Permit Application Status

PRRES20243094


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20243094
Building Permit - Residential
Hold
NZC HOMES LLC
NEW SINGLE FAMILY
NEW HOUSE. FINISHED/UNFINISHED BASEMENT. COVERED DECK. STOP WORK ORDER generated on 04/18/2025 12:00 AM by username 'Dustin Agcopra'.
06/17/2024
07/29/2024
01/06/2025
Locations
Contacts
NICK ZVACEK CONSTRUCTION LLC, Address:1009 INDUSTRIAL DR, Phone:(816) 213-7204  
NZC HOMES LLC, Address:1009 INDUSTRIAL DR  
Dominick Zvacek, Address:1009 Industrial Drive, Phone:(816) 213-7204  
COMFORT SYSTEMS HTG/CLG, Address:128 W Markey Rd, Phone:(816) 322-1013  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
CENTURY PLUMBING, Address:14001 CENTURY LN, Phone:(816) 765-6066  
NZCONSTRUCTIONLLC@GMAIL.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331401-Water Tap Fee $3,973.00 $3,973.00 Paid 07/29/2024
8350015-Water Meter Fee $748.03 $748.03 Paid 07/29/2024
8331507-Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 07/29/2024
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 07/29/2024
7232302-Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 07/29/2024
9110078-Valuation Fee New Single Family $1,545.86 $1,545.86 Paid 07/29/2024
Outstanding Fees Amount Paid Owing Date Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
9110080-3rd and Subsequent Inspection Fee (Per Hour) $75.00 $0.00 $75.00 Not Paid
9110080-3rd and Subsequent Inspection Fee (Per Hour) $75.00 $0.00 $75.00 Not Paid


$225.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Plot Plan Inspection Pending
Occupancy Inspection - Codes Residential Pending
Piers/Caissons Inspection - Residential Pending
Misc
Corrective Action Required
08/29/2024
South most pier belled to 18” no 18” for full depth.
Driveway Inspection Pending
Misc
Informational
04/15/2025
4-7-25 Dustin A, dw is formed and compacted. Approved to pour . 4-15-25 Dustin A, Dw is poured. The saw cuts do not reach joints . Will need to be extended.
Erosion Control Inspection Residential Pending 4/18/2025
Misc
Corrective Action Required
11/26/2024
Erosion control in compliance
Erosion Control Inspection Residential Failed 8/7/2024 8/7/2024 08/07/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
08/07/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Maintain over grown vegetation
Sewer Service Inspection - R Passed 8/7/2024 08/07/2024
Erosion Control Inspection Residential Partial 8/8/2024 08/08/2024
DCM2 ESC DEFICIENT INSTALLATION
Resolved
08/08/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Maintain over grown vegetation
Misc
Informational
08/08/2024
Erosion control in compliance at time of inspection
Water Service Inspection - R Partial 8/9/2024 08/09/2024
Misc
Informational
08/09/2024
Partial pex from house to meter location
Water Service Inspection - R Passed 8/13/2024 08/13/2024
Misc
Resolved
08/13/2024
Partial pex from house to meter location
Underslab Plumbing Inspection - Residential Failed 8/15/2024 08/15/2024
Misc
Corrective Action Required
08/15/2024
Inspection denied gravel drive not installed erosion control not in compliance
Erosion Control Inspection Residential Failed 8/27/2024 08/15/2024
Misc
Resolved
08/15/2024
Erosion control in compliance at time of inspection
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
08/15/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
DCM5 ESC INSP DENIED
Corrective Action Required
08/15/2024
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION. Install gravel drive per city requirements
Underslab Plumbing Inspection - Residential Passed 8/27/2024 08/27/2024
Misc
Resolved
08/27/2024
Inspection denied gravel drive not installed erosion control not in compliance
Piers/Caissons Inspection - Residential Failed 8/27/2024 8/27/2024 08/27/2024
Misc
Corrective Action Required
08/27/2024
Piers not correct size Piers to be 18”x36” to plans
Piers/Caissons Inspection - Residential Not Ready 8/29/2024 08/29/2024
Misc
Corrective Action Required
08/27/2024
South most pier belled to 18” no 18” for full depth.
Gas Service Inspection - Residential Failed 11/26/2024 11/26/2024
Misc
Corrective Action Required
11/26/2024
-Complete gas to fireplace with rigid gas piping and retest
Electrical Service Inspection Passed 11/26/2024 11/26/2024
All Rough Inspection - Residential Failed 11/26/2024 11/26/2024 11/26/2024
Misc
Corrective Action Required
11/26/2024
-Nail siding along edges @ 6” oc -Protect plumbing at laundry -Protect dryer duct at top plates with BOCA plates -Strap exterior wall top plates where bored more than 50% ft g to throughout -Nail corner studs w/ 16d@12” oc or equivalent nailing -Fb fireplace and adjacent wall space from attic -Provide purlin support at max 4 ft intervals -Provide engineer recheck the roof beam size above great room. Currently (2)2x12 is installed; or support to stair bearing wall -Protect refrigerator water line with BOCA plate -Nail and install missing hangers at stair -Protect water service line in basement bedroom -Connect duct to basement bathroom fan -Anchor basement sill plates within 12” of break -Fb basement bedroom and bathroom wall from fur down ceiling space (pack in more insulation) -Solid block the cantilevered joists above bearing wall (Insulate cantilevered joists space first) -Bond gas piping -Protect wiring running across bottom of joists near panel **DO NOT INSULATE
Erosion Control Inspection Residential Partial 11/26/2024 11/26/2024
DCM3 ESC REQUIRED 2 DAY
Resolved
11/26/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Misc
Corrective Action Required
08/15/2024
Erosion control in compliance
All Rough Inspection - Residential Failed 12/6/2024 12/6/2024 12/06/2024
Misc
Corrective Action Required
11/26/2024
-Protect dryer duct at top plates with BOCA plates -Provide engineer recheck the roof beam size above great room. Currently (2)2x12 is installed; or support to stair bearing wall -Anchor basement sill plates within 12” of break -Fb basement bedroom and bathroom wall from fur down ceiling space (pack in more insulation) **DO NOT INSULATE
All Rough Inspection - Residential Failed 12/12/2024 12/12/2024
Misc
Corrective Action Required
12/06/2024
-Protect dryer duct at top plates with BOCA plates -Provide engineer recheck the roof beam size above great room. Currently (2)2x12 is installed; or support to stair bearing wall -Fb basement bedroom and bathroom wall from fur down ceiling space (pack in more insulation) **DO NOT INSULATE
All Rough Inspection - Residential Failed 12/16/2024 12/16/2024
Misc
Corrective Action Required
12/12/2024
-Protect dryer duct at top plates with BOCA plates -Provide engineer recheck the roof beam size above great room. Currently (2)2x12 is installed; or support to stair bearing wall -Fb basement bedroom and bathroom wall from fur down ceiling space (pack in more insulation) **DO NOT INSULATE
All Rough Inspection - Residential Failed 12/18/2024 12/18/2024 12/18/2024
Misc
Corrective Action Required
12/16/2024
-remove block from return air stud bay at basement bed hall wall -OK TO INSULATE
Gas Service Inspection - Residential Failed 12/18/2024 12/18/2024 12/18/2024
Misc
Resolved
12/18/2024
-Complete gas to fireplace with rigid gas piping and retest
G2417.4.1 Test Pressure
Corrective Action Required
12/18/2024
INSPECTION, TESTING AND PURGING. AMENDED 7-945. The test pressure to be used shall be not less than one and one-half times the proposed maximum working pressure, but not less than 10 psig (68.9kPa) irrespective of design pressure. For welded piping, and for piping carrying gas at pressures in excess of fourteen (14) inches water column pressure, the test pressure shall not be less than 60 psig. Where the test pressure exceeds 125 psig (862 kPa gauge), the test pressure shall not exceed a value that produces a hoop stress in the piping greater than 50 percent of the specified minimum yield strength of the pipe.
All Rough Inspection - Residential Failed 12/30/2024 12/30/2024 12/30/2024
Misc
Corrective Action Required
12/18/2024
-remove block from return air stud bay at basement front bed hall wall. Pan in furr down -OK TO INSULATE
Gas Service Inspection - Residential Passed 12/30/2024 12/30/2024 12/30/2024
G2417.4.1 Test Pressure
Resolved
12/30/2024
INSPECTION, TESTING AND PURGING. AMENDED 7-945. The test pressure to be used shall be not less than one and one-half times the proposed maximum working pressure, but not less than 10 psig (68.9kPa) irrespective of design pressure. For welded piping, and for piping carrying gas at pressures in excess of fourteen (14) inches water column pressure, the test pressure shall not be less than 60 psig. Where the test pressure exceeds 125 psig (862 kPa gauge), the test pressure shall not exceed a value that produces a hoop stress in the piping greater than 50 percent of the specified minimum yield strength of the pipe.
All Rough Inspection - Residential Passed 1/6/2025 1/7/2025 01/07/2025
Misc
Resolved
01/07/2025
-remove block from return air stud bay at basement front bed hall wall. Pan in furr down -OK TO INSULATE
Footing Inspection - Residential Passed 01/07/2025
Driveway Inspection Partial 4/7/2025 4/7/2025 04/07/2025
Misc
Informational
04/07/2025
4-7-25 Dustin A, dw is formed and compacted. Approved to pour .
Sidewalk Inspection Partial 4/7/2025 4/7/2025 04/07/2025
Misc
Informational
04/07/2025
4/7/25 Dustin A, sw is formed and compacted. Slopes are in compliance . Will need white cure and expansion joints at all joints. Approved to pour
Driveway Inspection Failed 4/15/2025 4/15/2025 04/15/2025
Misc
Informational
04/07/2025
4-7-25 Dustin A, dw is formed and compacted. Approved to pour . 4-15-25 Dustin A, Dw is poured. The saw cuts do not reach joints . Will need to be extended.
Sidewalk Inspection Passed 4/15/2025 4/15/2025 04/15/2025
Misc
Informational
04/07/2025
4/7/25 Dustin A, sw is formed and compacted. Slopes are in compliance . Will need white cure and expansion joints at all joints. Approved to pour 4-15-25 Dustin A, sw has been poured to city specs and slopes are in compliance. Passed
Erosion Control Inspection Residential Failed - Stop Work 4/15/2025 4/15/2025 04/18/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
04/15/2025
4-15-25 Dustin A, silt fence is down . EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 4-18-25 Dustin A, Erosion control has not been corrected
Documents & Images
Date Uploaded File Type Document Name
06/17/2024 106SFV_License_Tax_Application
06/21/2024 Permit Codes Residential Plan Review
07/10/2024 Permit Codes Residential Plan Review
07/22/2024 Plot Plan APPROVED PLOT PLAN
07/24/2024 106SVF_ResidentialPermitApplicationCorrected
07/25/2024 Approved Plans APPROVED PLANS
07/25/2024 Permit Codes Residential Plan Review
07/29/2024 Permit DS Building Permit
07/29/2024 Receipt Receipt for transaction: 2024-006332
07/31/2024 3RD Party Insp Report THIRD PARTY FOOTING INSPECTION
08/07/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/08/2024 Letter INSPECTION SUMMARY
08/08/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/13/2024 Letter INSPECTION SUMMARY
08/15/2024 Letter INSPECTION SUMMARY
08/15/2024 Letter INSPECTION SUMMARY
08/27/2024 Letter INSPECTION SUMMARY
08/27/2024 Letter INSPECTION SUMMARY
08/29/2024 Letter INSPECTION SUMMARY
11/26/2024 Letter INSPECTION SUMMARY
11/26/2024 Letter INSPECTION SUMMARY
11/26/2024 Letter INSPECTION SUMMARY
11/26/2024 Letter INSPECTION SUMMARY
12/06/2024 Letter INSPECTION SUMMARY
12/12/2024 Letter INSPECTION SUMMARY
12/16/2024 Letter INSPECTION SUMMARY
12/18/2024 Letter INSPECTION SUMMARY
12/18/2024 Letter INSPECTION SUMMARY
12/30/2024 Letter INSPECTION SUMMARY
12/30/2024 Letter INSPECTION SUMMARY
04/07/2025 Letter INSPECTION SUMMARY
04/07/2025 Letter INSPECTION SUMMARY
04/15/2025 Letter INSPECTION SUMMARY
04/15/2025 Letter INSPECTION SUMMARY
04/15/2025 Letter INSPECTION SUMMARY
04/15/2025 Letter INSPECTION SUMMARY
04/18/2025 Letter Stop Work Order
04/18/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home