Permit Application Status

PRRES20193377


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20193377
Building Permit - Residential
Certificate of Occupancy
MCGRAW HOMES INC
NEW SINGLE FAMILY
NEW HOUSE - FINISHED BASEMENT - COVERED DECK
11/18/2019
11/20/2019
10/21/2020
Locations
Contacts
MCGRAW HOMES INC, Address:902 SE WILLOW PL, Phone:(816) 985-6909  
MCGRAW HOMES INC, Address:902 SE WILLOW PL, Phone:(816) 985-6909  
APEX HEATING & AIR CONDITIONING INC, Address:1202 NW EAGLE RIDGE BLVD, Phone:(816) 228-2739  
UNITED ELECTRIC COMPANY, Address:PO BOX 723, Phone:(816) 795-2744  
A BRIGHT PLUMBING LLC, Address:18107 E 18TH TER N, Phone:(816) 215-0730  
chad@mcgraw-homes.com  
Reviews
Review Type Outcome Est. Completion Date Completed
Residential Plan Review Approved 11/20/2019 11/19/2019
Kim Brennan
10 Combustion air
Corrective Action Required
11/18/2019

Provide combustion air calculations and specify transfer air grilles for fuel burning appliances located in confined space(s). (IRC Chapter 17 and Section G2407)
Plot Plan Review Approved 11/20/2019 11/19/2019
Kim Brennan
Property boundary
Corrective Action Required
11/18/2019

Property boundary distances and bearings, as shown on the recorded plat, must be provided on the plot plan. Bearing on the the front of the lot facing Catalina Ave is incorrect. Please see plat
Basement elevation
Corrective Action Required
11/18/2019

The Basement floor elevation and basement type (e.g. full/standard, daylight, walk-out, etc.) Plot plan shows daylight and the MDP shows a full basement. Please change accordingly
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,232.66 $1,232.66 Paid 11/20/2019
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 11/20/2019
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 11/20/2019
8331507-Sewer Connection Fee $390.00 $390.00 Paid 11/20/2019
8331401-Water Tap Fee $3,477.00 $3,477.00 Paid 11/20/2019
8350015-Water Meter Fee $425.02 $425.02 Paid 11/20/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 11/22/2019 (8:00) 11/22/2019 at 8:30 AM 11/22/2019
Underslab Plumbing Inspection - Residential Passed 12/26/2019 12/26/2019 at 9:35 AM 12/26/2019
Sewer Service Inspection - R Passed 12/31/2019 12/31/2019 at 2:30 PM 12/31/2019
Water Service Inspection - R Passed 1/6/2020 1/6/2020 01/06/2020
Piers/Caissons Inspection - Residential Passed 3/2/2020 (11:00) 3/2/2020 at 11:10 AM 03/02/2020
Electrical Service Inspection Passed 3/27/2020 03/27/2020
Gas Service Inspection - Residential Passed 3/27/2020 03/27/2020
All Rough Inspection - Residential Failed 3/27/2020 at 8:05 AM 03/27/2020
Misc
Corrective Action Required
03/27/2020
FRAMING: -Nail corner studs at front bedroom wall -Missing stud at closet/pantry wall -Install security blocking for rear exterior door -Fb fireplace space from roof -Nail together lvl beams -Fb basement bedroom wall from joist -Header off cut joist below front bathroom -Install double joist under front bedroom closet bearing point MECHANICAL: -Lower supply duct to basement bathroom ceiling level -Upper combustion air opening must be within 12” of ceiling **OK TO INSULATE
All Rough Inspection - Residential Failed 3/31/2020 3/31/2020 at 8:30 AM 03/31/2020
Misc
Corrective Action Required
03/27/2020
-Fb basement bedroom wall from joist **The NE bedroom rear wall is still open to the joist space
All Rough Inspection - Residential Passed 4/1/2020 at 9:20 AM 04/01/2020
Misc
Resolved
04/01/2020
-Fb basement bedroom wall from joist **The NE bedroom rear wall is still open to the joist space
Driveway Inspection Partial 05/29/2020
Misc
Informational
05/29/2020
Driveway - forms and materials passed pre-inspection.
Sidewalk Inspection Partial 6/1/2020 6/1/2020 06/01/2020
Misc
Informational
06/01/2020
Sidewalk- forms and materials passed pre-inspection.
Driveway Inspection Passed 6/4/2020 6/4/2020 06/04/2020
Misc
Informational
05/29/2020
Driveway - forms and materials passed pre-inspection.
Misc
Informational
06/04/2020
Driveway passed final inspection.
Sidewalk Inspection Passed 6/4/2020 6/4/2020 06/04/2020
Misc
Informational
06/01/2020
Sidewalk- forms and materials passed pre-inspection.
Misc
Informational
06/04/2020
Sidewalk passed final inspection.
Occupancy Inspection - Codes Residential Failed 9/10/2020 9/10/2020 09/10/2020
Misc
Corrective Action Required
09/10/2020
**INSTALL EROSION CONTROLALONG THE STREET -Bring to final grade the sewer manhole at front -Final grade, sod, downspout and sump pump extensions -Make sure that the sewer tracer wire and port are installed and available at grade level -Garage door bottom bracket shall be installed within 10” of floor -Install a receptacle for left side shelf cabinet. Fish the circuit from the receptacle at the back side of wall -Support receptacle yokes at wet bar -Install bedroom window hardware -Cover exposed staples behind wet bar. Yes, this is covered in the code as a dangerous condition -Provide min 100 square inches area for each combustion air opening -Provide min 1” clearance from water heater b-vent to combustible
Occupancy Inspection - Codes Residential Full C of O 10/21/2020 10/21/2020 10/21/2020
Misc
Resolved
10/21/2020
-Make sure that the sewer tracer wire and port are installed and available at grade level -Garage door bottom bracket shall be installed within 10” of floor -Install a receptacle for left side shelf cabinet. Fish the circuit from the receptacle at the back side of wall -Support receptacle yokes at wet bar -Install bedroom window hardware -Cover exposed staples behind wet bar. Yes, this is covered in the code as a dangerous condition -Provide min 100 square inches area for each combustion air opening -Provide min 1” clearance from water heater b-vent to combustible
Documents & Images
Date Uploaded File Type Document Name
11/18/2019 Letter Codes Residential Plan Review
11/20/2019 Receipt Receipt for transaction: 2019-007408
11/20/2019 Letter DS Building Permit
11/21/2019 Engineer Report/Study DOC112119-009
11/21/2019 Plot Plan DOC112119-010
11/22/2019 Letter INSPECTION SUMMARY
12/26/2019 Letter INSPECTION SUMMARY
12/31/2019 Letter INSPECTION SUMMARY
01/06/2020 Letter INSPECTION SUMMARY
03/02/2020 Letter INSPECTION SUMMARY
03/27/2020 Letter INSPECTION SUMMARY
03/27/2020 Letter INSPECTION SUMMARY
03/27/2020 Letter INSPECTION SUMMARY
03/31/2020 Letter INSPECTION SUMMARY
04/01/2020 Letter INSPECTION SUMMARY
05/29/2020 Letter INSPECTION SUMMARY
06/01/2020 Letter INSPECTION SUMMARY
06/04/2020 Letter INSPECTION SUMMARY
06/04/2020 Letter INSPECTION SUMMARY
06/04/2020 Letter INSPECTION SUMMARY
09/10/2020 Letter INSPECTION SUMMARY
10/21/2020 Letter Codes Final Certificate of Occupancy
10/21/2020 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home