Planning Application Status

PL2022417




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2022417
Residences, Reunion and Reserve at Blackwell - Mass Grading and ESC
Engineering Plan Review
Engineering Plan Review
Approved
11/29/2022
RESIDENCES AT BLACKWELL LLC
Locations
Contacts
RESIDENCES AT BLACKWELL LLC, Address:21 SE 29TH TER  
GRIFFIN RILEY PROPERTY GROUP, Address:21 SE 29TH TER, Phone:(816) 366-7900  
SCHLAGEL & ASSOCIATES, Address:14920 W 107TH ST, Phone:(913) 492-5158  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 06/19/2023 06/20/2023
Gene Williams, P.E.
Engineering Review No Comments 06/19/2023 06/09/2023
Gene Williams, P.E.
Engineering Review Corrections 05/22/2023 05/19/2023
Gene Williams, P.E.
Corrective Action Required
05/19/2023

It appears the only item that has changed since the last submittal is a note stating that EWDB-3 is to be installed after the drainage easement has been obtained. It was our understanding you were going to provide a re-design of the system to accommodate the single sediment basin, and this does not appear to have been done. EWDB-2 shows an exit pipe entering a basin which will not be constructed until the future, so this is not going to be possible as shown. Please evaluate, review, and provide a re-design which accommodates the changes. It would be preferred that a separate plan be developed which eliminates any indication of EWDB-3 until such time that the off-site drainage easement has been obtained.
Corrective Action Required
05/19/2023

The erosion and sediment control plan shows the installation of gutter buddies on "at-grade" curb inlets. This will prevent the storm collection and conveyance system from achieving its design objectives, and may lead to structure and/or street flooding. Please eliminate gutter buddies at the "at-grade" locations. The gutter buddies can be utilized in a sump condition, but only if a suitable overflow route is established for the clogged condition. Please revise as appropriate.
Corrective Action Required
05/19/2023

Was a SWPPP submitted for this project? I cannot find where this was uploaded to the project file. Please upload the SWPPP to this file.
Engineering Review Approved with Conditions 04/17/2023 04/13/2023
Gene Williams, P.E.
Engineering Review Corrections 02/07/2023 03/03/2023
Gene Williams, P.E.
Corrective Action Required
03/03/2023

The plans are lacking the outlet pipe details for both sediment basins. In addition, a site-specific plan for both sediment basins was missing. As shown on the standard detail, a site-specific design is always required for a sediment basin. This includes all aspects of the system, including elevations, pipe type, diameter, etc.
Corrective Action Required
03/03/2023

An off-site private storm drainage easement is required to connect to the existing storm line within Tract D, Summit Mill 2nd Plat. The easement shall be a private easement dedicated to the homeowners assocation rather than the City.
Corrective Action Required
03/03/2023

Turf reinforcement mat should be shown within the side slopes of sediment basins and detention basins. Please revise as appropriate.
Corrective Action Required
03/03/2023

Turf reinforcement mat should be shown along the east/west swale located along the north of the development.
Corrective Action Required
03/03/2023

Turf reinforcement mat should be shown along the west property line of the development within the swale.
Engineering Review Corrections 12/16/2022 12/16/2022
Gene Williams, P.E.
Corrective Action Required
12/16/2022

A SWPPP is required prior to formal approval due to the size of the project being greater than 1 acre.
Corrective Action Required
12/16/2022

Phasing table shows the sediment basins to be constructed when 10 acres or more of disturbed area are completed. These features should be constructed during the first phase of erosion and sediment control, not after 10 acres have been disturbed. Please revise.
Corrective Action Required
12/16/2022

An off-site easement appears to be needed at the drainage point of EWDB #3. This off-site easement should be private rather than public. Please provide a courtesy review copy of the easement, along with an 8.5 by 11 inch exhibit showing the limits of the private easement in graphic format prior to execution and recording.
Corrective Action Required
12/16/2022

It is understood that mass grading as shown on this plan will be undertaken at once rather than phased over the life of the project (i.e., Traditions at Blackwell, Reserve at Blackwell, etc.). If this is not the case, please respond. This has a bearing on the review of the off-site sanitary and off-site water line, and since our understanding is that the mass grading will take place during the platting of the first phase (i.e., the Residences at Blackwell), this is key to the review since the City will not desire overland lines to be laid in areas of extensive future grading.
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
11/29/2022 Application Form Application and Affidavit_Rev 0_PL2022413
11/30/2022 Plans 22-102 LAND DISTURBANCE - REV0 - 2022_11_30
12/16/2022 Letter DE-Comment Letter (Engineering Plans)
01/24/2023 Plans 22-102 LAND DISTURBANCE - REV1 - 2023_01_23
01/24/2023 Letter Response to Comments - Engineering Plans - Erosion and Sediment Control dated 12-16-2022
01/24/2023 Engineer Report/Study 22-102 Final Stormwater Management Plan
02/24/2023 Activity Document MDNR Permit for Residences-Traditions-Reserve at Blackwell
01/24/2023 Engineer Report/Study 22-102 Final Stormwater Management Plan
03/03/2023 Letter DE-Comment Letter (Engineering Plans)
04/03/2023 Plans 22-102 RESIDENCES AT BLACKWELL - MASS GRADING AND EROSION CONTROL - REV2 - 2023_03_23
04/03/2023 Letter Response to Comments dated 3-3-2023 for PL2022417 Mass Grading and Erosion Control
04/13/2023 Email obsoleteSTKY APPROVAL APR2023
05/15/2023 Engineer Report/Study 22-102 - Blackwell Final Stormwater Management Plan - Rev3
05/15/2023 Engineer Report/Study 22-102 - LAND DISTURBANCE - REV2 - 2023_05_15
05/19/2023 Letter DE-Comment Letter (Engineering Plans)
06/05/2023 Letter Response to Comments dated 5-19-2023 for PL2022417 Mass Grading and Erosion Control
06/05/2023 Engineer Report/Study swp2
06/06/2023 Plans 22-102 - LAND DISTURBANCE - REV3 - 2023_06_06
06/09/2023 Email STKY APPROVAL JUN2023
06/12/2023 Plans 22-102 - LAND DISTURBANCE - REV3 - 2023_06_12
06/12/2023 Engineers Estimate 22-102 - COST EST - 2023_06_12
06/20/2023 Approved Plans RELEASED FOR CONSTRUCTION
06/20/2023 Activity Document FeeWorksheet
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home