Permit Application Status

PRCOM20245783


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20245783
Building Permit - Commercial
Issued
CITY OF LEES SUMMIT
NEW COMMERCIAL
LEE'S SUMMIT JOINT OPERATIONS FACILITY - NEW FIRE DISPATCH, ADMIN, FIRE TRAINING, AND EMERGENCY OPERATIONS CENTER
11/01/2024
02/19/2025
06/08/2025
Locations
Contacts
CITY OF LEES SUMMIT, Address:207 SW MARKET ST  
Titan Built, LLC, Address:8207 Melrose Drive, #200  
Keith Williams - Titan Built, Phone:(913) 439-8638  
METRO AIR CONDITIONING , Address:8151 MCCOY ST, Phone:(913) 888-3991  
S & S ELECTRICAL CONTRACTING LLC, Address:574 NW 1921 RD, Phone:(816) 847-2433  
SALADINO PLUMBING & HEATING COMPANY, Address:2210 TELEVISION PL, Phone:(816) 833-9900  
HOEFER WELKER, Address:4622 PENNSULVANIA AVE, SUITE 1400, Phone:(913) 307-3837  
UES dba GEOTECHNOLOGY LLC, Address:5055 ANTIOCH RD, Phone:(913) 438-1900  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved 09/16/2025 09/19/2025
Joe Frogge
ICC A117.1 604.3.1 Water closet width
Resolved
09/19/2025

ICC A117.1-2009 Section 604.10.2 Size. The minimum area of an ambulatory accessible compartment shall be 60 inches (1525 mm) minimum in depth and 36 inches (915 mm) in width. Action required: Amend plans to comly. See detail A1/A-402
Fire Plan Review Approved 09/16/2025 09/15/2025
Craig Hill
Alarm Plan Review Rejected 07/09/2025 07/15/2025
Craig Hill
Misc
Corrective Action Required
07/15/2025

Action Required: Make alerting devices in rooms 005, 004, 121, 120, 116, 115, 107, 105, 138, and 140 strobes only.
Miscellaneous Correction
Corrective Action Required
07/15/2025

Action Required: Add strobs to rooms 036 and 038.
Sprinkler Plan Review Released for Construction 06/26/2025 06/23/2025
Craig Hill
Misc
Resolved
06/23/2025

Action Required: Provide code reference for extinguishing system.
Miscellaneous Correction
Corrective Action Required
06/16/2025

Action Required: Each individual room with a toilet needs a sprinkler head. The room in between 028 and 029 requires a sprinkler.
Miscellaneous Correction
Corrective Action Required
06/18/2025

Action Required: Provide information on FDC conection and location to include ball drip.
Sprinkler Plan Review Rejected 05/16/2025 05/13/2025
Craig Hill
Misc
Corrective Action Required
05/13/2025

Action Required: Provide code reference for extinguishing system.
Building Plan Review Approved 03/31/2025 03/27/2025
Joe Frogge
Misc
Corrective Action Required
03/24/2025

This review is for both the operations facility and vehicle building. A separate permit for vehicle building will be created at a later date. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
Elevator Equipment Permit
Corrective Action Required
03/24/2025

Prior to the installation or construction of any elevator equipment, an elevator equipment permit shall be obtained from the Missouri Department of Public Safety or its authorized representative. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
Elevator Equipment Inspection
Corrective Action Required
03/24/2025

Prior to the operation of any new elevator equipment or the issuance of the operating certificate, such elevator equipment shall be inspected by a licensed inspector. Testing must be performed in accordance with these rules and regulations. The testing must be witnessed by a licensed inspector. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
Elevator Certificate of Inspection
Corrective Action Required
03/24/2025

Elevator Safety Act and Rules 701.361 - Each privately owned or operated installation and each installation owned or operated by the state of Missouri or any political subdivision of the state shall have a certificate of inspection and meet the safety code promulgated pursuant to sections 701.350 to 701.380. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
Building Plan Review Approved with Conditions 01/27/2025 02/14/2025
Joe Frogge
IBC 423.1 - Special Occ - Storm Shelters
Resolved
02/14/2025

2014 ICC/NSSA Section 106.1.1 Peer Review. A peer review by an independent registered design professional for compliance with the requirements of Chapters 3, 5, 6 and 7 shall be conducted for the following storm shelter types: 1. Community shelters with an occupant load greater than 50. 2. Storm shelters in elementary schools, secondary schools, and day care facilities with an occupant load greater than 16. 3. Storm shelters in Risk Category IV (essential facilities) as defined in Table 1604.5 in the International Building Code. Action required: Provide peer review of storm shelter. 12/9/2024 - acknowledged in letter. 1/22/2025 - Provide verification that designs have addressed comments in peer review letters.
Misc
Corrective Action Required
01/17/2025

This review is for both the operations facility and vehicle building. A separate permit for vehicle building will be created at a later date. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
Elevator Equipment Permit
Corrective Action Required
01/17/2025

Prior to the installation or construction of any elevator equipment, an elevator equipment permit shall be obtained from the Missouri Department of Public Safety or its authorized representative. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
Elevator Equipment Inspection
Corrective Action Required
01/17/2025

Prior to the operation of any new elevator equipment or the issuance of the operating certificate, such elevator equipment shall be inspected by a licensed inspector. Testing must be performed in accordance with these rules and regulations. The testing must be witnessed by a licensed inspector. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
Elevator Certificate of Inspection
Corrective Action Required
01/17/2025

Elevator Safety Act and Rules 701.361 - Each privately owned or operated installation and each installation owned or operated by the state of Missouri or any political subdivision of the state shall have a certificate of inspection and meet the safety code promulgated pursuant to sections 701.350 to 701.380. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
IPC 604.8 Water pressure reducing valve
Resolved
01/22/2025

2018 IPC 604.8 Water Pressure reducing valve or regulator. Where water pressure within a building exceeds 80 psi static, an approved water-pressure reducing valve conforming to ASSE 1003 or CSA B356 with strainer shall be installed to reduce the pressure in the building water distribution piping to not greater than 80 psi static. Action required: Provide pressure reducing valve at water entry. (Our Water Department requires PRV installation in all locations regardless of pressure) 12/9/2024 - An RPZ backflow device does not function as a PRV.
Licensed Contractors Approved 01/27/2025 01/24/2025
Joe Frogge
LC - MEP Subs
Resolved
01/24/2025

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 12/9/2024 - acknowledged in letter. 1/22/2025 - Saladino not currently licensed with us.
Fire Plan Review Approved 01/27/2025 01/24/2025
Craig Hill
Special Inspections Review Approved 01/15/2025
Joe Frogge
Final Development Plan Review Approved 01/15/2025 01/13/2025
Grant White
Fire Plan Review Rejected 12/09/2024 12/09/2024
Craig Hill
Posting of occupant load
Corrective Action Required
12/02/2024

2018 IFC 1004.3- Posting of occupant load. Every room or space that is an assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent. Confirm at inspection.
Construction documents for fire alarm systems
Corrective Action Required
12/02/2024

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Action Required: Provide deferred submittal for alarm system. Not required for the vehicle storage building to the North.
Knox box required
Corrective Action Required
12/02/2024

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. Action Required: Provide Knox Box for building access.
Locks on gates or barriers
Corrective Action Required
12/02/2024

2018 IFC 506.1.1-Locks. An approved lock shall be installed on gates or similar barriers when required by the fire code official. Action Required: Provide Knox Box Gate & Key Switch to all gates entering secure parking area.
Construction documents - Fire protection systems
Corrective Action Required
12/02/2024

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action Required: Provide deferred submittal for protection system. Not required for vehicle storage building to the North.
Key boxes for non-standardized fire service elevator keys
Corrective Action Required
12/02/2024

2018 IFC 506.1.2 Key boxes for non-standardized fire service elevator keys. Key boxes provided for non-standardized fire service elevator keys shall comply with Section 506.1 and 506.2 or as approved by the fire code official. Action Requirerd: Provide elevator knox box next to elevator.
Emergency power for illumination
Corrective Action Required
12/02/2024

2018 IFC 1008.3.1 & 3.2 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises' electrical supply. In the event of power supply failure, an emergency electrical system shall automatically illuminate all of the following: 1. Aisles and unenclosed egress stairways in rooms and spaces that require two or mor means of egress. 2. Corridors, interior exit stairways and ramps and exit passageways in buildings required to have two or more exits. 3. Exterior egress components at other than their levels of exit discharge until exit discharge is accomplished for buildings required to have two or more exits. Action Required: Provide emergency exterior illumination at all marked exits from the building.
Miscellaneous Correction
Corrective Action Required
12/02/2024

Provide manual emergency shutdown controls for generator and a whole building emergency shutdown knox key switch.
Miscellaneous Correction
Corrective Action Required
12/09/2024

2018 IFC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply. 1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Aisles. 2. Corridors. 3. Exit access stairways and ramps. 1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Interior exit access stairways and ramps. 2. Interior and exterior exit stairways and ramps. 3. Exit passageways. 4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1. 5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge. 1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas: 1. Electrical equipment rooms. 2. Fire command centers. 3. Fire pump rooms. 4. Generator rooms. 5. Public restrooms with an area greater than 300 square feet. Action required: Provide emergency lighting at exterior landing of all exits.
Building Plan Review Rejected 12/09/2024 12/09/2024
Joe Frogge
Final Development Plan
Resolved
01/13/2025

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
IBC 1704.2 Special Inspections
Resolved
01/15/2025

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections. 12/9/2024 - acknowledged in letter.
IBC 423.1 - Special Occ - Storm Shelters
Corrective Action Required
12/02/2024

2014 ICC/NSSA Section 106.1.1 Peer Review. A peer review by an independent registered design professional for compliance with the requirements of Chapters 3, 5, 6 and 7 shall be conducted for the following storm shelter types: 1. Community shelters with an occupant load greater than 50. 2. Storm shelters in elementary schools, secondary schools, and day care facilities with an occupant load greater than 16. 3. Storm shelters in Risk Category IV (essential facilities) as defined in Table 1604.5 in the International Building Code. Action required: Provide peer review of storm shelter. 12/9/2024 - acknowledged in letter.
Misc
Corrective Action Required
12/02/2024

This review is for both the operations facility and vehicle building. A separate permit for vehicle building will be created at a later date. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
Project cost
Resolved
12/09/2024

The project cost, which is used to establish the permit fee, has not been provided. Action required: Provide separate cost valuations for operations facility and vehicle building.
IBC 1007.2.1 Two exits or exit access doorways - distance apart
Resolved
12/09/2024

1007.1.1 Two exits or exit access doorways. Where two exits, exit access doorways, exit access stairways or ramps, or any combination thereof, are required from any portion of the exit access, they shall be placed a distance apart equal to not less than one-half of the length of the maximum overall diagonal dimension of the building or area to be served measured in a straight line between them. Interlocking or scissor stairways shall be counted as one exit stairway. (See code for exceptions) **From Commentary: "The need for exits from a space or story to be independent of each other cannot be overstated. Each occupant of each floor must be provided with the required number of exits without having to pass through one exit to gain access to another. Each exit is required to be independent of other exits to prohibit such areas from merging downstream and becoming, in effect, one exit." Action required: Given that the 2 exits lead to same exterior space you will need to proved an additional exit out of main level Training room.
IBC 1803.1 General - geotech
Resolved
12/09/2024

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf. (12,000psf cited on S-000)
IPC 403.2 Separate facilities
Resolved
12/10/2024

2018 IPC 403.2 Separate Facilities. (As amended by Lee’s Summit Code of Ordinances Section 7-405) Where plumbing fixtures are required, separate facilities shall be provided for each sex. Exceptions: 1. Separate facilities shall not be required for dwelling units and sleeping units. 2. Separate facilities shall not be required in structures or tenant spaces with a total occupant load, including both employees and customers, of 15 or fewer. 3. Separate facilities shall not be required in mercantile occupancies in which the maximum occupant load is 100 or fewer. 4. Separate facilities shall not be required in business occupancies in which the maximum occupant load is 25 or fewer. Action required: Either label restrooms per gender or submit for Code Modification Request to use more modern code adoption years. 12/9/2024 - CMR pending
Code analysis required
Resolved
12/09/2024

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Clarify use of A3 category. I would call this entire thing a B but am open to interpretations.
Elevator Equipment Permit
Corrective Action Required
12/02/2024

Prior to the installation or construction of any elevator equipment, an elevator equipment permit shall be obtained from the Missouri Department of Public Safety or its authorized representative. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
Elevator Equipment Inspection
Corrective Action Required
12/02/2024

Prior to the operation of any new elevator equipment or the issuance of the operating certificate, such elevator equipment shall be inspected by a licensed inspector. Testing must be performed in accordance with these rules and regulations. The testing must be witnessed by a licensed inspector. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
Elevator Certificate of Inspection
Corrective Action Required
12/02/2024

Elevator Safety Act and Rules 701.361 - Each privately owned or operated installation and each installation owned or operated by the state of Missouri or any political subdivision of the state shall have a certificate of inspection and meet the safety code promulgated pursuant to sections 701.350 to 701.380. Action required: Comment is informational. 12/9/2024 - acknowledged in letter.
ICC A117.1 304.3 Turning Space
Resolved
12/09/2024

ICC A117.1 Section 304.3 Size. Turning spaces shall comply with Section 304.3.1 or 304.3.2. 304.3.1 Circular Space. 304.3.1.1 New Buildings and facilities. In new buildings and facilities, the turning space shall be a circular space with a 67-inch minimum diameter. (see code for information regarding allowed overlapping) 304.3.1.2 Existing buildings and facilities. In existing buildings and facilities, the turning space shall be a circular space with a 60-inch minimum diameter. (see code for information regarding allowed overlapping) Action required: Provide enough room in ADA Shower for a turning space.
IPC 604.8 Water pressure reducing valve
Corrective Action Required
12/02/2024

2018 IPC 604.8 Water Pressure reducing valve or regulator. Where water pressure within a building exceeds 80 psi static, an approved water-pressure reducing valve conforming to ASSE 1003 or CSA B356 with strainer shall be installed to reduce the pressure in the building water distribution piping to not greater than 80 psi static. Action required: Provide pressure reducing valve at water entry. (Our Water Department requires PRV installation in all locations regardless of pressure) 12/9/2024 - An RPZ backflow device does not function as a PRV.
Planning - Screening of ground mounted equipment
Resolved
12/09/2024

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. (re: CU-V1 at vehicle building on sheet M-103)
IMC 606.2.1 Duct detector
Resolved
12/09/2024

2018 IMC 606.2.1 Return air systems. Smoke detectors shall be installed in return air systems with a design capacity greater than 2,000 cfm, in the return air duct or plenum upstream of any filters, exhaust air connections, outdoor air connections, or decontamination equipment and appliances. Exception: Smoke detectors are not required in the return air system where all portions of the building served by the air distribution system are protected by area smoke detectors connected to a fire alarm system in accordance with the International Fire Code. The area smoke detection system shall comply with Section 606.4. Action required: Provide duct mounted smoke detector in return air duct at DOAS-1 and CRAC-1, 2, & 3. (see schedules on M-601 & M-602)
NEC Article 210.63 Heating, air-conditioning and refrigeration outlet
Resolved
12/09/2024

2017 NEC Article 210.63 Heating, Air-Conditioning, and Refrigeration Equipment Outlet. A 125-volt, single-phase, 15- or 20-ampere-rated receptacle outlet shall be installed at an accessible location for the servicing of heating, air-conditioning, and refrigeration equipment. The receptacle shall be located on the same level and within 25 feet of the heating, air-conditioning, and refrigeration equipment. The receptacle outlet shall not be connected to the load side of the equipment disconnecting means. Action required: Provide additional receptacle or relocate receptacle shown in Utility Yard. (all equipment must have receptacle within 25')
IBC 1008.3 Emergency power for illumination - at exit discharge
Resolved
12/09/2024

2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply. 1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Aisles. 2. Corridors. 3. Exit access stairways and ramps. 1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Interior exit access stairways and ramps. 2. Interior and exterior exit stairways and ramps. 3. Exit passageways. 4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1. 5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge. 1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas: 1. Electrical equipment rooms. 2. Fire command centers. 3. Fire pump rooms. 4. Generator rooms. 5. Public restrooms with an area greater than 300 square feet. Action required: Provide emergency lighting at exterior landing of all exits.
Licensed Contractors Rejected 12/09/2024 12/09/2024
Joe Frogge
LC - General Contractor
Resolved
12/09/2024

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Provide the name, email address & phone number for the on-site contact.
LC - MEP Subs
Corrective Action Required
12/02/2024

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 12/9/2024 - acknowledged in letter.
Fire Plan Review Rejected 11/18/2024 11/18/2024
Craig Hill
Misc
Corrective Action Required
11/18/2024

1007.1.1 Two exits or exit access doorways. Where two exits, exit access doorways, exit access stairways or ramps, or any combination thereof, are required from any portion of the exit access, they shall be placed a distance apart equal to not less than one-half of the length of the maximum overall diagonal dimension of the building or area to be served measured in a straight line between them. Interlocking or scissor stairways shall be counted as one exit stairway. Action required: Proved an additional exit out of main level Training room. The 2 exits lead to the sam exterior space.
Posting of occupant load
Corrective Action Required
11/18/2024

2018 IFC 1004.3- Posting of occupant load. Every room or space that is an assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent. Confirm at inspection.
Construction documents for fire alarm systems
Corrective Action Required
11/18/2024

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Action Required: Provide deferred submittal for alarm system. This is to include the vehicle storage building to the North.
Knox box required
Corrective Action Required
11/18/2024

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. Action Required: Provide Knox Box for building access.
Locks on gates or barriers
Corrective Action Required
11/18/2024

2018 IFC 506.1.1-Locks. An approved lock shall be installed on gates or similar barriers when required by the fire code official. Action Required: Provide Knox Box Gate & Key Switch to all gates entering secure parking area.
Construction documents - Fire protection systems
Corrective Action Required
11/18/2024

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action Required: Provide deferred submittal for protection system. This is to include the vehicle storage building to the North.
Key boxes for non-standardized fire service elevator keys
Corrective Action Required
11/18/2024

2018 IFC 506.1.2 Key boxes for non-standardized fire service elevator keys. Key boxes provided for non-standardized fire service elevator keys shall comply with Section 506.1 and 506.2 or as approved by the fire code official. Action Requirerd: Provide elevator knox box next to elevator.
Emergency power for illumination
Corrective Action Required
11/18/2024

2018 IFC 1008.3.1 & 3.2 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises' electrical supply. In the event of power supply failure, an emergency electrical system shall automatically illuminate all of the following: 1. Aisles and unenclosed egress stairways in rooms and spaces that require two or mor means of egress. 2. Corridors, interior exit stairways and ramps and exit passageways in buildings required to have two or more exits. 3. Exterior egress components at other than their levels of exit discharge until exit discharge is accomplished for buildings required to have two or more exits. Action Required: Provide emergency exterior illumination at all marked exits from the building.
Miscellaneous Correction
Corrective Action Required
11/18/2024

Provide manual emergency shutdown controls for generator and a whole building emergency shutdown knox key switch.
Building Plan Review Rejected 11/18/2024 11/18/2024
Joe Frogge
Final Development Plan
Corrective Action Required
11/15/2024

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational.
IBC 1704.2 Special Inspections
Corrective Action Required
11/15/2024

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections.
IBC 423.1 - Special Occ - Storm Shelters
Corrective Action Required
11/15/2024

2014 ICC/NSSA Section 106.1.1 Peer Review. A peer review by an independent registered design professional for compliance with the requirements of Chapters 3, 5, 6 and 7 shall be conducted for the following storm shelter types: 1. Community shelters with an occupant load greater than 50. 2. Storm shelters in elementary schools, secondary schools, and day care facilities with an occupant load greater than 16. 3. Storm shelters in Risk Category IV (essential facilities) as defined in Table 1604.5 in the International Building Code. Action required: Provide peer review of storm shelter.
Misc
Corrective Action Required
11/15/2024

This review is for both the operations facility and vehicle building. A separate permit for vehicle building will be created at a later date. Action required: Comment is informational.
Project cost
Corrective Action Required
11/15/2024

The project cost, which is used to establish the permit fee, has not been provided. Action required: Provide separate cost valuations for operations facility and vehicle building.
IBC 1007.2.1 Two exits or exit access doorways - distance apart
Corrective Action Required
11/15/2024

1007.1.1 Two exits or exit access doorways. Where two exits, exit access doorways, exit access stairways or ramps, or any combination thereof, are required from any portion of the exit access, they shall be placed a distance apart equal to not less than one-half of the length of the maximum overall diagonal dimension of the building or area to be served measured in a straight line between them. Interlocking or scissor stairways shall be counted as one exit stairway. (See code for exceptions) **From Commentary: "The need for exits from a space or story to be independent of each other cannot be overstated. Each occupant of each floor must be provided with the required number of exits without having to pass through one exit to gain access to another. Each exit is required to be independent of other exits to prohibit such areas from merging downstream and becoming, in effect, one exit." Action required: Given that the 2 exits lead to same exterior space you will need to proved an additional exit out of main level Training room.
IBC 1803.1 General - geotech
Corrective Action Required
11/15/2024

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf. (12,000psf cited on S-000)
IPC 403.2 Separate facilities
Corrective Action Required
11/15/2024

2018 IPC 403.2 Separate Facilities. (As amended by Lee’s Summit Code of Ordinances Section 7-405) Where plumbing fixtures are required, separate facilities shall be provided for each sex. Exceptions: 1. Separate facilities shall not be required for dwelling units and sleeping units. 2. Separate facilities shall not be required in structures or tenant spaces with a total occupant load, including both employees and customers, of 15 or fewer. 3. Separate facilities shall not be required in mercantile occupancies in which the maximum occupant load is 100 or fewer. 4. Separate facilities shall not be required in business occupancies in which the maximum occupant load is 25 or fewer. Action required: Either label restrooms per gender or submit for Code Modification Request to use more modern code adoption years.
Code analysis required
Corrective Action Required
11/15/2024

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Clarify use of A3 category. I would call this entire thing a B but am open to interpretations.
Elevator Equipment Permit
Corrective Action Required
11/15/2024

Prior to the installation or construction of any elevator equipment, an elevator equipment permit shall be obtained from the Missouri Department of Public Safety or its authorized representative. Action required: Comment is informational.
Elevator Equipment Inspection
Corrective Action Required
11/15/2024

Prior to the operation of any new elevator equipment or the issuance of the operating certificate, such elevator equipment shall be inspected by a licensed inspector. Testing must be performed in accordance with these rules and regulations. The testing must be witnessed by a licensed inspector. Action required: Comment is informational.
Elevator Certificate of Inspection
Corrective Action Required
11/15/2024

Elevator Safety Act and Rules 701.361 - Each privately owned or operated installation and each installation owned or operated by the state of Missouri or any political subdivision of the state shall have a certificate of inspection and meet the safety code promulgated pursuant to sections 701.350 to 701.380. Action required: Comment is informational.
ICC A117.1 304.3 Turning Space
Corrective Action Required
11/15/2024

ICC A117.1 Section 304.3 Size. Turning spaces shall comply with Section 304.3.1 or 304.3.2. 304.3.1 Circular Space. 304.3.1.1 New Buildings and facilities. In new buildings and facilities, the turning space shall be a circular space with a 67-inch minimum diameter. (see code for information regarding allowed overlapping) 304.3.1.2 Existing buildings and facilities. In existing buildings and facilities, the turning space shall be a circular space with a 60-inch minimum diameter. (see code for information regarding allowed overlapping) Action required: Provide enough room in ADA Shower for a turning space.
IPC 604.8 Water pressure reducing valve
Corrective Action Required
11/15/2024

2018 IPC 604.8 Water Pressure reducing valve or regulator. Where water pressure within a building exceeds 80 psi static, an approved water-pressure reducing valve conforming to ASSE 1003 or CSA B356 with strainer shall be installed to reduce the pressure in the building water distribution piping to not greater than 80 psi static. Action required: Provide pressure reducing valve at water entry. (Our Water Department requires PRV installation in all locations regardless of pressure)
Planning - Screening of ground mounted equipment
Corrective Action Required
11/18/2024

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. (re: CU-V1 at vehicle building on sheet M-103)
IMC 606.2.1 Duct detector
Corrective Action Required
11/18/2024

2018 IMC 606.2.1 Return air systems. Smoke detectors shall be installed in return air systems with a design capacity greater than 2,000 cfm, in the return air duct or plenum upstream of any filters, exhaust air connections, outdoor air connections, or decontamination equipment and appliances. Exception: Smoke detectors are not required in the return air system where all portions of the building served by the air distribution system are protected by area smoke detectors connected to a fire alarm system in accordance with the International Fire Code. The area smoke detection system shall comply with Section 606.4. Action required: Provide duct mounted smoke detector in return air duct at DOAS-1 and CRAC-1, 2, & 3. (see schedules on M-601 & M-602)
NEC Article 210.63 Heating, air-conditioning and refrigeration outlet
Corrective Action Required
11/18/2024

2017 NEC Article 210.63 Heating, Air-Conditioning, and Refrigeration Equipment Outlet. A 125-volt, single-phase, 15- or 20-ampere-rated receptacle outlet shall be installed at an accessible location for the servicing of heating, air-conditioning, and refrigeration equipment. The receptacle shall be located on the same level and within 25 feet of the heating, air-conditioning, and refrigeration equipment. The receptacle outlet shall not be connected to the load side of the equipment disconnecting means. Action required: Provide additional receptacle or relocate receptacle shown in Utility Yard. (all equipment must have receptacle within 25')
IBC 1008.3 Emergency power for illumination - at exit discharge
Corrective Action Required
11/18/2024

2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply. 1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Aisles. 2. Corridors. 3. Exit access stairways and ramps. 1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Interior exit access stairways and ramps. 2. Interior and exterior exit stairways and ramps. 3. Exit passageways. 4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1. 5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge. 1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas: 1. Electrical equipment rooms. 2. Fire command centers. 3. Fire pump rooms. 4. Generator rooms. 5. Public restrooms with an area greater than 300 square feet. Action required: Provide emergency lighting at exterior landing of all exits.
Licensed Contractors Rejected 11/18/2024 11/15/2024
Joe Frogge
LC - General Contractor
Corrective Action Required
11/15/2024

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Provide the name, email address & phone number for the on-site contact.
LC - MEP Subs
Corrective Action Required
11/15/2024

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Commercial $101,216.00 $101,216.00 Paid 02/19/2025
Commercial Excise Tax Fee $61,561.50 $61,561.50 Paid 11/05/2024
$61,561.50
Sanitary Sewer Insp Fees $270.00 $270.00 Paid 01/13/2025
Paved Surface Inspection Fee $23,008.80 $23,008.80 Paid 01/13/2025
Water Insp Fee $1,479.00 $1,479.00 Paid 01/13/2025
Site Grading Fee $14,115.54 $14,115.54 Paid 01/13/2025
Storm Sewer Inspection Fee $4,279.50 $4,279.50 Paid 01/13/2025
Water Tap Fee $37,080.00 $37,080.00 Paid 01/13/2025
Water Meter Fee $4,946.72 $4,946.72 Paid 01/13/2025
Sanitary Sewer Development Fee $21,342.00 $21,342.00 Paid 01/13/2025
Water Test Fee $200.00 $200.00 Paid 01/13/2025
Outstanding Fees Amount Paid Owing Date Paid
After Hours Inspections (Public Works)(Per Hour) $450.00 $0.00 $450.00 Not Paid


$450.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Rated Assembly Inspection Pending
Grading/Excavation/Fill Inspection Pending
Sanitary Sewer - Air Test Pending
Sanitary Sewer - Mandrel Pending
Sanitary Sewer - Vacuum Pending
Pavement-Proof Roll Pending
Install Street and Stop Signs Pending
Site Visit Pending
Misc
Informational
02/27/2025
02/07/25 Friday JMJ Grading of project site earlier in the week, No related work for approximate 3 days of this week. 02/27/25 Thursday JMJ Met with contractor onsite to exchange contact info and discuss the progress of project. Grading of site will continue.
Sprinkler - Hydrostatic Test Pending
Sprinkler - Flow Test Pending
Pavement-Stabilized Subgrade Pending
Misc
Informational
05/23/2025
05/23/25 Friday JMJ (Hanrahan Asphalt Paving Co. Inc.) Contractor paved KCMMB A3 for parking stalls approximately 132tons.
Sprinkler - Hydrostatic Test Pending
Alarm Test Pending
Alarm Test Pending
Alarm Test Pending
Alarm Test Pending
Alarm Test Pending
Alarm Test Pending
Alarm Test Pending
Miscellaneous Inspection Pending
Suspended Slab Inspection Pending
Underslab Electrical Inspection - Commercial Pending
Misc
Corrective Action Required
07/30/2025
-From West line 4 to north electrical room -From electrical room to line 10 for future -From line 4 to line 10 complete -Conduit at SE mech room -Conduit from S and E exterior to electrical room -Lower slab between line 1-4 ok -Mechanical yard conduit for generators -Ground loop at mechanical yard for generators
Storm Sewer Construction Inspection Pending
Misc
Informational
08/15/2025
07/30/25 Wednesday JMJ (Rodriguez / Wendell) 60' of 18" HPDE storm pipe between structure 101 to 102. 08/04/25 Monday (Rodriguez / Wendell) Set curb inlet 103 and laid 27 feet of 18inch storm pipe. 08/13/25 Wednesday (Rodriguez / Wendell) Contractor installed 100' of 15" storm pipe between curb inlet 103 and nyloplast 104. 08/15/25 Friday (Rodriguez / Wendell) Thursday contractor installed 44' of 15" storm and nyloplast. Today contractor installed approximately 40 of storm structure 104.'
Sanitary Sewer Construction Inspection Pending
Misc
Informational
08/21/2025
08/07/25 Thursday JMJ (Rodriguez - Wendell) Contractor installed tie-in into the existing sanitary main with 8"X6" wye, and approximately 60' of 6" SDR-26. 08/08/25 Friday JMJ (Rodriguez - Wendell) Contractor continues to install 6" sanitary as-per project plans. Sidenote: Contractor has been having issues with getting the gravel bedding materials to install sanitary pipe. Contractor may install pipping and backfill and come back re-excavate and install required gravel/bedding amounts. Contractor were able to secure the bedding required and installed 100' of 6" sanitary and 2 clean-outs connected to the building. 08/19/25 Tuesday JMJ (Rodriguez - Wendell) Contractor install sanitary from police department and newly constructed building. Constructed 56' of 8" & 46' of 6" 1-8"X6" reducer, 1-6"X4" reducer, and 1-6" inch 90 degree bend. 08/20/25 Wednesday JMJ (Rodriguez - Wendell) Contractor installed 100' of 10" roof drain 1-10"X10" tee, 2-10"X6" reducers, and 2-6" 90. 08/21/25 Thursday JMJ (Rodriguez - Wendell) Contractor install 30' of 6" roof drain for the newly constructed building.
Water Line - Coliform Test 1 Pending
Water Line - Hydrostatic Test Pending
Underground Plumbing Inspection - Commercial Pending
Misc
Informational
09/12/2025
Gas line for grill, from serice to mid-building East side.
Erosion Control Inspection Pending
Miscellaneous Correction
Informational
09/24/2025
02/26/25 JMJ Erosion Control has been in place and functioning properly since the beginning of project. 03/12/25 Wednesday JMJ Erosion Control appears to be functional. 06/04/25 Wednesday JMJ Erosion Control appears to be functional. 07/17/25 Friday JMJ Erosion Control appears need repair to the silt fence around the project, weeds need to cleared around silt fencing, and silt needs to be sweep - up . 09/24/25 Wednesday clean up required due to constant rains yesterday.
Miscellaneous Inspection Pending
Curb - Proof Roll Pending
Misc
Informational
09/26/2025
9-22-25 PS Contractor performed proof roll on east lot for curb construction. There are areas along east side of lot that did not pass. Contractor correcting and will schedule another proof roll for Wed 9/24 9-26-25 PS Reinspect of proof roll in areas of parking lot inspected of 9-22 for curbs due to weather and corrections made. Areas passed proof roll on verified load
Miscellaneous Inspection Pending
Retaining Wall Inspection Pending
Misc
Informational
10/02/2025
09/30/25 Tuesday JMJ (Gen. Titians, BC Hardscape) Wall construction will be 6' plus in height when complete. This construction will need to be approved by the design engineer or third party. Contractor began working on the wall yesterday. Foundation appear to be sound, (Batter) wall construction visual is present, foundation brick levels appear to be sturdy. 10/02/25 Thursday JMJ (Gen. Titians, BC Hardscape) Contractor to construct the retaining wall.
Piers/Caissons Inspection - Commercial Pending
Misc
Informational
10/14/2025
-Piers for (2) light pole bases at NE lot -piers for (4) light pole bases at NE lot E central and south side -Piers for (2) light poles at North existing lot -(5) light pole bases at west drive - (2) light pole bases south of retention basin
Pavement-Aggregate Base Pending
Misc
Informational
10/20/2025
10/20/25 Monday JMJ ( Gen. Titan, Sub. Hanrahan Asphalt, Third party testing UES)
Pavement-Curb Construction Pending
Misc
Informational
10/20/2025
9/29/25 Monday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor poured curb on the Eastside of New constructed building. Third party UES was onsite to preformed required testing of concrete. 9/30/25 Tuesday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor continued the installation of curbs on the Eastside of newly constructed building approximately 18yds were poured yesterday and 18yds today. Contractor used white cure on curbs. 10/01/25 Thursday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor continued to pour curb on the Westside of entrance/exit that is between the new building & new addition to Police Department. Contractor plans to continue to pour approximately 18yds of curbs. 10/17/25 Friday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor began to pour forms on the Westside of building approximately 12 yards. 10/20/25 Monday JMJ (Gen. Titan, Sub George J. Shaw Constrution, Third party UES) Contractor continued to pour curbs on the Westside of building.
Pavement-Surface Pending
Misc
Informational
10/21/2025
05/23/25 Friday JMJ (Hanrahan Asphalt Paving Co. Inc.) Contractor installed approximately 425tons of KCMMB A2 for parking lot.
Misc
Informational
10/21/2025
10/16/25 Thursday JMJ ( Gen. Titans Construction, George Shaw.) Contractor plans to pour approximately 16 yards of KCMMB. Concrete will be poured around light pole base in the existing parking lot area. 10/17/25 Friday JMJ (Gen. Titan, Sub. George Shaw Const.) Contractor poured 10yards of of KCMMB concrete continuing around light pole bases in the existing parking lot. 10/21/25 Tuesday JMJ ( Gen. Titan, Sub. George Shaw Const.) Contractor laid the first layer of the KCMMB A2 Pavement-Surface on the Eastside of the new constructed building.
Detention Basin Pending
Misc
Informational
10/28/2025
10/28/25 Tuesday JMJ ( Gen. Titan, Sub, Rodriguez) Contractor began excavating the basin and the skimmer.
Underground Electrical Inspection - Commercial Pending
Misc
Informational
11/03/2025
-Ufer located at NW corner of electrical room -(4) 3” conduit from transformer to building -4" conduit from south of building to east side for data **Light poles -(3) light poles at SE lot -(5) at west side -From light pole at SE to ESO in island and to gas pump and to building
Foundation Inspection - Commercial Pending 11/4/2025
Misc
Corrective Action Required
04/10/2025
-Exterior wall from C5 to C9; C/9 to C/10 to F/10; wall on line D -Elevator pit walls
Electrical Service Inspection Pending 11/5/2025 11/5/2025
Above Ceiling Inspection Pending 11/5/2025 11/5/2025
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
11/03/2025
Soffits in 04, 05 Hard lids at 012-013, 136, 137, 149
In-wall Inspection Pending 11/5/2025 11/5/2025
Misc
Informational
11/03/2025
**The following areas approved: 2nd floor from line 1-3 complete -019, 020, 021, 012, 013, 015, 016 OK to cover -103 exterior wall ok /West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok -Clear story eyebrow framing at North, south and west complete **Exterior wall and eyebrow framing ok to cover -1st floor south side complete 022, 025, 027-034, 036-038, 045, 110-116, 121, 124-128, -2nd floor exterior wall framing complete except at room 120 ***OK TO 1 SIDE ONLY AS NEEDED -RP
Site Visit Partial 2/7/2025 2/7/2025 02/07/2025
Misc
Informational
02/07/2025
02/07/25 Friday JMJ Grading of project site earlier in the week, No related work for approximate 3 days of this week.
Erosion Control Inspection Residential Partial 02/26/2025
Miscellaneous Correction
Informational
02/26/2025
02/26/25 JMJ Erosion Control has been in place and functioning properly since the beginning of project.
Site Visit Partial 2/27/2025 2/27/2025 02/27/2025
Misc
Informational
02/07/2025
02/07/25 Friday JMJ Grading of project site earlier in the week, No related work for approximate 3 days of this week. 02/27/25 Thursday JMJ Met with contractor onsite to exchange contact info and discuss the progress of project. Grading of site will continue.
Footing Inspection - Commercial Failed 3/11/2025 3/11/2025 03/11/2025
Misc
Informational
03/11/2025
Footing not ready yet for inspection. Superintendent just wanted a friendly chitchat since he never had a pre-con meeting
Erosion Control Inspection Residential Partial 03/12/2025
Miscellaneous Correction
Informational
02/26/2025
02/26/25 JMJ Erosion Control has been in place and functioning properly since the beginning of project. 03/12/25 Wednesday JMJ Erosion Control appears to be functional.
Footing Inspection - Commercial Partial 3/14/2025 3/14/2025 03/14/2025
Misc
Informational
03/11/2025
THE FOLLOWING AREAS ARE APPROVED
Informational
03/14/2025
South mechanical yard to 1A Line M1 to H1
Underground Electrical Inspection - Commercial Partial 3/18/2025 3/18/2025 03/18/2025
Misc
Informational
03/18/2025
Ufer located at NW corner of electrical room
Footing Inspection - Commercial Partial 3/18/2025 3/18/2025 03/18/2025
Misc
Informational
03/14/2025
THE FOLLOWING AREAS ARE APPROVED
Informational
03/14/2025
South mechanical yard complete Line 1 complete Line A complete Line 4 from A to C
Footing Inspection - Commercial Partial 3/20/2025 3/20/2025 03/20/2025
Misc
Informational
03/18/2025
THE FOLLOWING AREAS ARE APPROVED
Informational
03/18/2025
South mechanical yard complete Line 1 complete Line A complete Line 4 complete Line M complete
Footing Inspection - Commercial Partial 3/21/2025 3/21/2025 03/21/2025
Misc
Informational
03/20/2025
THE FOLLOWING AREAS ARE APPROVED
Informational
03/20/2025
South mechanical yard complete Line 1 complete Line 5 from B to C Line A complete Line B complete Line 4 complete Line M complete Line C from 5 to 9
Footing Inspection - Commercial Partial 3/24/2025 3/24/2025 03/24/2025
Misc
Informational
03/21/2025
THE FOLLOWING AREAS ARE APPROVED
Informational
03/21/2025
South mechanical yard complete Line 1 complete Line 5 from B to C Line A complete Line B complete Line 4 complete Line M complete Line C from 5 to 9 Line K complete Line L complete East entry stoop complete
Footing Inspection - Commercial Partial 3/28/2025 3/28/2025 03/28/2025
Misc
Informational
03/24/2025
THE FOLLOWING AREAS ARE APPROVED
Informational
03/24/2025
South mechanical yard complete Line 1 complete Line 5 complete Line A complete Line B complete Line 4 complete Line M complete Line C complete Line K complete Line L complete Line 10 from F to C Interior pads complete except at 9/F and 9/H East entry stoop complete Elevator pit mat complete
Foundation Inspection - Commercial Partial 3/31/2025 3/31/2025 03/31/2025
Misc
Corrective Action Required
03/31/2025
Exterior wall from C5 to C9
Footing Inspection - Commercial Partial 04/01/2025
Misc
Informational
03/28/2025
THE FOLLOWING AREAS ARE APPROVED
Informational
03/28/2025
Perimeter footings complete Interior pads complete Transformer pad East entry stoop complete Elevator pit mat complete
Foundation Inspection - Commercial Partial 4/2/2025 4/2/2025 04/02/2025
Misc
Corrective Action Required
03/31/2025
Exterior wall from C5 to C9
Foundation Inspection - Commercial Partial 4/3/2025 4/3/2025 04/03/2025
Misc
Corrective Action Required
04/02/2025
Exterior wall from C5 to C9 -Elevator pit walls
Underslab Plumbing Inspection - Commercial Partial 4/10/2025 4/10/2025 04/10/2025
Misc
Corrective Action Required
04/10/2025
Partial underslab plumbing: 6" building drain from approx. line 6 to exterior sewer; 2 showers and laundry
Foundation Inspection - Commercial Partial 4/10/2025 04/10/2025
Misc
Corrective Action Required
04/03/2025
-Exterior wall from C5 to C9; C/9 to C/10 to F/10; wall on line D -Elevator pit walls
Underslab Plumbing Inspection - Commercial Partial 4/15/2025 4/15/2025 04/15/2025
Misc
Corrective Action Required
04/10/2025
DWV from line 4 north complete
Underslab Plumbing Inspection - Commercial Partial 4/17/2025 4/17/2025 04/17/2025
Misc
Corrective Action Required
04/15/2025
DWV from line 4 north complete -Storm lines at west side from line 4 north to line 10
Underslab Electrical Inspection - Commercial Partial 4/22/2025 4/22/2025 04/17/2025
Misc
Corrective Action Required
04/17/2025
From West line 4 to north electrical room
Underslab Electrical Inspection - Commercial Partial 4/18/2025 4/18/2025 04/18/2025
Misc
Corrective Action Required
04/17/2025
-From West line 4 to north electrical room -From electrical room to line 10 for future
Underslab Plumbing Inspection - Commercial Partial 04/18/2025
Misc
Corrective Action Required
04/17/2025
DWV from line 4 north complete -Storm lines from 4 north to line 10
Footing Inspection - Commercial Failed 4/21/2025 4/21/2025 04/21/2025
Misc
Informational
04/01/2025
4/21-Footing not ready for inspection.
THE FOLLOWING AREAS ARE APPROVED
Informational
04/01/2025
Perimeter footings complete Interior pads complete Transformer pad East entry stoop complete Elevator pit mat complete
Footing Inspection - Commercial Partial 4/22/2025 4/22/2025 04/22/2025
Misc
Informational
04/21/2025
4/21-Footing not ready for inspection.
THE FOLLOWING AREAS ARE APPROVED
Informational
04/21/2025
Perimeter footings complete Interior pads complete Transformer pad East entry stoop complete Elevator pit mat complete
Underslab Electrical Inspection - Commercial Partial 4/23/2025 4/23/2025 04/23/2025
Misc
Corrective Action Required
04/18/2025
-From West line 4 to north electrical room -From electrical room to line 10 for future -From line 4 to line 10 complete
Footing Inspection - Commercial Partial 4/24/2025 4/24/2025 04/24/2025
Misc
Informational
04/22/2025
4/21-Footing not ready for inspection.
THE FOLLOWING AREAS ARE APPROVED
Informational
04/22/2025
Perimeter footings complete Interior pads complete Transformer pad East entry stoop complete Elevator pit mat complete
Underslab Electrical Inspection - Commercial Partial 5/13/2025 5/13/2025 05/13/2025
Misc
Corrective Action Required
04/23/2025
-From West line 4 to north electrical room -From electrical room to line 10 for future -From line 4 to line 10 complete -Conduit at SE mech room
Pavement-Stabilized Subgrade Partial 5/23/2025 5/23/2025 05/23/2025
Misc
Informational
05/23/2025
05/23/25 Friday JMJ (Hanrahan Asphalt Paving Co. Inc.) Contractor paved KCMMB A3 for parking stalls approximately 132tons.
Pavement-Surface Partial 5/23/2025 5/23/2025 05/23/2025
Misc
Informational
05/23/2025
05/23/25 Friday JMJ (Hanrahan Asphalt Paving Co. Inc.) Contractor installed approximately on 05/22/25 Thursday 425tons of KCMMB A2 for parking lot. Contractor will install approximately 450tons of KCMMB A@ today 05/23/25 Friday.
Erosion Control Inspection Partial 06/04/2025
Miscellaneous Correction
Informational
03/12/2025
02/26/25 JMJ Erosion Control has been in place and functioning properly since the beginning of project. 03/12/25 Wednesday JMJ Erosion Control appears to be functional. 06/04/25 Wednesday JMJ Erosion Control appears to be functional.
Water Line - Construction Inspection Partial 6/9/2025 6/9/2025 06/09/2025
Misc
Informational
06/09/2025
06/09/25 Monday JMJ Contractor is working to install fire line.
Water Line - Construction Inspection Partial 6/9/2025 6/9/2025 06/09/2025
Misc
Informational
06/09/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today.
Water Line - Construction Inspection Partial 6/10/2025 6/10/2025 06/10/2025
Misc
Informational
06/09/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in.
Water Line - Construction Inspection Partial 06/10/2025
Misc
Informational
06/10/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today.
Underslab Plumbing Inspection - Commercial Partial 6/17/2025 6/17/2025 06/17/2025
Misc
Corrective Action Required
04/18/2025
DWV from line 4 north complete -Storm lines complete
Underslab Plumbing Inspection - Commercial Passed 6/18/2025 06/18/2025
Misc
Resolved
06/18/2025
DWV from line 4 north complete -Storm lines complete
Suspended Slab Inspection Partial 6/23/2025 6/23/2025 06/23/2025
Misc
Corrective Action Required
06/23/2025
From line 1 to 3/4 approved
In-wall Inspection Partial 06/23/2025
Misc
Corrective Action Required
06/23/2025
West side roof facade to line 4 ok South side roof facade ok
All Rough Inspection - Commercial Passed 6/23/2025 6/23/2025 06/23/2025
Misc
Informational
06/23/2025
Inspections completed as In Wall
Storm Sewer Construction Inspection Partial 6/23/2025 6/23/2025 06/23/2025
Misc
Informational
06/23/2025
06/23/25 Monday JMJ ( Gen-Titans, Sub-Rodriguez) Contractor has successfully installed storm box 300 contractor continues to work of the storm line.
Underslab Electrical Inspection - Commercial Partial 6/24/2025 06/24/2025
Misc
Corrective Action Required
05/13/2025
-From West line 4 to north electrical room -From electrical room to line 10 for future -From line 4 to line 10 complete -Conduit at SE mech room -Conduit from S and E exterior to electrical room
Water Line - Construction Inspection Partial 06/24/2025
Misc
Informational
06/10/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street.
Storm Sewer Construction Inspection Partial 6/25/2025 6/25/2025 06/25/2025
Misc
Informational
06/23/2025
06/23/25 Monday JMJ ( Gen-Titans, Sub-Rodriguez) Contractor has successfully installed storm box 300 contractor continues to work of the storm line. 06/25/25 Wednesday JMJ Gen (Gen-Titans, Sub-Rodriguez) 65 feet of 36" storm 36" flared end section, pored toe wall and collars on storm 300.
Water Line - Construction Inspection Partial 6/25/2025 6/25/2025 06/25/2025
Misc
Informational
06/24/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street. 06/25/25 Wednesday JMJ (Titans, Rodriguez Const.) Contractor completed the bore pit and began pushing double walled (certa-lock) 6" water main.
Water Line - Construction Inspection Partial 6/26/2025 6/26/2025 06/26/2025
Misc
Informational
06/25/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/12/25 Thursday JMJ ( Gen. Titan, & sub. Rodriguez Mechanical Construction) Contractor excavated and place backflow vault. Contractor ran into heavy rock and was not able to lay pipe today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street. 06/25/25 Wednesday JMJ (Titans, Rodriguez Const.) Contractor completed the bore pit and began pushing double walled (certa-lock) 6" water main. 06/26/25 Thursday JMJ (Titans, Rodriguez Const.) Contractor was able to install 2/45 bends that angle toward the backflow vault and the 6" water line. The backflow components were installed and 6" fire line was continued.
Water Line - Construction Inspection Partial 6/27/2025 6/27/2025 06/27/2025
Misc
Informational
06/26/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/12/25 Thursday JMJ ( Gen. Titan, & sub. Rodriguez Mechanical Construction) Contractor excavated and place backflow vault. Contractor ran into heavy rock and was not able to lay pipe today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street. 06/25/25 Wednesday JMJ (Titans, Rodriguez Const.) Contractor completed the bore pit and began pushing double walled (certa-lock) 6" water main. 06/26/25 Thursday JMJ (Titans, Rodriguez Const.) Contractor was able to install 2/45 bends that angle toward the backflow vault and the 6" water line. The backflow components were installed and 6" fire line was continued. 06/27/25 Friday JMJ (Titans, Rodriguez Const.) Contractor installed water meter on the domestic water as per project plans.
Storm Sewer Construction Inspection Partial 6/27/2025 6/27/2025 06/27/2025
Misc
Informational
06/25/2025
06/23/25 Monday JMJ ( Gen-Titans, Sub-Rodriguez) Contractor has successfully installed storm box 300 contractor continues to work of the storm line. 06/25/25 Wednesday JMJ (Gen-Titans, Sub-Rodriguez) 65 feet of 36" storm 36" flared end section, pored toe wall and collars on storm 300. 06/27/25 Friday JMJ (+Gen-Titans, Sub-Rodriguez) Contractor tie-in the existing what storm box 300 approximately 60' of 30" HDPE storm line 300.
Suspended Slab Inspection Passed 06/30/2025
Misc
Resolved
06/30/2025
From line 1 to 3/4 approved
Storm Sewer Construction Inspection Partial 6/30/2025 6/30/2025 07/01/2025
Misc
Informational
06/27/2025
06/23/25 Monday JMJ ( Gen-Titans, Sub-Rodriguez) Contractor has successfully installed storm box 300 contractor continues to work of the storm line. 06/25/25 Wednesday JMJ (Gen-Titans, Sub-Rodriguez) 65 feet of 36" storm 36" flared end section, pored toe wall and collars on storm 300. 06/27/25 Friday JMJ (Gen-Titans, Sub-Rodriguez) Contractor tie-in the existing what storm box 300 approximately 60' of 30" HDPE storm line 300. 06/30/25 Monday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 40' of 15" HDPE storm line 202 and collars on storm structure.
Water Line - Construction Inspection Partial 6/30/2025 6/30/2025 07/01/2025
Misc
Informational
06/27/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/12/25 Thursday JMJ ( Gen. Titan, & sub. Rodriguez Mechanical Construction) Contractor excavated and place backflow vault. Contractor ran into heavy rock and was not able to lay pipe today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street. 06/25/25 Wednesday JMJ (Titans, Rodriguez Const.) Contractor completed the bore pit and began pushing double walled (certa-lock) 6" water main. 06/26/25 Thursday JMJ (Titans, Rodriguez Const.) Contractor was able to install 2/45 bends that angle toward the backflow vault and the 6" water line. The backflow components were installed and 6" fire line was continued. 06/27/25 Friday JMJ (Titans, Rodriguez Const.) Contractor installed water meter on the domestic water as per project plans. 06/30/25 Monday JMJ (Titans, Rodriguez Const.) Contractor poured kickers behind 45 deg bends , tee for fire line and straddle block.
Storm Sewer Construction Inspection Partial 7/1/2025 7/1/2025 07/01/2025
Misc
Informational
07/01/2025
06/23/25 Monday JMJ ( Gen-Titans, Sub-Rodriguez) Contractor has successfully installed storm box 300 contractor continues to work of the storm line. 06/25/25 Wednesday JMJ (Gen-Titans, Sub-Rodriguez) 65 feet of 36" storm 36" flared end section, pored toe wall and collars on storm 300. 06/27/25 Friday JMJ (Gen-Titans, Sub-Rodriguez) Contractor tie-in the existing what storm box 300 approximately 60' of 30" HDPE storm line 300. 06/30/25 Monday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 40' of 15" HDPE storm structure 202 and collars on storm structure. 07/01/25 Tuesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm structure 203 and continues the installation of storm line 200.
Underslab Electrical Inspection - Commercial Partial 7/2/2025 7/2/2025 07/02/2025
Misc
Corrective Action Required
06/24/2025
-From West line 4 to north electrical room -From electrical room to line 10 for future -From line 4 to line 10 complete -Conduit at SE mech room -Conduit from S and E exterior to electrical room -Lower slab between line 1-4 ok
Storm Sewer Construction Inspection Partial 7/2/2025 7/2/2025 07/02/2025
Misc
Informational
07/01/2025
06/23/25 Monday JMJ ( Gen-Titans, Sub-Rodriguez) Contractor has successfully installed storm box 300 contractor continues to work of the storm line. 06/25/25 Wednesday JMJ (Gen-Titans, Sub-Rodriguez) 65 feet of 36" storm 36" flared end section, pored toe wall and collars on storm 300. 06/27/25 Friday JMJ (Gen-Titans, Sub-Rodriguez) Contractor tie-in the existing what storm box 300 approximately 60' of 30" HDPE storm line 300. 06/30/25 Monday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 40' of 15" HDPE storm structure 202 and collars on storm structure. 07/01/25 Tuesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm structure 203 and continues the installation of storm line 200. 07/02/25 Wednesday JMJ ( Gen. Titans, Sub. Rodriguez) Contractor installed approximately 100' of 15" HDPE storm line 200 and poured collar & invert for box 203.
Water Line - Construction Inspection Partial 7/7/2025 7/7/2025 07/07/2025
Misc
Informational
07/01/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/12/25 Thursday JMJ ( Gen. Titan, & sub. Rodriguez Mechanical Construction) Contractor excavated and place backflow vault. Contractor ran into heavy rock and was not able to lay pipe today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street. 06/25/25 Wednesday JMJ (Titans, Rodriguez Const.) Contractor completed the bore pit and began pushing double walled (certa-lock) 6" water main. 06/26/25 Thursday JMJ (Titans, Rodriguez Const.) Contractor was able to install 2/45 bends that angle toward the backflow vault and the 6" water line. The backflow components were installed and 6" fire line was continued. 06/27/25 Friday JMJ (Titans, Rodriguez Const.) Contractor installed water meter on the domestic water as per project plans. 06/30/25 Monday JMJ (Titans, Rodriguez Const.) Contractor poured kickers behind 45 deg bends , tee for fire line and straddle block. 07/07/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installing irrigation water line.
Storm Sewer Construction Inspection Partial 7/9/2025 7/9/2025 07/09/2025
Misc
Informational
07/02/2025
06/23/25 Monday JMJ ( Gen-Titans, Sub-Rodriguez) Contractor has successfully installed storm box 300 contractor continues to work of the storm line. 06/25/25 Wednesday JMJ (Gen-Titans, Sub-Rodriguez) 65 feet of 36" storm 36" flared end section, pored toe wall and collars on storm 300. 06/27/25 Friday JMJ (Gen-Titans, Sub-Rodriguez) Contractor tie-in the existing what storm box 300 approximately 60' of 30" HDPE storm line 300. 06/30/25 Monday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 40' of 15" HDPE storm structure 202 and collars on storm structure. 07/01/25 Tuesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm structure 203 and continues the installation of storm line 200. 07/02/25 Wednesday JMJ ( Gen. Titans, Sub. Rodriguez) Contractor installed approximately 100' of 15" HDPE storm line 200 and poured collar & invert for box 203. 07/09/25 Wednesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm box 204, 10' of 15"HDPE storm line, concrete was poured for collar & invert.
In-wall Inspection Partial 7/11/2025 7/11/2025 07/11/2025
Misc
Corrective Action Required
06/23/2025
West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok
Water Line - Construction Inspection Partial 7/11/2025 7/11/2025 07/15/2025
Misc
Informational
07/07/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/12/25 Thursday JMJ ( Gen. Titan, & sub. Rodriguez Mechanical Construction) Contractor excavated and place backflow vault. Contractor ran into heavy rock and was not able to lay pipe today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street. 06/25/25 Wednesday JMJ (Titans, Rodriguez Const.) Contractor completed the bore pit and began pushing double walled (certa-lock) 6" water main. 06/26/25 Thursday JMJ (Titans, Rodriguez Const.) Contractor was able to install 2/45 bends that angle toward the backflow vault and the 6" water line. The backflow components were installed and 6" fire line was continued. 06/27/25 Friday JMJ (Titans, Rodriguez Const.) Contractor installed water meter on the domestic water as per project plans. 06/30/25 Monday JMJ (Titans, Rodriguez Const.) Contractor poured kickers behind 45 deg bends , tee for fire line and straddle block. 07/07/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installing irrigation water line. 07/11/25 Friday JMJ (Titans, Rodriguez Const.) Contractor tie-in 12"X6" Tee with 6" gate valve. Contractor will install 90 degree bends with all threads at the top and bottom 90's. Contractor will form a cage to pour the top backing. Shoring was installed to turn on water after the tie-in was completed. 07/14/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installed the 2/90 deg with all-threads to help with the restrain. I will forward pic to Water Supervisor and Inspection Field Manager. Thrust blocks were poured behind bends all excavation was backfilled.
Erosion Control Inspection Partial 7/18/2025 7/18/2025 07/18/2025
Miscellaneous Correction
Informational
06/04/2025
02/26/25 JMJ Erosion Control has been in place and functioning properly since the beginning of project. 03/12/25 Wednesday JMJ Erosion Control appears to be functional. 06/04/25 Wednesday JMJ Erosion Control appears to be functional. 07/17/25 Friday JMJ Erosion Control appears need repair to the silt fence around the project, weeds need to cleared around silt fencing, and silt needs to be sweep - up .
Underslab Electrical Inspection - Commercial Partial 7/21/2025 7/21/2025 07/21/2025
Misc
Corrective Action Required
07/02/2025
-From West line 4 to north electrical room -From electrical room to line 10 for future -From line 4 to line 10 complete -Conduit at SE mech room -Conduit from S and E exterior to electrical room -Lower slab between line 1-4 ok -Mechanical yard conduit for generators
Storm Sewer Construction Inspection Partial 7/25/2025 7/25/2025 07/28/2025
Misc
Informational
07/09/2025
06/23/25 Monday JMJ ( Gen-Titans, Sub-Rodriguez) Contractor has successfully installed storm box 300 contractor continues to work of the storm line. 06/25/25 Wednesday JMJ (Gen-Titans, Sub-Rodriguez) 65 feet of 36" storm 36" flared end section, pored toe wall and collars on storm 300. 06/27/25 Friday JMJ (Gen-Titans, Sub-Rodriguez) Contractor tie-in the existing what storm box 300 approximately 60' of 30" HDPE storm line 300. 06/30/25 Monday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 40' of 15" HDPE storm structure 202 and collars on storm structure. 07/01/25 Tuesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm structure 203 and continues the installation of storm line 200. 07/02/25 Wednesday JMJ ( Gen. Titans, Sub. Rodriguez) Contractor installed approximately 100' of 15" HDPE storm line 200 and poured collar & invert for box 203. 07/09/25 Wednesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm box 204, 10' of 15"HDPE storm line, concrete was poured for collar & invert. 07/25/25 Friday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 160' of 8" roof drain and a clean-out.
Storm Sewer Construction Inspection Partial 7/23/2025 7/23/2025 07/28/2025
Misc
Informational
07/28/2025
06/23/25 Monday JMJ ( Gen-Titans, Sub-Rodriguez) Contractor has successfully installed storm box 300 contractor continues to work of the storm line. 06/25/25 Wednesday JMJ (Gen-Titans, Sub-Rodriguez) 65 feet of 36" storm 36" flared end section, pored toe wall and collars on storm 300. 06/27/25 Friday JMJ (Gen-Titans, Sub-Rodriguez) Contractor tie-in the existing what storm box 300 approximately 60' of 30" HDPE storm line 300. 06/30/25 Monday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 40' of 15" HDPE storm structure 202 and collars on storm structure. 07/01/25 Tuesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm structure 203 and continues the installation of storm line 200. 07/02/25 Wednesday JMJ ( Gen. Titans, Sub. Rodriguez) Contractor installed approximately 100' of 15" HDPE storm line 200 and poured collar & invert for box 203. 07/09/25 Wednesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm box 204, 10' of 15"HDPE storm line, concrete was poured for collar & invert. 07/23/25 Wednesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 85' of 8" roof drains 3/8"X8" tees, 1-8"X4" tee one clean-out, and 20' of 4" roof drain. 07/25/25 Friday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 160' of 8" roof drain and a clean-out.
Water Line - Hydrostatic Test Partial 7/28/2025 7/28/2025 07/28/2025
Misc
Informational
07/28/2025
07/28/25 Monday JMJ (CP Excavating Kameron) Contractor passed the two hour hydro static test.
Underslab Electrical Inspection - Commercial Partial 07/30/2025
Misc
Corrective Action Required
07/21/2025
-From West line 4 to north electrical room -From electrical room to line 10 for future -From line 4 to line 10 complete -Conduit at SE mech room -Conduit from S and E exterior to electrical room -Lower slab between line 1-4 ok -Mechanical yard conduit for generators -Ground loop at mechanical yard for generators
Storm Sewer Construction Inspection Partial 07/30/2025
Misc
Informational
07/30/2025
07/30/25 Wednesday JMJ (Rodriguez / Wendell) 60' of 18" HPDE storm pipe between structure 101 to 102.
Storm Sewer Construction Inspection Partial 7/31/2025 7/31/2025 07/31/2025
Misc
Informational
07/28/2025
06/23/25 Monday JMJ ( Gen-Titans, Sub-Rodriguez) Contractor has successfully installed storm box 300 contractor continues to work of the storm line. 06/25/25 Wednesday JMJ (Gen-Titans, Sub-Rodriguez) 65 feet of 36" storm 36" flared end section, pored toe wall and collars on storm 300. 06/27/25 Friday JMJ (Gen-Titans, Sub-Rodriguez) Contractor tie-in the existing what storm box 300 approximately 60' of 30" HDPE storm line 300. 06/30/25 Monday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 40' of 15" HDPE storm structure 202 and collars on storm structure. 07/01/25 Tuesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm structure 203 and continues the installation of storm line 200. 07/02/25 Wednesday JMJ ( Gen. Titans, Sub. Rodriguez) Contractor installed approximately 100' of 15" HDPE storm line 200 and poured collar & invert for box 203. 07/09/25 Wednesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm box 204, 10' of 15"HDPE storm line, concrete was poured for collar & invert. 07/23/25 Wednesday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 85' of 8" roof drains 3/8"X8" tees, 1-8"X4" tee one clean-out, and 20' of 4" roof drain. 07/25/25 Friday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed 160' of 8" roof drain and a clean-out. 07/31/25 Thursday JMJ (Gen. Titans, Sub. Rodriguez) Contractor installed storm pipe 18" HDPE & structure 101 to 102.
Storm Sewer Construction Inspection Partial 08/04/2025
Misc
Informational
07/31/2025
07/30/25 Wednesday JMJ (Rodriguez / Wendell) 60' of 18" HPDE storm pipe between structure 101 to 102. 08/04/25 Monday (Rodriguez / Wendell) Set curb inlet 103 and laid 27 feet of 18inch storm pipe.
Miscellaneous Inspection Passed 8/5/2025 8/5/2025 08/05/2025
Water Line - Construction Inspection Partial 8/5/2025 8/5/2025 08/06/2025
Misc
Informational
07/15/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/12/25 Thursday JMJ ( Gen. Titan, & sub. Rodriguez Mechanical Construction) Contractor excavated and place backflow vault. Contractor ran into heavy rock and was not able to lay pipe today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street. 06/25/25 Wednesday JMJ (Titans, Rodriguez Const.) Contractor completed the bore pit and began pushing double walled (certa-lock) 6" water main. 06/26/25 Thursday JMJ (Titans, Rodriguez Const.) Contractor was able to install 2/45 bends that angle toward the backflow vault and the 6" water line. The backflow components were installed and 6" fire line was continued. 06/27/25 Friday JMJ (Titans, Rodriguez Const.) Contractor installed water meter on the domestic water as per project plans. 06/30/25 Monday JMJ (Titans, Rodriguez Const.) Contractor poured kickers behind 45 deg bends , tee for fire line and straddle block. 07/07/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installing irrigation water line. 07/11/25 Friday JMJ (Titans, Rodriguez Const.) Contractor tie-in 12"X6" Tee with 6" gate valve. Contractor will install 90 degree bends with all threads at the top and bottom 90's. Contractor will form a cage to pour the top backing. Shoring was installed to turn on water after the tie-in was completed. 07/14/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installed the 2/90 deg with all-threads to help with the restrain. I will forward pic to Water Supervisor and Inspection Field Manager. Thrust blocks were poured behind bends all excavation was backfilled. 08/05/25 Tuesday JMJ (Titans, Rodriguez Const. - Wendell) Contractor connected the 6" waterline to the building with 12' of pipe and 2-45 degree bends, and 4" waterline to the building with 14' with 2-45 degree bends All threaded all fittings on both lines.
In-wall Inspection Partial 8/6/2025 08/06/2025
Misc
Corrective Action Required
07/11/2025
West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok **1st floor exterior side only ok to cover
Sanitary Sewer Construction Inspection Partial 8/7/2025 8/7/2025 08/07/2025
Misc
Informational
08/07/2025
08/07/25 Thursday JMJ (Rodriguez - Wendell) Contractor installed tie-in into the existing sanitary main with 8"X6" wye, and approximately 60' of 6" SDR-26.
Sanitary Sewer Construction Inspection Partial 8/8/2025 8/8/2025 08/08/2025
Misc
Informational
08/07/2025
08/07/25 Thursday JMJ (Rodriguez - Wendell) Contractor installed tie-in into the existing sanitary main with 8"X6" wye, and approximately 60' of 6" SDR-26. 08/08/25 Friday JMJ (Rodriguez - Wendell) Contractor continues to install 6" sanitary as-per project plans. Sidenote: Contractor has been having issues with getting the gravel bedding materials to install sanitary pipe. Contractor may install pipping and backfill and come back re-excavate and install required gravel/bedding amounts.
Sanitary Sewer Construction Inspection Partial 8/8/2025 8/8/2025 08/08/2025
Misc
Informational
08/08/2025
08/07/25 Thursday JMJ (Rodriguez - Wendell) Contractor installed tie-in into the existing sanitary main with 8"X6" wye, and approximately 60' of 6" SDR-26. 08/08/25 Friday JMJ (Rodriguez - Wendell) Contractor continues to install 6" sanitary as-per project plans. Sidenote: Contractor has been having issues with getting the gravel bedding materials to install sanitary pipe. Contractor may install pipping and backfill and come back re-excavate and install required gravel/bedding amounts. Contractor were able to secure the bedding required and installed 100' of 6" sanitary and 2 clean-outs connected to the building.
Storm Sewer Construction Inspection Partial 8/13/2025 8/13/2025 08/14/2025
Misc
Informational
08/04/2025
07/30/25 Wednesday JMJ (Rodriguez / Wendell) 60' of 18" HPDE storm pipe between structure 101 to 102. 08/04/25 Monday (Rodriguez / Wendell) Set curb inlet 103 and laid 27 feet of 18inch storm pipe. 08/13/25 Wednesday (Rodriguez / Wendell) Contractor installed 100' of 15" storm pipe between curb inlet 103 and nyloplast 104.
In-wall Inspection Partial 8/14/2025 8/14/2025 08/14/2025
Misc
Corrective Action Required
08/06/2025
West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok **1st floor exterior side only ok to cover Rms 020, 021, 040, 041, 157 Ok to one side for equipment
Storm Sewer Construction Inspection Partial 8/15/2025 8/15/2025 08/15/2025
Misc
Informational
08/14/2025
07/30/25 Wednesday JMJ (Rodriguez / Wendell) 60' of 18" HPDE storm pipe between structure 101 to 102. 08/04/25 Monday (Rodriguez / Wendell) Set curb inlet 103 and laid 27 feet of 18inch storm pipe. 08/13/25 Wednesday (Rodriguez / Wendell) Contractor installed 100' of 15" storm pipe between curb inlet 103 and nyloplast 104. 08/15/25 Friday (Rodriguez / Wendell) Thursday contractor installed 44' of 15" storm and nyloplast. Today contractor installed approximately 40 of storm structure 104.'
Miscellaneous Inspection Failed 8/19/2025 8/19/2025 08/19/2025
In-wall Inspection Partial 10/7/2025 10/7/2025 08/19/2025
Misc
Corrective Action Required
08/14/2025
West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok **Exterior framing ok to cover Rms 020, 021, 040, 041, 157 Ok to one side for equipment
Electrical Service Inspection Failed 8/19/2025 8/19/2025 08/19/2025
Sanitary Sewer Construction Inspection Partial 8/19/2025 8/19/2025 08/20/2025
Misc
Informational
08/08/2025
08/07/25 Thursday JMJ (Rodriguez - Wendell) Contractor installed tie-in into the existing sanitary main with 8"X6" wye, and approximately 60' of 6" SDR-26. 08/08/25 Friday JMJ (Rodriguez - Wendell) Contractor continues to install 6" sanitary as-per project plans. Sidenote: Contractor has been having issues with getting the gravel bedding materials to install sanitary pipe. Contractor may install pipping and backfill and come back re-excavate and install required gravel/bedding amounts. Contractor were able to secure the bedding required and installed 100' of 6" sanitary and 2 clean-outs connected to the building. 08/19/25 Tuesday JMJ (Rodriguez - Wendell) Contractor install sanitary from police department and newly constructed building. Constructed 56' of 8" & 46' of 6" 1-8"X6" reducer, 1-6"X4" reducer, and 1-6" inch 90 degree bend.
Underground Electrical Inspection - Commercial Partial 8/20/2025 8/20/2025 08/20/2025
Misc
Informational
03/18/2025
-Ufer located at NW corner of electrical room -(4) 3” conduit from transformer to building
Sanitary Sewer Construction Inspection Partial 08/21/2025
Misc
Informational
08/20/2025
08/07/25 Thursday JMJ (Rodriguez - Wendell) Contractor installed tie-in into the existing sanitary main with 8"X6" wye, and approximately 60' of 6" SDR-26. 08/08/25 Friday JMJ (Rodriguez - Wendell) Contractor continues to install 6" sanitary as-per project plans. Sidenote: Contractor has been having issues with getting the gravel bedding materials to install sanitary pipe. Contractor may install pipping and backfill and come back re-excavate and install required gravel/bedding amounts. Contractor were able to secure the bedding required and installed 100' of 6" sanitary and 2 clean-outs connected to the building. 08/19/25 Tuesday JMJ (Rodriguez - Wendell) Contractor install sanitary from police department and newly constructed building. Constructed 56' of 8" & 46' of 6" 1-8"X6" reducer, 1-6"X4" reducer, and 1-6" inch 90 degree bend. 08/20/25 Wednesday JMJ (Rodriguez - Wendell) Contractor installed 100' of 10" roof drain 1-10"X10" tee, 2-10"X6" reducers, and 2-6" 90.
Sanitary Sewer Construction Inspection Partial 8/21/2025 8/21/2025 08/21/2025
Misc
Informational
08/21/2025
08/07/25 Thursday JMJ (Rodriguez - Wendell) Contractor installed tie-in into the existing sanitary main with 8"X6" wye, and approximately 60' of 6" SDR-26. 08/08/25 Friday JMJ (Rodriguez - Wendell) Contractor continues to install 6" sanitary as-per project plans. Sidenote: Contractor has been having issues with getting the gravel bedding materials to install sanitary pipe. Contractor may install pipping and backfill and come back re-excavate and install required gravel/bedding amounts. Contractor were able to secure the bedding required and installed 100' of 6" sanitary and 2 clean-outs connected to the building. 08/19/25 Tuesday JMJ (Rodriguez - Wendell) Contractor install sanitary from police department and newly constructed building. Constructed 56' of 8" & 46' of 6" 1-8"X6" reducer, 1-6"X4" reducer, and 1-6" inch 90 degree bend. 08/20/25 Wednesday JMJ (Rodriguez - Wendell) Contractor installed 100' of 10" roof drain 1-10"X10" tee, 2-10"X6" reducers, and 2-6" 90. 08/21/25 Thursday JMJ (Rodriguez - Wendell) Contractor install 30' of 6" roof drain for the newly constructed building.
In-wall Inspection Partial 8/25/2025 8/25/2025 08/25/2025
Misc
Corrective Action Required
08/19/2025
West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok **Exterior framing ok to cover Rms 020, 021, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top
Water Line - Construction Inspection Partial 8/25/2025 8/25/2025 08/26/2025
Misc
Informational
08/06/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/12/25 Thursday JMJ ( Gen. Titan, & sub. Rodriguez Mechanical Construction) Contractor excavated and place backflow vault. Contractor ran into heavy rock and was not able to lay pipe today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street. 06/25/25 Wednesday JMJ (Titans, Rodriguez Const.) Contractor completed the bore pit and began pushing double walled (certa-lock) 6" water main. 06/26/25 Thursday JMJ (Titans, Rodriguez Const.) Contractor was able to install 2/45 bends that angle toward the backflow vault and the 6" water line. The backflow components were installed and 6" fire line was continued. 06/27/25 Friday JMJ (Titans, Rodriguez Const.) Contractor installed water meter on the domestic water as per project plans. 06/30/25 Monday JMJ (Titans, Rodriguez Const.) Contractor poured kickers behind 45 deg bends , tee for fire line and straddle block. 07/07/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installing irrigation water line. 07/11/25 Friday JMJ (Titans, Rodriguez Const.) Contractor tie-in 12"X6" Tee with 6" gate valve. Contractor will install 90 degree bends with all threads at the top and bottom 90's. Contractor will form a cage to pour the top backing. Shoring was installed to turn on water after the tie-in was completed. 07/14/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installed the 2/90 deg with all-threads to help with the restrain. I will forward pic to Water Supervisor and Inspection Field Manager. Thrust blocks were poured behind bends all excavation was backfilled. 08/05/25 Tuesday JMJ (Titans, Rodriguez Const. - Wendell) Contractor connected the 6" waterline to the building with 12' of pipe and 2-45 degree bends, and 4" waterline to the building with 14' with 2-45 degree bends All threaded all fittings on both lines. 08/26/25 Tuesday JMJ (Titans, Rodriguez Const - Wendell) Contractor work on general construction of fire line.
In-wall Inspection Partial 08/27/2025
Misc
Corrective Action Required
08/25/2025
West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok **Exterior wall and eyebrow framing ok to cover -Rms 020, 021, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top
Water Line - Hydrostatic Test Passed 8/27/2025 8/27/2025 08/27/2025
Misc
Informational
07/28/2025
07/28/25 Wednesday JMJ (Rodriguez - Wendell) Contractor passed the two hour hydro static test @ 200psi.
Water Line - Construction Inspection Partial 8/27/2025 8/27/2025 08/27/2025
Misc
Informational
08/26/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/12/25 Thursday JMJ ( Gen. Titan, & sub. Rodriguez Mechanical Construction) Contractor excavated and place backflow vault. Contractor ran into heavy rock and was not able to lay pipe today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street. 06/25/25 Wednesday JMJ (Titans, Rodriguez Const.) Contractor completed the bore pit and began pushing double walled (certa-lock) 6" water main. 06/26/25 Thursday JMJ (Titans, Rodriguez Const.) Contractor was able to install 2/45 bends that angle toward the backflow vault and the 6" water line. The backflow components were installed and 6" fire line was continued. 06/27/25 Friday JMJ (Titans, Rodriguez Const.) Contractor installed water meter on the domestic water as per project plans. 06/30/25 Monday JMJ (Titans, Rodriguez Const.) Contractor poured kickers behind 45 deg bends , tee for fire line and straddle block. 07/07/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installing irrigation water line. 07/11/25 Friday JMJ (Titans, Rodriguez Const.) Contractor tie-in 12"X6" Tee with 6" gate valve. Contractor will install 90 degree bends with all threads at the top and bottom 90's. Contractor will form a cage to pour the top backing. Shoring was installed to turn on water after the tie-in was completed. 07/14/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installed the 2/90 deg with all-threads to help with the restrain. I will forward pic to Water Supervisor and Inspection Field Manager. Thrust blocks were poured behind bends all excavation was backfilled. 08/05/25 Tuesday JMJ (Titans, Rodriguez Const. - Wendell) Contractor connected the 6" waterline to the building with 12' of pipe and 2-45 degree bends, and 4" waterline to the building with 14' with 2-45 degree bends All threaded all fittings on both lines. 08/26/25 Tuesday JMJ (Titans, Rodriguez Const - Wendell) Contractor work on general construction of fire line. 08/27/25 Wednesday JMJ (Titans, Rodriguez Const. - Wendell) Contractor chlorinated fire/water line.
In-wall Inspection Partial 9/2/2025 9/2/2025 09/02/2025
Misc
Informational
09/02/2025
**The following areas approved: -020, 021 OK to cover West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok **Exterior wall and eyebrow framing ok to cover -Rms 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top ***OK TO 1 SIDE ONLY AS NEEDED -RP
Underground Electrical Inspection - Commercial Partial 9/2/2025 09/02/2025
Misc
Informational
08/20/2025
-Ufer located at NW corner of electrical room -(4) 3” conduit from transformer to building -4" conduit from south of building to east side for data
Piers/Caissons Inspection - Commercial Partial 9/4/2025 9/4/2025 09/04/2025
Misc
Informational
09/04/2025
-Piers for (2) light pole bases at NE lot
Water Line - Construction Inspection Passed 9/4/2025 9/4/2025 09/04/2025
Misc
Informational
08/27/2025
06/09/25 Monday JMJ Contractor is working to install domestic & fire line. 100' of 4" & 6" PVC was installed today. 06/10/25 Tuesday JMJ Contractor continues to install parallel domestic and fire line. Contractor has located the 12" water main on the Westside Main St. that the 12"X6" tee for the tie-in. Contractor installed approximately 100' of 4" domestic & 100' 6" fire line today. 06/12/25 Thursday JMJ ( Gen. Titan, & sub. Rodriguez Mechanical Construction) Contractor excavated and place backflow vault. Contractor ran into heavy rock and was not able to lay pipe today. 06/24/25 Tuesday JMJ (Titans, Rodriguez Const.) Contractor work to bore 6" fire hydrant across Main Street. 06/25/25 Wednesday JMJ (Titans, Rodriguez Const.) Contractor completed the bore pit and began pushing double walled (certa-lock) 6" water main. 06/26/25 Thursday JMJ (Titans, Rodriguez Const.) Contractor was able to install 2/45 bends that angle toward the backflow vault and the 6" water line. The backflow components were installed and 6" fire line was continued. 06/27/25 Friday JMJ (Titans, Rodriguez Const.) Contractor installed water meter on the domestic water as per project plans. 06/30/25 Monday JMJ (Titans, Rodriguez Const.) Contractor poured kickers behind 45 deg bends , tee for fire line and straddle block. 07/07/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installing irrigation water line. 07/11/25 Friday JMJ (Titans, Rodriguez Const.) Contractor tie-in 12"X6" Tee with 6" gate valve. Contractor will install 90 degree bends with all threads at the top and bottom 90's. Contractor will form a cage to pour the top backing. Shoring was installed to turn on water after the tie-in was completed. 07/14/25 Monday JMJ (Titans, Rodriguez Const.) Contractor installed the 2/90 deg with all-threads to help with the restrain. I will forward pic to Water Supervisor and Inspection Field Manager. Thrust blocks were poured behind bends all excavation was backfilled. 08/05/25 Tuesday JMJ (Titans, Rodriguez Const. - Wendell) Contractor connected the 6" waterline to the building with 12' of pipe and 2-45 degree bends, and 4" waterline to the building with 14' with 2-45 degree bends All threaded all fittings on both lines. 08/26/25 Tuesday JMJ (Titans, Rodriguez Const - Wendell) Contractor work on general construction of fire line. 08/2725 Wednesday JMJ (Titans, Rodriguez Const. - Wendell) Contractor chlorinated fire/water line. 09/04/25 Thursday JMJ (Titans, Rodriguez Const. - Wendell) Contractor flush the line fire line.
Piers/Caissons Inspection - Commercial Partial 9/5/2025 9/5/2025 09/05/2025
Misc
Informational
09/04/2025
-Piers for (2) light pole bases at NE lot -piers for (4) light pole bases at NE lot E central and south side
Piers/Caissons Inspection - Commercial Partial 9/8/2025 9/8/2025 09/08/2025
Misc
Informational
09/05/2025
-Piers for (2) light pole bases at NE lot -piers for (4) light pole bases at NE lot E central and south side -Piers for (2) light poles at North existing lot
Underground Electrical Inspection - Commercial Partial 9/9/2025 9/9/2025 09/09/2025
Misc
Informational
09/02/2025
-Ufer located at NW corner of electrical room -(4) 3” conduit from transformer to building -4" conduit from south of building to east side for data **Light poles -(3) light poles at SE lot
Underground Electrical Inspection - Commercial Partial 9/11/2025 9/11/2025 09/11/2025
Misc
Informational
09/09/2025
-Ufer located at NW corner of electrical room -(4) 3” conduit from transformer to building -4" conduit from south of building to east side for data **Light poles -(3) light poles at SE lot -From light pole at SE to ESO in island and to gas pump
In-wall Inspection Failed 9/11/2025 9/11/2025 09/11/2025
Misc
Informational
09/02/2025
**The following areas approved: -020, 021 OK to cover West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok **Exterior wall and eyebrow framing ok to cover -Rms 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top 9/11/25-Partial for 2nd floor-Secure all mc within 12" of boxes ***OK TO 1 SIDE ONLY AS NEEDED -RP
Underground Plumbing Inspection - Commercial Partial 9/12/2025 9/12/2025 09/12/2025
Misc
Resolved
09/12/2025
Provide pressure test at gas line -OK to backfill
Misc
Informational
09/12/2025
Gas line for grill, from serice to mid-building East side.
In-wall Inspection Partial 9/15/2025 09/15/2025
Misc
Informational
09/11/2025
**The following areas approved: -020, 021 OK to cover West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok **Exterior wall and eyebrow framing ok to cover -Rms 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top 2nd floor from line 1-3 complete ***OK TO 1 SIDE ONLY AS NEEDED -RP
Underground Electrical Inspection - Commercial Partial 9/15/2025 09/15/2025
Misc
Informational
09/11/2025
-Ufer located at NW corner of electrical room -(4) 3” conduit from transformer to building -4" conduit from south of building to east side for data **Light poles -(3) light poles at SE lot -From light pole at SE to ESO in island and to gas pump and to within 20’ if east side of building
Underground Electrical Inspection - Commercial Partial 9/16/2025 9/16/2025 09/16/2025
Misc
Informational
09/15/2025
-Ufer located at NW corner of electrical room -(4) 3” conduit from transformer to building -4" conduit from south of building to east side for data **Light poles -(3) light poles at SE lot -From light pole at SE to ESO in island and to gas pump and to building
Curb - Proof Roll Partial 9/22/2025 9/22/2025 09/22/2025
Misc
Informational
09/22/2025
9-22-25 PS Contractor performed proof roll on east lot for curb construction. There are areas along east side of lot that did not pass. Contractor correcting and will schedule another proof roll for Wed 9/24
In-wall Inspection Partial 09/24/2025
Misc
Informational
09/15/2025
**The following areas approved: -020, 021 OK to cover West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok **Exterior wall and eyebrow framing ok to cover -Rms 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top 2nd floor from line 1-3 complete ***OK TO 1 SIDE ONLY AS NEEDED -RP
Erosion Control Inspection Partial 9/24/2025 9/24/2025 09/24/2025
Miscellaneous Correction
Informational
07/18/2025
02/26/25 JMJ Erosion Control has been in place and functioning properly since the beginning of project. 03/12/25 Wednesday JMJ Erosion Control appears to be functional. 06/04/25 Wednesday JMJ Erosion Control appears to be functional. 07/17/25 Friday JMJ Erosion Control appears need repair to the silt fence around the project, weeds need to cleared around silt fencing, and silt needs to be sweep - up . 09/24/25 Wednesday clean up required due to constant rains yesterday.
Erosion Control Inspection Partial 9/24/2025 9/24/2025 09/24/2025
Miscellaneous Correction
Informational
09/24/2025
02/26/25 JMJ Erosion Control has been in place and functioning properly since the beginning of project. 03/12/25 Wednesday JMJ Erosion Control appears to be functional. 06/04/25 Wednesday JMJ Erosion Control appears to be functional. 07/17/25 Friday JMJ Erosion Control appears need repair to the silt fence around the project, weeds need to cleared around silt fencing, and silt needs to be sweep - up . 09/24/25 Wednesday clean up required due to constant rains yesterday.
In-wall Inspection Partial 9/26/2025 9/26/2025 09/26/2025
Misc
Informational
09/24/2025
**The following areas approved: 2nd floor from line 1-3 complete -020, 021, 012, 013, 015, 016 OK to cover West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok **Exterior wall and eyebrow framing ok to cover -Rms 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top ***OK TO 1 SIDE ONLY AS NEEDED -RP
Curb - Proof Roll Partial 9/26/2025 9/26/2025 09/26/2025
Misc
Informational
09/22/2025
9-22-25 PS Contractor performed proof roll on east lot for curb construction. There are areas along east side of lot that did not pass. Contractor correcting and will schedule another proof roll for Wed 9/24 9-26-25 PS Reinspect of proof roll in areas of parking lot inspected of 9-22 for curbs due to weather and corrections made. Areas passed proof roll on verified load
In-wall Inspection Partial 9/29/2025 9/29/2025 09/29/2025
Misc
Informational
09/26/2025
**The following areas approved: 2nd floor from line 1-3 complete -020, 021, 012, 013, 015, 016 OK to cover /West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok -Clear story eyebrow framing at North, south and west complete **Exterior wall and eyebrow framing ok to cover -Rms 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top ***OK TO 1 SIDE ONLY AS NEEDED -RP
Pavement-Curb Construction Partial 9/29/2025 9/29/2025 09/29/2025
Misc
Informational
09/29/2025
9/29/25 Monday JMJ ( Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor poured curb on the Eastside of New constructed building. Third party UES was onsite to preformed required testing of concrete.
Pavement-Curb Construction Partial 9/30/2025 9/30/2025 09/30/2025
Misc
Informational
09/29/2025
9/29/25 Monday JMJ ( Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor poured curb on the Eastside of New constructed building. Third party UES was onsite to preformed required testing of concrete. 9/30/25 Tuesday JMJ ( Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor continued the installation of curbs on the Eastside of newly constructed building approximately 18yds were poured yesterday and 18yds today. Contractor used white cure on curbs.
Retaining Wall Inspection Partial 9/30/2025 9/30/2025 09/30/2025
Misc
Informational
09/30/2025
09/30/25 Tuesday JMJ (Gen. Titians, BC Hardscape) Wall construction will be 6' plus in height when complete. This construction will need to be approved by the design engineer or third party. Contractor began working on the wall yesterday. Foundation appear to be sound, (Batter) wall construction visual is present, foundation brick levels appear to be sturdy.
In-wall Inspection Partial 10/1/2025 10/01/2025
Misc
Informational
09/29/2025
**The following areas approved: 2nd floor from line 1-3 complete -020, 021, 012, 013, 015, 016 OK to cover /West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok -Clear story eyebrow framing at North, south and west complete **Exterior wall and eyebrow framing ok to cover -Rms007-009, 011, 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top ***OK TO 1 SIDE ONLY AS NEEDED -RP
Pavement-Curb Construction Partial 10/2/2025 10/2/2025 10/02/2025
Misc
Informational
09/30/2025
9/29/25 Monday JMJ ( Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor poured curb on the Eastside of New constructed building. Third party UES was onsite to preformed required testing of concrete. 9/30/25 Tuesday JMJ ( Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor continued the installation of curbs on the Eastside of newly constructed building approximately 18yds were poured yesterday and 18yds today. Contractor used white cure on curbs. 10/01/25 Thursday JMJ ( Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor continued to pour curb on the Westside of entrance/exit that is between the new building & new addition to Police Department. Contractor plans to continue to pour approximately 18yds of curbs,
Retaining Wall Inspection Partial 10/2/2025 10/2/2025 10/02/2025
Misc
Informational
09/30/2025
09/30/25 Tuesday JMJ (Gen. Titians, BC Hardscape) Wall construction will be 6' plus in height when complete. This construction will need to be approved by the design engineer or third party. Contractor began working on the wall yesterday. Foundation appear to be sound, (Batter) wall construction visual is present, foundation brick levels appear to be sturdy. 10/02/25 Thursday JMJ (Gen. Titians, BC Hardscape) Contractor to construct the retaining wall.
In-wall Inspection Failed 10/3/2025 10/3/2025 10/03/2025
Misc
Informational
10/01/2025
**The following areas approved: 2nd floor from line 1-3 complete -020, 021, 012, 013, 015, 016 OK to cover /West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok -Clear story eyebrow framing at North, south and west complete **Exterior wall and eyebrow framing ok to cover -Rms007-009, 011, 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top ***OK TO 1 SIDE ONLY AS NEEDED -RP
Piers/Caissons Inspection - Commercial Partial 10/6/2025 10/6/2025 10/06/2025
Misc
Informational
09/08/2025
-Piers for (2) light pole bases at NE lot -piers for (4) light pole bases at NE lot E central and south side -Piers for (2) light poles at North existing lot -(4) light pole bases at west drive
In-wall Inspection Partial 10/8/2025 10/08/2025
Misc
Informational
10/03/2025
**The following areas approved: 2nd floor from line 1-3 complete -020, 021, 012, 013, 015, 016 OK to cover /West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok -Clear story eyebrow framing at North, south and west complete **Exterior wall and eyebrow framing ok to cover -Rms007-009, 011, 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top -1st floor south side complete ***OK TO 1 SIDE ONLY AS NEEDED -RP
Footing Inspection - Commercial Partial 10/9/2025 10/9/2025 10/09/2025
Misc
Informational
04/24/2025
4/21-Footing not ready for inspection.
THE FOLLOWING AREAS ARE APPROVED
Informational
04/24/2025
Perimeter footings complete Interior pads complete Transformer pad East entry stoop complete Elevator pit mat complete
THE FOLLOWING AREAS ARE APPROVED
Informational
10/09/2025
- Footing at front entrance, planters
Piers/Caissons Inspection - Commercial Partial 10/10/2025 10/10/2025 10/10/2025
Misc
Informational
10/06/2025
-Piers for (2) light pole bases at NE lot -piers for (4) light pole bases at NE lot E central and south side -Piers for (2) light poles at North existing lot -(4) light pole bases at west drive - (2) light pole bases south of retention basin
Piers/Caissons Inspection - Commercial Partial 10/14/2025 10/14/2025 10/14/2025
Misc
Informational
10/10/2025
-Piers for (2) light pole bases at NE lot -piers for (4) light pole bases at NE lot E central and south side -Piers for (2) light poles at North existing lot -(5) light pole bases at west drive - (2) light pole bases south of retention basin
Footing Inspection - Commercial Passed 10/15/2025 10/15/2025 10/15/2025
Misc
Resolved
10/15/2025
4/21-Footing not ready for inspection.
THE FOLLOWING AREAS ARE APPROVED
Resolved
10/15/2025
Perimeter footings complete Interior pads complete Transformer pad East entry stoop complete Elevator pit mat complete
THE FOLLOWING AREAS ARE APPROVED
Resolved
10/15/2025
- Footing at front entrance, planters
Gas Service Inspection - Commercial Passed 10/15/2025 10/15/2025
Pavement-Surface Partial 10/16/2025 10/16/2025 10/16/2025
Misc
Informational
05/23/2025
05/23/25 Friday JMJ (Hanrahan Asphalt Paving Co. Inc.) Contractor installed approximately 425tons of KCMMB A2 for parking lot. 10/16/25 Thursday JMJ (Gen. Titans, Sub. Hanrahan Asphalt Paving Co. Inc.) Contractor plans to lay base asphalt on existing South parking lot and tight corners around curbs.
Misc
Informational
10/16/2025
10/16/25 Thursday JMJ ( Gen. Titans Construction, George Shaw.) Contractor plans to pour approximately 16 yards of KCMMB. Concrete will be poured around light pole base in the existing parking lot area.
Pavement-Surface Partial 10/17/2025 10/17/2025 10/17/2025
Misc
Informational
10/16/2025
05/23/25 Friday JMJ (Hanrahan Asphalt Paving Co. Inc.) Contractor installed approximately 425tons of KCMMB A2 for parking lot.
Misc
Informational
10/16/2025
10/16/25 Thursday JMJ ( Gen. Titans Construction, George Shaw.) Contractor plans to pour approximately 16 yards of KCMMB. Concrete will be poured around light pole base in the existing parking lot area. 10/17/25 Friday JMJ (Gen. Titan, Sub George Shaw Const.) Contractor poured 10yards of of KCMMB concrete continuing around light pole bases in the existing parking lot.
Pavement-Curb Construction Partial 10/17/2025 10/17/2025 10/17/2025
Misc
Informational
10/02/2025
9/29/25 Monday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor poured curb on the Eastside of New constructed building. Third party UES was onsite to preformed required testing of concrete. 9/30/25 Tuesday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor continued the installation of curbs on the Eastside of newly constructed building approximately 18yds were poured yesterday and 18yds today. Contractor used white cure on curbs. 10/01/25 Thursday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor continued to pour curb on the Westside of entrance/exit that is between the new building & new addition to Police Department. Contractor plans to continue to pour approximately 18yds of curbs. 10/17/25 Friday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor began to pour forms on the Westside of building approximately 12 yards.
In-wall Inspection Partial 10/20/2025 10/20/2025 10/20/2025
Misc
Informational
10/08/2025
**The following areas approved: 2nd floor from line 1-3 complete -020, 021, 012, 013, 015, 016 OK to cover /West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok -Clear story eyebrow framing at North, south and west complete **Exterior wall and eyebrow framing ok to cover -Rms007-009, 011, 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top -1st floor south side complete -1st floor north side: 022, 025, 027-034, 036-038, 045 ***OK TO 1 SIDE ONLY AS NEEDED -RP
Pavement-Aggregate Base Partial 10/20/2025 10/20/2025 10/20/2025
Misc
Informational
10/20/2025
10/20/25 Monday JMJ ( Gen. Titan, Sub. Hanrahan Asphalt, Third party testing UES)
Pavement-Curb Construction Partial 10/20/2025 10/20/2025 10/20/2025
Misc
Informational
10/17/2025
9/29/25 Monday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor poured curb on the Eastside of New constructed building. Third party UES was onsite to preformed required testing of concrete. 9/30/25 Tuesday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor continued the installation of curbs on the Eastside of newly constructed building approximately 18yds were poured yesterday and 18yds today. Contractor used white cure on curbs. 10/01/25 Thursday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor continued to pour curb on the Westside of entrance/exit that is between the new building & new addition to Police Department. Contractor plans to continue to pour approximately 18yds of curbs. 10/17/25 Friday JMJ (Gen. Titans,Sub. George J. Shaws Construction, Third party UES) Contractor began to pour forms on the Westside of building approximately 12 yards. 10/20/25 Monday JMJ (Gen. Titan, Sub George J. Shaw Constrution, Third party UES) Contractor continued to pour curbs on the Westside of building.
Pavement-Surface Partial 10/21/2025 10/21/2025 10/21/2025
Misc
Informational
10/17/2025
05/23/25 Friday JMJ (Hanrahan Asphalt Paving Co. Inc.) Contractor installed approximately 425tons of KCMMB A2 for parking lot.
Misc
Informational
10/17/2025
10/16/25 Thursday JMJ ( Gen. Titans Construction, George Shaw.) Contractor plans to pour approximately 16 yards of KCMMB. Concrete will be poured around light pole base in the existing parking lot area. 10/17/25 Friday JMJ (Gen. Titan, Sub. George Shaw Const.) Contractor poured 10yards of of KCMMB concrete continuing around light pole bases in the existing parking lot. 10/21/25 Tuesday JMJ ( Gen. Titan, Sub. George Shaw Const., Third party testing UES) Contractor laid the first layer of the KCMMB A2 Pavement-Surface on the Eastside of the new constructed building.
In-wall Inspection Partial 10/23/2025 10/23/2025
Misc
Informational
10/20/2025
**The following areas approved: 2nd floor from line 1-3 complete -020, 021, 012, 013, 015, 016 OK to cover -103 exterior wall ok /West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok -Clear story eyebrow framing at North, south and west complete **Exterior wall and eyebrow framing ok to cover -Rms007-009, 011, 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top -1st floor south side complete -1st floor north side: 022, 025, 027-034, 036-038, 045 ***OK TO 1 SIDE ONLY AS NEEDED -RP
Detention Basin Partial 10/28/2025 10/28/2025 10/28/2025
Misc
Informational
10/28/2025
10/28/25 Tuesday JMJ ( Gen. Titan, Sub, Rodriguez) Contractor began excavating the basin and the skimmer.
In-wall Inspection Partial 10/29/2025 10/29/2025 10/29/2025
Misc
Informational
10/23/2025
**The following areas approved: 2nd floor from line 1-3 complete -020, 021, 012, 013, 015, 016 OK to cover -103 exterior wall ok /West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok -Clear story eyebrow framing at North, south and west complete **Exterior wall and eyebrow framing ok to cover -Rms007-009, 011, 019, 040, 041, 157 Ok to one side for equipment -Main floor, south of line 4-OK to one side from ceiling level to top -1st floor south side complete -1st floor north side: 022, 025, 027-034, 036-038, 045 -2nd floor exterior wall framing complete except at room 120 ***OK TO 1 SIDE ONLY AS NEEDED -RP
Above Ceiling Inspection Partial 10/31/2025 10/31/2025 10/31/2025
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
10/31/2025
Soffits in 04, 05 Hard lids at 012-013
In-wall Inspection Partial 10/31/2025 10/31/2025 10/31/2025
Misc
Informational
10/29/2025
**The following areas approved: 2nd floor from line 1-3 complete -020, 021, 012, 013, 015, 016 OK to cover -103 exterior wall ok /West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok -Clear story eyebrow framing at North, south and west complete **Exterior wall and eyebrow framing ok to cover -1st floor south side complete 022, 025, 027-034, 036-038, 045, 110-116, 121, 124-128 -2nd floor exterior wall framing complete except at room 120 ***OK TO 1 SIDE ONLY AS NEEDED -RP
Above Ceiling Inspection Partial 11/3/2025 11/3/2025 11/03/2025
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
10/31/2025
Soffits in 04, 05 Hard lids at 012-013, 136, 137, 149
In-wall Inspection Partial 11/3/2025 11/3/2025 11/03/2025
Misc
Informational
10/31/2025
**The following areas approved: 2nd floor from line 1-3 complete -019, 020, 021, 012, 013, 015, 016 OK to cover -103 exterior wall ok /West side roof facade to line 4 ok South side roof facade ok -CMU Walls at loading dock ok -Clear story eyebrow framing at North, south and west complete **Exterior wall and eyebrow framing ok to cover -1st floor south side complete 022, 025, 027-034, 036-038, 045, 110-116, 121, 124-128, -2nd floor exterior wall framing complete except at room 120 ***OK TO 1 SIDE ONLY AS NEEDED -RP
Underground Electrical Inspection - Commercial Partial 11/3/2025 11/3/2025 11/03/2025
Misc
Informational
09/16/2025
-Ufer located at NW corner of electrical room -(4) 3” conduit from transformer to building -4" conduit from south of building to east side for data **Light poles -(3) light poles at SE lot -(5) at west side -From light pole at SE to ESO in island and to gas pump and to building
Documents & Images
Date Uploaded File Type Document Name
11/01/2024 Application Form APPLICATION
11/01/2024 Application Form excise tax
11/04/2024 Plans LSJOF_Construction Set Volume 2
11/04/2024 Specifications LSJOF_Specs Volume 1
11/04/2024 Specifications LSJOF_Specs Volume 2
11/04/2024 Engineer Report/Study LSJOF_StormwaterReport
11/04/2024 Engineer Report/Study LSJOF_Struct Calcs
11/04/2024 Plans LSJOF_Construction Set Volume 1
11/05/2024 Application Form Exise tax application
11/15/2024 Letter License Tax Bill
11/18/2024 Letter DS P/R Corrections Document
12/02/2024 Letter LSJOF_ADD03 Narrative_For Reference_2024-12-02
12/02/2024 Code Mod Request LSJOF_Code Modification Request COMMERCIAL_2024-12-02
12/02/2024 Plans LSJOF_Construction Set Volume 1_REV 1_2024-12-02
12/02/2024 Plans LSJOF_Construction Set Volume 2_REV 1_2024-12-02
12/02/2024 Letter LSJOF PERMIT COMMENT RESPONSE_2024-12-02
12/09/2024 Specifications LSJOF_087100 - DOOR HARDWARE_REV 1_2024-12-09
12/09/2024 Letter LSJOF_ADD03 Narrative_For Reference_REV 1_2024-12-09
12/09/2024 Engineer Report/Study LSJOF_FINAL STORMWATER REPORT_REV 1_2024-12-09
12/09/2024 Engineer Report/Study LSJOF_SWPPP_REV 1_2024-12-09
12/10/2024 Code Mod Request approved restroom CMR
12/10/2024 Letter DS P/R Corrections Document
01/13/2025 Receipt Receipt for transaction: 2025-000206
01/13/2025 Letter DS Building Permit
01/15/2025 Letter Initial SI Letter of Intent
01/16/2025 Plans LSJOF_Construction Set Volume 2_REV 2_2025-01-16
01/16/2025 Plans LSJOF_Construction Set Volume 3_REV 2_2025-01-16
01/16/2025 Engineer Report/Study LSJOF_ICC500 PEER REVIEW_2025-01-16
01/16/2025 Letter LSJOF_PERMIT COMMENT RESPONSE_2025-01-16
01/16/2025 Plans LSJOF_Construction Set Volume 1_REV 2_2025-01-16
02/07/2025 Letter INSPECTION SUMMARY
02/12/2025 Letter LSJOF Storm Shelter Peer Review Response_REV 0_2025-02-12
02/14/2025 Letter LSJOF_ASI002 Narrative_For Reference_2025-02-14
02/14/2025 Letter LSJOF_ASI003 Narrative_For Reference_2025-02-14
02/14/2025 Letter LSJOF_ASI004 Narrative_For Reference_2025-02-14
02/14/2025 Letter LSJOF_CCD 001 Narrative_For Reference_2025-02-14
02/14/2025 Letter LSJOF_CCD 002 Narrative_For Reference_2025-02-14
02/14/2025 Engineer Report/Study LSJOF_Storm Shelter Peer Review Response_REV 1_2025-02-14
02/14/2025 Engineer Report/Study LSJOF_Struct Calcs_REV 1_2025-02-14
02/14/2025 Plans LSJOF_Construction Set Volume 1_REV 3_2025-02-14
02/14/2025 Plans LSJOF_Construction Set Volume 3_REV 3_2025-02-14
02/14/2025 Letter LSJOF_ASI001 Narrative_For Reference_2025-02-14
02/14/2025 Plans LSJOF_Construction Set Volume 2_REV 3_2025-02-14
02/14/2025 Approved Plans Approved plans Vol1
02/14/2025 Approved Plans Approved plans Vol2
02/19/2025 Receipt Receipt for transaction: 2025-000983
02/27/2025 Letter INSPECTION SUMMARY
03/11/2025 Letter INSPECTION SUMMARY
03/11/2025 Letter INSPECTION SUMMARY
03/12/2025 Letter INSPECTION SUMMARY
03/14/2025 Letter INSPECTION SUMMARY
03/14/2025 Letter LSJOF_ASI005 Narrative_For Reference_2025-03-14
03/14/2025 Letter LSJOF_ASI006 Narrative_For Reference_2025-03-14
03/14/2025 Letter LSJOF_ASI007 Narrative_For Reference_2025-03-14
03/14/2025 Plans LSJOF_Construction Set Volume 2_REV 4_2025-03-14
03/18/2025 Letter INSPECTION SUMMARY
03/18/2025 Letter INSPECTION SUMMARY
03/20/2025 Letter INSPECTION SUMMARY
03/21/2025 Letter INSPECTION SUMMARY
03/27/2025 Approved Plans Approved plans - Vol1
03/27/2025 Approved Plans Approved plans - Vol2
03/28/2025 Letter INSPECTION SUMMARY
03/28/2025 Letter INSPECTION SUMMARY
03/31/2025 Letter INSPECTION SUMMARY
04/01/2025 Letter INSPECTION SUMMARY
04/02/2025 Letter INSPECTION SUMMARY
04/03/2025 Letter INSPECTION SUMMARY
04/10/2025 Letter INSPECTION SUMMARY
04/10/2025 Letter INSPECTION SUMMARY
04/15/2025 Letter INSPECTION SUMMARY
04/17/2025 Letter INSPECTION SUMMARY
04/17/2025 Letter INSPECTION SUMMARY
04/18/2025 Letter INSPECTION SUMMARY
04/18/2025 Letter INSPECTION SUMMARY
04/21/2025 Letter INSPECTION SUMMARY
04/22/2025 Letter INSPECTION SUMMARY
04/23/2025 Letter INSPECTION SUMMARY
04/24/2025 Letter INSPECTION SUMMARY
05/02/2025 5-25-0011 - LS Joint Ops - FS Plans_STAMPED
05/02/2025 5-25-0011 - LS Joint Ops - Submittal_STAMPED
05/13/2025 Letter INSPECTION SUMMARY
05/13/2025 Letter Fire (Sprinkler) Plan Review
05/23/2025 Letter INSPECTION SUMMARY
05/23/2025 Letter INSPECTION SUMMARY
05/23/2025 Letter INSPECTION SUMMARY
06/04/2025 Letter INSPECTION SUMMARY
06/09/2025 Letter INSPECTION SUMMARY
06/09/2025 Letter INSPECTION SUMMARY
06/10/2025 Letter INSPECTION SUMMARY
06/10/2025 Letter INSPECTION SUMMARY
06/12/2025 Plans CALCS
06/12/2025 Plans PLANS
06/17/2025 Letter INSPECTION SUMMARY
06/17/2025 5-25-0011 - LS Joint Ops - FS Plans_Rev01_stamped
06/17/2025 Keller Letter 06_12_25
06/18/2025 Letter INSPECTION SUMMARY
06/23/2025 Letter INSPECTION SUMMARY
06/23/2025 5-25-0011 - LS Joint Ops - FS Plans_Rev01_stamped RFC
06/23/2025 Letter INSPECTION SUMMARY
06/23/2025 Letter INSPECTION SUMMARY
06/23/2025 Letter Fire (Sprinkler) Plan Review
06/23/2025 Letter INSPECTION SUMMARY
06/24/2025 Letter INSPECTION SUMMARY
06/24/2025 Letter INSPECTION SUMMARY
06/25/2025 Letter INSPECTION SUMMARY
06/25/2025 Letter INSPECTION SUMMARY
06/25/2025 ALARM PLANS
06/26/2025 Letter INSPECTION SUMMARY
06/27/2025 Letter INSPECTION SUMMARY
06/27/2025 Letter INSPECTION SUMMARY
06/30/2025 Letter INSPECTION SUMMARY
07/01/2025 Letter INSPECTION SUMMARY
07/01/2025 Letter INSPECTION SUMMARY
07/01/2025 Letter INSPECTION SUMMARY
07/02/2025 Letter INSPECTION SUMMARY
07/02/2025 Letter INSPECTION SUMMARY
07/07/2025 Letter INSPECTION SUMMARY
07/09/2025 Letter INSPECTION SUMMARY
07/11/2025 Letter INSPECTION SUMMARY
07/15/2025 Letter Fire (Alarm) Plan Review Notice
07/15/2025 Letter INSPECTION SUMMARY
07/18/2025 Letter INSPECTION SUMMARY
07/18/2025 Letter Fire (Alarm) Plan Review Notice
07/21/2025 Letter INSPECTION SUMMARY
07/28/2025 Letter INSPECTION SUMMARY
07/28/2025 Letter INSPECTION SUMMARY
07/28/2025 Letter INSPECTION SUMMARY
07/28/2025 Letter INSPECTION SUMMARY
07/30/2025 Letter INSPECTION SUMMARY
07/30/2025 Letter INSPECTION SUMMARY
07/31/2025 Letter INSPECTION SUMMARY
08/05/2025 Letter INSPECTION SUMMARY
08/06/2025 Letter INSPECTION SUMMARY
08/06/2025 Letter INSPECTION SUMMARY
08/06/2025 Letter INSPECTION SUMMARY
08/07/2025 Letter INSPECTION SUMMARY
08/08/2025 Letter INSPECTION SUMMARY
08/08/2025 Letter INSPECTION SUMMARY
08/14/2025 Letter INSPECTION SUMMARY
08/14/2025 Letter INSPECTION SUMMARY
08/15/2025 Letter INSPECTION SUMMARY
08/19/2025 Letter INSPECTION SUMMARY
08/19/2025 Letter INSPECTION SUMMARY
08/19/2025 Letter INSPECTION SUMMARY
08/20/2025 Letter INSPECTION SUMMARY
08/20/2025 Letter INSPECTION SUMMARY
08/21/2025 Letter INSPECTION SUMMARY
08/21/2025 Letter INSPECTION SUMMARY
08/25/2025 Letter INSPECTION SUMMARY
08/26/2025 Letter INSPECTION SUMMARY
08/27/2025 Letter INSPECTION SUMMARY
08/27/2025 Letter INSPECTION SUMMARY
08/27/2025 Letter INSPECTION SUMMARY
08/27/2025 Letter INSPECTION SUMMARY
09/02/2025 Letter INSPECTION SUMMARY
09/02/2025 Letter INSPECTION SUMMARY
09/04/2025 Letter INSPECTION SUMMARY
09/05/2025 Letter INSPECTION SUMMARY
09/08/2025 Letter Narrative_Rev 5_PL2024270
09/08/2025 Letter LSJOF_ASI011 Narrative_For Reference_2025-09-08
09/08/2025 Letter LSJOF_ASI012 Narrative_For Reference_2025-09-08
09/08/2025 Letter LSJOF-CCD 003 Narrative_For Reference_2025-09-08
09/08/2025 Plans Construction Set_REV 5_2025-09-08
09/08/2025 Plans LSJOF_Construction Set Volume 2_REV 5_2025-09-08
09/08/2025 Plans LSJOF_Construction Set Volume 3_REV 5_2025-09-08
09/08/2025 Letter LSJOF_ASI009 Narrative_For Reference_2025-09-08
09/08/2025 Letter INSPECTION SUMMARY
09/09/2025 Letter INSPECTION SUMMARY
09/11/2025 Letter INSPECTION SUMMARY
09/11/2025 Letter INSPECTION SUMMARY
09/12/2025 Letter INSPECTION SUMMARY
09/12/2025 Letter INSPECTION SUMMARY
09/12/2025 Letter INSPECTION SUMMARY
09/15/2025 Letter INSPECTION SUMMARY
09/15/2025 Letter INSPECTION SUMMARY
09/16/2025 Letter DS P/R Corrections Document
09/16/2025 Letter INSPECTION SUMMARY
09/19/2025 Approved Plans Approved construction plans Vol1
09/19/2025 Approved Plans Approved construction plans Vol2
09/22/2025 IMG_0007
09/22/2025 Letter INSPECTION SUMMARY
09/24/2025 Letter INSPECTION SUMMARY
09/24/2025 Letter INSPECTION SUMMARY
09/24/2025 Letter INSPECTION SUMMARY
09/26/2025 Letter INSPECTION SUMMARY
09/26/2025 Letter INSPECTION SUMMARY
09/29/2025 Letter INSPECTION SUMMARY
09/29/2025 Letter INSPECTION SUMMARY
09/30/2025 Letter INSPECTION SUMMARY
09/30/2025 Letter INSPECTION SUMMARY
10/01/2025 Letter INSPECTION SUMMARY
10/02/2025 Letter INSPECTION SUMMARY
10/03/2025 Letter INSPECTION SUMMARY
10/06/2025 Letter INSPECTION SUMMARY
10/08/2025 Letter INSPECTION SUMMARY
10/08/2025 Letter INSPECTION SUMMARY
10/09/2025 Letter INSPECTION SUMMARY
10/10/2025 Letter INSPECTION SUMMARY
10/14/2025 Letter INSPECTION SUMMARY
10/15/2025 Letter INSPECTION SUMMARY
10/15/2025 Letter INSPECTION SUMMARY
10/16/2025 Letter INSPECTION SUMMARY
10/16/2025 Letter INSPECTION SUMMARY
10/17/2025 Letter INSPECTION SUMMARY
10/17/2025 Letter INSPECTION SUMMARY
10/20/2025 Letter INSPECTION SUMMARY
10/20/2025 Letter INSPECTION SUMMARY
10/20/2025 Letter INSPECTION SUMMARY
10/21/2025 Letter INSPECTION SUMMARY
10/21/2025 Letter INSPECTION SUMMARY
10/23/2025 Letter INSPECTION SUMMARY
10/28/2025 Letter INSPECTION SUMMARY
10/29/2025 Letter INSPECTION SUMMARY
10/31/2025 Letter INSPECTION SUMMARY
10/31/2025 Letter INSPECTION SUMMARY
11/03/2025 Letter INSPECTION SUMMARY
11/03/2025 Letter INSPECTION SUMMARY
11/03/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home