Summary
PRRES20214074
Building Permit - Residential
Certificate of Occupancy
CLAYTON PROPERTIES GROUP INC
NEW SINGLE FAMILY
NEW HOUSE. FINISHED WALKOUT BASEMENT. COVERED DECK.
08/05/2021
08/10/2021
02/05/2022
07/12/2022
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
CLAYTON PROPERTIES GROUP INC, Address:120 SE 30TH ST  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
MIKE@SUMMITHOMESKC.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331507-Sewer Connection Fee $360.00 $360.00 Paid 08/10/2021
Water Tap Fee $3,655.00 $3,655.00 Paid 08/10/2021
Water Meter Fee $479.24 $479.24 Paid 08/10/2021
Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 08/10/2021
Valuation Fee New Single Family $1,002.03 $1,002.03 Paid 08/10/2021
Right of Way Permit Fee $80.00 $80.00 Paid 08/10/2021
Not Ready Inspection Fee $50.00 $50.00 Paid 07/06/2022
Not Ready Inspection Fee $50.00 $50.00 Paid 07/06/2022
3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 07/06/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 9/22/2021 (1:30) 9/22/2021 09/22/2021
Misc
Informational
09/22/2021
UFER LOCATED REAR FOUNDATION WALL GARAGE
Underslab Plumbing Inspection - Residential Failed 11/3/2021 11/3/2021 11/03/2021
Misc
Corrective Action Required
11/03/2021
Drain tile not installed
Underslab Plumbing Inspection - Residential Passed 11/17/2021 11/17/2021 11/17/2021
Misc
Resolved
11/17/2021
Sewer Service Inspection - R Passed 11/29/2021 (1:15) 11/29/2021 11/29/2021
Water Service Inspection - R Passed 12/1/2021 (9:15) 12/1/2021 12/01/2021
Erosion Control Inspection Residential Failed 02/14/2022
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/14/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Gas Service Inspection - Residential Passed 2/14/2022 2/14/2022 02/14/2022
All Rough Inspection - Residential Failed 2/23/2022 2/23/2022 02/23/2022
Misc
Corrective Action Required
02/23/2022
-Address erosion control at front of lot, maintain silt fence and clean all mud at front of lot in street, <--have this corrected before scheduling reinspection -Tension straps at garage PFH per plans code -Install anchor bolt at garage PFH -Install H2.5 or equivalent at all hip trusses throughout -Install H2.5 hold downs or equivalent at dbl girder truss garage, master bed -solid shim studs short of top plate at garage -Install all flashing boots at roof penetrations -fireblock great room fireplace open to attic space at master bed wall -complete gas line connection to fireplace and secure gas line at fireplace -provide full bearing support for top plate at north wall front bedroom -top plate to top plate connection as required by code front entry wall -CS-PF bracing design at dining room sliding glass door per plans/IRC R602.10.6.4 -LVL header at dining room sliding glass door continuous corner to corner per plans -top plate to top plate connection as required by code at dining room sliding glass door exterior wall -solid block all sheathing breaks throughout -nail all intersecting corners at 12" oc -EC#2 800 lb tension strap at dining room corner per plans -dining room bracing per plans at dining room windows -all truss hangers per plans at garage -all truss lateral bracing per plans -fireblock garage wall stair side between studs open to attic space above -anchor bolts required with 12” of plate break at basement -tighten all anchor bolts throughout basement - seal all top plate penetrations - see dining room 1st floor, finished basement -sheath at top plate basement den exterior wall, open to deck ledger -secure NM every 4.5’ through furred downs at finish basement -fireblock vertical to horizontal at furred down soffit ends at finished basement -address overbored 2x10 joist for DWV at basement bedroom -provide min 1” clearance from combustibles at b vent basement mech -CS-PF bracing design per plans at basement sliding door, (2) 2x12 header continuous corner to corner per plans -solid block between joists every 48” oc at kitchen island per plans -nail all exterior sheathing per plans -remove bonding screw from sub panel at basement mech **DECK INCOMPLETE AT ALL ROUGH**
Electrical Service Inspection Failed 2/23/2022 2/23/2022 02/23/2022
Misc
Corrective Action Required
02/23/2022
-remove bonding screw from sub panel at basement mech
Erosion Control Inspection Residential Failed 2/23/2022 2/23/2022 02/23/2022
DCM3 ESC REQUIRED 2 DAY
Resolved
02/23/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Misc
Corrective Action Required
02/23/2022
-Address erosion control at front of lot, maintain silt fence and clean all mud at front of lot in street
Electrical Service Inspection Passed 3/14/2022 3/14/2022 03/14/2022
Misc
Resolved
03/14/2022
All Rough Inspection - Residential Failed 3/14/2022 3/14/2022 03/14/2022
Misc
Corrective Action Required
02/23/2022
-Install H2.5 or equivalent at all hip trusses throughout -top plate to top plate connection as required by code front entry wall -CS-PF bracing design at dining room sliding glass door per plans/IRC R602.10.6.4, nail all exterior sheathing per design -EC#2 800 lb tension strap at dining room corner per plans, 800# capacity fastened to the edge of the braced wall panel closest to the corner and to framing below, see detail page S1.0 in plans -dining room bracing per plans at dining room windows, nail exterior sheathing per plans -all truss hangers per plans at garage - seal all top and bottom plate penetrations - see dining room 1st floor, finished basement -fireblock vertical to horizontal at furred down soffit ends at finished basement -CS-PF bracing design per plans at basement sliding door, (2) 2x12 header continuous corner to corner per plans -nail all exterior sheathing per plans
All Rough Inspection - Residential Not Ready 3/23/2022 3/23/2022 03/23/2022
Misc
Corrective Action Required
03/14/2022
-Install H2.5 or equivalent at all hip trusses throughout ( TRUSS SCREWS TO BE INSTALLED THROUGH A DOUBLE TOP PLATE SOME ONLY IN TOP PLATE ) - seal all top and bottom plate penetrations ( not done 3/23/22 dwv master vanity, sliding glass door deck ) -fireblock vertical to horizontal at furred down soffit ends at finished basement ( 3/23/22 not done bed 3 & 4 ) ( seal gap in fire block at top plate wall with service panel basement )
All Rough Inspection - Residential Not Ready 3/28/2022 3/28/2022 03/28/2022
Misc
Corrective Action Required
03/23/2022
-Install H2.5 or equivalent at all hip trusses throughout ( TRUSS SCREWS TO BE INSTALLED THROUGH A DOUBLE TOP PLATE SOME ONLY IN TOP PLATE ) : garage not done screws only catch top plate 3/28/22 : -fireblock vertical to horizontal at furred down soffit ends at finished basement ( 3/23/22 not done bed 3 & 4 ) ( seal gap in fire block at top plate wall with service panel basement ) : Per 2018 IRC R302.11 Fireblocking : ( not done 3/28/22 ) OK TO INSULATE
All Rough Inspection - Residential Passed 3/29/2022 3/29/2022 03/29/2022
Misc
Resolved
03/29/2022
Driveway Inspection Partial 4/13/2022 4/13/2022 04/13/2022
Misc
Informational
04/13/2022
Forms were placed and aggregate was present and compacted. RP 4-13-22
Driveway Inspection Passed 4/22/2022 4/22/2022 04/22/2022
Misc
Informational
04/13/2022
Forms were placed and aggregate was present and compacted. RP 4-13-22
Misc
Informational
04/22/2022
Finished driveway meets LS specs. RP 4-22-22
Erosion Control Inspection Residential Failed 6/10/2022 06/10/2022
Misc
Corrective Action Required
02/23/2022
-Address erosion control at front of lot, maintain silt fence and clean all mud at front of lot in street NO FURTHER INSPECTIONS UNTIL CORRECTIONS ARE MADE.
Occupancy Inspection - Codes Residential Failed 6/10/2022 6/10/2022 06/10/2022
Miscellaneous Correction
Corrective Action Required
06/10/2022
INSPECTION DENIED -EROSION CONTROL needs corrections before next inspection - no address numbers ( not paper in window)
Occupancy Inspection - Codes Residential Failed 6/14/2022 6/14/2022 06/14/2022
Miscellaneous Correction
Corrective Action Required
06/10/2022
- Post address - Provide gutters and down spouts - Splash blocks - Finish sidewalk - Final grading and sod - Irrigation permit ( if installing ) - Provide proper ledger bolts for deck - Provide 2@ 1/2” through bolts on each post to beam connections - Provide landing for deck stairs - Sump discharge minimum of 36” away from foundation
Erosion Control Inspection Residential Failed 6/14/2022 06/14/2022
Misc
Corrective Action Required
06/10/2022
-Address erosion control at front of lot, maintain silt fence and clean all mud at front of lot in street NO FURTHER INSPECTIONS UNTIL CORRECTIONS ARE MADE.
Erosion Control Inspection Residential Passed 07/06/2022
Misc
Resolved
07/06/2022
Occupancy Inspection - Codes Residential Failed 7/6/2022 7/6/2022 07/06/2022
Miscellaneous Correction
Corrective Action Required
06/14/2022
- PAY FEES - Finish sidewalk - COMPLETE sod - Irrigation permit ( NOT ISSUED AT THIS TIME )
Sidewalk Inspection Failed 07/07/2022
Misc
Corrective Action Required
07/07/2022
Sidewalk has not been poured. Plot plan shows sidewalk extends from East property line to ADA ramp. This needs to be poured. 7/7/22 ES
Occupancy Inspection - Codes Residential Failed 7/7/2022 7/7/2022 07/07/2022
Miscellaneous Correction
Corrective Action Required
07/06/2022
- Finish sidewalk **Sidewalk not completed to property line
Occupancy Inspection - Codes Residential Temporary C of O 7/8/2022 7/8/2022 07/08/2022
Miscellaneous Correction
Corrective Action Required
07/07/2022
- Finish sidewalk **Sidewalk not completed to property line TCO expiration 8/7/22
Sidewalk Inspection Partial 7/11/2022 7/11/2022 07/11/2022
Misc
Corrective Action Required
07/07/2022
Sidewalk has not been poured. Plot plan shows sidewalk extends from East property line to ADA ramp. This needs to be poured. 7/7/22 ES
Misc
Informational
07/11/2022
Sidewalk panel and replacement ADA turning space were formed up with aggregate in and compacted. 7/11/22 ES
Sidewalk Inspection Passed 7/15/2022 7/15/2022 07/12/2022
Misc
Corrective Action Required
07/11/2022
Sidewalk has not been poured. Plot plan shows sidewalk extends from East property line to ADA ramp. This needs to be poured. 7/7/22 ES
Misc
Informational
07/11/2022
Sidewalk panel and replacement ADA turning space were formed up with aggregate in and compacted. 7/11/22 ES Sidewalk and ADA TS both meet LS and ADA specs. 7/12/22 ES
Occupancy Inspection - Codes Residential Full C of O 7/13/2022 7/13/2022 07/12/2022
Miscellaneous Correction
Resolved
07/12/2022
- Finish sidewalk **Sidewalk not completed to property line TCO expiration 8/7/22
Documents & Images
Date Uploaded File Type Document Name
08/05/2021 W1 #30 - Permit App
08/09/2021 Approved Plans APPROVED TRUSS LAYOUT
08/09/2021 Approved Plans APPROVED TRUSS PACKAGE
08/09/2021 Approved Plans APPROVED DRAWINGS
08/09/2021 Permit Codes Residential Plan Review
08/10/2021 Plot Plan APPROVED PLOT PLAN
08/10/2021 Permit Codes Residential Plan Review
08/10/2021 Permit DS Building Permit
08/10/2021 Receipt Receipt for transaction:2021-006368
09/22/2021 Letter INSPECTION SUMMARY
11/03/2021 Letter INSPECTION SUMMARY
11/17/2021 Letter INSPECTION SUMMARY
11/29/2021 Letter INSPECTION SUMMARY
12/01/2021 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
03/11/2022 W1 30 Overbore Joist Repair
03/14/2022 Letter INSPECTION SUMMARY
03/14/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/28/2022 Letter INSPECTION SUMMARY
03/29/2022 Letter INSPECTION SUMMARY
04/13/2022 Letter INSPECTION SUMMARY
04/22/2022 Letter INSPECTION SUMMARY
06/10/2022 Letter INSPECTION SUMMARY
06/10/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
07/06/2022 Letter INSPECTION SUMMARY
07/06/2022 Letter INSPECTION SUMMARY
07/06/2022 Receipt Receipt for transaction:2022-005521
07/07/2022 Letter INSPECTION SUMMARY
07/07/2022 Letter INSPECTION SUMMARY
07/08/2022 Letter Codes Temporary Certificate of Occupancy
07/11/2022 Letter INSPECTION SUMMARY
07/12/2022 Letter INSPECTION SUMMARY
07/12/2022 Letter Codes Final Certificate of Occupancy
07/12/2022 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home