Summary
PL2022292
Raintree Village Senior Living-Phase 1: Off-Site Sanitary Sewer Plan
Engineering Plan Review
Engineering Plan Review
Approved
08/10/2022
CCRC OF LEES SUMMIT LLC
Locations
Contacts
CCRC OF LEES SUMMIT LLC, Address:6731 W 121ST ST STE 100  
Jordan Anderson, Address:Scenic Development, Phone:(913) 730-1094  
Julie Sellers, Address:Olsson Associates, Phone:(816) 361-1177  
Scott Ready, Phone: 8169691225  
CITY OF LEES SUMMIT MISSOURI, Address:220 SE GREEN ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Record Drawings Review No Comments 01/21/2025 01/22/2025
Sue Pyles, P.E.
Engineering Review No Comments 02/02/2024 01/23/2024
Sue Pyles, P.E.
Engineering Review No Comments 04/10/2023 04/11/2023
Sue Pyles, P.E.
Engineering Review No Comments 03/07/2023 03/07/2023
Sue Pyles, P.E.
Engineering Review Corrections 02/17/2023 02/17/2023
Sue Pyles, P.E.
Corrective Action Required
02/17/2023

Include the casing pipe wall thickness in the plan set.
Corrective Action Required
02/17/2023

Please include the City's Sanitary Sewer Stub Connection standard detail.
Engineering Review Corrections 09/01/2022 09/01/2022
Sue Pyles, P.E.
Corrective Action Required
09/01/2022

General: • Submit an Engineer's Estimate of Probable Construction Costs. • Submit a copy of the MDNR permit. • The easement width, 30’, appears too narrow in some locations. Please review and revise as necessary. • The City does not allow public infrastructure to be located under retaining walls. Please investigate other options.
Corrective Action Required
09/01/2022

Sheet S1.0: • Revise General Note 2. “CPD-DS-LDD” does not apply. • The City does not allow ABS or VCP pipe. Please revise General Notes 4 & 5 accordingly.
Corrective Action Required
09/01/2022

Sheet S2.0: • Please label the existing MH with the City’s MH number, 60-163, in both Plan and Profile view. • Revise the line type downstream of SS 1-1 in Plan view. • Include note that connection to the existing MH is by core drilling. • Include invert elevation in from the west at the existing MH. • The drop across the EX MH does not meet City requirements. Please revise.
Corrective Action Required
09/01/2022

Sheet S2.1: • Include bore info at the retaining wall in Plan view to match the other bore locations. • The casing pipe diameter appears too small to work with a 10” pipe. Please revise diameter and include wall thickness. • Include any special design requirements for the pipe being bored. • The drop across SS 1-4 does not meet City requirements. Please revise.
Corrective Action Required
09/01/2022

Sheets S3.0-S3.1: • Only include applicable details in the plan set. • Add the Casing Pipe standard detail to the plan set. • The City requires bedding be placed to a minimum 12” above the top of pipe. Please revise the detail accordingly.
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
08/17/2022 Plans 08_10_2022_RAINTREE VILLAGE_SANITARY
09/01/2022 Letter DE-Comment Letter (Engineering Plans)
10/11/2022 Plans 2022_10_10_RAINTREE VILLAGE_SANITARY PLANS
10/11/2022 Letter 2022_10_10_RAINTREE VILLAGE_SANITARY_RESPONSE_LETTER
10/11/2022 Engineers Estimate 2022-10-03_RaintreeVillagePublic_Sanitary_Cost_Estimate
02/03/2023 Engineers Estimate 2023-01-20_Public_Sanitary_Cost_Estimate
02/03/2023 Plans 2023_01_20_RAINTREE VILLAGE_SANITARY PLANS
02/17/2023 Letter DE-Comment Letter (Engineering Plans)
02/28/2023 Letter 2023_02_28_GNCV_Comment Response Letter_Commercial Final Development Plan_City
02/28/2023 Plans 2023_02_28_RAINTREE VILLAGE_SANITARY PLANS
03/07/2023 Activity Document Fees PL2022292 Raintree Village Senior Living Ph 1 Offsite Sanitary
03/08/2023 Approved Plans Raintree Village Offsite Sanitary Plans Approved 03 08 23
03/08/2023 Email PL2022292 Raintree Village Sr_ Living Ph 1 Offsite Sanitary Plan Approval Information
03/30/2023 Letter Sanitary Sewer Easement Agreement_20230330102839
03/30/2023 Letter Executed Sanitary Sewer Easement 03282023
03/30/2023 Letter Choyce LLC
03/31/2023 Letter Sanitary Sewer Easement
04/11/2023 Letter PL2020292 Raintree Village Senior Living Ph 1 Offsite MDNR Conc. Letter SAN Signed
08/14/2023 Letter 2023E0050520 - Recorded Sanitary Sewer Easement
08/14/2023 Letter 2023E0050521 - Recorded Sanitary Sewer Easement
08/14/2023 Letter 2023E0050522 - Recorded Sanitary Sewer Easement
01/19/2024 Plans S2_1 SANITARY SEWER PLAN PROFILE
01/19/2024 Plans S3_1 DETAILS SHEET
01/23/2024 Approved Plans Raintree Village Offsite Sanitary Sheet S2.1Revision Approved 01 23 24
01/14/2025 Plans 2025.01.07_Public Sanitary Sewer Asbuilts
01/27/2025 Accepted Record Drawings Raintree Village Sr Living Offsite Sanitary AsBuilts Accepted RD
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home