Permit Application Status

PRSITE20180219


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSITE20180219
Development - Site
Final Acceptance
PARROT PROPERTIES INC - John Bondon
DEVELOPMENT COMPLETE
01/30/2018
05/02/2018
12/21/2021
Locations
Contacts
CITYSCAPE CONSTRUCTION VIEW HIGH LLC, Address:10 W CARMEL DR STE 200, Phone:(317) 574-1600 Ext:100  
PARROT PROPERTIES INC - John Bondon, Address:11303 VIEW HIGH DR, Phone:(816) 616-2208  
RYAN ADAMS, Phone:(913) 216-0124  
CITY OF LEES SUMMIT MISSOURI, Address:220 SE GREEN ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 01/30/2018 02/20/2018
Steve Robbins
Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Insp Fees $5,010.41 $5,010.41 Paid 01/30/2018
Water Insp Fee $9,962.20 $9,962.20 Paid 01/30/2018
Water Test Fee $800.00 $800.00 Paid 01/30/2018
Storm Sewer Inspection Fee $15,303.71 $15,303.71 Paid 01/30/2018
Paved Surface Inspection Fee $29,825.08 $29,825.08 Paid 01/30/2018
$29,825.09
Site Grading Fee $31,542.95 $31,542.95 Paid 01/30/2018
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Passed 02/21/2018
Sanitary Sewer Construction Inspection Partial 6/5/2018 at 10:45 AM 06/05/2018
PW-Main inspection
Informational
06/05/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
Sanitary Sewer Construction Inspection Partial 6/6/2018 at 9:00 AM 06/06/2018
PW-Main inspection
Informational
06/05/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/06/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
Sanitary Sewer Construction Inspection Partial 6/6/2018 at 2:00 PM 06/06/2018
PW-Main inspection
Informational
06/06/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/06/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/06/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
Sanitary Sewer Construction Inspection Partial 6/7/2018 at 2:00 PM 06/07/2018
PW-Main inspection
Informational
06/06/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/06/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/06/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/07/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
Sanitary Sewer Construction Inspection Partial 6/8/2018 at 2:45 PM 06/08/2018
PW-Main inspection
Informational
06/07/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/07/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/07/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/07/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/08/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
Sanitary Sewer Construction Inspection Partial 6/11/2018 at 8:55 AM 06/11/2018
PW-Main inspection
Informational
06/08/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/08/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/08/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/08/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/08/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/11/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
Sanitary Sewer Construction Inspection Partial 6/13/2018 at 8:58 AM 06/13/2018
PW-Main inspection
Informational
06/11/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/11/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/11/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/11/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/11/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/11/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
06/13/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
Sanitary Sewer Construction Inspection Partial 6/13/2018 at 1:00 PM 06/13/2018
PW-Main inspection
Informational
06/13/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/13/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/13/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/13/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/13/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/13/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
06/13/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
06/13/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
Sanitary Sewer Construction Inspection Partial 6/14/2018 at 10:30 AM 06/15/2018
PW-Main inspection
Informational
06/13/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/13/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/13/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/13/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/13/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/13/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
06/13/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
06/13/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
06/15/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
Sanitary Sewer Construction Inspection Partial 6/15/2018 at 10:30 AM 06/15/2018
PW-Main inspection
Informational
06/15/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/15/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/15/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/15/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/15/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/15/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
06/15/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
06/15/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
06/15/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
06/15/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
Sanitary Sewer Construction Inspection Partial 6/18/2018 at 9:10 AM 06/18/2018
PW-Main inspection
Informational
06/15/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/15/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/15/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/15/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/15/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/15/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
06/15/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
06/15/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
06/15/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
06/15/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
06/18/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
Sanitary Sewer Construction Inspection Partial 6/19/2018 at 10:30 AM 06/19/2018
PW-Main inspection
Informational
06/18/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/18/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/18/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/18/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/18/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/18/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
06/18/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
06/18/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
06/18/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
06/18/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
06/18/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
06/19/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
Sanitary Sewer Construction Inspection Partial 6/22/2018 at 9:00 AM 06/22/2018
PW-Main inspection
Informational
06/19/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/19/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/19/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/19/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/19/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/19/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
06/19/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
06/19/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
06/19/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
06/19/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
06/19/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
06/19/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
06/22/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
Sanitary Sewer Construction Inspection Partial 6/25/2018 at 11:00 AM 06/25/2018
PW-Main inspection
Informational
06/22/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/22/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/22/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/22/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/22/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/22/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
06/22/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
06/22/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
06/22/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
06/22/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
06/22/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
06/22/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
06/22/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
06/25/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
Storm Sewer Construction Inspection Partial 6/28/2018 at 12:30 PM 06/28/2018
PW-Storm Sewer Inspection
Informational
06/28/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
Sanitary Sewer Construction Inspection Partial 6/29/2018 at 9:00 AM 06/29/2018
PW-Main inspection
Informational
06/25/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/25/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/25/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/25/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/25/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/25/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
06/25/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
06/25/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
06/25/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
06/25/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
06/25/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
06/25/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
06/25/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
06/25/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
06/29/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
Storm Sewer Construction Inspection Partial 7/5/2018 at 1:00 PM 07/05/2018
PW-Storm Sewer Inspection
Informational
06/28/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
07/05/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
Sanitary Sewer Construction Inspection Partial 7/5/2018 at 1:30 PM 07/05/2018
PW-Main inspection
Informational
06/29/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
06/29/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
06/29/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
06/29/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
06/29/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
06/29/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
06/29/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
06/29/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
06/29/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
06/29/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
06/29/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
06/29/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
06/29/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
06/29/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
06/29/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
PW-Main inspection
Informational
07/05/2018
Everything is completed up to MH A-7 including inverts and trench checks. They have stopped working on the sanitary for now and have moved to the storm sewer.Steve Robbins 07/05/2018 2:56 PM
Storm Sewer Construction Inspection Partial 7/9/2018 at 12:00 PM 07/09/2018
PW-Storm Sewer Inspection
Informational
07/05/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
07/05/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
07/09/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
Storm Sewer Construction Inspection Partial 7/10/2018 at 12:45 PM 07/10/2018
PW-Storm Sewer Inspection
Informational
07/09/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
07/09/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
07/09/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
07/10/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
Storm Sewer Construction Inspection Partial 7/11/2018 at 11:45 AM 07/11/2018
PW-Storm Sewer Inspection
Informational
07/10/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
07/10/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
07/10/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
07/10/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
07/11/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
Storm Sewer Construction Inspection Partial 7/13/2018 at 1:30 PM 07/13/2018
PW-Storm Sewer Inspection
Informational
07/11/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
07/11/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
07/11/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
07/11/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
07/11/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
07/13/2018
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
Storm Sewer Construction Inspection Partial 7/16/2018 at 11:40 AM 07/16/2018
PW-Storm Sewer Inspection
Informational
07/13/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
07/13/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
07/13/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
07/13/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
07/13/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
07/13/2018
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
PW-Storm Sewer Inspection
Informational
07/16/2018
They are now working on the rcp line coming out of the retention basin.. They are now on the 4th stick of pipe. They were not working on the other line today.Steve Robbins 07/16/2018 3:08 PM
Storm Sewer Construction Inspection Partial 7/17/2018 at 1:15 PM 07/17/2018
PW-Storm Sewer Inspection
Informational
07/16/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
07/16/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
07/16/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
07/16/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
07/16/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
07/16/2018
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
PW-Storm Sewer Inspection
Informational
07/16/2018
They are now working on the rcp line coming out of the retention basin.. They are now on the 4th stick of pipe. They were not working on the other line today.Steve Robbins 07/16/2018 3:08 PM
PW-Storm Sewer Inspection
Informational
07/17/2018
They are still working on the rcp pipe it appears to be on the 5th stick of pipe, they are encasing with rock and backfilling. On the other storm line coming out of the retention basin they are installing box 105.Steve Robbins 07/17/2018 3:55 PM
Storm Sewer Construction Inspection Partial 7/20/2018 at 2:00 PM 07/20/2018
PW-Storm Sewer Inspection
Informational
07/17/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
07/17/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
07/17/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
07/17/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
07/17/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
07/17/2018
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
PW-Storm Sewer Inspection
Informational
07/17/2018
They are now working on the rcp line coming out of the retention basin.. They are now on the 4th stick of pipe. They were not working on the other line today.Steve Robbins 07/16/2018 3:08 PM
PW-Storm Sewer Inspection
Informational
07/17/2018
They are still working on the rcp pipe it appears to be on the 5th stick of pipe, they are encasing with rock and backfilling. On the other storm line coming out of the retention basin they are installing box 105.Steve Robbins 07/17/2018 3:55 PM
PW-Storm Sewer Inspection
Informational
07/20/2018
The concrete encasement next to box 105 has been installed as is the encasement for 101 and 100. Also, the storm boxes for 104, 103, 102, 101, and 100 have been installed in the past 3 days. Line 1 has been installed with 177 ft of rcp and box 8 was installed.Steve Robbins 07/20/2018 4:10 PM
Sanitary Sewer Construction Inspection Partial 7/23/2018 at 1:30 PM 07/20/2018
PW-Main inspection
Informational
07/05/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
07/05/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
07/05/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
07/05/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
07/05/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
07/05/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
07/05/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
07/05/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
07/05/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
07/05/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
07/05/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
07/05/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
07/05/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
07/05/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
07/05/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
PW-Main inspection
Informational
07/05/2018
Everything is completed up to MH A-7 including inverts and trench checks. They have stopped working on the sanitary for now and have moved to the storm sewer.Steve Robbins 07/05/2018 2:56 PM
PW-Main inspection
Informational
07/20/2018
MH A-3 has been installed they are working toward A-4 and the service line that is before a-4.Steve Robbins 07/20/2018 4:23 PM
Sanitary Sewer Construction Inspection Partial 7/23/2018 at 1:15 PM 07/23/2018
PW-Main inspection
Informational
07/20/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
07/20/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
07/20/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
07/20/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
07/20/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
07/20/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
07/20/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
07/20/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
07/20/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
07/20/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
07/20/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
07/20/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
07/20/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
07/20/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
07/20/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
PW-Main inspection
Informational
07/20/2018
Everything is completed up to MH A-7 including inverts and trench checks. They have stopped working on the sanitary for now and have moved to the storm sewer.Steve Robbins 07/05/2018 2:56 PM
PW-Main inspection
Informational
07/20/2018
MH A-3 has been installed they are working toward A-4 and the service line that is before a-4.Steve Robbins 07/20/2018 4:23 PM
PW-Main inspection
Informational
07/23/2018
They are still moving toward A-4 , they have installed a wye for the service line, they have not installed the trench check yet.Steve Robbins 07/23/2018 2:25 PM
Storm Sewer Construction Inspection Partial 7/23/2018 at 2:00 PM 07/23/2018
PW-Storm Sewer Inspection
Informational
07/20/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
07/20/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
07/20/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
07/20/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
07/20/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
07/20/2018
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
PW-Storm Sewer Inspection
Informational
07/20/2018
They are now working on the rcp line coming out of the retention basin.. They are now on the 4th stick of pipe. They were not working on the other line today.Steve Robbins 07/16/2018 3:08 PM
PW-Storm Sewer Inspection
Informational
07/20/2018
They are still working on the rcp pipe it appears to be on the 5th stick of pipe, they are encasing with rock and backfilling. On the other storm line coming out of the retention basin they are installing box 105.Steve Robbins 07/17/2018 3:55 PM
PW-Storm Sewer Inspection
Informational
07/20/2018
The concrete encasement next to box 105 has been installed as is the encasement for 101 and 100. Also, the storm boxes for 104, 103, 102, 101, and 100 have been installed in the past 3 days. Line 1 has been installed with 177 ft of rcp and box 8 was installed.Steve Robbins 07/20/2018 4:10 PM
PW-Storm Sewer Inspection
Informational
07/23/2018
They are working on installing box 100, they hit a lot of shale. Steve Robbins 07/23/2018 2:36 PM
Retaining Wall Inspection Partial 7/23/2018 at 2:25 PM 07/23/2018
Informational
07/23/2018
The retaining wall by view high dr. has been completed, the 3rd party inspector has been out checking this and sending his reports. There are several more retaining walls to be completed in the project.Steve Robbins 07/23/2018 4:29 PM
Sanitary Sewer Construction Inspection Partial 7/30/2018 at 10:15 AM 07/30/2018
PW-Main inspection
Informational
07/23/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
07/23/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
07/23/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
07/23/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
07/23/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
07/23/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
07/23/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
07/23/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
07/23/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
07/23/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
07/23/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
07/23/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
07/23/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
07/23/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
07/23/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
PW-Main inspection
Informational
07/23/2018
Everything is completed up to MH A-7 including inverts and trench checks. They have stopped working on the sanitary for now and have moved to the storm sewer.Steve Robbins 07/05/2018 2:56 PM
PW-Main inspection
Informational
07/23/2018
MH A-3 has been installed they are working toward A-4 and the service line that is before a-4.Steve Robbins 07/20/2018 4:23 PM
PW-Main inspection
Informational
07/23/2018
They are still moving toward A-4 , they have installed a wye for the service line, they have not installed the trench check yet.Steve Robbins 07/23/2018 2:25 PM
PW-Main inspection
Informational
07/30/2018
It appears that a-4 and the service line to the building by a-4 has been installed. They are working toward a-5 which has already been installed.Steve Robbins 07/30/2018 2:43 PM
Sanitary Sewer Construction Inspection Partial 7/31/2018 at 2:30 PM 08/01/2018
PW-Main inspection
Informational
07/30/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
07/30/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
07/30/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
07/30/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
07/30/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
07/30/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
07/30/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
07/30/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
07/30/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
07/30/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
07/30/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
07/30/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
07/30/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
07/30/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
07/30/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
PW-Main inspection
Informational
07/30/2018
Everything is completed up to MH A-7 including inverts and trench checks. They have stopped working on the sanitary for now and have moved to the storm sewer.Steve Robbins 07/05/2018 2:56 PM
PW-Main inspection
Informational
07/30/2018
MH A-3 has been installed they are working toward A-4 and the service line that is before a-4.Steve Robbins 07/20/2018 4:23 PM
PW-Main inspection
Informational
07/30/2018
They are still moving toward A-4 , they have installed a wye for the service line, they have not installed the trench check yet.Steve Robbins 07/23/2018 2:25 PM
PW-Main inspection
Informational
07/30/2018
It appears that a-4 and the service line to the building by a-4 has been installed. They are working toward a-5 which has already been installed.Steve Robbins 07/30/2018 2:43 PM
PW-Main inspection
Informational
08/01/2018
They have laid pipe to MH a-5 and the 2 service lines have been installed, the trench checks have not yet been installed. They are installing invert for a-3, a-4 and a-5.Steve Robbins 08/01/2018 3:14 PM
Storm Sewer Construction Inspection Partial 8/1/2018 at 2:50 PM 08/01/2018
PW-Storm Sewer Inspection
Informational
07/23/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
07/23/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
07/23/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
07/23/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
07/23/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
07/23/2018
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
PW-Storm Sewer Inspection
Informational
07/23/2018
They are now working on the rcp line coming out of the retention basin.. They are now on the 4th stick of pipe. They were not working on the other line today.Steve Robbins 07/16/2018 3:08 PM
PW-Storm Sewer Inspection
Informational
07/23/2018
They are still working on the rcp pipe it appears to be on the 5th stick of pipe, they are encasing with rock and backfilling. On the other storm line coming out of the retention basin they are installing box 105.Steve Robbins 07/17/2018 3:55 PM
PW-Storm Sewer Inspection
Informational
07/23/2018
The concrete encasement next to box 105 has been installed as is the encasement for 101 and 100. Also, the storm boxes for 104, 103, 102, 101, and 100 have been installed in the past 3 days. Line 1 has been installed with 177 ft of rcp and box 8 was installed.Steve Robbins 07/20/2018 4:10 PM
PW-Storm Sewer Inspection
Informational
07/23/2018
They are working on installing box 100, they hit a lot of shale. Steve Robbins 07/23/2018 2:36 PM
PW-Storm Sewer Inspection
Informational
08/01/2018
Stormbox 64,63, and 62 have all been installed. They have also installed 110,120,121, and 130. They will be working toward 61 and 60 tomorrow. Today they were also pouring inverts on several of the structures.Steve Robbins 08/01/2018 3:35 PM
Water Line - Construction Inspection Partial 8/13/2018 at 1:45 PM 08/13/2018
PW-Main inspection
Informational
08/13/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
Water Line - Construction Inspection Partial 8/15/2018 at 2:45 PM 08/15/2018
PW-Main inspection
Informational
08/13/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
PW-Main inspection
Informational
08/15/2018
They have installed the waterline up to bldg. 3 they have poured the thrust blocks for the turn going to 3. The tees are coming in the morning so they can begin the service line connections.Steve Robbins 08/15/2018 3:52 PM
Water Line - Construction Inspection Partial 8/24/2018 at 10:30 AM 08/24/2018
PW-Main inspection
Informational
08/15/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
PW-Main inspection
Informational
08/15/2018
They have installed the waterline up to bldg. 3 they have poured the thrust blocks for the turn going to 3. The tees are coming in the morning so they can begin the service line connections.Steve Robbins 08/15/2018 3:52 PM
PW-Main inspection
Informational
08/24/2018
The water and fireline has been installed up to building 5, they are installing service lines and fire hydrants as they go. They are also installing thrust blocks.Steve Robbins 08/24/2018 3:53 PM
Storm Sewer Construction Inspection Partial 8/24/2018 at 10:50 AM 08/24/2018
PW-Storm Sewer Inspection
Informational
08/01/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
08/01/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
08/01/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
08/01/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
08/01/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
08/01/2018
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
PW-Storm Sewer Inspection
Informational
08/01/2018
They are now working on the rcp line coming out of the retention basin.. They are now on the 4th stick of pipe. They were not working on the other line today.Steve Robbins 07/16/2018 3:08 PM
PW-Storm Sewer Inspection
Informational
08/01/2018
They are still working on the rcp pipe it appears to be on the 5th stick of pipe, they are encasing with rock and backfilling. On the other storm line coming out of the retention basin they are installing box 105.Steve Robbins 07/17/2018 3:55 PM
PW-Storm Sewer Inspection
Informational
08/01/2018
The concrete encasement next to box 105 has been installed as is the encasement for 101 and 100. Also, the storm boxes for 104, 103, 102, 101, and 100 have been installed in the past 3 days. Line 1 has been installed with 177 ft of rcp and box 8 was installed.Steve Robbins 07/20/2018 4:10 PM
PW-Storm Sewer Inspection
Informational
08/01/2018
They are working on installing box 100, they hit a lot of shale. Steve Robbins 07/23/2018 2:36 PM
PW-Storm Sewer Inspection
Informational
08/01/2018
Stormbox 64,63, and 62 have all been installed. They have also installed 110,120,121, and 130. They will be working toward 61 and 60 tomorrow. Today they were also pouring inverts on several of the structures.Steve Robbins 08/01/2018 3:35 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
No storm sewer has been done this week with the rain. They have just been doing water line work.Steve Robbins 08/24/2018 3:57 PM
Sanitary Sewer Construction Inspection Partial 8/30/2018 at 10:15 AM 08/30/2018
PW-Main inspection
Informational
08/01/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
08/01/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
08/01/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
08/01/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
08/01/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
08/01/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
08/01/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
08/01/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
08/01/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
08/01/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
08/01/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
08/01/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
08/01/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
08/01/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
08/01/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
PW-Main inspection
Informational
08/01/2018
Everything is completed up to MH A-7 including inverts and trench checks. They have stopped working on the sanitary for now and have moved to the storm sewer.Steve Robbins 07/05/2018 2:56 PM
PW-Main inspection
Informational
08/01/2018
MH A-3 has been installed they are working toward A-4 and the service line that is before a-4.Steve Robbins 07/20/2018 4:23 PM
PW-Main inspection
Informational
08/01/2018
They are still moving toward A-4 , they have installed a wye for the service line, they have not installed the trench check yet.Steve Robbins 07/23/2018 2:25 PM
PW-Main inspection
Informational
08/01/2018
It appears that a-4 and the service line to the building by a-4 has been installed. They are working toward a-5 which has already been installed.Steve Robbins 07/30/2018 2:43 PM
PW-Main inspection
Informational
08/01/2018
They have laid pipe to MH a-5 and the 2 service lines have been installed, the trench checks have not yet been installed. They are installing invert for a-3, a-4 and a-5.Steve Robbins 08/01/2018 3:14 PM
Informational
08/30/2018
They have not been doing any of the on-site private sanitary for awhile. Right now they are working on water.Steve Robbins 08/30/2018 10:48 AM
Water Line - Construction Inspection Partial 8/30/2018 at 10:30 AM 08/30/2018
PW-Main inspection
Informational
08/24/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
PW-Main inspection
Informational
08/24/2018
They have installed the waterline up to bldg. 3 they have poured the thrust blocks for the turn going to 3. The tees are coming in the morning so they can begin the service line connections.Steve Robbins 08/15/2018 3:52 PM
PW-Main inspection
Informational
08/24/2018
The water and fireline has been installed up to building 5, they are installing service lines and fire hydrants as they go. They are also installing thrust blocks.Steve Robbins 08/24/2018 3:53 PM
Informational
08/30/2018
The Bair contractors are not working today, they are still on the backflow preventer and the vault for the meter that is for the private water line.Steve Robbins 08/30/2018 10:53 AM
Water Line - Construction Inspection Partial 9/4/2018 at 10:30 AM 09/04/2018
PW-Main inspection
Informational
08/30/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
PW-Main inspection
Informational
08/30/2018
They have installed the waterline up to bldg. 3 they have poured the thrust blocks for the turn going to 3. The tees are coming in the morning so they can begin the service line connections.Steve Robbins 08/15/2018 3:52 PM
Informational
09/04/2018
The contractors have installed the fire line and the service line up to building 8. During this process they have installed the fire hydrants , fire line , and service line with tees and thrust blocks. Today they are by building 8. Steve Robbins 09/04/2018 11:23 AM
Sanitary Sewer Construction Inspection Partial 9/11/2018 at 2:50 PM 09/11/2018
PW-Main inspection
Informational
08/30/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
08/30/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
08/30/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
08/30/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
08/30/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
08/30/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
08/30/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
08/30/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
08/30/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
08/30/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
08/30/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
08/30/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
08/30/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
08/30/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
08/30/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
PW-Main inspection
Informational
08/30/2018
Everything is completed up to MH A-7 including inverts and trench checks. They have stopped working on the sanitary for now and have moved to the storm sewer.Steve Robbins 07/05/2018 2:56 PM
PW-Main inspection
Informational
08/30/2018
MH A-3 has been installed they are working toward A-4 and the service line that is before a-4.Steve Robbins 07/20/2018 4:23 PM
PW-Main inspection
Informational
08/30/2018
They are still moving toward A-4 , they have installed a wye for the service line, they have not installed the trench check yet.Steve Robbins 07/23/2018 2:25 PM
PW-Main inspection
Informational
08/30/2018
It appears that a-4 and the service line to the building by a-4 has been installed. They are working toward a-5 which has already been installed.Steve Robbins 07/30/2018 2:43 PM
PW-Main inspection
Informational
09/11/2018
Bair has core drilled into public MH A-4 and is installing an 8" private main that has 3 wyes on this run. They have installed the 1st wye. They will install the trench checks later. Steve Robbins 09/11/2018 3:17 PM
Sanitary Sewer Construction Inspection Partial 9/21/2018 at 11:00 AM 09/21/2018
PW-Main inspection
Informational
09/11/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
09/11/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
09/11/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
09/11/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
09/11/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
09/11/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
09/11/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
09/11/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
09/11/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
09/11/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
09/11/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
09/11/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
09/11/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
09/11/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
09/11/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
PW-Main inspection
Informational
09/11/2018
Everything is completed up to MH A-7 including inverts and trench checks. They have stopped working on the sanitary for now and have moved to the storm sewer.Steve Robbins 07/05/2018 2:56 PM
PW-Main inspection
Informational
09/11/2018
MH A-3 has been installed they are working toward A-4 and the service line that is before a-4.Steve Robbins 07/20/2018 4:23 PM
PW-Main inspection
Informational
09/11/2018
They are still moving toward A-4 , they have installed a wye for the service line, they have not installed the trench check yet.Steve Robbins 07/23/2018 2:25 PM
PW-Main inspection
Informational
09/11/2018
It appears that a-4 and the service line to the building by a-4 has been installed. They are working toward a-5 which has already been installed.Steve Robbins 07/30/2018 2:43 PM
PW-Main inspection
Informational
09/11/2018
Bair has core drilled into public MH A-4 and is installing an 8" private main that has 3 wyes on this run. They have installed the 1st wye. They will install the trench checks later. Steve Robbins 09/11/2018 3:17 PM
Informational
09/21/2018
Bair is not working today, they are working on toward MH A-2.Steve Robbins 09/21/2018 3:44 PM
Storm Sewer Construction Inspection Partial 9/26/2018 at 7:45 AM 09/26/2018
PW-Storm Sewer Inspection
Informational
08/24/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
08/24/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
They are now working on the rcp line coming out of the retention basin.. They are now on the 4th stick of pipe. They were not working on the other line today.Steve Robbins 07/16/2018 3:08 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
They are still working on the rcp pipe it appears to be on the 5th stick of pipe, they are encasing with rock and backfilling. On the other storm line coming out of the retention basin they are installing box 105.Steve Robbins 07/17/2018 3:55 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
The concrete encasement next to box 105 has been installed as is the encasement for 101 and 100. Also, the storm boxes for 104, 103, 102, 101, and 100 have been installed in the past 3 days. Line 1 has been installed with 177 ft of rcp and box 8 was installed.Steve Robbins 07/20/2018 4:10 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
They are working on installing box 100, they hit a lot of shale. Steve Robbins 07/23/2018 2:36 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
Stormbox 64,63, and 62 have all been installed. They have also installed 110,120,121, and 130. They will be working toward 61 and 60 tomorrow. Today they were also pouring inverts on several of the structures.Steve Robbins 08/01/2018 3:35 PM
PW-Storm Sewer Inspection
Informational
08/24/2018
No storm sewer has been done this week with the rain. They have just been doing water line work.Steve Robbins 08/24/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
All the storm has been completed except for line 4 and part of line 3, they should be getting to this pretty soon.Steve Robbins 09/26/2018 8:00 AM
Sanitary Sewer Construction Inspection Partial 10/1/2018 at 9:00 AM 10/01/2018
PW-Main inspection
Informational
09/21/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
09/21/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
09/21/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
09/21/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
09/21/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
09/21/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
09/21/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
09/21/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
09/21/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
09/21/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
09/21/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
09/21/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
09/21/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
09/21/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
09/21/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
PW-Main inspection
Informational
09/21/2018
Everything is completed up to MH A-7 including inverts and trench checks. They have stopped working on the sanitary for now and have moved to the storm sewer.Steve Robbins 07/05/2018 2:56 PM
PW-Main inspection
Informational
09/21/2018
MH A-3 has been installed they are working toward A-4 and the service line that is before a-4.Steve Robbins 07/20/2018 4:23 PM
PW-Main inspection
Informational
09/21/2018
They are still moving toward A-4 , they have installed a wye for the service line, they have not installed the trench check yet.Steve Robbins 07/23/2018 2:25 PM
PW-Main inspection
Informational
09/21/2018
It appears that a-4 and the service line to the building by a-4 has been installed. They are working toward a-5 which has already been installed.Steve Robbins 07/30/2018 2:43 PM
PW-Main inspection
Informational
10/01/2018
It appears that all of A-line has been installed They still have some inverts to be installed.Steve Robbins 10/01/2018 9:24 AM
Water Line - Construction Inspection Partial 10/1/2018 at 9:15 AM 10/01/2018
PW-Main inspection
Informational
09/04/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
PW-Main inspection
Informational
10/01/2018
The water line has been installed up to building 10. The thrust blocks and fire hydrants have been installed up to this point.Steve Robbins 10/01/2018 9:44 AM
Fire Line - Hydrostatic Test Partial 10/1/2018 at 9:30 AM 10/01/2018
PW-Misc
Informational
10/01/2018
The hydrostatic pressure twst for the 4" service line has been passed. They are planning on possibly doing the fire line today.Steve Robbins 10/01/2018 9:51 AM
Fire Line - Hydrostatic Test Partial 10/2/2018 at 11:00 AM 10/04/2018
PW-Misc
Informational
10/01/2018
The hydrostatic pressure twst for the 4" service line has been passed. They are planning on possibly doing the fire line today.Steve Robbins 10/01/2018 9:51 AM
PW-Misc
Informational
10/04/2018
The hydrostatic pressure test for fire line has passed 200psi for 2hrs. This is a partial completion of the water lines that have been installed.Steve Robbins 10/04/2018 7:54 AM
Water Line - Construction Inspection Partial 10/12/2018 at 10:00 AM 10/12/2018
PW-Main inspection
Informational
10/01/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
PW-Main inspection
Informational
10/01/2018
The water line has been installed up to building 10. The thrust blocks and fire hydrants have been installed up to this point.Steve Robbins 10/01/2018 9:44 AM
PW-Main inspection
Corrective Action Required
10/12/2018
No work has been going on this entire week due to all the rain.Steve Robbins 10/12/2018 1:46 PM
Water Line - Construction Inspection Partial 10/24/2018 at 3:15 PM 10/24/2018
PW-Main inspection
Informational
10/12/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
PW-Main inspection
Informational
10/12/2018
The water line has been installed up to building 10. The thrust blocks and fire hydrants have been installed up to this point.Steve Robbins 10/01/2018 9:44 AM
PW-Main inspection
Corrective Action Required
10/12/2018
No work has been going on this entire week due to all the rain.Steve Robbins 10/12/2018 1:46 PM
Misc
Informational
10/24/2018
Bair is planning on starting up on the water again next week around building 10 and working toward the other backflow preventer.Steve Robbins 10/24/2018 3:37 PM
Sanitary Sewer Construction Inspection Passed 10/24/2018 at 2:00 PM 10/24/2018
PW-Main inspection
Informational
10/01/2018
The contractor, Bair Excavating has begun work on the private sanitary, they are installing 8" sdr 26. They started on MH A-5, the 12" public sanitary has not yet been installed and it will be installed by Blue Nile Construction. They started with MH A-5 and hit alot of rock today, when I left around 2:30 they did not have the MH installed yet.Steve Robbins 06/05/2018 3:30 PM
PW-Main inspection
Informational
10/01/2018
They are still hitting alot of rock and have not yet installed MH A-5. I will check back later.Steve Robbins 06/06/2018 9:25 AM
PW-Main inspection
Informational
10/01/2018
They are still working on trying to get MH a-5 installed because of all the rock they hit.Steve Robbins 06/06/2018 3:24 PM
PW-Main inspection
Informational
10/01/2018
They were still hitting alot of rock, MH A-5 has been installed, but not wrapped yet, the contractors were working on getting A-6 installed before they leave for the evening. They are installing sdr-26 12" pipe. I spoke with Dan about tracer wire for the service line on private and we will not require tracer wire but will require trench checks for the private service lines. Steve Robbins 06/07/2018 3:58 PM
PW-Main inspection
Informational
10/01/2018
They have installed MH a-5 and a-6 and the pipe in between them. They still hit alot of rock todaySteve Robbins 06/08/2018 3:35 PM.
PW-Main inspection
Informational
10/01/2018
The contractors are backfilling with 6" of rock and then dirt over the pipe they have installed. They are still hitting alot of rock so things are very slow moving.Steve Robbins 06/11/2018 9:14 AM
PW-Main inspection
Informational
10/01/2018
Brice Lawson 06/13/2018 3:41 PM Larry Bair construction continues installing the 8" SDR 26 sewer pipe between MH A6 and C1. They are getting close to installing MH C1.
PW-Main inspection
Informational
10/01/2018
Brice Lawson 06/13/2018 3:45 PM Larry Bair construction continues to install the 8" sanitary between mh A6 and C1. They are getting closer to getting ready to install mh C1.
PW-Main inspection
Informational
10/01/2018
The service line between a-6 and c-1 has been installed with a wye, but they have not done the trench check yet. MH c-1 has been installed and they pipe going toward MH c-2 , there will be one more service line going toward c-2.Steve Robbins 06/15/2018 7:13 AM
PW-Main inspection
Informational
10/01/2018
The MH C-1 has been installed and they were close to installing the next service line on c-line going towards c-2. They are planning on installing inverts and trench checks next week on what they have installed.Steve Robbins 06/15/2018 3:46 PM
PW-Main inspection
Informational
10/01/2018
The contractors are still workingt towards MH c-2, they have not pourd the trench checks yet.Steve Robbins 06/18/2018 12:04 PM
PW-Main inspection
Informational
10/01/2018
Brice Lawson 06/19/2018 3:43 PM The base for mh c-2 is in place. The sanitary main has been connected to it. The contractor was in the process of excating the trench for the NW stub at mh C-2. They were getting ready to install the stub without a riser and I informed them that the plans show a riser to be installed on the stub. I also informed them that a trench check is required on the two proposed stubs that will connect to MH C-2.
PW-Main inspection
Informational
10/01/2018
MH c-2 was installed on 6/20 while I was at a class. The 2 service lines that were installed A line and C line have been completed with a trench check. There are suppose to be 2 service lines coming out of MH C-2, they want to have them come out of the main instead because a because a retention wall is going to be right over the service lines. I talked with Gene Williams and he was ok with them doing that. Yesterday and today they have been working out of MH A-6 going toward A-7, they have installed t wye for the service line between a-6 and a-7. Steve Robbins 06/22/2018 3:07 PM
PW-Main inspection
Informational
10/01/2018
No one was working today due to the rain this morning.Steve Robbins 06/25/2018 3:42 PM
PW-Main inspection
Informational
10/01/2018
While I was at my class they have installed MH A-7 and the service line that comes out the MH. They also finished installing the service line from MH A-6 to 7. They were finishing the trench checks and pouring inverts this afternoonl.Steve Robbins 06/29/2018 4:08 PM
PW-Main inspection
Informational
10/01/2018
Everything is completed up to MH A-7 including inverts and trench checks. They have stopped working on the sanitary for now and have moved to the storm sewer.Steve Robbins 07/05/2018 2:56 PM
PW-Main inspection
Informational
10/01/2018
MH A-3 has been installed they are working toward A-4 and the service line that is before a-4.Steve Robbins 07/20/2018 4:23 PM
PW-Main inspection
Informational
10/01/2018
They are still moving toward A-4 , they have installed a wye for the service line, they have not installed the trench check yet.Steve Robbins 07/23/2018 2:25 PM
PW-Main inspection
Informational
10/01/2018
It appears that a-4 and the service line to the building by a-4 has been installed. They are working toward a-5 which has already been installed.Steve Robbins 07/30/2018 2:43 PM
PW-Main inspection
Informational
10/01/2018
It appears that all of A-line has been installed They still have some inverts to be installed.Steve Robbins 10/01/2018 9:24 AM
Miscellaneous Correction
Informational
10/24/2018
Bair core drilled into Public existing MH D-1. The plans for Meridian shows to tie into and existiing Wye on D-line, but othe off-site sanitary plans did not call for a wye to be installed. I spoke with Gene and we decided they could core drill into the existing MH D-1 with a 8" pipe and run to the building for the service line. It calls for a clean-out a 100ft. The contractor has installed the 8" service line from the MH and covered with rock and was backfilling . This now completes all of the on-site sanitary.Steve Robbins 10/24/2018 3:47 PM
Retaining Wall Inspection Partial 10/29/2018 at 2:00 PM 11/01/2018
Misc
Informational
11/01/2018
The retaing wall on the west and north sides of the property has been completed. PSI has been doing testing for the sight.Steve Robbins 11/01/2018 8:41 AM
Water Line - Construction Inspection Partial 10/30/2018 at 11:00 AM 11/01/2018
PW-Main inspection
Informational
10/24/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
PW-Main inspection
Informational
10/24/2018
The water line has been installed up to building 10. The thrust blocks and fire hydrants have been installed up to this point.Steve Robbins 10/01/2018 9:44 AM
PW-Main inspection
Corrective Action Required
10/24/2018
No work has been going on this entire week due to all the rain.Steve Robbins 10/12/2018 1:46 PM
PW-Main inspection
Informational
10/24/2018
A main inspection has uncovered the following problems. -------------------------------------- Bair is planning on starting up on the water again next week around building 10 and working toward the other backflow preventer.Steve Robbins 10/24/2018 3:37 PM
PW-Main inspection
Informational
11/01/2018
The crew has started back up with working on the water line they are working from building 9 toward village park dr. where they will be installing the next backflow preventer.Steve Robbins 11/01/2018 8:44 AM
Storm Sewer Construction Inspection Partial 11/8/2018 at 11:00 AM 11/08/2018
PW-Storm Sewer Inspection
Informational
09/26/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
09/26/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
They are now working on the rcp line coming out of the retention basin.. They are now on the 4th stick of pipe. They were not working on the other line today.Steve Robbins 07/16/2018 3:08 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
They are still working on the rcp pipe it appears to be on the 5th stick of pipe, they are encasing with rock and backfilling. On the other storm line coming out of the retention basin they are installing box 105.Steve Robbins 07/17/2018 3:55 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
The concrete encasement next to box 105 has been installed as is the encasement for 101 and 100. Also, the storm boxes for 104, 103, 102, 101, and 100 have been installed in the past 3 days. Line 1 has been installed with 177 ft of rcp and box 8 was installed.Steve Robbins 07/20/2018 4:10 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
They are working on installing box 100, they hit a lot of shale. Steve Robbins 07/23/2018 2:36 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
Stormbox 64,63, and 62 have all been installed. They have also installed 110,120,121, and 130. They will be working toward 61 and 60 tomorrow. Today they were also pouring inverts on several of the structures.Steve Robbins 08/01/2018 3:35 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
No storm sewer has been done this week with the rain. They have just been doing water line work.Steve Robbins 08/24/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
09/26/2018
All the storm has been completed except for line 4 and part of line 3, they should be getting to this pretty soon.Steve Robbins 09/26/2018 8:00 AM
Misc
Informational
11/08/2018
No more work has been done on the stormwater.
Pavement-Stabilized Subgrade Partial 11/8/2018 at 11:30 AM 11/09/2018
Misc
Informational
11/09/2018
The contractors from Bair Excavating have been installing geo-grid and rock for the private road and parking spaces on this site. The have it installed up to apt. 5 and are working their way down to apt. 8and 9.Steve Robbins 11/09/2018 1:24 PM
Pavement-Stabilized Subgrade Partial 11/12/2018 at 1:00 PM 11/26/2018
Misc
Informational
11/09/2018
The contractors from Bair Excavating have been installing geo-grid and rock for the private road and parking spaces on this site. The have it installed up to apt. 5 and are working their way down to apt. 8and 9.Steve Robbins 11/09/2018 1:24 PM
Misc
Informational
11/26/2018
The contractors from Bair have installed the geo-grid and rock for the parking lot up to building 5 on both sides.
Water Line - Construction Inspection Partial 11/29/2018 at 9:00 AM 11/30/2018
PW-Main inspection
Informational
11/01/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
PW-Main inspection
Informational
11/01/2018
The water line has been installed up to building 10. The thrust blocks and fire hydrants have been installed up to this point.Steve Robbins 10/01/2018 9:44 AM
PW-Main inspection
Corrective Action Required
11/01/2018
No work has been going on this entire week due to all the rain.Steve Robbins 10/12/2018 1:46 PM
PW-Main inspection
Informational
11/01/2018
A main inspection has uncovered the following problems. -------------------------------------- Bair is planning on starting up on the water again next week around building 10 and working toward the other backflow preventer.Steve Robbins 10/24/2018 3:37 PM
PW-Main inspection
Informational
11/01/2018
The crew has started back up with working on the water line they are working from building 9 toward village park dr. where they will be installing the next backflow preventer.Steve Robbins 11/01/2018 8:44 AM
PW-Main inspection
Informational
11/30/2018
Bair construction is continuing to install the water line they are around buildigng 14 and heading toward where the backflow preventer will be installed.Steve Robbins 11/30/2018 9:00 AM
Retaining Wall Inspection Partial 12/10/2018 at 8:00 AM 12/11/2018
Misc
Informational
11/01/2018
The retaing wall on the west and north sides of the property has been completed. PSI has been doing testing for the sight.Steve Robbins 11/01/2018 8:41 AM
Misc
Informational
12/11/2018
They have all the retainging walls up for the buildings 1-7 in that area. PSI has been out testing for the retaining walls.Steve Robbins 12/11/2018 8:14 AM
Pavement-Stabilized Subgrade Partial 12/11/2018 at 8:00 AM 12/11/2018
Misc
Informational
11/26/2018
The contractors from Bair Excavating have been installing geo-grid and rock for the private road and parking spaces on this site. The have it installed up to apt. 5 and are working their way down to apt. 8and 9.Steve Robbins 11/09/2018 1:24 PM
Misc
Informational
11/26/2018
The contractors from Bair have installed the geo-grid and rock for the parking lot up to building 5 on both sides.
Misc
Informational
12/11/2018
The have now installed rock and geo-grid up to building 11 and 12. It needs to cure out.Steve Robbins 12/11/2018 8:26 AM
Pavement-Surface Partial 1/24/2019 at 2:00 PM 01/24/2019
Misc
Informational
01/24/2019
The base asphalt for the private street/parking lot has been installed up to building 9. This allows the fire dept. to get back there and get to a hydrant if needed. They are allowed to build vertical now.Steve Robbins 01/24/2019 4:49 PM
Fire Line Construction Inspection Partial 1/24/2019 01/24/2019
Misc
Informational
01/24/2019
The fire line has been installed up to building 9. The fire hydrants are also installed up to 9. They are now constructing the buildings.Steve Robbins 01/24/2019 4:56 PM
Storm Sewer Construction Inspection Partial 2/13/2019 at 9:00 AM 02/13/2019
PW-Storm Sewer Inspection
Informational
11/08/2018
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
11/08/2018
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
They are now working on the rcp line coming out of the retention basin.. They are now on the 4th stick of pipe. They were not working on the other line today.Steve Robbins 07/16/2018 3:08 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
They are still working on the rcp pipe it appears to be on the 5th stick of pipe, they are encasing with rock and backfilling. On the other storm line coming out of the retention basin they are installing box 105.Steve Robbins 07/17/2018 3:55 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
The concrete encasement next to box 105 has been installed as is the encasement for 101 and 100. Also, the storm boxes for 104, 103, 102, 101, and 100 have been installed in the past 3 days. Line 1 has been installed with 177 ft of rcp and box 8 was installed.Steve Robbins 07/20/2018 4:10 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
They are working on installing box 100, they hit a lot of shale. Steve Robbins 07/23/2018 2:36 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
Stormbox 64,63, and 62 have all been installed. They have also installed 110,120,121, and 130. They will be working toward 61 and 60 tomorrow. Today they were also pouring inverts on several of the structures.Steve Robbins 08/01/2018 3:35 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
No storm sewer has been done this week with the rain. They have just been doing water line work.Steve Robbins 08/24/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
11/08/2018
All the storm has been completed except for line 4 and part of line 3, they should be getting to this pretty soon.Steve Robbins 09/26/2018 8:00 AM
Misc
Informational
11/08/2018
No more work has been done on the stormwater.
PW-Storm Sewer Inspection
Informational
02/13/2019
Corrections need to be made to the Storm Sewer. There is still a large pile of dirt/rock in the way of where the final sections of the stormwater pipe needs to be laid. It cannot be completed until it has been removed.Steve Robbins 02/13/2019 2:39 PM
Water Line - Construction Inspection Partial 2/19/2019 at 9:00 AM 03/05/2019
PW-Main inspection
Informational
11/30/2018
The backflow preventer and the meter vault have been dug and 6" fire line and 4" water line have begun to be installed. They are working there way down starting at blgd 1 and 2 and are now toward blgd. 3 and 4 making the turn. They are installing fire hydrants and service lines along the way.Steve Robbins 08/13/2018 1:58 PM
PW-Main inspection
Informational
11/30/2018
The water line has been installed up to building 10. The thrust blocks and fire hydrants have been installed up to this point.Steve Robbins 10/01/2018 9:44 AM
PW-Main inspection
Corrective Action Required
11/30/2018
No work has been going on this entire week due to all the rain.Steve Robbins 10/12/2018 1:46 PM
PW-Main inspection
Informational
11/30/2018
A main inspection has uncovered the following problems. -------------------------------------- Bair is planning on starting up on the water again next week around building 10 and working toward the other backflow preventer.Steve Robbins 10/24/2018 3:37 PM
PW-Main inspection
Informational
11/30/2018
The crew has started back up with working on the water line they are working from building 9 toward village park dr. where they will be installing the next backflow preventer.Steve Robbins 11/01/2018 8:44 AM
PW-Main inspection
Informational
11/30/2018
Bair construction is continuing to install the water line they are around buildigng 14 and heading toward where the backflow preventer will be installed.Steve Robbins 11/30/2018 9:00 AM
Misc
Informational
03/05/2019
The service line and the fire line have all been installed. They have also installed the backflow preventer on both roads. They have hydrostatic tested approximately half of the water line and fire line. The service water line has not been chlorinated or had samples taken as of yet.Steve Robbins 03/05/2019 9:49 AM
Fire Line - Hydrostatic Test Partial 4/29/2019 04/29/2019
PW-Misc
Informational
10/04/2018
The hydrostatic pressure twst for the 4" service line has been passed. They are planning on possibly doing the fire line today.Steve Robbins 10/01/2018 9:51 AM
PW-Misc
Informational
10/04/2018
The hydrostatic pressure test for fire line has passed 200psi for 2hrs. This is a partial completion of the water lines that have been installed.Steve Robbins 10/04/2018 7:54 AM
Misc
Informational
04/29/2019
Hydrostatic pressure test of 8 inch fire line passed 200 PSI for over 2 hrs. Still need to test the 4 inch domestic line. RP 4/29/19
Water Line - Hydrostatic Test Failed 4/30/2019 05/03/2019
Misc
Corrective Action Required
05/03/2019
Water line lost 10 PSI during the test. Mike’s crew is going to work on the line and reschedule another test next week.
Water Line - Hydrostatic Test Passed 5/6/2019 05/10/2019
Misc
Corrective Action Required
05/03/2019
Water line lost 10 PSI during the test. Mike’s crew is going to work on the line and reschedule another test next week.
Misc
Informational
05/10/2019
Water line held 150 PSI for 2 hrs. RP 5-10-19
Water Line - Coliform Test 1 Passed 5/15/2019 05/23/2019
Misc
Informational
05/23/2019
Water line passed it’s first Bac-T test on 4-19-19
Water Line - Coliform Test 1 Partial 5/23/2019 05/23/2019
Misc
Informational
05/23/2019
There was no Bac-T test performed here yet. I opened the wrong address inspection. RP 5-23-19
Water Line - Coliform Test 1 Partial 5/23/2019 07/23/2019
Misc
Informational
05/23/2019
There was no Bac-T test performed here yet. I opened the wrong address inspection. RP 5-23-19
Misc
Informational
07/23/2019
Lief chlorinated the water line to 100 parts per million. We will dechlorinate the line tomorrow at 8:30am. RP 7-23-19
Pavement-Surface Partial 9/3/2019 09/20/2019
Misc
Informational
01/24/2019
The base asphalt for the private street/parking lot has been installed up to building 9. This allows the fire dept. to get back there and get to a hydrant if needed. They are allowed to build vertical now.Steve Robbins 01/24/2019 4:49 PM
PW-Misc
Informational
09/20/2019
The base asphalt for the parking area up to building 9 was damaged over the winter months and due to all the fork lifts and the buildiing that had been going on. O'Donnel Way Asphalt Company came in an did repairs to the base where needed and put in new base asphalt. We did spot proofrolls on this as I observed heavey trucks driving back and forth over a period of 3-4 weeks. They are ready for surface up to building 9.
Commercial Curb Inspection Partial 7/10/2019 09/20/2019
Misc
Informational
09/20/2019
The curbs for the parking lot up to building9 have all been installed. Nothing from building 9-17 has been done.
Street - Surface Course Partial 9/19/2019 10/30/2019
PW-Misc
Informational
10/30/2019
The surface asphalt has been installed up to building 9.
Commercial Curb Inspection Partial 11/21/2019 11/21/2019
Misc
Informational
09/20/2019
The curbs for the parking lot up to building9 have all been installed. Nothing from building 9-17 has been done.
Misc
Informational
11/21/2019
The curbs for the remaining buildings 9-17 have been partially installed, they are still working around the storm boxes that need to be hand poured. When this is finished it will complete all the curbs for the on-site.
Storm Sewer Construction Inspection Passed 11/19/2019 11/21/2019
PW-Storm Sewer Inspection
Informational
02/13/2019
Brice Lawson 06/28/2018 3:20 PM Larry Bair Construction was in the process of breaking rock in the trench for storm line 10 between 107 and 108 near the retention basin. It appeared that 1 section of 30" HDPE pipe was installed in the trench and was partially bedded in rock. Leif let me know that they plan to install trench checks on the private sanitary stubs tomorrow at 10am. I let Steve know that they plan to do this.
PW-Storm Sewer Inspection
Informational
02/13/2019
The contractors started at 108 in the retention basin, they are almost to structure 107, there is a 16ft. concrete encasement right before structure 107.Steve Robbins 07/05/2018 2:53 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
Structure 107 has been installed and they are hitting alot of rock going towards 106.Steve Robbins 07/09/2018 4:00 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
They were installing structure 106 today, they are also working on concrete encasement for the storm pipe.Steve Robbins 07/10/2018 3:53 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
The encasement between 107 and 106 has been completed. They were working toward 105.Steve Robbins 07/11/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
The inverts have been completed up to 106, they have laid aboout 80 feet of 30"hdpe pipe heading toward 105.Steve Robbins 07/13/2018 1:55 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
They are now working on the rcp line coming out of the retention basin.. They are now on the 4th stick of pipe. They were not working on the other line today.Steve Robbins 07/16/2018 3:08 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
They are still working on the rcp pipe it appears to be on the 5th stick of pipe, they are encasing with rock and backfilling. On the other storm line coming out of the retention basin they are installing box 105.Steve Robbins 07/17/2018 3:55 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
The concrete encasement next to box 105 has been installed as is the encasement for 101 and 100. Also, the storm boxes for 104, 103, 102, 101, and 100 have been installed in the past 3 days. Line 1 has been installed with 177 ft of rcp and box 8 was installed.Steve Robbins 07/20/2018 4:10 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
They are working on installing box 100, they hit a lot of shale. Steve Robbins 07/23/2018 2:36 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
Stormbox 64,63, and 62 have all been installed. They have also installed 110,120,121, and 130. They will be working toward 61 and 60 tomorrow. Today they were also pouring inverts on several of the structures.Steve Robbins 08/01/2018 3:35 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
No storm sewer has been done this week with the rain. They have just been doing water line work.Steve Robbins 08/24/2018 3:57 PM
PW-Storm Sewer Inspection
Informational
02/13/2019
All the storm has been completed except for line 4 and part of line 3, they should be getting to this pretty soon.Steve Robbins 09/26/2018 8:00 AM
Misc
Informational
02/13/2019
No more work has been done on the stormwater.
PW-Storm Sewer Inspection
Informational
02/13/2019
Corrections need to be made to the Storm Sewer. There is still a large pile of dirt/rock in the way of where the final sections of the stormwater pipe needs to be laid. It cannot be completed until it has been removed.Steve Robbins 02/13/2019 2:39 PM
Misc
Informational
11/21/2019
The remaining storm sewer boxes /curb inlets have been installed and completed. This now completes all the storm boxes for the private roads.
Erosion Control Inspection Failed 2/27/2020 02/27/2020
Misc
Corrective Action Required
02/27/2020
I was informed by the building inspector that the site was needed to be cleaned up. The sit is in violation, mud and silt on the roads, gutter buddys need to be cleaned out and any dirt piles need to be protected by silt fence so they are not draining down the storm. Please take care of this matter right away. We will check back on Monday March 2. If this matter is not resolved inspections by the building inspector may be denied until it is cleaned up.
Retaining Wall Inspection Passed 11/20/2019 12/21/2021
Misc
Informational
12/11/2018
The retaing wall on the west and north sides of the property has been completed. PSI has been doing testing for the sight.Steve Robbins 11/01/2018 8:41 AM
Misc
Informational
12/11/2018
They have all the retainging walls up for the buildings 1-7 in that area. PSI has been out testing for the retaining walls.Steve Robbins 12/11/2018 8:14 AM
Fire Line Construction Inspection Passed 12/21/2021
Misc
Informational
01/24/2019
The fire line has been installed up to building 9. The fire hydrants are also installed up to 9. They are now constructing the buildings.Steve Robbins 01/24/2019 4:56 PM
Fire Line - Hydrostatic Test Passed 12/21/2021
PW-Misc
Informational
04/29/2019
The hydrostatic pressure twst for the 4" service line has been passed. They are planning on possibly doing the fire line today.Steve Robbins 10/01/2018 9:51 AM
PW-Misc
Informational
04/29/2019
The hydrostatic pressure test for fire line has passed 200psi for 2hrs. This is a partial completion of the water lines that have been installed.Steve Robbins 10/04/2018 7:54 AM
Misc
Informational
04/29/2019
Hydrostatic pressure test of 8 inch fire line passed 200 PSI for over 2 hrs. Still need to test the 4 inch domestic line. RP 4/29/19
Street - Surface Course Passed 12/28/2021
PW-Misc
Informational
10/30/2019
The surface asphalt has been installed up to building 9.
Documents & Images
Date Uploaded File Type Document Name
01/30/2018 Receipt Receipt for transaction: 2018-000352
02/21/2018 Letter DE-Permit
02/21/2018 Permit Meridian at View High Permit
06/01/2018 Permit View High at Meridian
06/05/2018 Letter DE-Daily Inspection Summary
06/06/2018 Letter DE-Daily Inspection Summary
06/06/2018 Letter DE-Daily Inspection Summary
06/07/2018 Letter DE-Daily Inspection Summary
06/08/2018 Letter DE-Daily Inspection Summary
06/11/2018 Letter DE-Daily Inspection Summary
06/13/2018 Letter DE-Daily Inspection Summary
06/15/2018 Letter DE-Daily Inspection Summary
06/15/2018 Letter DE-Daily Inspection Summary
06/18/2018 Letter DE-Daily Inspection Summary
06/19/2018 Letter DE-Daily Inspection Summary
06/22/2018 Letter DE-Daily Inspection Summary
06/25/2018 Letter DE-Daily Inspection Summary
06/28/2018 Letter DE-Daily Inspection Summary
06/29/2018 Letter DE-Daily Inspection Summary
07/05/2018 Letter DE-Daily Inspection Summary
07/05/2018 Letter DE-Daily Inspection Summary
07/09/2018 Letter DE-Daily Inspection Summary
07/10/2018 Letter DE-Daily Inspection Summary
07/11/2018 Letter DE-Daily Inspection Summary
07/11/2018 Letter DE-Daily Inspection Summary
07/13/2018 Letter DE-Daily Inspection Summary
07/16/2018 Letter DE-Daily Inspection Summary
07/17/2018 Letter DE-Daily Inspection Summary
07/20/2018 Letter DE-Daily Inspection Summary
07/20/2018 Letter DE-Daily Inspection Summary
07/23/2018 Letter DE-Daily Inspection Summary
07/23/2018 Letter DE-Daily Inspection Summary
07/23/2018 Letter DE-Daily Inspection Summary
07/30/2018 Letter DE-Daily Inspection Summary
08/01/2018 Letter DE-Daily Inspection Summary
08/01/2018 Letter DE-Daily Inspection Summary
08/13/2018 Letter DE-Daily Inspection Summary
08/15/2018 Letter DE-Daily Inspection Summary
08/24/2018 Letter DE-Daily Inspection Summary
08/24/2018 Letter DE-Daily Inspection Summary
08/30/2018 Letter DE-Daily Inspection Summary
08/30/2018 Letter DE-Daily Inspection Summary
09/04/2018 Letter DE-Daily Inspection Summary
09/11/2018 Letter DE-Daily Inspection Summary
09/21/2018 Letter DE-Daily Inspection Summary
09/26/2018 Letter DE-Daily Inspection Summary
09/26/2018 Letter DE-Daily Inspection Summary
10/01/2018 Letter DE-Daily Inspection Summary
10/01/2018 Letter DE-Daily Inspection Summary
10/01/2018 Letter DE-Daily Inspection Summary
10/04/2018 Letter DE-Daily Inspection Summary
10/12/2018 Letter DE-Daily Inspection Summary
10/24/2018 Letter DE-Daily Inspection Summary
10/24/2018 Letter DE-Daily Inspection Summary
11/01/2018 Letter DE-Daily Inspection Summary
11/01/2018 Letter DE-Daily Inspection Summary
11/08/2018 Letter DE-Daily Inspection Summary
11/09/2018 Letter DE-Daily Inspection Summary
11/12/2018 Letter Inspection Summary
11/12/2018 Letter Inspection Summary
11/26/2018 Letter DE-Daily Inspection Summary
11/30/2018 Letter DE-Daily Inspection Summary
12/11/2018 Letter DE-Daily Inspection Summary
12/11/2018 Letter DE-Daily Inspection Summary
01/24/2019 Letter DE-Daily Inspection Summary
01/24/2019 Letter DE-Daily Inspection Summary
03/05/2019 Letter DE-Daily Inspection Summary
04/29/2019 Letter INSPECTION SUMMARY
05/03/2019 Letter INSPECTION SUMMARY
05/10/2019 Letter INSPECTION SUMMARY
05/23/2019 Letter INSPECTION SUMMARY
05/23/2019 Letter INSPECTION SUMMARY
07/23/2019 Letter INSPECTION SUMMARY
09/20/2019 Letter DE-Daily Inspection Summary
09/20/2019 Letter DE-Daily Inspection Summary
10/30/2019 Letter DE-Daily Inspection Summary
11/07/2019 Letter Certificate of Partial Substantial Completion for Meridian At View High Aprartments
11/18/2019 Letter Meridian at View High Signed Partial Substantial and Punch List
11/21/2019 Letter DE-Daily Inspection Summary
11/21/2019 Letter DE-Daily Inspection Summary
02/27/2020 Letter DE-Daily Inspection Summary
01/11/2021 Letter DE-Certificate of Substantial Completion Multiple Lot
01/11/2021 Letter DE-Punch List
12/21/2021 Letter DE-Certificate of Final Acceptance (Commercial)
12/29/2021 Letter INSPECTION SUMMARY
12/29/2021 Letter INSPECTION SUMMARY
12/29/2021 Letter INSPECTION SUMMARY
12/29/2021 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.