Planning Application Status

PL2021253




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2021253
Lakewood Business Center on I-470
Preliminary Plat
Preliminary Plat
Approved
07/06/2021
NORTH OAK SAFETY STORAGE, LLC
Locations
Contacts
NORTH OAK SAFETY STORAGE, LLC, Address:1120 NW EAGLE RIDGE BLVD, Phone:(816) 229-8115  
NORTH OAK SAFETY STORAGE, LLC, Address:1120 NW EAGLE RIDGE BLVD, Phone:(816) 229-8115  
POWELL CWM INC, Address:3200 S STATE ROUTE 291 BLDG 1, Phone:(816) 373-4800  
NORTH OAK SAFETY STORAGE LLC, Address:1120 NW EAGLE RIDGE BLVD  
Reviews
Review Type Outcome Est. Completion Date Completed
Traffic Review No Comments 11/29/2021 11/29/2021
Mike Weisenborn
Engineering Review Approved with Conditions 11/29/2021 11/29/2021
Gene Williams, P.E.
DE C&O #01 Eng Plans – FP/PP
Corrective Action Required
11/29/2021

All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final plat and approved prior to the approval of the final plat. All public infrastructure must be substantially complete, prior to the issuance of any building permits.
DE C&O #03 Eng & Insp Fees
Corrective Action Required
11/29/2021

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
DE C&O #04 Cert FA or Escrow
Corrective Action Required
11/29/2021

All subdivision-related public improvements must have a Certificate of Final Acceptance prior to approval of the final plat, unless security is provided in the manner set forth in the City's Unified Development Ordinance (UDO) Section 7.340. If security is provided, building permits may be issued upon issuance of a Certificate of Substantial Completion of the public infrastructure as outlined in Article 3, Division V, Sections 3.540 and 3.550 and Article 3, Division IV, Section 3.475 of the UDO, respectively.
DE C&O #06 Land Disturbance
Corrective Action Required
11/29/2021

A Land Disturbance Permit shall be obtained from the City if groundbreaking will take place prior to the issuance of a site development permit, building permit, or prior to the approval of the Final Development Plan / Engineering Plans.
DE C&O #07 Easements
Corrective Action Required
11/29/2021

All permanent off-site easements, in a form acceptable to the City, shall be executed and recorded with the Jackson County Recorder of Deeds prior to the issuance of a Certificate of Substantial Completion or approval of the final plat. A certified copy shall be submitted to the City for verification.
DE C&O #12 Cut & Fill
Corrective Action Required
11/29/2021

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
DE C&O #13 ADA Sidewalk Ramps
Corrective Action Required
11/29/2021

All ADA sidewalk ramps shall be constructed by the developer at the time the street is constructed.
DE C&O #14 Common Area Sidewalks
Corrective Action Required
11/29/2021

All sidewalks adjacent to a common area tract, unplatted land or any land where no structure is intended to be built, and is required, shall be constructed by the developer at the time the street is constructed.
Corrective Action Required
11/29/2021

Sanitary sewer analysis is currently under review by Water Utilities staff. Any recommendations concerning limitations on peak base flow from an industrial user shall be evaluated after a review of this report has been completed.
Fire Review No Comments 11/29/2021 11/23/2021
Jim Eden
Planning Review No Comments 11/29/2021 11/18/2021
Victoria Nelson
Traffic Review No Comments 08/31/2021 08/27/2021
Michael Park
Engineering Review Corrections 08/31/2021 08/27/2021
Gene Williams, P.E.
Corrective Action Required
08/26/2021

The sanitary sewer study was incomplete. The analysis shall include flows from existing pump station upstream of the site, as well as watershed downstream of the site. This analysis shall be extended to include the line(s) all the way to the west lake at Lakewood, just prior to entering the 30 inch line beneath the lake. Measured flow data is provided separately below for the pump station, as well as future build-out conditions for the future pump station(s).
Corrective Action Required
08/26/2021

Existing conditions: 14 million gallons per day (MGD) from the Tudor lift station upstream of the project. Anticipated flows within 10 years are 14 MGD from Tudor pump station, and 1.65 MGD from the Property Reserve, Inc. pump station #2 for a grand total of 15.65 MGD. Anticipated flows within 20 years are 14 MGD from the Tudor pump station, 1.65 from the Property Reserve, Inc. pump station #2, and 4.08 MGD from the Property Reserve, Inc. pump station #3.
Corrective Action Required
08/26/2021

Sanitary sewer analysis shall provide an analysis of the existing condition, the conditions within 10 years, and the conditions within 20 years. Each scenario shall be evaluated separately within the report.
Corrective Action Required
08/26/2021

As-builts may be utilized, or GIS records to perform the analysis described above.
Corrective Action Required
08/26/2021

The sanitary sewer analysis shall include all pumped flows contributing to the lines associated with this site, along with all drainage areas associated with the lines upstream and downstream of this site. It shall end at manhole #10-174 near the west lake at Lakewood.
Corrective Action Required
08/26/2021

Sanitary sewer analysis shall include diagrams of the drainage areas being analyzed, diagrams of the downstream and upstream contributers to flow, sanitary sewer lines being analyzed, profile views of the sanitary sewer lines downstream of the site, tables showing calculated flows, k vales, rainfall intensity, chart values, drainage area, time of concentration, and any other information necessary to support the conclusions and recommendations contained within the report.
Corrective Action Required
08/26/2021

Sanitary analysis discusses infiltration and inflow under Section 2.0 Methodology. The fourth sentence states the I&I is 0.381 cfs/acre using Figure 6501-3. Shouldn't this be 0.381 cfs? The chart presents I&I in cfs/acre, and our calculations and unit analysis yield 0.38 cfs rather than 0.38 cfs/acre.
Corrective Action Required
08/26/2021

Recommend the sanitary sewer analysis include the maximum peak base flow for the site within the conclusions and recommendations. As shown in the methodology section of the report, this value is 291,000 gallons per day. This figure shall be useful to a potential buyer to determine future allowances for industrial use.
Corrective Action Required
08/26/2021

Plan sheets were uploaded "one sheet at a time". For future submittals, please submit the Preliminary Plat as a single pdf multi-page document.
Corrective Action Required
08/26/2021

Sheet 1 of 4 "Preliminary Plat" sheet is illegible. It appears the document was folded to a point where a portion was not included, scanned, and uploaded, and portions of the document are missing near the fold.
Corrective Action Required
08/26/2021

Sheet 1 of 4 "Preliminary Plat" sheet is missing the ADA ramp across MacGuire at the location of the missing (i.e., folded) area on the sheet.
Corrective Action Required
08/26/2021

Storm drainage plan does not appear to include the 48 inch line entering the site from the southwest. In addition, it appears an open channel is planned between Lots 4/3 and 2/5. This open channel is also shown in an access easement and general utility easement. Why was this designed as an open channel? It would appear an enclosed undergound system would be better suited for this area. Why was the 48 inch pipe not shown? Why was a 30 inch pipe selected for the preliminary design between Lots 6 and 7? We realize this is a preliminary plan, but it does not appear realistic. Please re-evaluate and provide a more realistic design.
Corrective Action Required
08/27/2021

A wider easement is required for the 108 inch pipe contained within the northeast portion of the site. The 15 foot easement is not sufficient. The width of the easement should be increased by a minimum of 10 feet on the west side of the easement to accommodate the large pipe diameter.
Corrective Action Required
08/27/2021

A 42 inch pipe is shown along the west side of Lot 1. Why was this size selected? It would appear this pipe size is too small based on the upstream conditions. Please see previous comments concerning the lack of a realistic design to manage stormwater for the site. We realize this is a preliminary plan, but a realistic plan should be provided.
Corrective Action Required
08/27/2021

A 36 inch storm line is shown exiting Lot 2 to the northeast beneath the street. Why was this size specified? Please see previous comments concerning upstream conditions, and providing a realistic preliminary stormwater design.
Corrective Action Required
08/27/2021

Sanitary sewer manholes should be located at the centerline of roads. Please revise.
Corrective Action Required
08/27/2021

Utility sheet shows a 10 inch sanitary sewer from the site entering an existing 8 inch sanitary sewer. Our records indicate the existing downstream sanitary sewer at the west end of Maguire is a 10 inch rather than an 8 inch line. Was your evaluation based on a field survey? Was it based on as-built Record Drawings? If so, our Record Drawings indicate this line is a 10 inch.
Corrective Action Required
08/27/2021

Utility sheet shows a 10 inch sanitary sewer entering the existing manhole at an angle not allowed by the Design and Construction Manual. It shall be no more than a 90 degree deflection angle. It currently shows 110+/- degree deflection angle.
Corrective Action Required
08/27/2021

Water main along Maguire shall be looped to the existing water main on the west end of Maguire. Please revise.
Corrective Action Required
08/27/2021

Off-site grading activities appear to be shown on Lot 27, Lakewood Business Center on I-470 Plat K. This shall require the acquisition of suitable agreements with the adjacent property owner.
Planning Review Approved with Conditions 08/31/2021 08/24/2021
Victoria Nelson
Miscellaneous Correction
Resolved
08/20/2021

Oil and Gas Wells. Please state whether or not there are active, inactive, or capped wells within the area. Refer to DNR Well Database and reference the site.
Miscellaneous Correction
Resolved
08/20/2021

Building Line. Please label the 20’ building line along all ROW frontages.
Miscellaneous Correction
Resolved
08/20/2021

Sidewalk. A 5’ sidewalk is required along the NE Hagan Rd frontages of all proposed lots.
Corrective Action Required
08/24/2021

Please see attached document in cityview for the proposed addresses at this time.
Fire Review No Comments 08/31/2021 08/23/2021
Jim Eden
Engineering Review Corrections 07/23/2021 07/22/2021
Gene Williams, P.E.
Corrective Action Required
07/22/2021

Application is incomplete in terms of required plans and reports. Please see requirements for a preliminary plat application, which shall include a separate utility plan (i.e., sanitary sewer and water line layout), separate grading plan, separate stormwater layout plan, sanitary sewer analysis (in report form) of the downstream system (as discussed during the pre-application meeting), and stormwater detention memorandum.
Corrective Action Required
07/22/2021

Review of City files show the existing basin north of the project was designed to manage increased peak stormwater flows for the project, based on criteria in existence at that time. The report is dated Nov. 14, 2009, and titled "Storm Water Management Report Regional Detention Ponds Lemone-Smith Property". Please reference this document in the stormwater memorandum. This document is also available at City Hall if a review is deemed necessary by the engineer.
Corrective Action Required
07/22/2021

Utility lines shall be labeled as to sizing and material type. This includes sanitary sewer lines and water lines.
Corrective Action Required
07/22/2021

If any other use than office/warehouse use is being proposed (such as industrial or manufacturing), a sanitary sewer analysis shall be required.
Corrective Action Required
07/22/2021

ADA ramps are shown at the intersection of Maguire Blvd. and Cargo Dr. using an outdated method. This method of constructing ADA ramps is no longer allowed. Turning space cannot be placed at the bottom of the ramp, and each ramp shall be mono-directional. Acceptable examples can be provided upon request.
Corrective Action Required
07/22/2021

Acquisition of an off-site easement or off-site agreement may be necessary to place the storm line to the north.
Planning Review Corrections 07/23/2021 07/21/2021
Victoria Nelson
Miscellaneous Correction
Corrective Action Required
07/21/2021

Oil and Gas Wells. Please state whether or not there are active, inactive, or capped wells within the area. Refer to DNR Well Database and reference the site.
Miscellaneous Correction
Corrective Action Required
07/21/2021

Building Line. Please label the 20’ building line along all ROW frontages.
Miscellaneous Correction
Corrective Action Required
07/21/2021

Sidewalk. A 5’ sidewalk is required along the NE Hagan Rd frontages of all proposed lots.
Traffic Review No Comments 07/23/2021 07/20/2021
Brad Cooley, P.E., RSPI
Fire Review No Comments 07/23/2021 07/19/2021
Jim Eden
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Preliminary Plat fee $874.00 $874.00 Paid 07/06/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Planning Commission Meeting 12/16/2021 5:00 PM Council Chambers 12/16/2021 05:00 PM
Public Hearing Review
Approved
12/16/2021
Documents & Images
Date Uploaded File Type Document Name
07/06/2021 Application Form Preliminary Plat Application_Revision 0_07-06-2021
07/06/2021 Plans Preliminary Plat S_Revision 0_07-06-2021
07/06/2021 Plans Legal Description_Revision 0_07-06-2021
07/06/2021 Plans Closure Report_Revision 0_07-06-2021
07/06/2021 Receipt Receipt for transaction:2021-005390
07/26/2021 Letter Applicant Letter - PP (PP)
08/13/2021 Plans Plan Sheet 1of4
08/13/2021 Plans Plan Sheet 2of4
08/13/2021 Plans Plan Sheet 3of4
08/13/2021 Plans Plan Sheet 4of4
08/18/2021 Letter Response letter
08/18/2021 Engineer Report/Study Stormwater Memorandum
08/18/2021 Engineer Report/Study The Sanitary Study
08/24/2021 Activity Document Address Lakewood Business Center
08/31/2021 Letter Applicant Letter - PP (PP)
10/19/2021 Engineer Report/Study 2021_10_14 Sanitary Sewer Report_Rev01
10/19/2021 Plans 2021-10-18 Prelim Plat-Lakewood Business
10/19/2021 Letter Comment Response Letter Template 2
11/30/2021 Letter Applicant Letter - PP (PP)
12/09/2021 Letter Staff Letter PL2021-253 PP Lakewood Business Center on I-470.docx
12/09/2021 Public Notice Document PL2021-253 PP Lakewood Business Center on I-470 Map
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home