Permit Application Status

PRRES20215839


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20215839
Building Permit - Residential
Certificate of Occupancy
CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE. WALKOUT BASEMENT. ROOF TRUSSES. FINISHED/UNFINISHED BASEMENT. COVERED DECK.
11/08/2021
11/11/2021
05/09/2022
09/15/2022
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
CMH PARKS INC, Address:5000 CLAYTON RD  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
AJ@SUMMITHOMESKC.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331507-Sewer Connection Fee $390.00 $390.00 Paid 11/11/2021
8331401-Water Tap Fee $3,655.00 $3,655.00 Paid 11/11/2021
8350015-Water Meter Fee $479.24 $479.24 Paid 11/11/2021
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 11/11/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 11/11/2021
9110078-Valuation Fee New Single Family $1,096.69 $1,096.69 Paid 11/11/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 09/13/2022
9110080-3rd and Subsequent Inspection Fee (Per Hour) $150.00 $150.00 Paid 09/13/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 1/11/2022 1/11/2022 01/11/2022
Misc
Informational
01/11/2022
APPROVED PER BRADLEY HUXOL 12/3/21
Underslab Plumbing Inspection - Residential Passed 1/11/2022 1/11/2022 01/11/2022
Sewer Service Inspection - R Passed 1/18/2022 01/18/2022
Water Service Inspection - R Partial 1/18/2022 1/18/2022 01/18/2022
Water Service Inspection - R Passed 1/19/2022 (1:00) 1/19/2022 01/19/2022
Electrical Service Inspection Passed 5/25/2022 05/25/2022
Gas Service Inspection - Residential Passed 5/25/2022 05/25/2022
All Rough Inspection - Residential Failed 5/25/2022 5/25/2022 05/25/2022
Misc
Corrective Action Required
05/25/2022
-provide nail protection plates all NM within 1 1/4” end of stud -provide stud shoes at exterior studs bored for electrical SE cable at garage -address stud pack for trpl girder truss at garage wall bored less than 5/8” from end of studs -address corner studs removed for electrical at NE corner garage -seal all top plate penetrations garage -fireblock at dryer duct top plate laundry -provide stud shoe at garage wall laundry bored for DWV -provide H2.5 truss hold down at truss master closet -provide protection plate at pex master shower -fur down for pex at master shower -install all exterior doors -protect ward flex gas piping at fireplace entry -Fireblock all through floor penetrations -nail all truss hangers -provide bocca protection plate at top plate DWV at great room/bath wall -fireblock HVAC at great room/bath wall -provide H2.5 truss hold downs at front bedroom -provide CS-PF portal bracing at great room exterior wall per plans -have engineer address C11 gable truss not provided with bearing on top plate -have engineer address dbl top plates that have been notched around full height studs on exterior gable walls, also the 2x4 studs are over 12’ -have engineer address B1 gable truss that has had webs cut and bottom chord removed -provide all truss lateral bracing per plans -dbl top plate requires min 24” lap between plate breaks- see great room -floor joist requires 1 1/2” bearing at end, see basement sump pump mech room, left of door -provide bocca protection plate bottom plate basement office -provide joist hangers at joist to dbl rim connection basement den -complete wall framing at den -land electrica to box at basement den windows -address floor joist over notched for DWV basement bath -seal top floor late penetrations basement bedroom -address (1) ply of dbl 2x10 joist not provided with full bearing at steel beam above basement bed hall -provide bocca protection plate at DWV top plate basement bedroom/bath wall -fireblock between top plate and foundation wall basement bedroom -fireblock vertical every 10’ behind studs at basement bedroom -provide 3” SCH 40 steel column at pier location “A” basement storage beam per plans -provide floor joists at basement bedroom #3 per plans -install all windows
Erosion Control Inspection Residential Partial 05/25/2022
All Rough Inspection - Residential Failed 6/6/2022 6/6/2022 06/06/2022
Misc
Corrective Action Required
05/25/2022
-provide stud shoes at exterior studs bored for electrical SE cable at garage -address corner studs removed for electrical at NE corner garage -install all exterior doors -Fireblock all through floor penetrations -provide CS-PF portal bracing at great room exterior wall per plans (plans call out for dbl 2x12 header corner to corner, nail all exterior sheathing per design) -have engineer address C11 gable truss not provided with bearing on top plate -have engineer address dbl top plates that have been notched around full height studs on exterior gable walls, also the 2x4 studs are over 12’ -have engineer address B1 gable truss that has had webs cut and bottom chord removed -provide all truss lateral bracing per plans -complete wall framing at den beneath windows -land electric to box at basement den windows -address floor joist over notched for DWV basement bath, (provide engineer letter on field fix) -fireblock between top plate and foundation wall basement bedroom -fireblock vertical every 10’ behind studs at basement bedroom -provide floor joists at basement bedroom #3 per plans -install all windows
Erosion Control Inspection Residential Failed 6/6/2022 6/6/2022 06/06/2022
Misc
Corrective Action Required
06/06/2022
Maintain gravel filter on drive
All Rough Inspection - Residential Not Ready 6/21/2022 6/21/2022 06/21/2022
Misc
Corrective Action Required
06/06/2022
6/21/22 - NOT READY -provide stud shoes at exterior studs bored for electrical SE cable at garage -address corner studs removed for electrical at NE corner garage -install all exterior doors -Fireblock all through floor penetrations -provide CS-PF portal bracing at great room exterior wall per plans (plans call out for dbl 2x12 header corner to corner, nail all exterior sheathing per design) -have engineer address C11 gable truss not provided with bearing on top plate -have engineer address dbl top plates that have been notched around full height studs on exterior gable walls, also the 2x4 studs are over 12’ -have engineer address B1 gable truss that has had webs cut and bottom chord removed -provide all truss lateral bracing per plans -complete wall framing at den beneath windows -land electric to box at basement den windows -address floor joist over notched for DWV basement bath, (provide engineer letter on field fix) -fireblock between top plate and foundation wall basement bedroom -fireblock vertical every 10’ behind studs at basement bedroom -provide floor joists at basement bedroom #3 per plans -install all windows
All Rough Inspection - Residential Failed 6/23/2022 6/23/2022 06/23/2022
Misc
Corrective Action Required
06/21/2022
-provide CS-PF portal bracing at great room exterior wall per plans (plans call out for dbl 2x12 header corner to corner, nail all exterior sheathing per design) -have engineer address B1 gable truss that has had webs cut and bottom chord removed (REPAIR PER ENGINEER LETTER) -fireblock between top plate and foundation wall basement bedroom -fireblock vertical every 10’ behind studs at basement bedroom -install all windows
All Rough Inspection - Residential Failed 6/27/2022 6/27/2022 06/27/2022
Misc
Corrective Action Required
06/23/2022
-provide CS-PF portal bracing at great room exterior wall per plans (plans call out for dbl 2x12 header corner to corner, nail all exterior sheathing per design) -have engineer address B1 gable truss that has had webs cut and bottom chord removed (REPAIR PER ENGINEER LETTER) -Address (3) broken trusses that have been field repaired at front bedroom with truss engineer **OK TO INSULATE**
All Rough Inspection - Residential Passed 6/30/2022 6/30/2022 06/30/2022
Misc
Resolved
06/30/2022
Erosion Control Inspection Residential Partial 06/30/2022
Misc
Resolved
06/30/2022
Maintain gravel filter on drive
Driveway Inspection Partial 7/18/2022 7/18/2022 07/18/2022
Misc
Informational
07/18/2022
7-18-22 RH. Forms were up and currently meet ADA and LS specification. Aggregate was placed and compacted. Contractor will be pouring today.
Sidewalk Inspection Partial 7/18/2022 7/18/2022 07/18/2022
Misc
Informational
07/18/2022
7-18-22 RH. Forms were up and currently meet ADA and LS specification. Aggregate was place and compacted. Crew is pouring today.
Driveway Inspection Passed 7/25/2022 7/25/2022 07/25/2022
Misc
Informational
07/18/2022
7-18-22 RH. Forms were up and currently meet ADA and LS specification. Aggregate was placed and compacted. Contractor will be pouring today. 7-25-22 RH. Driveway was poured and meets ADA and LS specification.
Sidewalk Inspection Passed 7/25/2022 7/25/2022 07/25/2022
Misc
Informational
07/18/2022
7-18-22 RH. Forms were up and currently meet ADA and LS specification. Aggregate was place and compacted. Crew is pouring today. 7-25-22 RH. Sidewalk was poured and meets ADA and LS specification.
Occupancy Inspection - Codes Residential Failed 9/13/2022 9/13/2022 09/13/2022
Misc
Corrective Action Required
09/13/2022
-submit as graded plot plan for review and approval -gutters and downspouts required -splash blocks -cover plates all outlets and switches -garbage disposal blocking under counter outlet use at kitchen island -install outlet at mud room countertop -secure deck guard rail -GFCI protection required at basement wet bar tv/clock receptacle, less than 6’ from sink -secure outlet weather box rear patio outlet -provide (2) 1/2” through bolts each post/beam connection at deck -Sump pump discharge min 36” from foundation
Erosion Control Inspection Residential Passed 9/13/2022 9/13/2022 09/13/2022
Plot Plan Inspection Passed 9/16/2022 09/15/2022
Occupancy Inspection - Codes Residential Full C of O 9/15/2022 9/15/2022 09/15/2022
Misc
Resolved
09/15/2022
Documents & Images
Date Uploaded File Type Document Name
11/08/2021 RR #116 - PERMIT APP
11/10/2021 Approved Plans APPROVED DRAWINGS
11/10/2021 Approved Plans APPROVED TRUSS PACKAGE
11/10/2021 Approved Plans APPROVED TRUSS LAYOUT
11/10/2021 Permit Codes Residential Plan Review
11/11/2021 Plot Plan APPROVED PLOT PLAN
11/11/2021 Permit Codes Residential Plan Review
11/11/2021 Permit DS Building Permit
11/11/2021 Receipt Receipt for transaction:2021-008674
01/10/2022 116 Reserve at Stoney Creek-FTNG
01/10/2022 116 Reserve at Stoney Creek-FDTN
01/11/2022 Letter INSPECTION SUMMARY
01/11/2022 Letter INSPECTION SUMMARY
01/18/2022 Letter INSPECTION SUMMARY
01/18/2022 Letter INSPECTION SUMMARY
01/19/2022 Letter INSPECTION SUMMARY
05/25/2022 Letter INSPECTION SUMMARY
05/25/2022 Letter INSPECTION SUMMARY
05/25/2022 Letter INSPECTION SUMMARY
05/25/2022 Letter INSPECTION SUMMARY
06/06/2022 Letter INSPECTION SUMMARY
06/06/2022 Letter INSPECTION SUMMARY
06/21/2022 116 Reserve at Stoney Creek Letter
06/21/2022 Letter INSPECTION SUMMARY
06/23/2022 Letter INSPECTION SUMMARY
06/27/2022 Letter INSPECTION SUMMARY
06/29/2022 MOsealtrussrepair
06/30/2022 116 Reserve at Stoney Creek Letter 2
06/30/2022 Letter INSPECTION SUMMARY
06/30/2022 Letter INSPECTION SUMMARY
07/18/2022 Letter INSPECTION SUMMARY
07/18/2022 Letter INSPECTION SUMMARY
07/25/2022 Letter INSPECTION SUMMARY
07/25/2022 Letter INSPECTION SUMMARY
09/13/2022 Receipt Receipt for transaction:2022-007482
09/13/2022 Letter INSPECTION SUMMARY
09/13/2022 Letter INSPECTION SUMMARY
09/15/2022 Plot Plan APPROVED AS BUILT PLOT PLAN
09/15/2022 Letter INSPECTION SUMMARY
09/15/2022 Letter Field Certificate of Occupancy
09/15/2022 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home