Permit Application Status

PRSUBD20214053


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20214053
Public Infrastructure
Final Acceptance
HUNT MIDWEST REAL ESTATE DEV INC
DEVELOPMENT COMPLETE
Full subdivision development
08/04/2021
03/02/2022
09/15/2023
Locations
Address
2829 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2825 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2821 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2817 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2813 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2809 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2805 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2759 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2755 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2751 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2747 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2743 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2739 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2735 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2731 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2734 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2742 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2750 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2222 SW CROWN DR, LEES SUMMIT, MO 64082

Address
2226 SW CROWN DR, LEES SUMMIT, MO 64082

Address
2230 SW CROWN DR, LEES SUMMIT, MO 64082

Address
2234 SW CROWN DR, LEES SUMMIT, MO 64082

Address
2233 SW CROWN DR, LEES SUMMIT, MO 64082

Address
2229 SW CROWN DR, LEES SUMMIT, MO 64082

Address
2225 SW CROWN DR, LEES SUMMIT, MO 64082

Address
2221 SW CROWN DR, LEES SUMMIT, MO 64082

Address
2218 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2222 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2226 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2230 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2234 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2233 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2229 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2225 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2221 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2217 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2213 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2835 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Address
2240 SW HEARTLAND CT, LEES SUMMIT, MO 64082

Address
2737 SW HEARTLAND RD, LEES SUMMIT, MO 64082

Property
273249

Property
273250

Property
273251

Property
273252

Property
273253

Property
273254

Property
273255

Property
273256

Property
273257

Property
273258

Property
273259

Property
273260

Property
273261

Property
273262

Property
273263

Property
273264

Property
273265

Property
273266

Property
273267

Property
273268

Property
273269

Property
273270

Property
273271

Property
273272

Property
273273

Property
273274

Property
273275

Property
273276

Property
273277

Property
273278

Property
273279

Property
273280

Property
273281

Property
273282

Property
273283

Property
273284

Property
273285

Property
273286

Property
273287

Property
273288

Address
2222 SW CROWN DR, LEES SUMMIT, MO 64082

Contacts
HUNT MIDWEST REAL ESTATE DEV INC, Address:8300 UNDERGROUND DR STE 200  
Reviews
Review Type Outcome Est. Completion Date Completed
Master Draingage As-built Review Approved 10/13/2022 06/06/2023
Mike Weisenborn
Licensed Contractors Approved 08/04/2021 02/06/2022
Mike Weisenborn
Engineering Review Approved with Conditions 01/26/2022 01/26/2022
Mike Weisenborn
Miscellaneous Correction
Corrective Action Required
01/26/2022

The 40 hour extended detention basin shall be constructed in the initial stage of the project, along with erosion and sediment control measures for the site. This basin is located in a depression to be formed within the floodplain fringe, and a Floodplain Development Permit shall be required prior to approval of any plans for the site.
Fees
Paid Fees Amount Paid Owing Date Paid
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 02/28/2022
91100C8-Sanitary Sewer Insp Fees $5,327.70 $5,327.70 Paid 02/28/2022
91100C9-Water Insp Fee $4,168.71 $4,168.71 Paid 02/28/2022
9110072-Water Test Fee $800.00 $800.00 Paid 02/28/2022
9110068-Storm Fee $5,827.93 $5,827.93 Paid 02/28/2022
9110081-Paved Surface Inspection Fee $6,867.57 $6,867.57 Paid 02/28/2022
9110071-Site Grading Fee $10,502.75 $10,502.75 Paid 02/28/2022
Outstanding Fees Amount Paid Owing Date Paid


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Grading/Excavation/Fill Inspection Partial 3/28/2022 3/28/2022 03/28/2022
Misc
Informational
03/14/2022
On 3.14.2022 Contractor, Randy Spalding Excavation were clearing and grubbing the project site. Clearing: Removing and disposing of all unwanted surface materials such as trees, brush, grass, weeds, downed trees, and other material. Grubbing: Removing and disposal of all unwanted vegetative matter from underground, such as stumps, roots, buried logs, and other debris. 3.15.2022 Mass grading throughout the project site. 3.16.2022 Mass Grading by Spalding Excavating throughout the entire project site. 3.17.2022 Mass grading throughout the project site b Randy Spalding Excavating. 3.18.2022 No Activity today. 3.21.2022 Mass grading by Spalding throughout the project site. Sanitary sewer pipe and manholes delivered to the project site.
Misc
Informational
03/28/2022
Spalding continues to mass grade and clear/move dirt on-site. 3/28/22 ES
Misc
Informational
06/21/2022
On Tuesday 6.21.2022 Spalding began grading the project site for roads. Redford filled in the holes made for water sampling. On Thursday 6.23.2022 Spalding Excavating is grading the pavement/roads/streets throughout the subdivision/project.
Misc
Informational
06/27/2022
On 6.27.2022 Spalding Excavating is grading in streets throughout the project site. Lots of dust and debris can be seen during the grading process therefore I requested a water truck to spray dust and dirt.
Misc
Informational
07/20/2022
7.20.2022 Spalding is cutting the grade for asphalt pavement application. Proof roll scheduled for tomorrow
Site Visit Partial 03/30/2022
Misc
Informational
03/30/2022
No work being performed. 3/30/22 ES
Sanitary Sewer Construction Inspection Partial 3/31/2022 03/31/2022
Misc
Informational
03/22/2022
On 3.22.2022 No Activity today Due to Rain. Construction site is very wet and muddy.
Misc
Informational
03/31/2022
Met with Patricik for initial tie-in for Little Blue.Steve Robbins 03/31/2022 4:32 PM
Misc
Informational
03/31/2022
Met with Patrick from Redford onsite. They were doing the initial tie in to LBVSD MH 50-011. There was a concrete collar poured around the lower portion of this manhole, they got approval from Dave Lilly with LBVSD to raise their point of entry in order to avoid coring through collar. This will change the incoming line from about a 9.5% to ~ 3% grade. 3/31/22 ES
Sanitary Sewer Construction Inspection Partial 4/1/2022 03/31/2022
Misc
Informational
03/31/2022
On 3.22.2022 No Activity today Due to Rain. Construction site is very wet and muddy.
Misc
Informational
03/31/2022
Met with Patricik for initial tie-in for Little Blue.Steve Robbins 03/31/2022 4:32 PM
Misc
Informational
03/31/2022
Met with Patrick from Redford onsite. They were doing the initial tie in to LBVSD MH 50-011. There was a concrete collar poured around the lower portion of this manhole, they got approval from Dave Lilly with LBVSD to raise their point of entry in order to avoid coring through collar. This will change the incoming flow from about a 9.5% to ~ 3% grade. 3/31/22 ES
Sanitary Sewer Construction Inspection Partial 03/31/2022
Misc
Informational
03/31/2022
On 3.22.2022 No Activity today Due to Rain. Construction site is very wet and muddy.
Misc
Informational
03/31/2022
Met with Patricik for initial tie-in for Little Blue.Steve Robbins 03/31/2022 4:32 PM
Misc
Informational
03/31/2022
Met with Patrick from Redford onsite. They were doing the initial tie in to LBVSD MH 50-011. There was a concrete collar poured around the lower portion of this manhole, they got approval from Dave Lilly with LBVSD to raise their point of entry in order to avoid coring through collar. This will change the incoming flow from about a 9.5% to ~ 3% grade. 3/31/22 ES On Monday 4.4.2022 Redford installed MH 1-1 and laid pipe to MH 1-2
Sanitary Sewer Construction Inspection Partial 04/05/2022
Misc
Informational
03/31/2022
On 3.22.2022 No Activity today Due to Rain. Construction site is very wet and muddy.
Misc
Informational
03/31/2022
Met with Patricik for initial tie-in for Little Blue.Steve Robbins 03/31/2022 4:32 PM
Misc
Informational
03/31/2022
Met with Patrick from Redford onsite. They were doing the initial tie in to LBVSD MH 50-011. There was a concrete collar poured around the lower portion of this manhole, they got approval from Dave Lilly with LBVSD to raise their point of entry in order to avoid coring through collar. This will change the incoming flow from about a 9.5% to ~ 3% grade. 3/31/22 ES
Misc
Informational
04/05/2022
Patrick’s crew was on-site working on sanitary lines 1 and 2. Spalding was also on-site continuing with grading. 4/5/22 ES On 4.6.2022 Wednesday Redford Construction laid up laterals for Lots 190 and 191 upto MH 1-3 On 4.7.2022 Thursday Redford Construction Laid up laterals for Lots 187, 188, 189, and 196 to MH 1-4 and poured inverts. On 4.8.2022 Friday Redford compacted Line 1.
Sanitary Sewer Construction Inspection Partial 04/11/2022
Misc
Informational
04/05/2022
On 3.22.2022 No Activity today Due to Rain. Construction site is very wet and muddy.
Misc
Informational
04/05/2022
Met with Patricik for initial tie-in for Little Blue.Steve Robbins 03/31/2022 4:32 PM
Misc
Informational
04/05/2022
Met with Patrick from Redford onsite. They were doing the initial tie in to LBVSD MH 50-011. There was a concrete collar poured around the lower portion of this manhole, they got approval from Dave Lilly with LBVSD to raise their point of entry in order to avoid coring through collar. This will change the incoming flow from about a 9.5% to ~ 3% grade. 3/31/22 ES
Misc
Informational
04/05/2022
Patrick’s crew was on-site working on sanitary lines 1 and 2. Spalding was also on-site continuing with grading. 4/5/22 ES
Misc
Informational
04/11/2022
4-11-22 AN crew is continuing to install sewer lines On Tuesday 4.12.2022 Redford installed MH 1-5 and MH 3-1 including laterals. Inverts were poured for line 2 and between MH 1-1 and MH 1-3. Laterals for lots 186 - 189 and 196 were installed. 4/13/2022 Redford installed Line 3 (no inverts poured) Laterals for lots 197 - 204 were installed. 4/14/2022 Redford installed sewer between MH 1-5 to MH 1-6 (no inverts poured). Laterals for lots 182 -185 and lot 204 were installed. 4/15/2022 MH 1-6 installed and all pipelines backfilled. 4.18.2022 MH 1-7 installed. Line 4 began installation MH 4-1 to MH 1-6
Site Visit Partial 04/20/2022
Misc
Informational
03/30/2022
No work being performed. 3/30/22 ES
Misc
Informational
04/20/2022
Redford on-site working on sanitary sewer. 4/20/22 ES
Sanitary Sewer Construction Inspection Partial 04/20/2022
Misc
Informational
04/11/2022
On 3.22.2022 No Activity today Due to Rain. Construction site is very wet and muddy.
Misc
Informational
04/11/2022
Met with Patricik for initial tie-in for Little Blue.Steve Robbins 03/31/2022 4:32 PM
Misc
Informational
04/11/2022
Met with Patrick from Redford onsite. They were doing the initial tie in to LBVSD MH 50-011. There was a concrete collar poured around the lower portion of this manhole, they got approval from Dave Lilly with LBVSD to raise their point of entry in order to avoid coring through collar. This will change the incoming flow from about a 9.5% to ~ 3% grade. 3/31/22 ES
Misc
Informational
04/11/2022
Patrick’s crew was on-site working on sanitary lines 1 and 2. Spalding was also on-site continuing with grading. 4/5/22 ES
Misc
Informational
04/11/2022
4-11-22 AN crew is continuing to install sewer lines
Misc
Informational
04/20/2022
Patrick’s crew was working on sanitary line 4. Running main from MH 4-2 to 4-3. Were working on getting 4-3 set and laterals installed off of line 4. 4/20/22 ES 4.22.2022 Redford completed Line 4 and poured inverts. Backfilled Line 4 and completed sanitary sewer construction.
Misc
Informational
05/16/2022
On 5.16.2022 Redford Construction elevated manhole rings above grade prior to asphalt application
Storm Sewer Construction Inspection Partial 05/12/2022
Misc
Informational
04/27/2022
On Wednesday 4.27.2022 Redford installed Line 1: storm boxes 1-3, 1-4, 1-5, 1-6, and 1-7 and backfilled. On 5.2.2022 Redford installed pipe between CI 1-6 and MH 5-1 and laid pipe up to structure 5-2 but did not have F-1 5-2. On 5.3.2022 Redford Construction installed pipe from CI 1-7 to structure FI 1-8 and piping from CI 2-1 to ES 1-1 including structures On 5.4.2022 Redford Construction installed Line 2 - CI 2-1, CI 2-2, CI 2-3, CI 2-4. Pipe collars were poured for Line 1, Line 2, and Line 5. On 5.6.2022 Redford received 6 storm boxes but no installation today because of heavy rains this week and very muddy conditions
Misc
Informational
05/09/2022
On 5.9.2022 Monday Redford set boxes 2-5, 3-1, 3-2, 4-1, and 4-2 On Tuesday 5.10.2022 Redford set box 5-2 field inlet. Poured pipe collars for Lines #1, 2, 3, and 4. Poured inverts for all boxes associated with those lines. 5.11.2022 Redford poured collar for Line #5. Installed Line #6 and boxes 6-2, 6-3, and 6-4.
Misc
Informational
05/12/2022
Installing storm on line 6. Working from box 6-4 towards 6-5
Storm Sewer Construction Inspection Partial 05/13/2022
Misc
Informational
05/12/2022
On Wednesday 4.27.2022 Redford installed Line 1: storm boxes 1-3, 1-4, 1-5, 1-6, and 1-7 and backfilled. On 5.2.2022 Redford installed pipe between CI 1-6 and MH 5-1 and laid pipe up to structure 5-2 but did not have F-1 5-2. On 5.3.2022 Redford Construction installed pipe from CI 1-7 to structure FI 1-8 and piping from CI 2-1 to ES 1-1 including structures On 5.4.2022 Redford Construction installed Line 2 - CI 2-1, CI 2-2, CI 2-3, CI 2-4. Pipe collars were poured for Line 1, Line 2, and Line 5. On 5.6.2022 Redford received 6 storm boxes but no installation today because of heavy rains this week and very muddy conditions
Misc
Informational
05/12/2022
On 5.9.2022 Monday Redford set boxes 2-5, 3-1, 3-2, 4-1, and 4-2 On Tuesday 5.10.2022 Redford set box 5-2 field inlet. Poured pipe collars for Lines #1, 2, 3, and 4. Poured inverts for all boxes associated with those lines. 5.11.2022 Redford poured collar for Line #5. Installed Line #6 and boxes 6-2, 6-3, and 6-4.
Misc
Informational
05/12/2022
Installing storm on line 6. Working from box 6-4 towards 6-5
Miscellaneous Correction
Informational
05/13/2022
Not working today, working at Hook Farms 2nd plat. 5/13/22 On 5.16.2022 Redford Construction completed Line 6 and poured concrete collars and inverts.
Misc
Informational
05/17/2022
On 5.17.2022 Redford backfilled Storm Line 6.
Sanitary Sewer - Air Test Passed 05/16/2022
Misc
Informational
05/16/2022
On 5.19.2022 I watched Redford conduct Air Test and pass MH 1-7 to MH 1-6; MH 1-6 to MH 4-1; MH 4-1 to MH 4-2; MH 1-6 to MH 1-5; and MH 1-5 to MH 3-1. On 5.20.2022 I watched Redford conduct Air Test and pass MH 1-1 to MH 1-2; MH 1-2 to MH 1-3; MH 1-3 to MH 2-1; MH 1-3 to MH 1-4; and MH 1-4 to MH 1-5
Sanitary Sewer - Mandrel Passed 05/16/2022
Misc
Informational
05/16/2022
On 5.20.2022 I observed Redford conduct Mandrel Test and pass for Lines 1,2,3, and 4.
Sanitary Sewer - Vacuum Passed 05/16/2022
Misc
Informational
05/16/2022
On 5.19.2022 I watched Redford conduct a Vacuum test and pass for MH 1-5, MH 1-6, MH 3-1, MH 4-1, MH 4-2 and and MH 4-3 On 5/20/2022 I watched Redford Construction conduct Vacuum Test and pass for MH 1-1, MH 1-2, MH 1-3, MH 1-4, and MH 2-1
Water Line - Construction Inspection Passed 06/08/2022
Misc
Informational
05/17/2022
On 5.17.2022 Redford installed approximately 520 LF of C900 water pipe of Line 1 and approximately 100 LF of Line 3.
Misc
Informational
05/20/2022
On 5.18.2022 Redford Construction installed approximately 400 LF of C900 pipe
Misc
Informational
05/20/2022
On 5.19.2022 Redford Construction completed installation of Line 2 approximately 400 LF of C900 pipe and approximately 300 LF of C900 pipe. 5/20/2022 Redford Construction installed approximately 450 LF of C900 pipe. Concrete blocks were installed for Lines 1, 2, and 3
Misc
Informational
06/03/2022
On 6.3.2022 New Water Main line tied to existing water main line in SW Hook Road. Concrete kicker is poured on Line 1 behind tee.
Misc
Informational
06/08/2022
On June 8, 2022 Redford has completed all the installation of the waterlines
Misc
Informational
06/10/2022
0n 6.10.2022 Redford pressurized line and inserted chlorine into the line and flushed line with water.
Misc
Informational
06/13/2022
On 6.13.2022 Redford dechlorinated the water main.
Misc
Informational
06/20/2022
On Monday 6/20/2022 Redford tied the water main into the existing system at SW Crown Drive 8x6 reducer and at SW Hook Road
Water Line - Coliform Test 1 Passed 06/20/2022
Water Line - Coliform Test 2 Passed 06/20/2022
Pavement-Curb Construction Partial 07/14/2022
Misc
Informational
07/14/2022
On 7.14.2022 JK Concrete Construction is installing curbing using KCMMB 4K (0-2”) SLAG TR concrete delivered by Geiger. Jaime Kidwell of JK Concrete was told by Geiger that dump tickets will be emailed Geiger no longer has additional copies of tickets. 7.15.2022 JK Concrete set up each storm box to pour the throats on Monday 7.18.2022
Misc
Informational
07/19/2022
On 7.19.2022 JK Concrete completed storm box corrections and pouring throats on the storm boxes. Spalding is backfilling behind the curbing. DJ 7.21.2022 Jaime Kidwell delivered concrete tickets and 221 cubic yards of concrete was used for curbs.
Site Visit Partial 07/18/2022
Misc
Informational
04/20/2022
No work being performed. 3/30/22 ES
Misc
Informational
04/20/2022
Redford on-site working on sanitary sewer. 4/20/22 ES
Misc
Informational
07/18/2022
7-18-22 RH. Arrived on site and no work for development services was working. 7.21.2022 Redford is adjusting manhole rings prior to asphalt placement
Misc
Informational
07/28/2022
7.28.2022 Redford installed roadblocks on Crown Drive.
Pavement-Proof Roll Passed 07/21/2022
Misc
Informational
07/08/2022
On 7.7.2022 Spalding used a 20.16 ton tandem truck to conduct a proof roll on chemical stabilization sub-grade pavement for streets and roads. The proof roll passed. 7.11.2022 Spalding used a 20 ton tandem truck to conduct a proof roll but failed because there were soft spots. On 7.13.2022 Spalding used a 19.58 ton tandem truck to conduct a proof roll on a rock sub-grade and the proof roll passed.
Misc
Informational
07/21/2022
On 7.21.2022 Spalding conducted a proof roll for asphalt pavement using a 20.54 ton tandem truck and pass the proof roll.
Pavement-Aggregate Base Partial 07/22/2022
Misc
Informational
03/22/2022
On 3.22.2022 No Activity today due to the rain. On 7.8.2022 Spalding installed rock sub-grade on top of chemical stabilization after using a 20.16 ton tandem truck to perform proof roll and pass proof roll on 7.7.2022
Misc
Informational
07/22/2022
On 7.22.2022 Superior Bowen applied 1,432.03 tons of Type 5 RC 40% base asphalt On 7.23.2022 Superior Bowen applied 830.15 tons of Type 5 V surface asphalt. Testing by CMTG Testing.
Erosion Control Inspection Failed 07/26/2022
Misc
Informational
03/14/2022
On Monday 3.14.2022 Contractor, Welch Silt Fence and Erosion Control installed erosion and sediment control measures.
Misc
Corrective Action Required
07/26/2022
7.26.2022 Mud is on the roads
Erosion Control Inspection Passed 8/15/2022 8/15/2022 08/15/2022
Misc
Informational
07/26/2022
On Monday 3.14.2022 Contractor, Welch Silt Fence and Erosion Control installed erosion and sediment control measures.
Misc
Corrective Action Required
07/26/2022
7.26.2022 Mud is on the roads
Misc
Informational
08/15/2022
8.15.2022 inlet protection is correctly installed. Vegetation is established.
Pavement-Aggregate Base Passed 8/15/2022 8/15/2022 08/15/2022
Misc
Informational
08/15/2022
8.15.2022 Superior Bowen completed installation and appears to be installed according to plans.
Pavement-Stabilized Subgrade Passed 8/15/2022 8/15/2022 08/15/2022
Misc
Informational
08/15/2022
8.15.2022 Spalding prepared subgrade
Sanitary Sewer Construction Inspection Passed 4/15/2022 4/15/2022 08/15/2022
Misc
Informational
04/20/2022
On 3.22.2022 No Activity today Due to Rain. Construction site is very wet and muddy.
Misc
Informational
04/20/2022
Met with Patricik for initial tie-in for Little Blue.Steve Robbins 03/31/2022 4:32 PM
Misc
Informational
04/20/2022
Met with Patrick from Redford onsite. They were doing the initial tie in to LBVSD MH 50-011. There was a concrete collar poured around the lower portion of this manhole, they got approval from Dave Lilly with LBVSD to raise their point of entry in order to avoid coring through collar. This will change the incoming flow from about a 9.5% to ~ 3% grade. 3/31/22 ES
Misc
Informational
04/20/2022
Patrick’s crew was on-site working on sanitary lines 1 and 2. Spalding was also on-site continuing with grading. 4/5/22 ES
Misc
Informational
04/20/2022
4-11-22 AN crew is continuing to install sewer lines
Misc
Informational
04/20/2022
Patrick’s crew was working on sanitary line 4. Running main from MH 4-2 to 4-3. Were working on getting 4-3 set and laterals installed off of line 4. 4/20/22 ES
Sanitary Sewer - Camera Test Passed 5/19/2022 5/19/2022 08/17/2022
Misc
Informational
08/17/2022
5.19.2022 Redford conducted Air and Vacuum testing of sanitary sewer system 5.20.2022 Redford conducted Air and Vacuum testing of sanitary sewer system and mandrel were pulled.
ESC - (Vegetation/Ground Cover) Failed 8/16/2022 8/16/2022 08/17/2022
Misc
Informational
08/17/2022
8.17.2022 Contractor needs to install inlet protection
Site Visit Complete 8/15/2022 8/15/2022 08/18/2022
Misc
Informational
07/18/2022
No work being performed. 3/30/22 ES
Misc
Informational
07/18/2022
Redford on-site working on sanitary sewer. 4/20/22 ES
Misc
Informational
07/18/2022
7-18-22 RH. Arrived on site and no work for development services was working.
Misc
Informational
08/15/2022
8.15.2022 JK Concrete installed handicap ramps using KCMMB 4K PSI (3” - 5” SLUMP) 8.18.2022 JK Concrete installed handicap ramps using KCMMB 4K (3” - 5” SLUMP) SLAG TR
Site Visit Partial 08/22/2022
Misc
Informational
08/15/2022
No work being performed. 3/30/22 ES
Misc
Informational
08/15/2022
Redford on-site working on sanitary sewer. 4/20/22 ES
Misc
Informational
08/15/2022
7-18-22 RH. Arrived on site and no work for development services was working.
Misc
Informational
08/15/2022
8.15.2022 JK Concrete installed handicap ramps 8-22-22 RH. No work on site for development today.
Site Visit Partial 08/23/2022
Misc
Informational
08/22/2022
No work being performed. 3/30/22 ES
Misc
Informational
08/22/2022
Redford on-site working on sanitary sewer. 4/20/22 ES
Misc
Informational
08/22/2022
7-18-22 RH. Arrived on site and no work for development services was working.
Misc
Informational
08/22/2022
8.15.2022 JK Concrete installed handicap ramps 8-22-22 RH. No work on site for development today. 8-23-22 RH. No work on site for development today.
Sidewalk Inspection Partial 08/23/2022
Misc
Informational
08/23/2022
8-23-22 RH. Sidewalk at entrance to site was formed up and aggregate was placed and compacted. Concrete was then poured that afternoon.
Sidewalk Inspection Passed 08/24/2022
Misc
Informational
08/23/2022
8-23-22 RH. Sidewalk at entrance to site was formed up and aggregate was placed and compacted. Concrete was then poured that afternoon. 8-24-22 RH. Sidewalk meets LS and ADA specification.
Pavement-Curb Construction Passed 8/16/2022 8/16/2022 08/25/2022
Misc
Informational
07/14/2022
On 7.14.2022 JK Concrete Construction is installing curbing using KCMMB 4K (0-2”) SLAG TR concrete delivered by Geiger. Jaime Kidwell of JK Concrete was told by Geiger that dump tickets will be emailed Geiger no longer has additional copies of tickets. 8-25-22 RH. Completed.
Pavement-Proof Roll Passed 7/21/2022 7/21/2022 08/25/2022
Misc
Informational
07/13/2022
On 7.7.2022 Spalding used a 20.16 ton tandem truck to conduct a proof roll on chemical stabilization sub-grade pavement for streets and roads. The proof roll passed. 7.11.2022 Spalding used a 20 ton tandem truck to conduct a proof roll but failed because there were soft spots. On 7.13.2022 Spalding used a 19.58 ton tandem truck to conduct a proof roll on a rock sub-grade and the proof roll passed. 8-25-22 RH. Proof Roll was complete.
Site Visit Partial 08/25/2022
Misc
Informational
08/23/2022
No work being performed. 3/30/22 ES
Misc
Informational
08/23/2022
Redford on-site working on sanitary sewer. 4/20/22 ES
Misc
Informational
08/23/2022
7-18-22 RH. Arrived on site and no work for development services was working.
Misc
Informational
08/23/2022
8.15.2022 JK Concrete installed handicap ramps 8-22-22 RH. No work on site for development today. 8-23-22 RH. No work on site for development today. 8-25-22 RH. No work on site today.
Site Visit Partial 08/30/2022
Misc
Informational
08/25/2022
No work being performed. 3/30/22 ES
Misc
Informational
08/25/2022
Redford on-site working on sanitary sewer. 4/20/22 ES
Misc
Informational
08/25/2022
7-18-22 RH. Arrived on site and no work for development services was working.
Misc
Informational
08/25/2022
8.15.2022 JK Concrete installed handicap ramps 8-22-22 RH. No work on site for development today. 8-23-22 RH. No work on site for development today. 8-25-22 RH. No work on site today. 8-30-22 RH. No work on site since 8-25-22.
Site Visit Partial 09/06/2022
Misc
Informational
08/30/2022
No work being performed. 3/30/22 ES
Misc
Informational
08/30/2022
Redford on-site working on sanitary sewer. 4/20/22 ES
Misc
Informational
08/30/2022
7-18-22 RH. Arrived on site and no work for development services was working.
Misc
Informational
08/30/2022
8.15.2022 JK Concrete installed handicap ramps 8-22-22 RH. No work on site for development today. 8-23-22 RH. No work on site for development today. 8-25-22 RH. No work on site today. 8-30-22 RH. No work on site since 8-25-22. 9-6-22 RH. No work for development since 8-30-22.
Erosion Control Inspection Partial 09/06/2022
Misc
Informational
09/06/2022
9-6-22 RH. Erosion control is up and in working order.
Storm Sewer Construction Inspection Passed 10/18/2022
Misc
Informational
05/13/2022
On Wednesday 4.27.2022 Redford installed Line 1: storm boxes 1-3, 1-4, 1-5, 1-6, and 1-7 and backfilled. On 5.2.2022 Redford installed pipe between CI 1-6 and MH 5-1 and laid pipe up to structure 5-2 but did not have F-1 5-2. On 5.3.2022 Redford Construction installed pipe from CI 1-7 to structure FI 1-8 and piping from CI 2-1 to ES 1-1 including structures On 5.4.2022 Redford Construction installed Line 2 - CI 2-1, CI 2-2, CI 2-3, CI 2-4. Pipe collars were poured for Line 1, Line 2, and Line 5. On 5.6.2022 Redford received 6 storm boxes but no installation today because of heavy rains this week and very muddy conditions
Misc
Informational
05/13/2022
On 5.9.2022 Monday Redford set boxes 2-5, 3-1, 3-2, 4-1, and 4-2 On Tuesday 5.10.2022 Redford set box 5-2 field inlet. Poured pipe collars for Lines #1, 2, 3, and 4. Poured inverts for all boxes associated with those lines. 5.11.2022 Redford poured collar for Line #5. Installed Line #6 and boxes 6-2, 6-3, and 6-4.
Misc
Informational
05/13/2022
Installing storm on line 6. Working from box 6-4 towards 6-5
Miscellaneous Correction
Informational
05/13/2022
Not working today, working at Hook Farms 2nd plat. 5/13/22
Misc
Informational
06/03/2022
On 6.3.2022 Redford construction installed the end section for the overflow structure to the creek. All storm sewers end sections were riprapped.
Grading/Excavation/Fill Inspection Passed 10/18/2022
Misc
Informational
03/28/2022
On 3.14.2022 Contractor, Randy Spalding Excavation were clearing and grubbing the project site. Clearing: Removing and disposing of all unwanted surface materials such as trees, brush, grass, weeds, downed trees, and other material. Grubbing: Removing and disposal of all unwanted vegetative matter from underground, such as stumps, roots, buried logs, and other debris. 3.15.2022 Mass grading throughout the project site. 3.16.2022 Mass Grading by Spalding Excavating throughout the entire project site. 3.17.2022 Mass grading throughout the project site b Randy Spalding Excavating. 3.18.2022 No Activity today. 3.21.2022 Mass grading by Spalding throughout the project site. Sanitary sewer pipe and manholes delivered to the project site.
Misc
Informational
03/28/2022
Spalding continues to mass grade and clear/move dirt on-site. 3/28/22 ES
Install Street and Stop Signs Passed 10/18/2022
Misc
Informational
10/18/2022
10-18-22 RH. Signs were installed.
Record Drawing Review Passed 10/20/2022
Misc
Informational
10/20/2022
10-20-22 RH. Reviewed plans in field and everything was in place and passed inspection.
Record Drawing Review Partial 11/17/2022 11/17/2022
Misc
Informational
11/17/2022
11-17-22 RH. Record drawings were reviewed and issues were brought up to Redford. Storm inlet needed adjusting due to it being to high or grade being off.
Record Drawing Review Partial 11/28/2022 11/28/2022
Misc
Informational
11/17/2022
11-17-22 RH. Record drawings were reviewed and issues were brought up to Redford. Storm inlet needed adjusting due to it being to high or grade being off. 11-28-22 RH. Still waiting for Redford to complete fixes.
Record Drawing Review Partial 12/5/2022 12/05/2022
Misc
Informational
11/28/2022
11-17-22 RH. Record drawings were reviewed and issues were brought up to Redford. Storm inlet needed adjusting due to it being to high or grade being off. 11-28-22 RH. Still waiting for Redford to complete fixes. 12-5-22 RH. Curbs still need replaced that were marked up.
Record Drawing Review Passed 12/12/2022 12/12/2022
Misc
Informational
12/05/2022
11-17-22 RH. Record drawings were reviewed and issues were brought up to Redford. Storm inlet needed adjusting due to it being to high or grade being off. 11-28-22 RH. Still waiting for Redford to complete fixes. 12-5-22 RH. Curbs still need replaced that were marked up.
Master Drainage As-built Inspection Passed 6/8/2023 06/08/2023
Misc
Informational
06/08/2023
6-8-23 RH. Master Drainage passed.
Documents & Images
Date Uploaded File Type Document Name
02/28/2022 Receipt Receipt for transaction:2022-001031
03/02/2022 Letter DE-Permit
03/08/2022 Approved Plans Retreat at Hook Farms, 2nd Plat Site Disturbance Plans Approved 3.8.22
03/08/2022 Approved Plans Retreat at Hook Farms, 2nd Plat Street & Storm Approved 3.8.22
03/08/2022 Approved Plans Retreat at Hook Farms, 2nd Plat, Sanitary Sewer Plans Approved 3.8.22
03/08/2022 Approved Plans Retreat at Hook Farms, 2nd Plat, Water Main Approved 3.8.22
03/23/2022 Letter INSPECTION SUMMARY
03/28/2022 Letter INSPECTION SUMMARY
03/30/2022 Letter INSPECTION SUMMARY
03/30/2022 Letter INSPECTION SUMMARY
03/31/2022 Letter INSPECTION SUMMARY
03/31/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/11/2022 Letter INSPECTION SUMMARY
04/20/2022 Letter INSPECTION SUMMARY
04/20/2022 Letter INSPECTION SUMMARY
04/22/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
05/12/2022 Letter INSPECTION SUMMARY
05/13/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter INSPECTION SUMMARY
06/07/2022 Letter INSPECTION SUMMARY
06/07/2022 Letter INSPECTION SUMMARY
06/07/2022 Letter INSPECTION SUMMARY
06/22/2022 Water Sample-Coliform test #1.passed
06/22/2022 Water Sample-Coliform test #2.passed
07/18/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/28/2022 Letter INSPECTION SUMMARY
07/28/2022 Letter INSPECTION SUMMARY
08/03/2022 Compressive Strength of Concrete_00001_Curb
08/03/2022 Compressive Strength of Concrete_00002_Curb
08/05/2022 Compaction Test Report_2022-07-06_Stabilized Subgrade
08/05/2022 Compaction Test Report_2022-07-08_Aggregate Base Course
08/23/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
08/24/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/30/2022 Letter INSPECTION SUMMARY
09/06/2022 Letter INSPECTION SUMMARY
09/06/2022 Letter INSPECTION SUMMARY
10/11/2022 Plans ERRONEOUS SEE NOTE 2022_10_11_HookFarms2nd-MASTER DRAINAGE PLAN
10/11/2022 Plans 22-10-11_RetreatHook2nd_Water_Asbuilts
10/11/2022 Plans 22-10-11_RetreatHook2nd_Sanitary_Asbuilts
10/11/2022 Plans 22-10-11_RetreatHook2nd_MasterDrainage_Asbuilts
10/11/2022 Plans 22-10-11_RetreatHook2nd_Street&Storm_Asbuilts
10/18/2022 Letter INSPECTION SUMMARY
10/18/2022 Letter INSPECTION SUMMARY
10/18/2022 Letter INSPECTION SUMMARY
10/20/2022 Letter INSPECTION SUMMARY
10/26/2022 Letter INSPECTION SUMMARY
11/01/2022 Plans 2022_11_01_RetreatatHookFarms2nd_MasterDrainagePlan
11/04/2022 Letter INSPECTION SUMMARY
11/11/2022 Plans 2022-11-11-RetreatatHookFarms2nd-MasterDrainagePlan
11/14/2022 Email RE_ PL2021165 The Retreat at Hook Farms 2nd Plat - As-Graded Master Drainage Plan Comments
11/14/2022 Letter INSPECTION SUMMARY
11/17/2022 Letter INSPECTION SUMMARY
11/28/2022 Letter INSPECTION SUMMARY
12/05/2022 Letter INSPECTION SUMMARY
12/12/2022 Letter INSPECTION SUMMARY
03/21/2023 Letter DE-Certificate of Substantial Completion Single Lot
03/22/2023 Retreat at Hook Farms 2nd Plat Substantial Completion
03/22/2023 Letter DE-Punch List
03/22/2023 Retreat at Hook Farms 2nd Plat Punch List
03/24/2023 Letter INSPECTION SUMMARY
06/08/2023 Letter INSPECTION SUMMARY
09/15/2023 Final Affidavit
09/15/2023 Retreat at Hook Farms 2nd Plat Maintenance Bond
09/15/2023 Letter DE-Certificate of Final Acceptance (Commercial)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.