Permit Application Status

PRRES20211894


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20211894
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - FINISHED AND UNFINISHED BASEMENT - COVERED DECK
04/20/2021
04/26/2021
10/23/2021
12/06/2022
Locations
Contacts
NEW MARK HOMES - KC LLC, Address:5207 NW CROOKED ROAD, Phone:(816) 969-9010  
ASHLEY@NEWMARKHOMESKC.COM  
HARRINGTON BROTHERS HEATING & COOLING, Address:15630 S KEELER ST, Phone:(913) 422-5444  
CLASS ONE ELECTRIC INC, Address:PO BOX 24343, Phone:(913) 915-1767  
R & R PLUMBING INC, Address:2001 GASLIGHT DR, Phone:(816) 772-5431  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 04/28/2021 04/26/2021
Brandon Kalwei
Residential Plan Review Approved 04/28/2021 04/26/2021
Brandon Kalwei
10 Combustion air
Corrective Action Required
04/26/2021

Provide combustion air calculations and specify transfer air grilles for fuel burning appliances located in confined space(s). (IRC Chapter 17 and Section G2407)
Residential Plan Review Rejected 04/26/2021 04/22/2021
Brandon Kalwei
10 Combustion air
Corrective Action Required
04/22/2021

Provide combustion air calculations and specify transfer air grilles for fuel burning appliances located in confined space(s). (IRC Chapter 17 and Section G2407)
Plot Plan Review Approved 04/26/2021 04/22/2021
Brandon Kalwei
Legal description
Corrective Action Required
04/22/2021

The legal description, including plat or phase number and lot number, and street address must be provided on the plot plan. Ln. needs to be added to the end of the address
Plot Plan Review Rejected 04/22/2021 04/21/2021
Brandon Kalwei
Legal description
Corrective Action Required
04/21/2021

The legal description, including plat or phase number and lot number, and street address must be provided on the plot plan. Ln. needs to be added to the end of the address
Residential Plan Review Rejected 04/22/2021 04/21/2021
Brandon Kalwei
07 Identify emergency escape openings from bedrooms
Corrective Action Required
04/21/2021

Identify emergency escape openings from bedrooms and basement(s). (IRC Section R310 as amended per Ordinance) No egress labeled for bedroom #5
10 Combustion air
Corrective Action Required
04/21/2021

Provide combustion air calculations and specify transfer air grilles for fuel burning appliances located in confined space(s). (IRC Chapter 17 and Section G2407)
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,286.60 $1,286.60 Paid 04/26/2021
8331507-Sewer Connection Fee $570.00 $570.00 Paid 04/26/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 04/26/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 04/26/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 04/26/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 04/26/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 02/22/2022
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 07/28/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Piers/Caissons Inspection - Residential Passed 6/22/2021 06/22/2021
Misc
Informational
06/22/2021
3RD PARTY BY BOB ROWE @ VAN DEURZEN SIGNED & SEALED BY CHAD STREETER DRILLED PIER FOUNDATION (39) 18" X 10'-14' BEARING ON BLUE SHALE AND LIMESTONE
Footing Inspection - Residential Passed 7/2/2021 7/2/2021 07/02/2021
Sewer Service Inspection - R Passed 7/30/2021 (10:00) 7/30/2021 07/30/2021
Water Service Inspection - R Passed 8/2/2021 (1:00) 8/2/2021 08/02/2021
Erosion Control Inspection Residential Failed 8/9/2021 08/09/2021
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
08/09/2021
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Underslab Plumbing Inspection - Residential Failed 8/9/2021 8/9/2021 08/09/2021
Miscellaneous Correction
Corrective Action Required
08/09/2021
REPLACE CRUSHED DRAIN TILE AT WALKOUT
Underslab Plumbing Inspection - Residential Passed 8/16/2021 8/16/2021 08/16/2021
Miscellaneous Correction
Resolved
08/16/2021
All Rough Inspection - Residential Failed 9/13/2021 9/13/2021 09/13/2021
Miscellaneous Correction
Corrective Action Required
09/13/2021
: PFH PORTAL FRAMEE ONLY : NAIL OFF HOLD DOWNS NAIL SHEATHING BREAKS PER PLAN SHEET 4.0 DETAIL 1
Piers/Caissons Inspection - Residential Passed 11/15/2021 (1:15) 11/15/2021 11/15/2021
All Rough Inspection - Residential Not Ready 1/27/2022 1/27/2022 01/27/2022
Miscellaneous Correction
Corrective Action Required
09/13/2021
HOUSE NOT READY FOR INSPECTION, LIST SUBJECT TO CHANGE. COMPLETE THESE ITEMS BEFORE RE INSPECT -Nail sheathing throughout -Nail sheathing at bottom plate PFH -Provide 2 1/4” x 3/16” square washer at PFF -Nail all corner and intersecting wall studs per code -Provide anchor bolt at end of plate at single car bay -Tighten anchor bolts -PFH straps not to top plate -Over notched joist at single car bay -Hip struts greater than 45 degrees -Provide roof boot at radon and dwv -Provide collar ties throughout -Rafters not tied to ceiling joists both garage walls -Nail rafters to top plate per code -Provide Joist hanger at single car bay -Nail hanger at beam in laundry -Seal top and bottom plate penetrations garage/ entry, garage/walk in closet, walk in closet bottom plate -Missing nails in joist hangers throughout owner’s entry -Strap both sides of laundry wall top plate cut at dwv -Fireblock top of fur out at laundry -Vent bath fans -Bocca plate at ceiling line pex in master shower -Connect rafter to joist at master tub -Missing joist hanger nails master bath throughout- COMPLETE NAILING OF ALL HANGERS THROUGHOUT THE HOUSE -Seal bottom plate penetrations at laundry, great room -Top plate penetrations pantry -Pan off electrical at return air in kitchen -Nail header joist to studs in owner’s entryway -Security blocking at strike plate back door -Address exterior walls not connected at top plate in great room/ dining -Fireblock dead space at great room -Seal floor penetrations at fireplace -Secure ward flex at fireplace -Solid block and nail sheathing at front -Flash and snow blocking at master -Fireblocking at fireplace to attic -Fireblocking at ceiling line coat closet -Bottom plate penetrations bath 2 -CS-PF per S4.1 all locations -Nail hangers at great room windows -(3) 2x6 at great room -(4) studs under beam in great room -Beam at great room to be (2) 16” LVL -Install listed floor box at entry -Address bearing of beam at great room/ back door -Later support at roof load beam above back door -Anchor column bases -Support stair stringers -Fireblocking throughout basement -Vent furnace -No pressure at gauge -Anchor bolts at basement door -Exterior walls not tied together basement -Vent sink at wet bar -Over notched joist at furnace -Struts in owner’s entry over spanned-See plans A4 -Bolt 2X10 to beam in unfinished space
Electrical Service Inspection Passed 1/27/2022 1/27/2022 01/27/2022
Gas Service Inspection - Residential Failed 1/27/2022 1/27/2022 01/27/2022
Misc
Corrective Action Required
01/27/2022
NO PRESSURE AT GAUGE
Gas Service Inspection - Residential Passed 2/23/2022 2/23/2022 02/23/2022
Misc
Resolved
02/23/2022
All Rough Inspection - Residential Failed 2/23/2022 2/23/2022 02/23/2022
Miscellaneous Correction
Corrective Action Required
01/27/2022
HOUSE NOT READY FOR INSPECTION, LIST SUBJECT TO CHANGE. COMPLETE THESE ITEMS BEFORE RE INSPECT -Fireblock top of fur out at laundry ( not done) -Address exterior walls not connected at top plate in great room/ dining -Solid block and nail sheathing at front ( not done ) -Fireblocking at ceiling line coat closet ( not done ) -CS-PF per S4.1 all locations ( engineers letter or detail) -(3) 2x6 at great room ( not full length) -Address bearing of beam at great room/ back door -Vent sink at wet bar ( seal upward penetration)
All Rough Inspection - Residential Passed 3/8/2022 3/8/2022 03/08/2022
Miscellaneous Correction
Resolved
03/08/2022
HOUSE NOT READY FOR INSPECTION, LIST SUBJECT TO CHANGE. COMPLETE THESE ITEMS BEFORE RE INSPECT -Fireblock top of fur out at laundry ( not done) -Address exterior walls not connected at top plate in great room/ dining -Solid block and nail sheathing at front ( not done ) -Fireblocking at ceiling line coat closet ( not done ) -CS-PF per S4.1 all locations ( engineers letter or detail) -(3) 2x6 at great room ( not full length) -Address bearing of beam at great room/ back door -Vent sink at wet bar ( seal upward penetration)
Driveway Inspection Partial 4/13/2022 4/13/2022 04/13/2022
Misc
Informational
04/13/2022
Forms were placed and aggregate was present and compacted. RP 4-13-22
Sidewalk Inspection Partial 4/13/2022 4/13/2022 04/13/2022
Misc
Informational
04/13/2022
Forms were placed and aggregate was present and compacted. RP 4-13-22
Driveway Inspection Passed 4/22/2022 4/22/2022 04/22/2022
Misc
Informational
04/13/2022
Forms were placed and aggregate was present and compacted. RP 4-13-22
Misc
Informational
04/22/2022
Finished driveway meets LS and ADA specs. RP 4-22-22
Sidewalk Inspection Passed 4/22/2022 4/22/2022 04/22/2022
Misc
Informational
04/13/2022
Forms were placed and aggregate was present and compacted. RP 4-13-22
Misc
Informational
04/22/2022
Finished sidewalk meets LS and ADA specs. RP 4-22-22
Plot Plan Inspection Passed 7/19/2022 07/19/2022
Erosion Control Inspection Residential Failed 7/19/2022 07/19/2022
DCM2 ESC DEFICIENT INSTALLATION
Resolved
07/19/2022
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
07/19/2022
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE. Mitchell Schwarz 07/19/2022 8:35 AM
Occupancy Inspection - Codes Residential Failed 7/19/2022 7/19/2022 07/19/2022
Misc
Corrective Action Required
07/19/2022
-erosion control to remain in compliance until sod is in place -sod -gutt -check water meter at time of sod -spark rings at kitchen outlets as will be required -security screws at basement door -address siding from concrete patio and side wall at back of lot -label all non GFCI outlets in unfinished spaces -complete stairs in garage -provide ladder at egress window well to code
Occupancy Inspection - Codes Residential Ready for Temp CO 7/26/2022 7/26/2022 07/26/2022
Misc
Corrective Action Required
07/19/2022
-erosion control to remain in compliance until sod is in place -sod -gutt -check water meter at time of sod Expiration of TCO 8/25/22
Erosion Control Inspection Residential Passed 7/26/2022 07/26/2022
DCM1 ESC REQUIRED NO FURTHER INSP
Resolved
07/26/2022
Occupancy Inspection - Codes Residential Temporary C of O 07/28/2022
Misc
Corrective Action Required
07/26/2022
-erosion control to remain in compliance until sod is in place -sod -gutt -check water meter at time of sod Expiration of TCO 8/25/22
Occupancy Inspection - Codes Residential Full C of O 12/8/2022 12/8/2022 12/06/2022
Misc
Resolved
12/06/2022
-erosion control to remain in compliance until sod is in place -sod -gutt -check water meter at time of sod Expiration of TCO 8/25/22
Plot Plan Inspection Passed 12/7/2022 12/06/2022
Documents & Images
Date Uploaded File Type Document Name
04/20/2021 Application Form APPLICATION
04/20/2021 Lot 125 Woodside
04/20/2021 04_19_2021_21-314 Lot 125 Woodside Ridge (Kelsey) by GP (Minor Nonstructural Changes added)
04/21/2021 Letter Codes Residential Plan Review
04/21/2021 Revised Lot 125
04/21/2021 Plot Plan APPROVED PLOT PLAN
04/21/2021 04_21_2021_21-314 Lot 125 Woodside Ridge (Kelsey) 4-21-21 returned with egress changes
04/22/2021 Letter Codes Residential Plan Review
04/26/2021 04_26_2021_21-314 Lot 125 Woodside Ridge (Kelsey) by GP returned with changes
04/26/2021 Approved Plans APPROVED PLANS
04/26/2021 Receipt Receipt for transaction:2021-002217
04/26/2021 Letter DS Building Permit
06/22/2021 2111 NW Killarney Ln_PIER INSP_2021-06-21
06/22/2021 2111 NW KILLARNEY LN_PIER PLAN_5-14-21
06/22/2021 Letter INSPECTION SUMMARY
06/22/2021 Approved Plans pier plan detail
07/02/2021 Letter INSPECTION SUMMARY
07/30/2021 Letter INSPECTION SUMMARY
08/02/2021 Letter INSPECTION SUMMARY
08/09/2021 Letter INSPECTION SUMMARY
08/09/2021 Letter INSPECTION SUMMARY
08/16/2021 Letter INSPECTION SUMMARY
08/16/2021 Letter INSPECTION SUMMARY
09/13/2021 Letter INSPECTION SUMMARY
11/15/2021 Letter INSPECTION SUMMARY
01/27/2022 Letter INSPECTION SUMMARY
01/27/2022 Letter INSPECTION SUMMARY
01/27/2022 Letter INSPECTION SUMMARY
01/27/2022 Letter INSPECTION SUMMARY
02/10/2022 2022_02_03_Lot 125 Woodside Ridge_Apex_EOR Compliance Letter
02/10/2022 2022_02_10_Lot 125 Woodside Ridge_Apex_EOR Compliance Letter
02/18/2022 Final_2022_02_16_Struct_LSMO_New Mark Homes
02/22/2022 Receipt Receipt for transaction:2022-000913
02/23/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
03/03/2022 2022_03_03_Lot 125 Woodside Ridge_Apex_EOR Compliance Letter
03/07/2022 2022_03_03_Lot 125 Woodside Ridge_Apex_EOR Compliance Letter(2)
03/08/2022 Letter INSPECTION SUMMARY
04/13/2022 Letter INSPECTION SUMMARY
04/13/2022 Letter INSPECTION SUMMARY
04/22/2022 Letter INSPECTION SUMMARY
04/22/2022 Letter INSPECTION SUMMARY
07/19/2022 Letter INSPECTION SUMMARY
07/19/2022 Letter INSPECTION SUMMARY
07/19/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/28/2022 Receipt Receipt for transaction:2022-006185
07/28/2022 Letter Codes Temporary Certificate of Occupancy
12/06/2022 Plot Plan APPROVED AS GRADED PLOT PLAN
12/06/2022 Letter Codes Final Certificate of Occupancy
12/06/2022 Letter Field Certificate of Occupancy
12/06/2022 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home