Permit Application Status

PRRES20250160


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20250160
Building Permit - Residential
Issued
NEW SINGLE FAMILY
NEW HOUSE - FINSIHED AND UNFINISHED BASEMENT - COVERED PATIO
01/15/2025
02/27/2025
07/26/2025
Locations
Contacts
ELEVATE DESIGN & BUILD LLC, Address:350 SW LONGVIEW BLVD, Phone:(816) 622-8826  
Elevate Design + Build , Address:350 Longview Blvd.   
SARA@ELEVATEDESIGNBUILDKC.COM  
5 STAR MECHANICAL, LLC, Address:PO BOX 793, Phone:(816) 679-0375  
ELECTRICAL CONNECTIONS, Address:20112 HOPS CREEK DR, Phone:(816) 838-6946  
S&B Plumbing, Inc., Address:PO Box 101, Phone:(913) 850-3445  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 02/27/2025
Right of Way Permit Fee $85.00 $85.00 Paid 02/27/2025
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 02/27/2025
Water Tap Fee $3,973.00 $3,973.00 Paid 02/27/2025
Water Meter Fee $748.03 $748.03 Paid 02/27/2025
Valuation Fee New Single Family $1,358.13 $1,358.13 Paid 02/27/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Plot Plan Inspection Pending
Erosion Control Inspection Residential Pending
Footing Inspection - Residential Pending
Occupancy Inspection - Codes Residential Pending
Sidewalk Inspection Pending
Driveway Inspection Pending
Misc
Informational
07/30/2025
07/24/25 Jamie S, DW is formed and compacted. Approved to pour. 07/30/25 Jamie S, DW still has forms up. Forms need to be pulled before inspection. Call in for reinspection once forms are pulled.
Sewer Service Inspection - R Passed 4/8/2025 4/8/2025 04/08/2025
Water Service Inspection - R Partial 4/9/2025 4/9/2025 04/09/2025
Underslab Plumbing Inspection - Residential Passed 4/9/2025 4/9/2025 04/09/2025
Water Service Inspection - R Passed 4/9/2025 4/9/2025 04/09/2025
All Rough Inspection - Residential Partial 5/8/2025 5/8/2025 05/08/2025
Misc
Informational
05/08/2025
Portal frame only front and rear
Electrical Service Inspection Passed 6/5/2025 6/5/2025 06/05/2025
Gas Service Inspection - Residential Failed 6/5/2025 6/5/2025 06/05/2025
Misc
Corrective Action Required
06/05/2025
Gauge reading at 0
All Rough Inspection - Residential Failed 6/5/2025 6/5/2025 06/05/2025
Misc
Informational
05/08/2025
Portal frame only front and rear
Misc
Corrective Action Required
06/05/2025
2623 SW Firefly - Remove thermostat wire from return air duct - Address electrical outlet in return air duct
Gas Service Inspection - Residential Passed 6/6/2025 6/6/2025 06/06/2025
Misc
Corrective Action Required
06/05/2025
Gauge reading at 0
All Rough Inspection - Residential Passed 6/6/2025 6/6/2025 06/06/2025
Misc
Informational
06/05/2025
Portal frame only front and rear
Misc
Resolved
06/06/2025
2623 SW Firefly
Driveway Inspection Partial 7/24/2025 7/24/2025 07/24/2025
Misc
Informational
07/24/2025
07/24/25 Jamie S, DW is formed and compacted. Approved to pour.
Driveway Inspection Partial 7/31/2025 7/31/2025 07/30/2025
Misc
Informational
07/24/2025
07/24/25 Jamie S, DW is formed and compacted. Approved to pour. 07/30/25 Jamie S, DW still has forms up. Forms need to be pulled before inspection. Call in for reinspection once forms are pulled.
Documents & Images
Date Uploaded File Type Document Name
01/15/2025 Tax_Application-25-1-15
01/15/2025 Permit Application-25-1-15
01/15/2025 Permit Application-25-1-15
01/15/2025 Tax_Application-25-1-15
01/16/2025 Permit Codes Residential Plan Review
01/27/2025 Permit Codes Residential Plan Review
01/30/2025 Approved Plans APPROVED PLANS
01/30/2025 Plot Plan APPROVED PLOT PLAN
01/30/2025 Permit Codes Residential Plan Review
02/27/2025 Permit DS Building Permit
02/27/2025 Receipt Receipt for transaction:2025-001170
03/25/2025 168 Hook Farms - FTG-Stamped
04/08/2025 Letter INSPECTION SUMMARY
04/09/2025 Letter INSPECTION SUMMARY
04/09/2025 Letter INSPECTION SUMMARY
04/09/2025 Letter INSPECTION SUMMARY
04/29/2025 HP-25-04-02 HF168 Gresytsone Modern
04/29/2025 Approved Plans APPROVED PLANS
05/08/2025 Letter INSPECTION SUMMARY
06/05/2025 Letter INSPECTION SUMMARY
06/05/2025 Letter INSPECTION SUMMARY
06/05/2025 Letter INSPECTION SUMMARY
06/06/2025 Letter INSPECTION SUMMARY
06/06/2025 Letter INSPECTION SUMMARY
07/24/2025 Letter INSPECTION SUMMARY
07/30/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home