Permit Application Status

PRSITE20231064


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSITE20231064
Development - Site
Final Acceptance
LEES SUMMIT SENIOR COMMUNITY LLC
DEVELOPMENT COMPLETE
THE PRINCETON - DETENTION BASIN CONVERSION STOP WORK ORDER generated on 05/17/2023 12:00 AM by username 'Patrick Schonfeldt'. STOP WORK ORDER removed on 05/19/2023 12:00 AM by username 'Patrick Schonfeldt'.
03/14/2023
03/30/2023
10/19/2023
Locations
Contacts
LEES SUMMIT SENIOR COMMUNITY LLC, Address:5051 S NATIONAL AVE STE 4-100  
TRINITY EXCAVATING & CONSTRUCTION INC, Address:313 W ELM STREET, Phone:(913) 829-6090  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 03/14/2023 03/28/2023
Dawn Bell
Fees
Paid Fees Amount Paid Owing Date Paid
Site Grading Fee $2,403.90 $2,403.90 Paid 04/13/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Site Visit Partial 4/3/2023 4/3/2023 04/03/2023
Misc
Informational
04/03/2023
4-3-23 PS Made site visit, no construction on site yet.
Erosion Control Inspection Partial 4/10/2023 4/10/2023 04/10/2023
Misc
Corrective Action Required
04/10/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance
Site Visit Partial 4/10/2023 4/10/2023 04/10/2023
Misc
Informational
04/03/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23
Site Visit Partial 4/11/2023 4/11/2023 04/11/2023
Misc
Informational
04/10/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection.
Erosion Control Inspection Partial 4/12/2023 4/12/2023 04/12/2023
Misc
Corrective Action Required
04/10/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection
Site Visit Partial 4/12/2023 4/12/2023 04/12/2023
Misc
Informational
04/11/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin
Site Visit Partial 4/13/2023 4/13/2023 04/13/2023
Misc
Informational
04/12/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation
Site Visit Partial 4/14/2023 4/14/2023 04/14/2023
Misc
Informational
04/13/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin
Site Visit Partial 4/17/2023 4/17/2023 04/17/2023
Misc
Informational
04/14/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin
Site Visit Partial 4/18/2023 4/18/2023 04/18/2023
Misc
Informational
04/17/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin
Site Visit Partial 4/19/2023 4/19/2023 04/19/2023
Misc
Informational
04/18/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock
Erosion Control Inspection Partial 4/20/2023 4/20/2023 04/20/2023
Misc
Corrective Action Required
04/12/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 4/21/2023 4/21/2023 04/21/2023
Misc
Informational
04/19/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development tonight
Site Visit Partial 4/24/2023 4/24/2023 04/24/2023
Misc
Informational
04/21/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today
Site Visit Partial 4/25/2023 4/25/2023 04/25/2023
Misc
Informational
04/24/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today
Site Visit Partial 4/26/2023 4/26/2023 04/26/2023
Misc
Informational
04/25/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today
Site Visit Partial 4/27/2023 4/27/2023 04/27/2023
Misc
Informational
04/26/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today
Erosion Control Inspection Partial 4/28/2023 4/28/2023 04/28/2023
Misc
Corrective Action Required
04/20/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 5/1/2023 5/1/2023 05/01/2023
Misc
Informational
04/27/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin
Site Visit Partial 5/2/2023 5/2/2023 05/02/2023
Misc
Informational
05/01/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock
Site Visit Partial 5/3/2023 5/3/2023 05/03/2023
Misc
Informational
05/02/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin
Site Visit Partial 5/4/2023 5/4/2023 05/04/2023
Misc
Informational
05/03/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin
Site Visit Partial 5/5/2023 5/5/2023 05/05/2023
Misc
Informational
05/04/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin
Site Visit Partial 5/8/2023 5/8/2023 05/08/2023
Misc
Informational
05/05/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin
Site Visit Partial 5/9/2023 5/9/2023 05/09/2023
Misc
Informational
05/08/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation
Site Visit Partial 5/10/2023 5/10/2023 05/10/2023
Misc
Informational
05/09/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation
Erosion Control Inspection Partial 5/11/2023 5/11/2023 05/11/2023
Misc
Corrective Action Required
04/28/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 5/12/2023 5/12/2023 05/12/2023
Misc
Informational
05/10/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles
Erosion Control Inspection Partial 5/15/2023 5/15/2023 05/15/2023
Misc
Corrective Action Required
05/11/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection
Erosion Control Inspection Failed - Stop Work 5/17/2023 5/17/2023 05/17/2023
Misc
Corrective Action Required
05/15/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps
Erosion Control Inspection Partial 5/19/2023 5/19/2023 05/19/2023
Misc
Corrective Action Required
05/17/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system
Site Visit Partial 5/19/2023 5/19/2023 05/19/2023
Misc
Informational
05/12/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin
Site Visit Partial 5/22/2023 5/22/2023 05/22/2023
Misc
Informational
05/19/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup
Site Visit Partial 5/23/2023 5/23/2023 05/23/2023
Misc
Informational
05/22/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site
Site Visit Partial 5/24/2023 5/24/2023 05/24/2023
Misc
Informational
05/23/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site.
Site Visit Partial 5/30/2023 5/30/2023 05/30/2023
Misc
Informational
05/24/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site
Erosion Control Inspection Partial 5/31/2023 5/31/2023 05/31/2023
Misc
Corrective Action Required
05/19/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection
Erosion Control Inspection Partial 6/1/2023 6/1/2023 06/01/2023
Misc
Corrective Action Required
05/31/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 6/2/2023 6/2/2023 06/02/2023
Misc
Informational
05/30/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today
Erosion Control Inspection Partial 6/5/2023 6/5/2023 06/05/2023
Misc
Corrective Action Required
06/01/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 6/5/2023 6/5/2023 06/05/2023
Misc
Informational
06/02/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today
Erosion Control Inspection Partial 6/6/2023 6/6/2023 06/06/2023
Misc
Corrective Action Required
06/05/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection
Erosion Control Inspection Partial 6/7/2023 6/7/2023 06/07/2023
Misc
Corrective Action Required
06/06/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection
Erosion Control Inspection Partial 6/15/2023 6/15/2023 06/15/2023
Misc
Corrective Action Required
06/07/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection
Erosion Control Inspection Partial 6/19/2023 6/19/2023 06/19/2023
Misc
Corrective Action Required
06/15/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 6/21/2023 6/21/2023 06/21/2023
Misc
Informational
06/05/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature
Site Visit Partial 6/22/2023 6/22/2023 06/22/2023
Misc
Informational
06/21/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today
Site Visit Partial 6/23/2023 6/23/2023 06/23/2023
Misc
Informational
06/22/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature
Erosion Control Inspection Partial 6/28/2023 6/28/2023 06/28/2023
Misc
Corrective Action Required
06/19/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 7/3/2023 7/3/2023 07/03/2023
Misc
Informational
06/23/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today
Erosion Control Inspection Partial 7/5/2023 7/5/2023 07/05/2023
Misc
Corrective Action Required
06/28/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 7/6/2023 7/6/2023 07/06/2023
Misc
Informational
07/03/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping
Site Visit Partial 7/10/2023 7/10/2023 07/10/2023
Misc
Informational
07/06/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working
Site Visit Partial 7/11/2023 7/11/2023 07/11/2023
Misc
Informational
07/10/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working
Erosion Control Inspection Partial 7/13/2023 7/13/2023 07/13/2023
Misc
Corrective Action Required
07/05/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection
Erosion Control Inspection Partial 7/17/2023 7/17/2023 07/17/2023
Misc
Corrective Action Required
07/13/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection
Erosion Control Inspection Partial 7/18/2023 7/18/2023 07/18/2023
Misc
Corrective Action Required
07/17/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection
Erosion Control Inspection Partial 7/19/2023 7/19/2023 07/19/2023
Misc
Corrective Action Required
07/18/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 7/20/2023 7/20/2023 07/20/2023
Misc
Informational
07/11/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site
Erosion Control Inspection Partial 7/21/2023 7/21/2023 07/21/2023
Misc
Corrective Action Required
07/19/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection 7-21-23 PS Erosion control acceptable at time of inspection
Erosion Control Inspection Partial 7/24/2023 7/24/2023 07/24/2023
Misc
Corrective Action Required
07/21/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection 7-21-23 PS Erosion control acceptable at time of inspection 7-24-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 7/26/2023 7/26/2023 07/26/2023
Misc
Informational
07/20/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site
Site Visit Partial 7/27/2023 7/27/2023 07/27/2023
Misc
Informational
07/26/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site
Erosion Control Inspection Partial 7/28/2023 7/28/2023 07/28/2023
Misc
Corrective Action Required
07/24/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection 7-21-23 PS Erosion control acceptable at time of inspection 7-24-23 PS Erosion control acceptable at time of inspection 7-28-23 PS Erosion control acceptable at time of inspection
Erosion Control Inspection Partial 7/31/2023 7/31/2023 07/31/2023
Misc
Corrective Action Required
07/28/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection 7-21-23 PS Erosion control acceptable at time of inspection 7-24-23 PS Erosion control acceptable at time of inspection 7-28-23 PS Erosion control acceptable at time of inspection 7-31-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 8/2/2023 8/2/2023 08/02/2023
Misc
Informational
07/27/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site
Erosion Control Inspection Partial 8/3/2023 8/3/2023 08/03/2023
Misc
Corrective Action Required
07/31/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection 7-21-23 PS Erosion control acceptable at time of inspection 7-24-23 PS Erosion control acceptable at time of inspection 7-28-23 PS Erosion control acceptable at time of inspection 7-31-23 PS Erosion control acceptable at time of inspection 8-3-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 8/4/2023 8/4/2023 08/04/2023
Misc
Informational
08/02/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin
Site Visit Partial 8/7/2023 8/7/2023 08/07/2023
Misc
Informational
08/04/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin
Site Visit Partial 8/9/2023 8/9/2023 08/09/2023
Misc
Informational
08/07/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin 8-9-23 PS Landscape crew has planted trees and placed sod and vegetation at basin
Erosion Control Inspection Partial 8/9/2023 8/9/2023 08/09/2023
Misc
Corrective Action Required
08/03/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection 7-21-23 PS Erosion control acceptable at time of inspection 7-24-23 PS Erosion control acceptable at time of inspection 7-28-23 PS Erosion control acceptable at time of inspection 7-31-23 PS Erosion control acceptable at time of inspection 8-3-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 8/10/2023 8/10/2023 08/10/2023
Misc
Informational
08/09/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin 8-9-23 PS Landscape crew has planted trees and placed sod and vegetation at basin 8-10-23 PS No activity on site
Site Visit Partial 8/14/2023 8/14/2023 08/14/2023
Misc
Informational
08/10/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin 8-9-23 PS Landscape crew has planted trees and placed sod and vegetation at basin 8-10-23 PS No activity on site 8-14-23 PS No activity on site, contractor has placed landscaping rocks, trees, vegetation
Erosion Control Inspection Partial 8/14/2023 8/14/2023 08/14/2023
Misc
Corrective Action Required
08/09/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection 7-21-23 PS Erosion control acceptable at time of inspection 7-24-23 PS Erosion control acceptable at time of inspection 7-28-23 PS Erosion control acceptable at time of inspection 7-31-23 PS Erosion control acceptable at time of inspection 8-3-23 PS Erosion control acceptable at time of inspection 8-14-23 PS Erosion control acceptable at time of inspection
Site Visit Partial 8/15/2023 8/15/2023 08/15/2023
Misc
Informational
08/14/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin 8-9-23 PS Landscape crew has planted trees and placed sod and vegetation at basin 8-10-23 PS No activity on site 8-14-23 PS No activity on site, contractor has placed landscaping rocks, trees, vegetation 8-15-23 PS No activity on site
Site Visit Partial 8/16/2023 8/16/2023 08/16/2023
Misc
Informational
08/15/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin 8-9-23 PS Landscape crew has planted trees and placed sod and vegetation at basin 8-10-23 PS No activity on site 8-14-23 PS No activity on site, contractor has placed landscaping rocks, trees, vegetation 8-15-23 PS No activity on site 8-16-23 PS Vegetation has been placed throughout bio retention basin. Water feature has been installed at basin
Site Visit Partial 8/21/2023 8/21/2023 08/21/2023
Misc
Informational
08/16/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin 8-9-23 PS Landscape crew has planted trees and placed sod and vegetation at basin 8-10-23 PS No activity on site 8-14-23 PS No activity on site, contractor has placed landscaping rocks, trees, vegetation 8-15-23 PS No activity on site 8-16-23 PS Vegetation has been placed throughout bio retention basin. Water feature has been installed at basin 8-21-23 PS No activity on site
Site Visit Partial 8/22/2023 8/22/2023 08/22/2023
Misc
Informational
08/21/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin 8-9-23 PS Landscape crew has planted trees and placed sod and vegetation at basin 8-10-23 PS No activity on site 8-14-23 PS No activity on site, contractor has placed landscaping rocks, trees, vegetation 8-15-23 PS No activity on site 8-16-23 PS Vegetation has been placed throughout bio retention basin. Water feature has been installed at basin 8-21-23 PS No activity on site 8-22-23 PS No activity on site
Site Visit Partial 8/24/2023 8/24/2023 08/24/2023
Misc
Informational
08/22/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin 8-9-23 PS Landscape crew has planted trees and placed sod and vegetation at basin 8-10-23 PS No activity on site 8-14-23 PS No activity on site, contractor has placed landscaping rocks, trees, vegetation 8-15-23 PS No activity on site 8-16-23 PS Vegetation has been placed throughout bio retention basin. Water feature has been installed at basin 8-21-23 PS No activity on site 8-22-23 PS No activity on site 8-24-23 PS Landscaper on site
Site Visit Partial 8/25/2023 8/25/2023 08/25/2023
Misc
Informational
08/24/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin 8-9-23 PS Landscape crew has planted trees and placed sod and vegetation at basin 8-10-23 PS No activity on site 8-14-23 PS No activity on site, contractor has placed landscaping rocks, trees, vegetation 8-15-23 PS No activity on site 8-16-23 PS Vegetation has been placed throughout bio retention basin. Water feature has been installed at basin 8-21-23 PS No activity on site 8-22-23 PS No activity on site 8-24-23 PS Landscaper on site 8-25-23 PS No activity on site
Erosion Control Inspection Passed 9/11/2023 9/11/2023 09/11/2023
Misc
Corrective Action Required
08/14/2023
4-10-23 PS Perimeter silt fence installed per plans. Add silt fence barrier at outlet for basin as shown on plans and add additional gravel at construction entrance 4-12-23 PS Contractor has added additional gravel at construction entrance and silt fence at basin outlet. Erosion control within compliance at inspection 4-20-23 PS Erosion control acceptable at time of inspection 4-28-23 PS Erosion control acceptable at time of inspection 5-17-23 PS Stop work order issued. Basin being emptied from rains with pump into storm sewer system. Residents alerted to silt heavy waters in creek downstream. Issues explained to contractor on site who stopped pumps 5-19-23 PS Contractor is not pumping or removing water that is in basin at this time. If moving to pump from basin at future Inspector will need to see that silt is not leaving site and entering storm system 5-31-23 PS Erosion control acceptable at time of inspection 6-1-23 PS Erosion control acceptable at time of inspection 6-5-23 PS Erosion control acceptable at time of inspection 6-6-23 PS Erosion control acceptable at time of inspection 6-15-23 PS Erosion control acceptable at time of inspection 6-19-23 PS Erosion control acceptable at time of inspection 6-28-23 PS Erosion control acceptable at time of inspection 7-5-23 PS Erosion control acceptable at time of inspection 7-13-23 PS Erosion control acceptable at time of inspection 7-17-23 PS Erosion control acceptable at time of inspection 7-21-23 PS Erosion control acceptable at time of inspection 7-24-23 PS Erosion control acceptable at time of inspection 7-28-23 PS Erosion control acceptable at time of inspection 7-31-23 PS Erosion control acceptable at time of inspection 8-3-23 PS Erosion control acceptable at time of inspection 8-14-23 PS Erosion control acceptable at time of inspection
ESC - (Vegetation/Ground Cover) Passed 9/11/2023 9/11/2023 09/11/2023
Misc
Informational
09/11/2023
9-11-23 PS Sod has been installed at project and is being watered on daily basis. Trees/vegetation planted on perimeter of basin and bio retention basin. Mulch has been added throughout bio retention basin
Site Visit Partial 9/11/2023 9/11/2023 09/11/2023
Misc
Informational
08/25/2023
4-3-23 PS Made site visit, no construction on site yet. 4-10-23 PS Meet Scott with Trinity excavation on site to inspect project erosion control and timeline. Construction expected to begin tomorrow 4-11-23 4-11-23 PS Contractor mobilizing equipment on site. No work at time of inspection. 4-12-23 PS Contractor has begun soil excavation of existing basin 4-13-23 PS Contractor continuing with site excavation 4-14-23 PS Contractor continuing with excavation of basin 4-17-23 PS Contractor on site excavating and breaking rock at basin 4-18-23 PS Contractor on site excavating at basin 4-19-23 PS Contractor continuing basin excavation and breaking rock 4-21-23 PS No work for development today 4-24-23 PS No work for development today 4-25-23 PS No work for development today 4-26-23 PS No work for development today 4-27-23 PS No work for development today 5-1-23 PS Contractor is on site breaking rock and excavating at basin 5-2-23 PS Contractor excavating basin and breaking rock 5-3-23 PS Contractor excavating basin 5-4-23 PS Contractor excavating basin 5-5-23 PS Contractor excavating basin 5-8-23 PS Contractor excavating basin 5-9-23 PS Contractor working to remove spoils piles from excavation 5-10-23 PS Contractor continuing to remove spoils piles from excavation 5-12-23 PS Contractor excavating at basin and removing spoils piles 5-19-23 PS Contractor placing rip rap along sides of basin 5-22-23 PS Contractor continuing to spread rip rap and site cleanup 5-23-23 PS No work on site 5-24-23 PS No work on site today. Contractor has removed equipment from site. 5-30-23 PS No work on site 6-2-23 PS No work on site today 6-5-23 PS No work on site today 6-21-23 PS Crew on site boring for electrical for basin water feature 6-22-23 PS No work on site for development today 6-23-23 PS Electrical trade on site working on electrical for water feature 7-3-23 PS No work on site for development today 7-6-23 PS Crew grading at basin and bio retention for landscaping 7-10-23 PS Landscaping contractor on site working 7-11-23 PS Landscaping contractors on site working 7-20-23 PS No work on site 7-26-23 PS Landscaping contractor on site 7-27-23 PS No activity on site 8-2-23 PS No activity on site 8-4-23 PS Landscaping contractor setting landscape rocks at basin 8-7-23 PS Landscape crew setting landscape rocks and trees at basin 8-9-23 PS Landscape crew has planted trees and placed sod and vegetation at basin 8-10-23 PS No activity on site 8-14-23 PS No activity on site, contractor has placed landscaping rocks, trees, vegetation 8-15-23 PS No activity on site 8-16-23 PS Vegetation has been placed throughout bio retention basin. Water feature has been installed at basin 8-21-23 PS No activity on site 8-22-23 PS No activity on site 8-24-23 PS Landscaper on site 8-25-23 PS No activity on site 9-11-23 PS Sod has been installed at project and is being watered on daily basis. Trees/vegetation planted on perimeter of basin and bio retention basin. Mulch has been added throughout bio retention basin. As built required on basin
Documents & Images
Date Uploaded File Type Document Name
03/14/2023 FeeWorkseetPrincetonPermanentPool
03/14/2023 STAMPED PLANS APPROVED - PRINCETON STORMWATER REVISIONS
03/30/2023 Receipt Receipt for transaction: 2023-001793
03/30/2023 Letter DE-Permit
04/03/2023 Letter INSPECTION SUMMARY
04/10/2023 Letter INSPECTION SUMMARY
04/10/2023 Letter INSPECTION SUMMARY
04/11/2023 Letter INSPECTION SUMMARY
04/12/2023 Letter INSPECTION SUMMARY
04/12/2023 Letter INSPECTION SUMMARY
04/13/2023 Letter INSPECTION SUMMARY
04/14/2023 Letter INSPECTION SUMMARY
04/13/2023 Receipt Receipt for transaction: 2023-002063
04/17/2023 Letter INSPECTION SUMMARY
04/18/2023 Letter INSPECTION SUMMARY
04/19/2023 Letter INSPECTION SUMMARY
04/20/2023 Letter INSPECTION SUMMARY
04/21/2023 Letter INSPECTION SUMMARY
04/24/2023 Letter INSPECTION SUMMARY
04/25/2023 Letter INSPECTION SUMMARY
04/26/2023 Letter INSPECTION SUMMARY
04/27/2023 Letter INSPECTION SUMMARY
04/28/2023 Letter INSPECTION SUMMARY
05/01/2023 Letter INSPECTION SUMMARY
05/02/2023 Letter INSPECTION SUMMARY
05/03/2023 Letter INSPECTION SUMMARY
05/04/2023 Letter INSPECTION SUMMARY
05/05/2023 Letter INSPECTION SUMMARY
05/08/2023 Letter INSPECTION SUMMARY
05/09/2023 Letter INSPECTION SUMMARY
05/10/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
05/12/2023 Letter INSPECTION SUMMARY
05/15/2023 Letter INSPECTION SUMMARY
05/17/2023 Letter Stop Work Order
05/19/2023 Letter INSPECTION SUMMARY
05/19/2023 Letter INSPECTION SUMMARY
05/22/2023 Letter INSPECTION SUMMARY
05/23/2023 Letter INSPECTION SUMMARY
05/24/2023 Letter INSPECTION SUMMARY
05/30/2023 Letter INSPECTION SUMMARY
05/31/2023 Letter INSPECTION SUMMARY
06/01/2023 Letter INSPECTION SUMMARY
06/02/2023 Letter INSPECTION SUMMARY
06/05/2023 Letter INSPECTION SUMMARY
06/05/2023 Letter INSPECTION SUMMARY
06/06/2023 Letter INSPECTION SUMMARY
06/07/2023 Letter INSPECTION SUMMARY
06/15/2023 Letter INSPECTION SUMMARY
06/19/2023 Letter INSPECTION SUMMARY
06/21/2023 Letter INSPECTION SUMMARY
06/22/2023 Letter INSPECTION SUMMARY
06/23/2023 Letter INSPECTION SUMMARY
06/28/2023 Letter INSPECTION SUMMARY
07/03/2023 Letter INSPECTION SUMMARY
07/05/2023 Letter INSPECTION SUMMARY
07/06/2023 Letter INSPECTION SUMMARY
07/10/2023 Letter INSPECTION SUMMARY
07/11/2023 Letter INSPECTION SUMMARY
07/13/2023 Letter INSPECTION SUMMARY
07/17/2023 Letter INSPECTION SUMMARY
07/18/2023 Letter INSPECTION SUMMARY
07/19/2023 Letter INSPECTION SUMMARY
07/20/2023 Letter INSPECTION SUMMARY
07/21/2023 Letter INSPECTION SUMMARY
07/24/2023 Letter INSPECTION SUMMARY
07/26/2023 Letter INSPECTION SUMMARY
07/27/2023 Letter INSPECTION SUMMARY
07/28/2023 Letter INSPECTION SUMMARY
07/31/2023 Letter INSPECTION SUMMARY
08/02/2023 Letter INSPECTION SUMMARY
08/03/2023 Letter INSPECTION SUMMARY
08/04/2023 Letter INSPECTION SUMMARY
08/07/2023 Letter INSPECTION SUMMARY
08/09/2023 Letter INSPECTION SUMMARY
08/09/2023 Letter INSPECTION SUMMARY
08/10/2023 Letter INSPECTION SUMMARY
08/14/2023 Letter INSPECTION SUMMARY
08/14/2023 Letter INSPECTION SUMMARY
08/15/2023 Letter INSPECTION SUMMARY
08/16/2023 Letter INSPECTION SUMMARY
08/21/2023 Letter INSPECTION SUMMARY
08/22/2023 Letter INSPECTION SUMMARY
08/24/2023 Letter INSPECTION SUMMARY
08/25/2023 Letter INSPECTION SUMMARY
09/11/2023 Letter INSPECTION SUMMARY
09/11/2023 Letter INSPECTION SUMMARY
09/11/2023 Letter INSPECTION SUMMARY
09/11/2023 Letter INSPECTION SUMMARY
10/19/2023 Letter DE-Certificate of Final Acceptance (Commercial)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home