Permit Application Status

PRSUBD20246560


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20246560
Public Infrastructure
Issued - Partial
DISCOVERY PARK LEES SUMMIT LLC
DEVELOPMENT COMPLETE
The Crossings at Discovery Park - New streets, storm drainage, sewer and water mains for the Discovery Crossing development at Discovery Park. *Issued partial for work on/along Cobern Road to coincide with Public Works Colbern Road project
12/31/2024
10/03/2025
03/21/2026
Locations
Contacts
DISCOVERY PARK LEES SUMMIT LLC, Address:4220 PHILIPS FARM RD  
Jeffrey Bartz, Address:8455 College Blvd  
  
  
ORR STREETS LOFTS LLC, Address:4240 PHILIPS FARM ROAD #109  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review - Street and Storm Approved with Conditions 09/29/2025 09/29/2025
Susan Nelson, P.E.
DE C&O #03 Eng & Insp Fees
Corrective Action Required
09/29/2025

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
DE Contact Field Eng. Inspector
Corrective Action Required
09/29/2025

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
DE Engineers Estimate
Corrective Action Required
09/29/2025

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit.
Traffic Review - Streets No Comments 09/29/2025 09/26/2025
Erin Ralovo
Miscellaneous Correction
Corrective Action Required
09/25/2025

It still appears that the signal is to be included with these improvements, whick I do not believe is the intent. If the signal is to be included please include the necessary sheets, if not, lable improvements to be done by others or grey them back.
Engineering Review - Street and Storm Corrections 09/22/2025 09/22/2025
Susan Nelson, P.E.
Miscellaneous Correction
Corrective Action Required
09/22/2025

Submit Engineer’s Estimate of Probable Construction Costs.
Miscellaneous Correction
Corrective Action Required
09/22/2025

The existing and proposed R/W line weights are reversed on Sheets C201 and C202. Please revise.
Miscellaneous Correction
Corrective Action Required
09/22/2025

Add the dimension for the one-foot minimum extension of the compacted base/subgrade beyond back of curb shown in the pavement typical sections.
Miscellaneous Correction
Corrective Action Required
09/22/2025

Sheet C302: Label the proposed storm line and utilize bold weights to better delineate work within these plans. Why do you show two pipe elevations into Structure 1-A? Label this structure on the plans. Provide adequate fall through the structure.
Traffic Review - Streets Corrections 09/22/2025 09/22/2025
Erin Ralovo
Miscellaneous Correction
Corrective Action Required
09/22/2025

It still appears that the signal is to be included with these improvements, whick I do not believe is the intent. If the signal is to be included please include the necessary sheets, if not, lable improvements to be done by others or grey them back.
Engineering Review - Street and Storm Corrections 09/15/2025 09/11/2025
Susan Nelson, P.E.
Miscellaneous Correction
Corrective Action Required
09/11/2025

Teams meeting held and resubmittal to follow.
Engineering Review - Street and Storm Corrections 01/15/2025 01/15/2025
Susan Nelson, P.E.
Miscellaneous Correction
Corrective Action Required
01/15/2025

Reconfigure the plan submittals for this project to appropriately divide the public infrastructure and the private infrastructure. Project number PRSUBD20246560 will be utilized for the public improvement plans along Colbern Rd., including the roadway modifications and the signal work. A new project number for a Final Development Plan will be utilized for the private development including the private infrastructure. Please contact the project manager, Dan Fernandez, for details on the creation of a new project number for future submittals.
Miscellaneous Correction
Corrective Action Required
01/15/2025

Right-of-way and utility easements must be modified along Colbern Rd. to accommodate the widening for the turn lanes and the addition of the shared use path. Show and label all right-of-way and utility easements on all plan sets. The submitted plat must be revised to reflect these right-of-way and utility easements modifications, see specific comments from that submittal.
Miscellaneous Correction
Corrective Action Required
01/15/2025

Add the following notes to the cover sheets. - All construction shall follow the City of Lee's Summit Design and Construction Manual as adopted by Ordinance 5813. Where discrepancies exist between these plans and the Design and Construction Manual, the Design and Construction Manual shall prevail. - The contractor shall contact the City’s Development Services Engineering Inspection to schedule a pre-construction meeting with a Field Engineering Inspector prior to any land disturbance work at (816) 969-1200.
Miscellaneous Correction
Corrective Action Required
01/15/2025

Add the following notes to the typical section sheets. - All concrete materials for paving curb and gutter, sidewalks, paths, commercial driveways and other pavements shall conform to the KCMMB specifications. - Compacted aggregate base must extend a minimum of 1 foot beyond the back of curb.
Miscellaneous Correction
Corrective Action Required
01/15/2025

The waterline that will be lowered by others (Sta. 11+19.91, Elev. 965.30) will be reviewed when the private water plans are submitted. The waterline crossing is called out twice on Sheet C302, where one is a waterline and the other is a sanitary sewer line.
Miscellaneous Correction
Corrective Action Required
01/15/2025

Show compacted fill below the pipe where the existing grade is below the bottom of the pipe in Storm Sewer 6 profile. Verify the pipes and drop through all structures, including but not limited to Structure 1-A.
Miscellaneous Correction
Corrective Action Required
01/15/2025

According to the standard sidewalk details, the cross slope for ramps and all directions for turning spaces should be called out as no more than 1.5%, please revise.
Miscellaneous Correction
Corrective Action Required
01/15/2025

Please verify and note that only ornamental trees and shrubs may be planted within any easements.
Miscellaneous Correction
Corrective Action Required
01/15/2025

Submit the SWPPP and a copy of the MDNR Land Disturbance Permit.
Traffic Review - Traffic Signal Corrections 01/15/2025 01/13/2025
Erin Ralovo
Miscellaneous Correction
Corrective Action Required
01/13/2025

Signal plans were not received.
Traffic Review - Streets Corrections 01/15/2025 01/13/2025
Erin Ralovo
Miscellaneous Correction
Corrective Action Required
01/13/2025

The turn arrows are not installed per the City standards.
Miscellaneous Correction
Corrective Action Required
01/13/2025

Signal plans will need to be approved with these plans. Please submit the signal design for review.
Miscellaneous Correction
Corrective Action Required
01/13/2025

Please provide more detail on the different pavement types for Roundabout versus Crosswalks versus roadway.
Miscellaneous Correction
Corrective Action Required
01/13/2025

Signing in the roundabout is insufficient. Please refer to the MUTCD Figure 2B-22 for proper Roundabout signing.
Miscellaneous Correction
Corrective Action Required
01/13/2025

Crosswalks should be signed with the W11-2 signs on both sides of the approach. The verticle Stop for pedestrian signs can be used in the medians if desired.
Miscellaneous Correction
Corrective Action Required
01/13/2025

Are there stripes on either side of the crosswalks? If so lable them on the plan sheet.
Miscellaneous Correction
Corrective Action Required
01/13/2025

Please add Keep Right signs on the noses of the splitter islands on Colbern Rd.
Miscellaneous Correction
Corrective Action Required
01/13/2025

The 10 FT "sidewalk" should be built to SHare Use Path standards. This requires a 6" concrete surface.
Fees
Paid Fees Amount Paid Owing Date Paid
Paved Surface Inspection Fee $14,408.79 $14,408.79 Paid 10/06/2025
Storm Sewer Inspection Fee $640.53 $640.53 Paid 10/06/2025
Water Test Fee $200.00 $200.00 Paid 10/06/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Curb - Proof Roll Pending
Pavement-Proof Roll Pending
Pavement-Aggregate Base Pending
Pavement-Stabilized Subgrade Pending
Pavement-Curb Construction Pending
Sidewalk Inspection Pending
Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home