Summary
PRRES20251907
Building Permit - Residential
Issued
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - ROOF TRUSSES -
05/09/2025
05/19/2025
11/09/2025
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
BRUCER@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 05/19/2025
Right of Way Permit Fee $85.00 $85.00 Paid 05/19/2025
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 05/19/2025
Water Tap Fee $3,973.00 $3,973.00 Paid 05/19/2025
Water Meter Fee $748.03 $748.03 Paid 05/19/2025
Valuation Fee New Single Family $1,274.16 $1,274.16 Paid 05/19/2025
Outstanding Fees Amount Paid Owing Date Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$300.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Plot Plan Inspection Pending
Occupancy Inspection - Codes Residential Pending
Erosion Control Inspection Residential Pending
DCM5 ESC INSP DENIED
Corrective Action Required
06/06/2025
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION. -INSTALL GAVEL ENTRANCE
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
06/06/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Driveway Inspection Pending
Misc
Informational
09/09/2025
9-3-25 Dustin A, DW is formed and compacted. Approved to pour 9/9/25 Tyler S. DW is not in compliance with city specs. Forms need to be pulled. Fail.
Footing Inspection - Residential Passed 6/2/2025 06/02/2025
Erosion Control Inspection Residential Partial 6/2/2025 6/2/2025 06/02/2025
Underslab Plumbing Inspection - Residential Not Ready 6/6/2025 6/6/2025 06/06/2025
Misc
Corrective Action Required
06/06/2025
Erosion control not in compliance inspection denied -Provide gravel entrance -provide backfill for viewing to inspect
Erosion Control Inspection Residential Failed 6/6/2025 06/06/2025
DCM5 ESC INSP DENIED
Corrective Action Required
06/06/2025
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION. -INSTALL GAVEL ENTRANCE
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
06/06/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Sewer Service Inspection - R Passed 6/6/2025 06/06/2025
Water Service Inspection - R Passed 6/10/2025 6/10/2025 06/10/2025
Underslab Plumbing Inspection - Residential Passed 6/11/2025 6/11/2025 06/11/2025
Misc
Resolved
06/11/2025
Erosion control not in compliance inspection denied -Provide gravel entrance -provide backfill for viewing to inspect
All Rough Inspection - Residential Partial 7/1/2025 7/1/2025 07/01/2025
Misc
Corrective Action Required
07/01/2025
Garage portal frame exterior nailing inspection only-okay to cover
Electrical Service Inspection Passed 7/16/2025 7/16/2025 07/16/2025
All Rough Inspection - Residential Not Ready 7/16/2025 7/16/2025 07/16/2025
Misc
Informational
07/16/2025
Garage portal frame exterior nailing inspection only-okay to cover
Misc
Corrective Action Required
07/16/2025
Home not ready for inspection -provide complete set of plans on site (including truss packet) -complete fire blocking throughout before inspection
Gas Service Inspection - Residential Passed 7/18/2025 7/18/2025 07/18/2025
All Rough Inspection - Residential Failed 7/18/2025 7/18/2025 07/18/2025
Misc
Resolved
07/18/2025
Garage portal frame exterior nailing inspection only-okay to cover
Misc
Resolved
07/18/2025
Home not ready for inspection -provide complete set of plans on site (including truss packet) -complete fire blocking throughout before inspection
Misc
Corrective Action Required
07/18/2025
-protect dryer vent at top plate protection must extend 2” below -seal dead space at primary bath toilet/primary bed entry wall -seal dead space at kitchen/bath 2 -nail all libs at intersecting wall studs 2nails per crossing -ensure truss hangers in garage are of correct size. Plans call for lus28 on N most 4 hangers -b2 and b4 trusses missing lateral bracing -nail f1 trusses together to plans -address over notched floor joist under primary bath toilet
All Rough Inspection - Residential Not Ready 7/23/2025 7/23/2025 07/23/2025
Misc
Corrective Action Required
07/18/2025
-seal dead space at owners entry -nail all libs at intersecting wall studs 2nails per crossing intersecting wall corners -ensure truss hangers in garage are of correct size. Plans call for lus28 on N most 4 hangers -b2 and b4 trusses missing lateral bracing -nail f1 trusses together to plans -address over notched floor joist under primary bath toilet
All Rough Inspection - Residential Not Ready 7/25/2025 7/25/2025 07/25/2025
Misc
Corrective Action Required
07/23/2025
Nothing done at time of inspection -seal dead space at owners entry -nail all libs at intersecting wall studs 2nails per crossing intersecting wall corners -ensure truss hangers in garage are of correct size. Plans call for lus28 on N most 4 hangers -b2 and b4 trusses missing lateral bracing -nail f1 trusses together to plans -address over notched floor joist under primary bath toilet
All Rough Inspection - Residential Failed 7/28/2025 7/28/2025 07/28/2025
Misc
Corrective Action Required
07/25/2025
- b4 and F1 truss missing lateral bracing
All Rough Inspection - Residential Passed 7/29/2025 7/29/2025 07/29/2025
Misc
Resolved
07/29/2025
- b4 and F1 truss missing lateral bracing
Driveway Inspection Partial 9/3/2025 9/3/2025 09/03/2025
Misc
Informational
09/03/2025
9-3-25 Dustin A, DW is formed and compacted. Approved to pour
Driveway Inspection Failed 9/10/2025 9/10/2025 09/09/2025
Misc
Informational
09/03/2025
9-3-25 Dustin A, DW is formed and compacted. Approved to pour 9/9/25 Tyler S. DW is not in compliance with city specs. Forms need to be pulled. Fail.
Documents & Images
Date Uploaded File Type Document Name
05/09/2025 BY #0170 - PERMIT APP
05/13/2025 Permit Codes Residential Plan Review
05/13/2025 Approved Plans APPROVED PLANS
05/13/2025 Approved Plans APPROVED TRUSS LAYOUT
05/13/2025 Approved Plans APPROVED TRUSS PACKET
05/15/2025 Plot Plan APPROVED PLOT PLAN
05/19/2025 Permit Codes Residential Plan Review
05/19/2025 Permit DS Building Permit
05/19/2025 Receipt Receipt for transaction:2025-003502
05/30/2025 M L Crose 1313 SE Ranchland St LSMO Footing Inspection Report 5-30-25
06/02/2025 Letter INSPECTION SUMMARY
06/02/2025 Letter INSPECTION SUMMARY
06/06/2025 Letter INSPECTION SUMMARY
06/06/2025 Letter INSPECTION SUMMARY
06/06/2025 Letter INSPECTION SUMMARY
06/10/2025 Letter INSPECTION SUMMARY
06/11/2025 Letter INSPECTION SUMMARY
07/01/2025 Letter INSPECTION SUMMARY
07/16/2025 Letter INSPECTION SUMMARY
07/16/2025 Letter INSPECTION SUMMARY
07/18/2025 Letter INSPECTION SUMMARY
07/18/2025 Letter INSPECTION SUMMARY
07/23/2025 Letter INSPECTION SUMMARY
07/25/2025 Letter INSPECTION SUMMARY
07/28/2025 Letter INSPECTION SUMMARY
07/29/2025 Letter INSPECTION SUMMARY
09/03/2025 Letter INSPECTION SUMMARY
09/09/2025 Letter INSPECTION SUMMARY
09/09/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home