Summary
PRRES20220580
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - FINISHED/UNFINISHED BASEMENT - COVERED DECK SUSPENDED PORCH AN ENGINEERED SOILS REPORT IS REQUIRED PRIOR TO ANY FOOTING APPROVAL
02/16/2022
03/08/2022
08/16/2022
01/11/2024
Locations
Contacts
WOOD BROTHERS CONSTRUCTION INC, Address:PO BOX 553, Phone:(816) 564-5024  
Wood Brothers Construction INC, Address:PO Box 553  
AFC HEATING AND COOLING, Address:824 NW MAIN ST , Phone:(816) 347-8388  
BMW ELECTRIC CO, Address:1238 W 31ST, Phone:(816) 289-3474  
PREFERRED PLUMBING INC, Address:1664 NW 415TH RD, Phone:(816) 828-1680  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,872.63 $1,872.63 Paid 03/08/2022
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 03/08/2022
7232302-Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 03/08/2022
8331507-Sewer Connection Fee $630.00 $630.00 Paid 03/08/2022
8331401-Water Tap Fee $3,655.00 $3,655.00 Paid 03/08/2022
8350015-Water Meter Fee $479.24 $479.24 Paid 03/08/2022
9110078-Valuation Fee New Single Family $364.28 $364.28 Paid 12/30/2022
$2,236.91
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 12/30/2022
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 01/04/2023
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 01/04/2023
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 01/04/2023
9110080-3rd and Subsequent Inspection Fee (Per Hour) $75.00 $75.00 Paid 02/01/2023
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 08/31/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 6/15/2022 06/15/2022
Misc
Informational
06/15/2022
third party inspection performed.
Underslab Plumbing Inspection - Residential Passed 6/15/2022 6/15/2022 06/15/2022
Sewer Service Inspection - R Passed 10/6/2022 (8:15) 10/6/2022 10/06/2022
Water Service Inspection - R Passed 10/10/2022 (1:00) 10/10/2022 10/10/2022
Gas Service Inspection - Residential Failed 12/19/2022 12/19/2022 12/19/2022
Misc
Corrective Action Required
12/19/2022
provide minimum 10 psi at gas pressure gauge for inspection bond gas line
Electrical Service Inspection Failed 12/19/2022 12/19/2022 12/19/2022
Misc
Corrective Action Required
12/19/2022
remove panel bonding screw from sub panel.
All Rough Inspection - Residential Failed 12/19/2022 12/19/2022 12/19/2022
Misc
Corrective Action Required
12/19/2022
-uncover garage portal frame nailing for inspection -fire block plumbing chase in garage to ceiling space -all anchor bolts to be in the middle 1/3 of sill plate -address holes in joists above mud room drilled closer than 2” to each other -address holes in joists above kitchen for electrical, pex & dwv closer than 2” to each other -missing nails in hanger above fridge area -furr out for dwv in pantry entry from kitchen -furr out for hood vent in pocket office -nail all exterior wall corners to code -uncover covered deck for inspection -missing hanger for double lvl above entry/living room -3 2x4 per plans under double lvl left of living room windows -missing hangers on double joist for overlook -fire block living room windows wall vertical to horizontal -fireblock fireplace walls right and left of fire place -secure gas line at fire place -support dwv in ceiling joist space right of entry every 48” OC traps and fitting not considered support -3 2x6 full length either side of front entry door per plans -solid block sheathing breaks at front door -missing nails in hangers above master bed -fire block wall space to ceiling space in master at window -protect NM With in 6’ of attic access -fire block bonus room wall space to master bedroom ceiling space -step to room E of bonus room greater than 7 3/4 -missing 3 1/2” sch 40 steel column in basement shown as D on plans -fire block vertically to horizontally in basement -fire block furr down ends in basement -provide support for furrdown ceiling joists in basement to floor joists above -seal penetrations in R/a joist space basement bedroom and hall to -remove bonding screw from sub panel -all anchor bolts in basement to be in the middle 1/3 of sill plate and tight -fireblock basement bath dead space to ceiling space -provide gas pressure gauge with minimum 10 psi -fire block under stairwell wall to furr down ceiling space Bond gas line -anchor bolts shall be located not more than 12 inches or less than seven bolt diameters from each end
Gas Service Inspection - Residential Failed 12/30/2022 12/30/2022
Misc
Corrective Action Required
12/19/2022
bond gas line
Electrical Service Inspection Failed 12/30/2022 12/30/2022 12/30/2022
Misc
Corrective Action Required
12/19/2022
remove panel bonding screw from sub panel.
All Rough Inspection - Residential Not Ready 12/30/2022 12/30/2022 12/30/2022
Misc
Corrective Action Required
12/19/2022
NO FURTHER INSPECTIONS UNTIL -GRAVEL FILTER IS MAINTAINED AT LOT ACCESS -CITY STAMPED PLANS ON SITE -ACCESS TO FRONT STOOP -fire block plumbing chase in garage to ceiling space -address holes in joists above mud room drilled closer than 2” to each other -address holes in joists above kitchen for electrical, pex & dwv closer than 2” to each other (Provide corrected engineer letter for above two items) -furr out for dwv in pantry entry from kitchen (now fire block) -furr out for hood vent in pocket office (now fire block) -nail all exterior wall corners to code (see pocket office) -uncover covered deck for inspection -missing hangers on double joist for overlook -fire block living room windows wall vertical to horizontal (missing multiple spaces , see furr out right and left of fireplace) -secure gas line at fire place -solid block sheathing breaks at front door -missing nails in hangers above master bed -protect NM With in 6’ of attic access -fire block bonus room wall space to master bedroom ceiling space(see bottom E wall) -missing 3 1/2” sch 40 steel column in basement shown as D on plans(no plans on site to check) -fire block vertically to horizontally in basement every 10’ -fire block furr down ends in basement -provide support for furrdown ceiling joists in basement to floor joists above -remove bonding screw from sub panel -all anchor bolts in basement to be in the middle 1/3 of sill plate and tight -fireblock basement bath dead space to ceiling space -fire block under stairwell wall to furr down ceiling space -Bond gas line -anchor bolts shall be located not more than 12 inches or less than seven bolt diameters from each end
Erosion Control Inspection Residential Failed 12/30/2022
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
12/30/2022
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
All Rough Inspection - Residential Not Ready 1/4/2023 1/4/2023 01/04/2023
Misc
Corrective Action Required
12/30/2022
NO FURTHER INSPECTIONS UNTIL -GRAVEL FILTER IS MAINTAINED AT LOT ACCESS -CITY STAMPED PLANS ON SITE -ACCESS TO FRONT STOOP -fire block plumbing chase in garage to ceiling space -address holes in joists above mud room drilled closer than 2” to each other -address holes in joists above kitchen for electrical, pex & dwv closer than 2” to each other (Provide corrected engineer letter for above two items) -furr out for dwv in pantry entry from kitchen (now fire block) -furr out for hood vent in pocket office (now fire block) -nail all exterior wall corners to code (see pocket office) -uncover covered deck for inspection -missing hangers on double joist for overlook -fire block living room windows wall vertical to horizontal (missing multiple spaces , see furr out right and left of fireplace) -secure gas line at fire place -solid block sheathing breaks at front door -missing nails in hangers above master bed -protect NM With in 6’ of attic access -fire block bonus room wall space to master bedroom ceiling space(see bottom E wall) -missing 3 1/2” sch 40 steel column in basement shown as D on plans(no plans on site to check) -fire block vertically to horizontally in basement every 10’ -fire block furr down ends in basement -provide support for furrdown ceiling joists in basement to floor joists above -remove bonding screw from sub panel -all anchor bolts in basement to be in the middle 1/3 of sill plate and tight -fireblock basement bath dead space to ceiling space -fire block under stairwell wall to furr down ceiling space -Bond gas line -anchor bolts shall be located not more than 12 inches or less than seven bolt diameters from each end
Electrical Service Inspection Not Ready 1/4/2023 1/4/2023 01/04/2023
Misc
Corrective Action Required
12/30/2022
remove panel bonding screw from sub panel.
Gas Service Inspection - Residential Not Ready 1/4/2023 1/4/2023 01/04/2023
Misc
Corrective Action Required
12/30/2022
bond gas line
All Rough Inspection - Residential Failed 1/10/2023 1/10/2023 01/10/2023
Misc
Corrective Action Required
01/04/2023
-fire block plumbing chase in garage to ceiling space -solid block sheathing breaks at front door -missing nails in hangers above master bed -fire block bonus room wall space to master bedroom ceiling space(see bottom E wall) -fire block vertically to horizontally in basement every 10’ -fire block furr down ends in basement -all anchor bolts in basement to be in the middle 1/3 of sill plate and tight -fireblock basement bath dead space to ceiling space -fire block under stairwell wall to furr down ceiling space -anchor bolts shall be located not more than 12 inches or less than seven bolt diameters from each end
Gas Service Inspection - Residential Passed 1/10/2023 1/10/2023 01/10/2023
Misc
Resolved
01/10/2023
bond gas line
Electrical Service Inspection Passed 1/10/2023 1/10/2023 01/10/2023
Misc
Resolved
01/10/2023
remove panel bonding screw from sub panel.
All Rough Inspection - Residential Failed 1/27/2023 1/27/2023 01/27/2023
Misc
Corrective Action Required
01/10/2023
-missing nails in hangers above master bed -fire block vertically to horizontally in basement every 10’ -fire block furr down ends in basement (see beam ends)
All Rough Inspection - Residential Passed 2/2/2023 2/2/2023 02/02/2023
Misc
Resolved
02/02/2023
-missing nails in hangers above master bed
Driveway Inspection Partial 4/18/2023 4/18/2023 04/18/2023
Misc
Informational
04/18/2023
4-18-23 RH. Driveway is formed up and aggregate was placed and compacted. Approved to pour.
Sidewalk Inspection Partial 5/1/2023 5/1/2023 04/18/2023
Misc
Informational
04/18/2023
4-18-23 RH. Sidewalk was formed up on the right side of house and aggregate was placed and compacted. Approved to pour.
Sidewalk Inspection Partial 4/25/2023 4/25/2023 04/25/2023
Misc
Informational
04/18/2023
4-18-23 RH. Sidewalk was formed up on the right side of house and aggregate was placed and compacted. Approved to pour. 4-25-23 RH. Sidewalk that was poured passed LS and ADA inspeciton.
Driveway Inspection Passed 4/25/2023 4/25/2023 04/25/2023
Misc
Informational
04/18/2023
4-18-23 RH. Driveway is formed up and aggregate was placed and compacted. Approved to pour. 4-25-23 RH. Driveway meets LS and ADA specification.
Sidewalk Inspection Partial 05/01/2023
Misc
Informational
04/25/2023
4-18-23 RH. Sidewalk was formed up on the right side of house and aggregate was placed and compacted. Approved to pour. 4-25-23 RH. Sidewalk that was poured passed LS and ADA inspeciton. 5-1-23 RH. Rest of sidewalk was formed up and aggregate was placed and compacted. Approved to pour.
Sidewalk Inspection Passed 5/24/2023 5/24/2023 05/24/2023
Misc
Informational
05/01/2023
4-18-23 RH. Sidewalk was formed up on the right side of house and aggregate was placed and compacted. Approved to pour. 4-25-23 RH. Sidewalk that was poured passed LS and ADA inspeciton. 5-1-23 RH. Rest of sidewalk was formed up and aggregate was placed and compacted. Approved to pour. 5-24-23 RH. Sidewalk meets LS and ADA specification.
Erosion Control Inspection Residential Failed 07/10/2023
DCM1 ESC REQUIRED NO FURTHER INSP
Resolved
07/10/2023
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/10/2023
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. MAINTAIN OVERGROWN VEGETATION
Occupancy Inspection - Codes Residential Failed 8/28/2023 8/28/2023 08/28/2023
Misc
Corrective Action Required
08/28/2023
-Erosion control failed -Sod not in place -Splash blocks not installed -Latch not working at sliding door -Spark rings are missing at tiled areas in kitchen -Missing all gutters and downspouts -Missing sump pump extension
Occupancy Inspection - Codes Residential Ready for Temp CO 8/31/2023 8/31/2023 08/31/2023
Misc
Corrective Action Required
08/28/2023
-address pending pier inspection -provide as graded plot plan -Splash blocks not installed -gutters being installed
Piers/Caissons Inspection - Residential Passed 01/11/2024
Plot Plan Inspection Passed 01/11/2024
Erosion Control Inspection Residential Passed 01/11/2024
DCM3 ESC REQUIRED 2 DAY
Resolved
01/11/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. MAINTAIN OVERGROWN VEGETATION
Occupancy Inspection - Codes Residential Full C of O 1/11/2024 01/11/2024
Misc
Resolved
01/11/2024
-address pending pier inspection -provide as graded plot plan -Splash blocks not installed -gutters being installed
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home