Summary
PRRES20242428
Building Permit - Residential
Issued
SUMMIT VIEW FARMS DEVELOPMENT GROUP LLC
NEW SINGLE FAMILY
NEW HOUSE. FINISHED/UNFINISHED BASEMENT. WALKOUT BASEMENT. COVERED DECK. STOP WORK ORDER generated on 10/17/2024 12:00 AM by username 'Dustin Agcopra'. STOP WORK ORDER removed on 10/30/2024 12:00 AM by username 'Dustin Agcopra'.
05/14/2024
05/21/2024
11/13/2024
Locations
Contacts
WOOD BROTHERS CONSTRUCTION INC, Address:PO BOX 553, Phone:(816) 564-5024  
SUMMIT VIEW FARMS DEVELOPMENT GROUP LLC, Address:13450 E STATE ROUTE 150  
Wood Brothers Construction INC, Address:PO Box 553  
AFC HEATING AND COOLING, Address:824 NW MAIN ST , Phone:(816) 347-8388  
ICO Electric, Address:1810 NW 1000th St  
PREFERRED PLUMBING INC, Address:1664 NW 415TH RD, Phone:(816) 828-1680  
WOODBROTHERSINC@GMAIL.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331401-Water Tap Fee $3,760.00 $3,760.00 Paid 05/21/2024
8350015-Water Meter Fee $680.46 $680.46 Paid 05/21/2024
8331507-Sanitary Sewer Development Fee $2,159.00 $2,159.00 Paid 05/21/2024
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 05/21/2024
7232302-Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 05/21/2024
9110078-Valuation Fee New Single Family $1,716.88 $1,716.88 Paid 05/21/2024
Outstanding Fees Amount Paid Owing Date Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$75.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Plot Plan Inspection Pending
Occupancy Inspection - Codes Residential Pending
Sidewalk Inspection Pending
Sidewalk Inspection Pending
Erosion Control Inspection Residential Pending
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
03/12/2025
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. -MAINTAIN SILT FENCE AROUND ENTIRE LOT
Driveway Inspection Pending
Misc
Informational
05/19/2025
5-6-25 Dustin A, Dw was formed and compacted. Approved to 5-19-25 Dustin A, dw is poured to city specs. Cross slopes were checked and were in compliance at this time . Will check again when sidewalk is poured
Footing Inspection - Residential Passed 06/20/2024
Sewer Service Inspection - R Passed 6/20/2024 6/20/2024 06/20/2024
Water Service Inspection - R Passed 6/21/2024 06/21/2024
Underslab Plumbing Inspection - Residential Passed 7/1/2024 7/1/2024 07/01/2024
Erosion Control Inspection Residential Failed 07/01/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
07/01/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Repair down silt fence
Erosion Control Inspection Residential Failed 08/05/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
07/01/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Repair down silt fence Maintain overgrown vegetation
All Rough Inspection - Residential Failed 8/16/2024 8/16/2024 08/16/2024
Miscellaneous Correction
Corrective Action Required
08/16/2024
-Exterior garage portal sheeting needs to extend to both top plates to tie in -Back patio framing passed, but can not be covered until electrical has been installed and passed
Erosion Control Inspection Residential Failed 8/16/2024 08/16/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
08/05/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Repair down silt fence Maintain overgrown vegetation
Erosion Control Inspection Residential Failed 10/14/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
08/16/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Repair down silt fence Maintain overgrown vegetation 10-14-24 Dustin A, Still not fixed
Erosion Control Inspection Residential Failed - Stop Work 10/17/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
10/14/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Repair down silt fence Maintain overgrown vegetation 10-14-24 Dustin A, Still not fixed 10-17-24 Dustin A, not corrected and there is gravel in rd
Erosion Control Inspection Residential Partial 10/30/2024 10/30/2024 10/30/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
10/17/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Repair down silt fence Maintain overgrown vegetation 10-14-24 Dustin A, Still not fixed 10-17-24 Dustin A, not corrected and there is gravel in rd 10-30-24 Dustin A, Corrected.
Piers/Caissons Inspection - Residential Failed 11/1/2024 11/1/2024 11/01/2024
Misc
Corrective Action Required
11/01/2024
Two outer piers okay Center pier not to size
Piers/Caissons Inspection - Residential Passed 11/4/2024 11/4/2024 11/04/2024
Misc
Resolved
11/04/2024
Two outer piers okay Center pier not to size
Erosion Control Inspection Residential Failed 12/12/2024 12/12/2024 12/12/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
10/30/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Repair down silt fence Maintain overgrown vegetation 10-14-24 Dustin A, Still not fixed 10-17-24 Dustin A, not corrected and there is gravel in rd 10-30-24 Dustin A, Corrected.
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
12/12/2024
12-12-24 Dustin A, Silt fence is down EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Erosion Control Inspection Residential Partial 12/17/2024 12/17/2024 12/17/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
12/12/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Repair down silt fence Maintain overgrown vegetation 10-14-24 Dustin A, Still not fixed 10-17-24 Dustin A, not corrected and there is gravel in rd 10-30-24 Dustin A, Corrected.
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
12/12/2024
12-12-24 Dustin A, Silt fence is down EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 12-17-24 Dustin A, Silt fence has been repaired
Electrical Service Inspection Passed 1/16/2025 1/16/2025 01/16/2025
Gas Service Inspection - Residential Failed 1/16/2025 1/16/2025 01/16/2025
G2417.4.1 Test Pressure
Corrective Action Required
01/16/2025
INSPECTION, TESTING AND PURGING. AMENDED 7-945. The test pressure to be used shall be not less than one and one-half times the proposed maximum working pressure, but not less than 10 psig (68.9kPa) irrespective of design pressure. For welded piping, and for piping carrying gas at pressures in excess of fourteen (14) inches water column pressure, the test pressure shall not be less than 60 psig. Where the test pressure exceeds 125 psig (862 kPa gauge), the test pressure shall not exceed a value that produces a hoop stress in the piping greater than 50 percent of the specified minimum yield strength of the pipe.
G2417.4 Test pressure measurement
Corrective Action Required
01/16/2025
INSPECTION, TESTING AND PURGING. Test pressure shall be measured with a manometer or with a pressure-measuring device designed and calibrated to read, record, or indicate a pressure loss caused by leakage during the pressure test period. The source of pressure shall be isolated before the pressure tests are made. Mechanical gauges used to measure test pressures shall have a range such that the highest end of the scale is not greater than five times the test pressure.
All Rough Inspection - Residential Failed 1/16/2025 1/16/2025 01/16/2025
Miscellaneous Correction
Corrective Action Required
01/16/2025
Not inspected -Exterior garage portal sheeting needs to extend to both top plates to tie in
Misc
Corrective Action Required
01/16/2025
-anchor bolts to be in the middle 1/3 sill plate throughout home -anchor bolts to be writhing 12” of plate breaks/ends -provide tension straps per plans and code at pfh -seal top plate penetration at garage owners entry -missing stud between double and single car garage wall -fire block garage wall/foyer wall to ceiling space -seal top plate penetration in mudroom -provide full bearing for rafter to top plate at pantry exterior wall -seal top plate penetration at dining room -missing king stud right of great room slider -strap top plates where cut at master suite/great room exterior wall -seal top plate penetration right of bed 2 windows -purlin and purlin supports not to plans (see south half of home) -complete panning for hvac in furr downs in basement -secure electrical in furr down -fire block wall space to ceiling space at all furr downs in basement where missing -missing stud rec room around corner right of slider -missing stud packs each side of basement slider -all “B” columns to be of correct side
All Rough Inspection - Residential Not Ready 2/25/2025 2/25/2025 02/25/2025
Miscellaneous Correction
Corrective Action Required
01/16/2025
Not inspected -Exterior garage portal sheeting needs to extend to both top plates to tie in
Misc
Corrective Action Required
01/16/2025
-anchor bolts to be in the middle 1/3 sill plate throughout home -provide tension straps per plans and code at pfh -seal top plate penetration at garage owners entry -seal top plate penetration in mudroom -seal top plate penetration at dining room -seal top plate penetration right of bed 2 windows -purlin and purlin supports not to plans (see south half of home) no plans on site to check -complete panning for hvac in furr downs in basement -secure electrical in furr down -fire block wall space to ceiling space at all furr downs in basement where missing -missing stud packs each side of basement slider (no plans on site to check ) -all “B” columns to be of correct side (no plans on site to check)
Gas Service Inspection - Residential Failed 2/25/2025 2/25/2025 02/25/2025
G2417.4.1 Test Pressure
Corrective Action Required
01/16/2025
INSPECTION, TESTING AND PURGING. AMENDED 7-945. The test pressure to be used shall be not less than one and one-half times the proposed maximum working pressure, but not less than 10 psig (68.9kPa) irrespective of design pressure. For welded piping, and for piping carrying gas at pressures in excess of fourteen (14) inches water column pressure, the test pressure shall not be less than 60 psig. Where the test pressure exceeds 125 psig (862 kPa gauge), the test pressure shall not exceed a value that produces a hoop stress in the piping greater than 50 percent of the specified minimum yield strength of the pipe. (Pressure was at 6psi)
G2417.4 Test pressure measurement
Corrective Action Required
01/16/2025
INSPECTION, TESTING AND PURGING. Test pressure shall be measured with a manometer or with a pressure-measuring device designed and calibrated to read, record, or indicate a pressure loss caused by leakage during the pressure test period. The source of pressure shall be isolated before the pressure tests are made. Mechanical gauges used to measure test pressures shall have a range such that the highest end of the scale is not greater than five times the test pressure.
All Rough Inspection - Residential Failed 3/12/2025 3/12/2025 03/12/2025
Miscellaneous Correction
Corrective Action Required
02/25/2025
Not inspected -Exterior garage portal sheeting needs to extend to both top plates to tie in
Misc
Corrective Action Required
02/25/2025
-purlin and purlin supports not to plans (see south half of home, see above bed 2) -fire block wall space to ceiling space at all furr downs in basement where missing(see rec room) -missing stud packs each side of basement slider -all “B” columns to be of correct size
Erosion Control Inspection Residential Failed 03/12/2025
DCM2 ESC DEFICIENT INSTALLATION
Resolved
03/12/2025
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Repair down silt fence Maintain overgrown vegetation 10-14-24 Dustin A, Still not fixed 10-17-24 Dustin A, not corrected and there is gravel in rd 10-30-24 Dustin A, Corrected.
DCM3 ESC REQUIRED 2 DAY
Resolved
03/12/2025
12-12-24 Dustin A, Silt fence is down EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 12-17-24 Dustin A, Silt fence has been repaired
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
03/12/2025
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. -MAINTAIN SILT FENCE AROUND ENTIRE LOT
Gas Service Inspection - Residential Passed 3/12/2025 3/12/2025 03/12/2025
G2417.4.1 Test Pressure
Resolved
03/12/2025
INSPECTION, TESTING AND PURGING. AMENDED 7-945. The test pressure to be used shall be not less than one and one-half times the proposed maximum working pressure, but not less than 10 psig (68.9kPa) irrespective of design pressure. For welded piping, and for piping carrying gas at pressures in excess of fourteen (14) inches water column pressure, the test pressure shall not be less than 60 psig. Where the test pressure exceeds 125 psig (862 kPa gauge), the test pressure shall not exceed a value that produces a hoop stress in the piping greater than 50 percent of the specified minimum yield strength of the pipe. (Pressure was at 6psi)
G2417.4 Test pressure measurement
Resolved
03/12/2025
INSPECTION, TESTING AND PURGING. Test pressure shall be measured with a manometer or with a pressure-measuring device designed and calibrated to read, record, or indicate a pressure loss caused by leakage during the pressure test period. The source of pressure shall be isolated before the pressure tests are made. Mechanical gauges used to measure test pressures shall have a range such that the highest end of the scale is not greater than five times the test pressure.
All Rough Inspection - Residential Failed 3/21/2025 03/21/2025
Miscellaneous Correction
Corrective Action Required
03/12/2025
Not inspected -Exterior garage portal sheeting needs to extend to both top plates to tie in (Uncover for inspection)
Misc
Resolved
03/21/2025
-purlin and purlin supports not to plans (see south half of home, see above bed 2) -fire block wall space to ceiling space at all furr downs in basement where missing(see rec room) -missing stud packs each side of basement slider -all “B” columns to be of correct size
All Rough Inspection - Residential Passed 3/21/2025 3/21/2025 03/21/2025
Miscellaneous Correction
Resolved
03/21/2025
Not inspected -Exterior garage portal sheeting needs to extend to both top plates to tie in (Uncover for inspection)
Driveway Inspection Partial 5/6/2025 5/6/2025 05/06/2025
Misc
Informational
05/06/2025
5-6-25 Dustin A, Dw was formed and compacted. Approved to pour
Driveway Inspection Partial 5/20/2025 5/20/2025 05/19/2025
Misc
Informational
05/06/2025
5-6-25 Dustin A, Dw was formed and compacted. Approved to 5-19-25 Dustin A, dw is poured to city specs. Cross slopes were checked and were in compliance at this time . Will check again when sidewalk is poured
Documents & Images
Date Uploaded File Type Document Name
05/14/2024 Signed Excise tax App
05/17/2024 Permit Codes Residential Plan Review
05/17/2024 Application Form Signed Residental Permit Application_1 (4)
05/21/2024 Plot Plan APPROVED PLOT PLAN
05/21/2024 Approved Plans APPROVED PLANS
05/21/2024 Permit Codes Residential Plan Review
05/21/2024 Permit DS Building Permit
05/21/2024 Receipt Receipt for transaction:2024-003716
05/24/2024 M L Crose 3116 SW Summit View Trail LSMO 3rd Party Footing Inspection Report 5-23-24
06/20/2024 Letter INSPECTION SUMMARY
06/20/2024 Letter INSPECTION SUMMARY
06/21/2024 Letter INSPECTION SUMMARY
07/01/2024 Letter INSPECTION SUMMARY
07/01/2024 Letter INSPECTION SUMMARY
08/05/2024 Letter INSPECTION SUMMARY
08/16/2024 Letter INSPECTION SUMMARY
08/16/2024 Letter INSPECTION SUMMARY
10/14/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter Stop Work Order
10/17/2024 Letter Stop Work Order
10/30/2024 3RD Party Insp Report 2024_08_19_3116 SW Summit View Trail_LSMO_inspection discrepancy response_Sealed
10/30/2024 Letter INSPECTION SUMMARY
11/01/2024 Letter INSPECTION SUMMARY
11/04/2024 Letter INSPECTION SUMMARY
12/12/2024 Letter INSPECTION SUMMARY
12/12/2024 Letter INSPECTION SUMMARY
12/17/2024 Letter INSPECTION SUMMARY
01/16/2025 Letter INSPECTION SUMMARY
01/16/2025 Letter INSPECTION SUMMARY
01/16/2025 Letter INSPECTION SUMMARY
02/25/2025 Letter INSPECTION SUMMARY
02/25/2025 Letter INSPECTION SUMMARY
03/12/2025 2024_08_19_3116 SW Summit View Trail_LSMO_inspection discrepancy response_Sealed
03/12/2025 20250302_075053
03/12/2025 Letter INSPECTION SUMMARY
03/12/2025 Letter INSPECTION SUMMARY
03/12/2025 Letter INSPECTION SUMMARY
03/20/2025 invoice_94125465
03/20/2025 invoice_94121683
03/20/2025 AISC
03/20/2025 17425028870386873205785558539182
03/21/2025 Letter INSPECTION SUMMARY
03/21/2025 Letter INSPECTION SUMMARY
05/06/2025 Letter INSPECTION SUMMARY
05/06/2025 Letter INSPECTION SUMMARY
05/19/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home