Summary
PRRES20250471
Building Permit - Residential
Issued
NEW SINGLE FAMILY
NEW HOUSE - FINISHED AND UNFINISHED BASEMENT - COVERED PATIO
02/11/2025
02/19/2025
08/12/2025
Locations
Contacts
ELEVATE DESIGN & BUILD LLC, Address:350 SW LONGVIEW BLVD, Phone:(816) 622-8826  
Elevate Design + Build , Address:350 Longview Blvd.   
SARA@ELEVATEDESIGNBUILDKC.COM  
5 STAR MECHANICAL, LLC, Address:PO BOX 793, Phone:(816) 679-0375  
ELECTRICAL CONNECTIONS, Address:20112 HOPS CREEK DR, Phone:(816) 838-6946  
S&B Plumbing, Inc., Address:PO Box 101, Phone:(913) 850-3445  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 02/19/2025
Right of Way Permit Fee $85.00 $85.00 Paid 02/19/2025
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 02/19/2025
Water Tap Fee $3,973.00 $3,973.00 Paid 02/19/2025
Water Meter Fee $748.03 $748.03 Paid 02/19/2025
Valuation Fee New Single Family $1,335.38 $1,335.38 Paid 02/19/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Driveway Inspection Pending
Misc
Informational
07/10/2025
07/03/25 Jamie S, DW are compacted and formed. Approved to Pour. 07/10/25 Jamie S, DW does not have requested grout on the curb to patch damage of the curb during construction. All surfaces must be cleaned off for inspection. Call in for reinspection once curb is grouted.
Erosion Control Inspection Residential Pending
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
08/01/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -SPREAD GRAVEL FILTER -EROSION CONTROL NOT COMPLETED AT FRONT OF LOT
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
08/01/2025
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE -complete erosion control to lot lines
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
08/01/2025
7-28-25 Dustin A, EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 7-30-25 Dustin A, Sod is being laid , will check status at a later date
Misc
Informational
08/01/2025
Sod has been installed, erosion control is in place at time of inspection 8-1-25
Occupancy Inspection - Codes Residential Pending
Misc
Corrective Action Required
08/01/2025
2610 SW Firefly - driveway inspection needed - House numbers needed - Label sump outlet as non gfci - Seal all penetrations in exterior - Outlet needed within 10’ of AC unit - Obtain irrigation permit
Footing Inspection - Residential Passed 4/2/2025 4/2/2025 04/02/2025
Erosion Control Inspection Residential Failed 4/4/2025 4/4/2025 04/04/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
04/04/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -SPREAD GRAVEL FILTER -EROSION CONTROL NOT COMPLETED AT FRONT OF LOT
Sewer Service Inspection - R Passed 4/8/2025 4/8/2025 04/08/2025
Underslab Plumbing Inspection - Residential Failed 4/10/2025 4/10/2025 04/10/2025
Misc
Corrective Action Required
04/10/2025
Provide backfill for viewing.
Water Service Inspection - R Passed 4/10/2025 4/10/2025 04/10/2025
Erosion Control Inspection Residential Failed 04/10/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
04/04/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -SPREAD GRAVEL FILTER -EROSION CONTROL NOT COMPLETED AT FRONT OF LOT
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
04/10/2025
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE -complete erosion control to lot lines
Underslab Plumbing Inspection - Residential Passed 4/17/2025 4/17/2025 04/17/2025
Misc
Corrective Action Required
04/10/2025
Provide backfill for viewing.
All Rough Inspection - Residential Partial 5/8/2025 5/8/2025 05/08/2025
Misc
Informational
05/08/2025
Portal frame only front and back porch
Electrical Service Inspection Passed 5/23/2025 5/23/2025 05/23/2025
Gas Service Inspection - Residential Passed 5/23/2025 5/23/2025 05/23/2025
All Rough Inspection - Residential Failed 5/23/2025 5/23/2025 05/23/2025
Misc
Informational
05/08/2025
Portal frame only front and back porch
Misc
Corrective Action Required
05/23/2025
2610 SW Firefly - Check bolts are middle 1/3rd of bottom plate in garage - Security blocking at back door - Fire blocking at top of 2 cavities on right and of fireplace - Fire blocking around post beam connection in stairway landing - Fire blocking at wall to soffit at bottom of stairs - Check top of steel post to beam connections in basement for fire blocking - Check fire blocking at all exterior walls in basement - Secure wire in soffit in bedroom 4 downstairs - Strap top plate at vent pipe in master bathroom - Address electrical in return air basement - Provide 1 1/2” bearing on bottom of stairs Check top stringers - Address cable/cat wire in return air in basement
All Rough Inspection - Residential Passed 5/28/2025 5/28/2025 05/28/2025
Misc
Informational
05/23/2025
Portal frame only front and back porch
Misc
Resolved
05/28/2025
2610 SW Firefly
Piers/Caissons Inspection - Residential Passed 7/2/2025 7/2/2025 07/02/2025
Driveway Inspection Partial 7/3/2025 7/3/2025 07/03/2025
Misc
Informational
07/03/2025
07/03/25 Jamie S, DW are compacted and formed. Approved to Pour.
Driveway Inspection Failed 7/10/2025 7/10/2025 07/10/2025
Misc
Informational
07/03/2025
07/03/25 Jamie S, DW are compacted and formed. Approved to Pour. 07/10/25 Jamie S, DW does not have requested grout on the curb to patch damage of the curb during construction. All surfaces must be cleaned off for inspection. Call in for reinspection once curb is grouted.
Erosion Control Inspection Residential Failed 7/28/2025 7/28/2025 07/28/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
04/10/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -SPREAD GRAVEL FILTER -EROSION CONTROL NOT COMPLETED AT FRONT OF LOT
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
04/10/2025
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE -complete erosion control to lot lines
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/28/2025
7-28-25 Dustin A, EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Erosion Control Inspection Residential Partial 7/30/2025 7/30/2025 07/30/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/28/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -SPREAD GRAVEL FILTER -EROSION CONTROL NOT COMPLETED AT FRONT OF LOT
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
07/28/2025
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE -complete erosion control to lot lines
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/28/2025
7-28-25 Dustin A, EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 7-30-25 Dustin A, Sod is being laid , will check status at a later date
Plot Plan Inspection Passed 8/1/2025 08/01/2025
Erosion Control Inspection Residential Partial 8/1/2025 08/01/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/30/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -SPREAD GRAVEL FILTER -EROSION CONTROL NOT COMPLETED AT FRONT OF LOT
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
07/30/2025
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE -complete erosion control to lot lines
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/30/2025
7-28-25 Dustin A, EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 7-30-25 Dustin A, Sod is being laid , will check status at a later date
Misc
Informational
08/01/2025
Sod has been installed, erosion control is in place at time of inspection 8-1-25
Occupancy Inspection - Codes Residential Failed 8/1/2025 8/1/2025 08/01/2025
Misc
Corrective Action Required
08/01/2025
2610 SW Firefly - driveway inspection needed - House numbers needed - Label sump outlet as non gfci - Seal all penetrations in exterior - Outlet needed within 10’ of AC unit - Obtain irrigation permit
Documents & Images
Date Uploaded File Type Document Name
02/13/2025 Permit Codes Residential Plan Review
02/13/2025 Approved Plans APPROVED PLANS
02/13/2025 Approved Plans APPROVED PLOT PLAN
02/13/2025 Application Form Permit Application-25-2-13
02/13/2025 Permit Codes Residential Plan Review
02/19/2025 Permit DS Building Permit
02/19/2025 Receipt Receipt for transaction:2025-000997
02/28/2025 Approved Plans APPROVED REVISED PLANS
03/27/2025 145 Hook Farms - FTG-Stamped
04/02/2025 Letter INSPECTION SUMMARY
04/04/2025 Letter INSPECTION SUMMARY
04/08/2025 Letter INSPECTION SUMMARY
04/10/2025 Letter INSPECTION SUMMARY
04/10/2025 Letter INSPECTION SUMMARY
04/10/2025 Letter INSPECTION SUMMARY
04/17/2025 Letter INSPECTION SUMMARY
05/08/2025 Letter INSPECTION SUMMARY
05/23/2025 Letter INSPECTION SUMMARY
05/23/2025 Letter INSPECTION SUMMARY
05/23/2025 Letter INSPECTION SUMMARY
05/28/2025 Letter INSPECTION SUMMARY
07/02/2025 Letter INSPECTION SUMMARY
07/03/2025 Letter INSPECTION SUMMARY
07/10/2025 Letter INSPECTION SUMMARY
07/28/2025 Letter INSPECTION SUMMARY
07/28/2025 Letter INSPECTION SUMMARY
07/30/2025 Letter INSPECTION SUMMARY
07/31/2025 145 Hook Farm As Graded 2610 Firefly
07/31/2025 Plot Plan APPROVED PLOT PLAN
08/01/2025 Letter INSPECTION SUMMARY
08/01/2025 Letter INSPECTION SUMMARY
08/01/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home