Summary


PRSITE20183936
Development - Site
Final Acceptance
CHOYCE LLC
DEVELOPMENT COMPLETE
Full site development
11/20/2018
12/03/2018
07/08/2020
Locations
Contacts
CHOYCE LLC, Address:PO BOX 847  
KEVIN HIGDON CONSTRUCTION, LLC, Address:P O BOX 847, Phone:(816) 524-9797  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 11/20/2018 11/30/2018
Steve Robbins
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $100.42 $100.42 Paid 11/21/2018
91100C9-Water Insp Fee $1,475.11 $1,475.11 Paid 11/21/2018
$1,475.12
9110072-Water Test Fee $200.00 $200.00 Paid 11/21/2018
9110068-Storm Fee $224.07 $224.07 Paid 11/21/2018
9110081-Street Inspections $1,117.02 $1,117.02 Paid 11/21/2018
9110071-Site Grading Fee $178.25 $178.25 Paid 11/21/2018
8331401-Water Tap Fee $3,409.00 $3,409.00 Paid 11/21/2018
8350015-Water Meter Fee $408.37 $408.37 Paid 11/21/2018
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Partial 12/3/2018 at 9:00 AM 12/03/2018
Misc
Informational
12/03/2018
The erosion control silt fence is installed and up properly.Steve Robbins 12/03/2018 3:31 PM
Erosion Control Inspection Passed 3/5/2019 at 10:00 AM 03/05/2019
Misc
Informational
12/03/2018
The erosion control silt fence is installed and up properly.Steve Robbins 12/03/2018 3:31 PM
PW-Misc
Informational
03/05/2019
The erosion control silt fence is still up appears to be in good condition. They have done a little foundation work but no infrastructure yet.Steve Robbins 03/05/2019 1:13 PM
Storm Sewer Construction Inspection Partial 06/14/2019
Misc
Informational
06/14/2019
Crew installed approx 200 LF of the HDPE storm line on site. The crew also stubbed into the existing field inlet structure. Crew is going to pour collar at later date. Photos are attached.
Water Line - Construction Inspection Failed 7/11/2019 07/11/2019
Corrective Action Required
07/11/2019
FIeld Engineering Inspectors John Dimauro and Marquelle Williams were doing a water construction inspection and discovered the contractor installed a 6x2 tee for the service connection instead of getting a tap from the water dept. When the water dept brought out the meter and pit they said the tap was done incorrectlyl and was suppose to be done by the water dept. Upon further review the water dept. has directed us to have the contractor remove the 6" gate valve and the valve on the fire hydrant assembly on the west side of the road. There will be one valve on the east side of the road where the main is located. The water dept. has stated that it is good practice to not have too many valves and in this case the only valve for the fire hydrant and water shut-off will be on the east side of the road on the main.
Driveway Inspection Partial 08/23/2019
Misc
Informational
08/23/2019
PRE POUR INSPECTION The crew has the commercial drive approach formed up. There appears to be sufficient compacted aggregate. The forms appear to be set for commercial depth. Curb will be poured monolithic.
Water Line - Construction Inspection Partial 8/23/2019 8/23/2019 08/23/2019
Misc
Informational
08/23/2019
The water line and hydrant appear to be installed according to the approved redesigned plan sheet with direction from the City of Lee’s Summit Water Utilities Dept. to not install a gate valve for isolating the hydrant. The crew is going to pour the thrust block at the 90° Bend this afternoon and will leave the trench and block exposed for inspection on Monday 8/26/19.
Erosion Control Inspection Failed 1/16/2020 01/16/2020
Misc
Corrective Action Required
01/16/2020
The large pile of dirt next to the building needs to have silt fence around it. Contractor has stated to the inspector that he would be moving the dirt soon, this has not happened, so some type of ESC needs to be installed.
Sanitary Sewer Construction Inspection Passed 2/19/2020 02/19/2020
Grading/Excavation/Fill Inspection Partial 2/19/2020 02/19/2020
Misc
Informational
02/19/2020
Final grade has not been completed, detention basin has been done. They are still working on installing sprinkler system and then will install sod.
Curb - Proof Roll Passed 02/19/2020
Storm - Material Verification Passed 02/19/2020
Storm - Pipe Passed 02/19/2020
Storm - Inlets Clean Passed 02/19/2020
Storm - Outlet Structure Passed 02/19/2020
Storm - Rip Rap Partial 2/19/2020 02/19/2020
Misc
Corrective Action Required
02/19/2020
All the rip-rap has been installed, the rip-rap by the flared end section in the detention basin needs to be cleaned out and possibly have a little more rip-rap installed.
Sewer Service Inspection Passed 02/24/2020
Sanitary Sewer Construction Inspection Passed 02/24/2020
Storm - Material Verification Passed 02/24/2020
Storm Sewer Construction Inspection Passed 02/24/2020
Misc
Informational
06/14/2019
Crew installed approx 200 LF of the HDPE storm line on site. The crew also stubbed into the existing field inlet structure. Crew is going to pour collar at later date. Photos are attached.
Driveway Inspection Passed 02/24/2020
Misc
Informational
08/23/2019
PRE POUR INSPECTION The crew has the commercial drive approach formed up. There appears to be sufficient compacted aggregate. The forms appear to be set for commercial depth. Curb will be poured monolithic.
ESC - (Vegetation/Ground Cover) Partial 6/15/2020 06/15/2020
Misc
Informational
06/15/2020
Sod has been installed around the entire building and the seed is beginning to come up on the lot next door.
Erosion Control Inspection Passed 3/3/2020 07/08/2020
Misc
Corrective Action Required
01/16/2020
The large pile of dirt next to the building needs to have silt fence around it. Contractor has stated to the inspector that he would be moving the dirt soon, this has not happened, so some type of ESC needs to be installed.
Grading/Excavation/Fill Inspection Passed 3/17/2020 07/08/2020
Storm - Rip Rap Passed 3/17/2020 07/08/2020
Misc
Corrective Action Required
02/19/2020
All the rip-rap has been installed, the rip-rap by the flared end section in the detention basin needs to be cleaned out and possibly have a little more rip-rap installed.
Water Service Inspection Passed 7/8/2020 07/08/2020
Misc
Corrective Action Required
04/17/2020
I received a call from the water dept. to meet them at the job site today. The connection for the service line has a leak at the main where the copper has been connected to the main. It appears that it just needs to be tighten up , they did not want to touch it because they didn't install it. The other reason they came out was to verify the serial number on the meter that was installed. When they looked at the meter it appears that you have 3/4 "meter and have installed a 1" copper line coming out of the meter. The water dept. is requesting that you install a 3/4" piece of copper coming out of the meter for 10 ft and then you can transition to whatever size you want after that. They also noted that the valve box on the fire hydrant is covered with dirt, may need to be raised.
Site Visit Complete 5/6/2020 07/08/2020
Misc
Corrective Action Required
04/17/2020
I received a call from the water dept. to meet them at the job site today. The connection for the service line has a leak at the main where the copper has been connected to the main. It appears that it just needs to be tighten up , they did not want to touch it because they didn't install it. The other reason they came out was to verify the serial number on the meter that was installed. When they looked at the meter it appears that you have 3/4 "meter and have installed a 1" copper line coming out of the meter. The water dept. is requesting that you install a 3/4" piece of copper coming out of the meter for 10 ft and then you can transition to whatever size you want after that. They also noted that the valve box on the fire hydrant is covered with dirt, may need to be raised.
Misc
Resolved
07/08/2020
The corrections have been made.
ESC - (Vegetation/Ground Cover) Passed 7/8/2020 07/08/2020
Misc
Informational
06/15/2020
Sod has been installed around the entire building and the seed is beginning to come up on the lot next door.
Documents & Images
Date Uploaded File Type Document Name
11/21/2018 Receipt Receipt for transaction: 2018-007338
12/03/2018 Letter DE-Permit
12/04/2018 Newberry Landing Lot 293
03/05/2019 Letter DE-Daily Inspection Summary
06/14/2019 Storm sewer trench
06/14/2019 Letter INSPECTION SUMMARY
07/11/2019 Letter DE-Daily Inspection Summary
08/23/2019 Letter INSPECTION SUMMARY
08/23/2019 .jpg
08/23/2019 image
08/23/2019 Letter INSPECTION SUMMARY
01/16/2020 Letter DE-Daily Inspection Summary
02/19/2020 Letter DE-Daily Inspection Summary
02/19/2020 Letter DE-Daily Inspection Summary
02/27/2020 Letter DE-Certificate of Substantial Completion Multiple Lot
02/27/2020 Letter DE-Punch List
03/02/2020 Binder1
04/17/2020 Letter DE-Daily Inspection Summary
06/15/2020 Letter DE-Daily Inspection Summary
07/08/2020 Letter DE-Daily Inspection Summary
07/08/2020 Newberry Landing- Lot 293 Final Accetptance
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home