Review Type |
Outcome |
Est. Completion Date |
Completed |
Building Codes Review
|
Approved with Conditions
|
06/17/2022
|
06/17/2022
|
|
Mike Weisenborn
|
|
Miscellaneous Correction
Corrective Action Required
Deferred retaining wall designs must be reviewed and approved prior to construction.
|
|
Miscellaneous Correction
Corrective Action Required
*following comment added after initial review due to oversight.
1-1/2" water tap not available. Must be 2". To be field verified.
|
|
|
Planning Review
|
No Comments
|
06/17/2022
|
06/13/2022
|
|
Hector Soto Jr.
|
|
|
Engineering Review
|
Approved with Conditions
|
06/17/2022
|
06/10/2022
|
|
Loic Nguinguiri, E.I.
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $17,187.24
|
|
Misc.
Corrective Action Required
1" type K copper pipe must extend from the 1" tap to a minimum of 10 feet beyond the location of the water meter.
|
|
|
Traffic Review
|
No Comments
|
06/17/2022
|
06/10/2022
|
|
Mike Weisenborn
|
|
|
Fire Review
|
Approved with Conditions
|
06/17/2022
|
06/10/2022
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Planning Review
|
Corrections
|
06/02/2022
|
06/02/2022
|
|
Hector Soto Jr.
|
|
Corrective Action Required
LAND USE SCHEDULE.
- Building Area (sq. ft.). Please clarify the proposed building square footage. The listed building area of 20,130 sq. ft. appears to be for the building footprint, but it appears from the floor plan on Sheet A1.1 that there is mezzanine or similar second story space above the office area. The listed building area needs to reflect the gross floor area. Provide a breakdown of the ground floor space, second story space and total building area.
- Floor Area Ratio. Revise the FAR to reflect any changes to the gross floor area based on comment above.
|
|
Corrective Action Required
PARKING. Provide supporting information from other locations (e.g. parking surveys) or industry standards demonstrating that the number of parking spaces provided for the proposed use and square footage is sufficient to satisfy the expected parking demand
|
|
|
Engineering Review
|
Corrections
|
06/02/2022
|
06/02/2022
|
|
Loic Nguinguiri, E.I.
|
|
Corrective Action Required
Revise the accuracy of the note that describes how the sump of the proposed BFPD will be drained. Illustrating this information on the WAT-12 construction standard detail is also acceptable.
|
|
Corrective Action Required
Revise the overlapping texts located in the title block of sheet C3.4.
|
|
Corrective Action Required
Revise the characteristics of the proposed water domestic service line, as per the phone call conversation with Mike W.
|
|
|
Fire Review
|
Approved with Conditions
|
06/02/2022
|
05/24/2022
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Traffic Review
|
No Comments
|
06/02/2022
|
05/24/2022
|
|
Mike Weisenborn
|
|
|
Building Codes Review
|
Approved with Conditions
|
06/02/2022
|
05/24/2022
|
|
Mike Weisenborn
|
|
Miscellaneous Correction
Corrective Action Required
Deferred retaining wall designs must be reviewed and approved prior to construction.
|
|
Miscellaneous Correction
Corrective Action Required
*following comment added after initial review due to oversight.
1-1/2" water tap not available. Must be 2". To be field verified.
|
|
|
Planning Review
|
Corrections
|
05/17/2022
|
05/18/2022
|
|
Hector Soto Jr.
|
|
Corrective Action Required
DIMENSION PLAN. Provide a dimension plan for the site in order for staff to verify that minimum standards such as drive aisle widths, parking space dimensions, building setbacks, etc.
The FDP response letter indicates that this item is addressed by the following: "Please see Architectural sheets". However, no new architectural sheets were uploaded for review.
|
|
Corrective Action Required
LAND USE SCHEDULE. Provide a table that includes the following information:
- Site Area (sq. ft.)
- Building Area (sq. ft.)
- Floor Area Ratio
- # of Required and Proposed Parking Spaces
- Impervious Coverage (sq. ft. and % of site)
- Open Space
The FDP response letter indicates that this item is addressed by the following: "Please see Architectural sheets". However, no new architectural sheets were uploaded for review.
|
|
Corrective Action Required
LIGHTING. Provide manufacturer specifications for all proposed pole light fixtures and wallpacks for review.
The FDP response letter indicates that this item is addressed by the following: "Please see Lighting sheets". However, no new lighting sheets were uploaded for review.
|
|
Corrective Action Required
EXTERIOR MATERIAL. Provide a spec sheet for the proposed textured metal panel to be used on the building.
The FDP response letter indicates that this item is addressed by the following: "Please see Architectural sheets". However, no new architectural sheets were uploaded for review.
|
|
|
Engineering Review
|
Corrections
|
05/17/2022
|
05/17/2022
|
|
Loic Nguinguiri, E.I.
|
|
Corrective Action Required
Provide a 0.5’ minimum drop in flowline elevation between the incoming 18” pipe (S) and the outgoing 18” pipe (E) within storm structure 2-2.
|
|
Corrective Action Required
The City requires a 6-inch minimum layer of aggregate backfill below the bottom of the pipe. Show it in the trenching and backfill detail.
|
|
Corrective Action Required
The sump of the fire backflow prevention device can be drained through the means of an infiltration gallery (filled with clean rocks), a daylight discharge or a connection to an existing storm structure. Select the most suitable option. Both the daylight and the storm structure connection can be made by gravitational flow or pressurized flow (sump pump).
|
|
Corrective Action Required
Include the revised landscaping sheet(s) with the civil set of plans.
|
|
Corrective Action Required
Please provide a stormwater memorandum that discusses how the runoff from the D-Bat project site will be managed.
|
|
Corrective Action Required
In the SWPPP report, discuss the presence of endangered species or critical natural habitat. Make sure to revise the address and the project name shown as well. The scope of work shown in the SWPPP and on the civil plans must match.
|
|
Corrective Action Required
Update the Engineer’s Opinion of Probable Construction Cost (EOOPCC) sheet. Add a private sanitary, an ESC and a site preparation (clearing + grading) section. Also, revise the quantity for concrete pavement, aggregate base and precast curb inlet. Remove the water meter cost item too, since that one will be inserted in the fee worksheet separately with the tap fee.
|
|
|
Traffic Review
|
No Comments
|
05/17/2022
|
05/10/2022
|
|
Mike Weisenborn
|
|
|
Fire Review
|
Approved with Conditions
|
05/17/2022
|
05/10/2022
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Building Codes Review
|
Approved with Conditions
|
05/17/2022
|
05/10/2022
|
|
Mike Weisenborn
|
|
Miscellaneous Correction
Corrective Action Required
Deferred retaining wall designs must be reviewed and approved prior to construction.
|
|
|
Planning Review
|
Corrections
|
05/06/2022
|
05/09/2022
|
|
Hector Soto Jr.
|
|
Corrective Action Required
DIMENSION PLAN. Provide a dimension plan for the site in order for staff to verify that minimum standards such as drive aisle widths, parking space dimensions, building setbacks, etc.
|
|
Corrective Action Required
LAND USE SCHEDULE. Provide a table that includes the following information:
- Site Area (sq. ft.)
- Building Area (sq. ft.)
- Floor Area Ratio
- # of Required and Proposed Parking Spaces
- Impervious Coverage (sq. ft. and % of site)
- Open Space
|
|
Corrective Action Required
OIL AND GAS WELLS. Add a note regarding the presence of any active, inactive and/or capped oil and gas wells on the property. Cite the source of information used to make the determination. Missouri DNR has an online database that can be cited for said information.
|
|
Corrective Action Required
STREETS. Labe the ROW width for NE Town Centre Drive.
|
|
Corrective Action Required
EASEMENT. Show and label the limits of the shared access easement that will be platted for the drive surrounding the site.
|
|
Corrective Action Required
LIGHTING. Provide manufacturer specifications for all proposed pole light fixtures and wallpacks for review.
|
|
Corrective Action Required
ADA ACCESSIBLE. Provide a detail of the ADA parking space signage to be used at the head of each accessible parking space. The required signs shall be mounted a minimum 5' above finished grade, measured to the bottom of the sign.
|
|
Corrective Action Required
EXTERIOR MATERIAL. Provide a spec sheet for the proposed textured metal panel to be used on the building.
|
|
|
Building Codes Review
|
Approved with Conditions
|
05/05/2022
|
05/05/2022
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Deferred retaining wall designs must be reviewed and approved prior to construction.
|
|
|
Engineering Review
|
Corrections
|
05/05/2022
|
05/04/2022
|
|
Loic Nguinguiri, E.I.
|
|
Corrective Action Required
Throughout the set of plans, add the sheet title in the title block as shown in the sheet index.
|
|
Corrective Action Required
Throughout the set of plans, revise the information shown in the title block as applicable. The project name and address shown do not refer to the D-Bat project location.
|
|
Corrective Action Required
Revise the 1st general note shown on sheet C1.0 to state that “All construction, including the work done in the right of way, shall follow the City of Lee’s Summit’s Design and Construction manual”.
|
|
Corrective Action Required
Revise the 4th general note shown on sheet C1.1 to state that “All construction shall follow the City of Lee’s Summit’s Design and Construction manual”.
|
|
Corrective Action Required
Revise the 11th general note shown on sheet C1.0 and the 14th general note shown on sheet C1.1 to state that “The contractor shall contact the City’s Development Services Engineering Inspection to schedule a pre-construction meeting with a field engineering inspector prior to any land disturbance work at (816) 969-1200”.
|
|
Corrective Action Required
Add a note or revise the concrete pavement section to show aggregate base + subgrade extending 1’ beyond back of curb.
|
|
Corrective Action Required
Should perimeter stone be added by the sanitary lateral connection point as well in order to keep consistency around the building?
|
|
Corrective Action Required
On sheet C1.2, show how far the proposed retaining wall with handrail is supposed to extend along the west side of the building.
|
|
Corrective Action Required
Provide/include a construction detail for the proposed retaining wall(s).
|
|
Corrective Action Required
Connection of proposed 6” fire line to existing 12” water main must be via a 12” x 6” cut-in tee, while connection of proposed 4" sanitary sewer lateral to public 10" sanitary main must be via a 10" x 4" cut-in wye. Information showing the size of the existing water main, under utility note 3, needs to be revised as well.
|
|
Corrective Action Required
On the utility plan sheet, label the size of both the existing public water and sanitary mains.
|
|
Corrective Action Required
On the utility plan sheet, identify/label the applicable bends located along both the proposed 6” fire line and 2” domestic service line.
|
|
Corrective Action Required
Show/indicate how the sump of the proposed fire backflow prevention device will be drained.
|
|
Corrective Action Required
Sidewalk construction must not exceed an 2% cross-slope and an 8.33% running slope. Therefore, it is recommended that the sidewalks be designed to include construction tolerances, which respectively refer to design slopes of 1.5% and 7.5%. Revise/include this information within the ADA note shown throughout the set of plans. Also, make sure that the sidewalk details shown on sheet C2.4 meet this ADA sidewalk requirement.
|
|
Corrective Action Required
Since structure 2-2 is intended to be built as part of the mega storage building permit, shouldn’t sheet C3.4 indicate a connection to it instead? Revise accordingly and make sure to show structure 2-2 as an existing structure in profile view.
|
|
Corrective Action Required
The 100-year hydraulic grade line runs way above the crown of pipe and appears to be too close to the throat of curb inlets. APWA Section 5600 requires a minimum clearance of 0.5 feet below any openings to the ground. Therefore, private storm line 3 may need to be upsized in order to meet this APWA storm requirement.
|
|
Corrective Action Required
Provide a 0.5’ minimum drop in flowline elevation within every storm structure where the angle between the incoming and outgoing pipe is above 22.5 degrees.
|
|
Corrective Action Required
We acknowledge that storm structure 2-2 and commercial entrances, as per the Mega Storage building permit, will need to be built prior to construction of private storm line 3 and the concrete parking lot. Otherwise, the construction of those pre-infrastructures would become the responsibility of the applicant for the current FDP project.
|
|
Corrective Action Required
Include a trenching an backfill detail. The City requires a 12-inch thick layer of aggregate backfill over the top of utility pipe.
|
|
Corrective Action Required
Only ornamental tree varieties are allowed within public easements. A 5’ minimum setback is also necessary from edge of existing public utility to edge of proposed overstory tree. Review and verify that the landscaping plan meets those requirements.
|
|
Corrective Action Required
Please provide a stormwater memorandum.
|
|
Corrective Action Required
Please provide a SWPPP report and a Missouri DNR permit.
|
|
Corrective Action Required
Please provide an Engineer’s Opinion of Probable Construction Cost (EOOPCC) sheet.
|
|
|
Traffic Review
|
No Comments
|
05/05/2022
|
05/03/2022
|
|
Brad Cooley, P.E., RSPI
|
|
|
Fire Review
|
Approved with Conditions
|
05/05/2022
|
04/25/2022
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|