022
Misc
Informational
02/14/2022
Jarrod from Redford Construction prepoured the invert for manhole A-1 because it will be placed on our existing sanitary line. RP 5-3-21
Misc
Informational
02/14/2022
Jarrod’s crew cut into the existing 8 inch sanitary line and set manhole A-1. They have started excavating for manhole A-2. RP 5-4-21
Misc
Informational
02/14/2022
They set manhole A-2, laid 120 feet of sanitary pipe and poured 3 concrete pipe anchors. RP 5-5-21
Misc
Informational
02/14/2022
Ran into a rock ledge today. They laid 30 feet of sanitary pipe, poured the last pipe anchor and set manhole A-3. RP 5-6-21
Misc
Informational
02/14/2022
Poured inverts for manhole A-2 and back filled the hill side from manholes A-1 to A-3. RP 5-7-21
Misc
Informational
02/14/2022
They set 200 feet of sanitary line and manhole A-4. RP 5-10-21
Misc
Informational
02/14/2022
They laid 150 feet of sanitary pipe and set manhole-5, service lateral for lot 1605, also poured inverts for manholes A-3 and A-4 and trench check for lot 1605. Also verified storm pipe and end section that was delivered, along with water pipe that was on site. Still waiting to verify curb inlets and fire hydrant. RP 5-11-21
Misc
Informational
02/14/2022
They had to break more rock today for the last section of sanitary line. They set the wye’s for lots 1604 and 1603. RP 5-12-21
Misc
Informational
02/14/2022
Set the last of the sanitary pipe for the main line and laterals for lots 1601, 1602 and 1603. Also set manhole A-6, poured inverts and trench checks. Also talked about location for utility marking tape and testing procedures for back filling under the roadway. RP 5-13-21
Misc
Informational
02/14/2022
Finished the extension on service laterals for lots 1603 and 1604. Had dirt brought in for back filling the trench, but will need to dig it back up for competition testing when the tester is available. RP 5-14-21
Misc
Informational
02/14/2022
Jarrod’s crew from Redford Construction set end section 1-1 and curb inlets 1-2 and 1-3. They also laid 84 feet of 15 inch HDPE storm pipe. RP 5-19-21
Misc
Informational
02/14/2022
Tenax LBO 302 geo grid was delivered for construction of roadway. RP 5-24-21
Misc
Informational
02/14/2022
Randy Spalding has started grading the roadway. RP 5-25-21
Misc
Informational
02/14/2022
KC Testing was on site taking compaction testing for the sanitary line and laterals in the roadway. RP 5-26-21
Misc
Informational
02/14/2022
Met with Steven and Ryan from the Water camera crew to determine if they would be able to access the whole line after testing is completed. They informed me that it shouldn’t be any issue. RP 6-7-21
Misc
Informational
02/14/2022
Camera crew was on site doing video inspections. RP 7-13-21
Misc
Informational
02/14/2022
Spalding cut roadway down to grade. They rolled out Tenax 302 geo grid and covered it with 10 inches of APWA Type 5 rock. RP 7-23-21
Misc
Informational
02/14/2022
Met with Cutter Gale on site. The last curb inlet has been formed and poured, but many sections of curbing still need to be grouted. Once grouted, they are ready to proceed with asphalt. RP 9-7-21
Misc
Informational
02/14/2022
Jarrod’s crew cut down the new valve risers to grade. The existing valve riser is not their responsibility. RP 11-2-21
Misc
Corrective Action Required
02/14/2022
Forms need to be removed from the sidewalk and curbing. Once removed, they can finish their backfilling. RP 2-14-22
Misc
Informational
02/24/2022
No work being done today due to the snow. RP 2-24-22
Erosion Control Inspection Partial 03/24/2022
Misc
Informational
10/13/2021
On 10/13/2021 there was sediment in the curb line draining to the storm inlet with a gutter buddy that was 80% clogged DJ
Misc
Informational
03/24/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Documents & Images
Date Uploaded File Type Document Name
02/09/2021 Receipt Receipt for transaction:2021-000629
04/21/2021 Approved Plans The Ridge at Winterset Summit Street and Storm Approved 4.21.21
04/21/2021 Approved Plans The Ridge at Winterset Summit Sanitary Sewers Approved 4.21.21
04/29/2021 Letter DE-Permit
05/03/2021 Letter INSPECTION SUMMARY
05/03/2021 Letter INSPECTION SUMMARY
05/04/2021 Letter INSPECTION SUMMARY
05/04/2021 Letter INSPECTION SUMMARY
05/05/2021 Letter INSPECTION SUMMARY
05/05/2021 Letter INSPECTION SUMMARY
05/07/2021 Letter INSPECTION SUMMARY
05/07/2021 Letter INSPECTION SUMMARY
05/07/2021 Letter INSPECTION SUMMARY
05/07/2021 Letter INSPECTION SUMMARY
05/11/2021 Letter INSPECTION SUMMARY
05/11/2021 Letter INSPECTION SUMMARY
05/11/2021 Letter INSPECTION SUMMARY
05/11/2021 Letter INSPECTION SUMMARY
05/11/2021 Letter INSPECTION SUMMARY
05/11/2021 Letter INSPECTION SUMMARY
05/11/2021 Letter INSPECTION SUMMARY
05/12/2021 Letter INSPECTION SUMMARY
05/12/2021 Letter INSPECTION SUMMARY
05/13/2021 Approved Plans The Ridge at Winterset Summit Water Approved 5.13.21
05/13/2021 Letter INSPECTION SUMMARY
05/13/2021 Letter INSPECTION SUMMARY
05/14/2021 Letter INSPECTION SUMMARY
05/14/2021 Letter INSPECTION SUMMARY
05/18/2021 Letter INSPECTION SUMMARY
05/24/2021 Letter INSPECTION SUMMARY
05/24/2021 Letter INSPECTION SUMMARY
05/24/2021 Letter INSPECTION SUMMARY
05/25/2021 Letter INSPECTION SUMMARY
05/25/2021 Letter INSPECTION SUMMARY
05/26/2021 Letter INSPECTION SUMMARY
06/07/2021 Letter INSPECTION SUMMARY
07/07/2021 Letter INSPECTION SUMMARY
07/07/2021 Letter INSPECTION SUMMARY
07/07/2021 Letter INSPECTION SUMMARY
07/13/2021 Letter INSPECTION SUMMARY
07/23/2021 Letter INSPECTION SUMMARY
07/23/2021 Letter INSPECTION SUMMARY
08/16/2021 Letter INSPECTION SUMMARY
08/17/2021 Letter INSPECTION SUMMARY
09/07/2021 Letter INSPECTION SUMMARY
09/09/2021 Letter INSPECTION SUMMARY
09/13/2021 Letter INSPECTION SUMMARY
09/13/2021 Letter INSPECTION SUMMARY
09/13/2021 Letter INSPECTION SUMMARY
09/14/2021 Letter INSPECTION SUMMARY
09/15/2021 Letter INSPECTION SUMMARY
09/24/2021 Letter INSPECTION SUMMARY
09/28/2021 Letter INSPECTION SUMMARY
09/28/2021 Letter INSPECTION SUMMARY
09/29/2021 Letter INSPECTION SUMMARY
09/29/2021 Letter INSPECTION SUMMARY
10/01/2021 Letter INSPECTION SUMMARY
10/01/2021 Letter INSPECTION SUMMARY
11/02/2021 Letter INSPECTION SUMMARY
11/06/2021 Letter INSPECTION SUMMARY
11/06/2021 Letter INSPECTION SUMMARY
11/06/2021 Letter INSPECTION SUMMARY
11/06/2021 Letter INSPECTION SUMMARY
11/06/2021 Letter INSPECTION SUMMARY
11/06/2021 Letter INSPECTION SUMMARY
11/06/2021 Letter INSPECTION SUMMARY
11/06/2021 Letter INSPECTION SUMMARY
11/29/2021 Letter INSPECTION SUMMARY
12/03/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
12/15/2021 Letter INSPECTION SUMMARY
12/23/2021 Letter INSPECTION SUMMARY
01/04/2022 THE RIDGE AT WINTERSET MDP ASBUILT
01/07/2022 Letter INSPECTION SUMMARY
01/28/2022 STREET AND STORM ASBUILTS 1-28-2022
01/28/2022 SANITARY ASBUILTS 1-28-2022
01/28/2022 WATER ASBUILTS 1-28-2022
01/31/2022 Letter DE-Certificate of Substantial Completion Multiple Lot
02/02/2022 Ridge at Winterset LSMO Affidavit Executed
02/02/2022 Security Document Ridge at Winterset Lee's Summit MO Maint Bond for Sanitary, Storm and Water Only
02/02/2022 Letter DE-Punch List
02/14/2022 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/24/2022 Letter INSPECTION SUMMARY
03/24/2022 Letter INSPECTION SUMMARY
08/07/2023 Security Document Maint Bond for Street
08/07/2023 Letter DE-Certificate of Final Acceptance (Commercial)
11/04/2024 Letter PW ROW Inspections Report
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.