Summary
PRRES20211583
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - ROOF TRUSSES - UNFINSIHED BASEMENT - COVERED DECK
04/06/2021
04/07/2021
02/16/2022
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
PERMITTING@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 04/08/2021 04/06/2021
Brandon Kalwei
Residential Plan Review Approved 04/08/2021 04/06/2021
Brandon Kalwei
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,565.19 $1,565.19 Paid 04/07/2021
8331504-EFHB Middle Big Creek, Full $636.12 $636.12 Paid 04/07/2021
8331507-Sewer Connection Fee $570.00 $570.00 Paid 04/07/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 04/07/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 04/07/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 04/07/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 04/07/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 01/11/2022
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 01/11/2022
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 01/11/2022
9110080-3rd and Subsequent Inspection Fee (Per Hour) $100.00 $100.00 Paid 01/11/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Failed 6/7/2021 6/7/2021 06/07/2021
Misc
Corrective Action Required
06/07/2021
FOOTING POURED WITHOUT INSPECTION THIRD PARTY INSPECITON REPORTS ARE REQUIRED TO BE UPLOADED TO PERMIT WITHIN 48 HOURS OF INSPECTION
Underslab Plumbing Inspection - Residential Failed 6/7/2021 6/7/2021 06/07/2021
Misc
Corrective Action Required
06/07/2021
INSPECTION DENIED FOOTING POURED WITHOUT INSPECTION THIRD PARTY INSPECITON REPORTS ARE REQUIRED TO BE UPLOADED TO PERMIT WITHIN 48 HOURS OF INSPECTION
Footing Inspection - Residential Passed 6/8/2021 6/8/2021 06/08/2021
Misc
Resolved
06/08/2021
Underslab Plumbing Inspection - Residential Passed 6/8/2021 6/8/2021 06/08/2021
Misc
Resolved
06/08/2021
All Rough Inspection - Residential Partial 8/3/2021 8/3/2021 08/03/2021
Misc
Informational
08/03/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Electrical Service Inspection Passed 10/8/2021 10/8/2021 10/08/2021
Gas Service Inspection - Residential Failed 10/8/2021 10/8/2021 10/08/2021
Misc
Corrective Action Required
10/08/2021
GAS PRESSURE MUST MAINTAIN 10 PSI MIN FOR TEST
All Rough Inspection - Residential Failed 10/8/2021 10/8/2021 10/08/2021
Misc
Informational
08/03/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
10/08/2021
-Overbored floor joist for DWV, SW garage for 2nd floor, repl or submit engineer letter -Anchor bolts required within 12” of plate break at garage -Dbl top plate requires 24” offset between plate breaks - see garage East wall, master bed west wall -Fireblock HVAC chase mud room garage entry -Add stud shoe at exterior stud bored for SER cable at master water closet -security blocking master bed exterior door -Bocca protection plate bottom plate DWV master bed/master shower wall -seal top plate penetration- master bed -secure gas flex line at fireplace -Support lvl ridge beam at covered deck, ridge straps, rafter ties -complete electrical at kitchen wall -(4) overbored floor joist for DWV 1st floor entry - repl or submit engineer letter -Repair subfloor from bedroom 1st floor -Seal bottom plate penetration from bedroom closet 1st floor, master shower -LIB bracing all locations per plans -Attic access per plans at garage -(6) 2x4 stud pack 2nd floor girder truss bearing per plans at 1st floor great room -Exterior wall bracing great room windows per plans -All truss hangers per plans -Secure HVAC duct 2nd floor both front bedroom closets -Truss stud shifted from chord, 2nd floor front bath -protect NM within 6’ of attic access 2nd floor -Wall bracing per plans 2nd floor stairway window -Nail all truss hangers 2nd floor -Truss V5 missing at covered deck ridge -Solid block between joists at cantilever -Shield service panel from DWV waste line above at basement -4” SCH 40 steel column at pier F, W10 x 26 steel beam at basement per plans -3.5” SCH 40 steel column at pier E, W10 x26 steel beam per plans -1” clearance required for b vent flue for furnace at basement, see NM against b vent -Pan off cantilever exterior
Sewer Service Inspection - R Passed 10/15/2021 (1:00) 10/15/2021 10/15/2021
Water Service Inspection - R Passed 10/15/2021 (1:00) 10/15/2021 10/15/2021
Erosion Control Inspection Residential Failed 10/15/2021 10/15/2021 10/15/2021
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
10/15/2021
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
All Rough Inspection - Residential Failed 10/20/2021 10/20/2021 10/20/2021
Misc
Informational
10/08/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
10/08/2021
-Dbl top plate requires 24” offset between plate breaks - see garage East wall -b vent at mud room chase requires 1” clearance from combustibles -seal top plate penetration- master bed -Support lvl ridge beam at covered deck, rafter ties bottom third of rafters -Seal bottom plate penetration from bedroom closet 1st floor, master shower -Exterior wall bracing design great room windows per plans -Nail exterior sheathing sliding glass door CS-PF per plans -All truss hangers per plans - see garage -Truss V5 missing at covered deck ridge -4” SCH 40 steel column at pier F, W10 x 26 steel beam at basement per plans **OK TO INSULATE, REMOVE INSULATION FROM ALL CORRECTIONS**
Gas Service Inspection - Residential Passed 10/28/2021 10/28/2021 10/28/2021
Misc
Resolved
10/28/2021
All Rough Inspection - Residential Not Ready 10/28/2021 10/28/2021 10/28/2021
Misc
Informational
10/20/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
10/20/2021
10/28/21 - NOT READY FOR INSPECTION, CORRECTIONS HAVE NOT BEEN ADDRESSED, FEES HAVE BEEN ADDED. INSULATION COVERING INSPECTION ITEMS AS WELL -Dbl top plate requires 24” offset between plate breaks - see garage East wall -b vent at mud room chase requires 1” clearance from combustibles -seal top plate penetration- master bed -Support lvl ridge beam at covered deck, rafter ties bottom third of rafters -Seal bottom plate penetration from bedroom closet 1st floor, master shower -Exterior wall bracing design great room windows per plans -Nail exterior sheathing sliding glass door CS-PF per plans -All truss hangers per plans - see garage -Truss V5 missing at covered deck ridge -4” SCH 40 steel column at pier F, W10 x 26 steel beam at basement per plans **OK TO INSULATE, REMOVE INSULATION FROM ALL CORRECTIONS**
All Rough Inspection - Residential Not Ready 10/29/2021 10/29/2021 10/29/2021
Misc
Informational
10/28/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
10/28/2021
10/29/21- MET BUILDER AT HOUSE FOR INSPECTION, BUILDER SAYS HE IS NOT READY FOR INSPECTION 10/28/21 - NOT READY FOR INSPECTION, CORRECTIONS HAVE NOT BEEN ADDRESSED, FEES HAVE BEEN ADDED. INSULATION COVERING INSPECTION ITEMS AS WELL -Dbl top plate requires 24” offset between plate breaks - see garage East wall -b vent at mud room chase requires 1” clearance from combustibles -seal top plate penetration- master bed -Support lvl ridge beam at covered deck, rafter ties bottom third of rafters -Seal bottom plate penetration from bedroom closet 1st floor, master shower -Exterior wall bracing design great room windows per plans -Nail exterior sheathing sliding glass door CS-PF per plans -All truss hangers per plans - see garage -4” SCH 40 steel column at pier F, W10 x 26 steel beam at basement per plans **OK TO INSULATE, REMOVE INSULATION FROM ALL CORRECTIONS**
All Rough Inspection - Residential Not Ready 11/2/2021 11/2/2021 11/02/2021
Misc
Informational
10/29/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
10/29/2021
11/2/21 - NOT ALL CORRECTIONS ADDRESSED, SOME CEILINGS AND AREAS HAVE BEEN ROCKED, DO NOT ROCK ANY FURTHER, NO APPROVAL HAS BEEN GIVEN TO ROCK 10/29/21- MET BUILDER AT HOUSE FOR INSPECTION, BUILDER SAYS HE IS NOT READY FOR INSPECTION 10/28/21 - NOT READY FOR INSPECTION, CORRECTIONS HAVE NOT BEEN ADDRESSED, FEES HAVE BEEN ADDED. INSULATION COVERING INSPECTION ITEMS AS WELL -Dbl top plate requires 24” offset between plate breaks - see garage East wall (see plate breaks to right of beam) -b vent at mud room chase requires 1” clearance from combustibles -Support lvl ridge beam at covered deck, rafter ties bottom third of rafters -Exterior wall bracing design great room windows per plans -have engineer address, osb on interior without continuous over band/rim joist **OK TO INSULATE, REMOVE INSULATION FROM ALL CORRECTIONS**
All Rough Inspection - Residential Failed 11/3/2021 11/3/2021 11/03/2021
Misc
Informational
11/02/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
11/02/2021
-rafter ties bottom third of rafters rear covered patio, discussed correction with framer on site **OK TO INSULATE AND ROCK**
All Rough Inspection - Residential Passed 12/16/2021 12/16/2021 12/16/2021
Misc
Resolved
12/16/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Resolved
12/16/2021
-rafter ties bottom third of rafters rear covered patio, discussed correction with framer on site **OK TO INSULATE AND ROCK**
Erosion Control Inspection Residential Failed 12/16/2021 12/16/2021
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
10/15/2021
EROSION CONTROL REQUIRED AT LOT REMOVE JOHN FROM STREET
Occupancy Inspection - Codes Residential Temporary C of O 1/20/2022 1/20/2022 01/20/2022
Misc
Corrective Action Required
01/20/2022
-final driveway inspection required, contact development services to schedule -final grade and sod -splash blocks at downspouts and sump pump discharge -complete stone/siding at front of house -address numbers must contrast in color from background color -seal all penetrations in siding, seal along top of AC disconnect and meter can **OK FOR TCO, TCO EXPIRES 3/14/22**
Plot Plan Inspection Passed 2/14/2022 2/14/2022 02/14/2022
Erosion Control Inspection Residential Passed 2/14/2022 2/14/2022 02/14/2022
DCM1 ESC REQUIRED NO FURTHER INSP
Resolved
02/14/2022
EROSION CONTROL REQUIRED AT LOT REMOVE JOHN FROM STREET
Occupancy Inspection - Codes Residential Failed 2/14/2022 2/14/2022 02/14/2022
Misc
Corrective Action Required
01/20/2022
-final driveway inspection required, contact development services to schedule -splash blocks at downspouts and sump pump discharge **OK FOR TCO, TCO EXPIRES 3/14/22**
Driveway Inspection Passed 12/1/2021 12/1/2021 02/15/2022
Misc
Informational
12/01/2021
On 12/1/2021 I performed a driveway inspection and pass the subgrade to pour concrete
Occupancy Inspection - Codes Residential Full C of O 2/16/2022 2/16/2022 02/16/2022
Misc
Resolved
02/16/2022
Driveway Inspection Passed 2/15/2022 04/28/2022
Misc
Informational
12/01/2021
On 12/1/2021 I performed a driveway inspection and pass the subgrade to pour concrete
Documents & Images
Date Uploaded File Type Document Name
04/06/2021 Application Form APPLICATION
04/06/2021 102 RESERVE AT STONEY CREEK TRUSS LAYOUT
04/06/2021 RR #102 - Sydney - Modern Prairie - Sheets- signed
04/06/2021 LOT 102 FINAL
04/06/2021 210331
04/06/2021 Approved Plans APPROVED PLANS
04/06/2021 Approved Plans APPROVED PLOT PLAN
04/06/2021 Approved Plans APPROVED TRUSS DRAWINGS
04/07/2021 Receipt Receipt for transaction:2021-001796
04/07/2021 Letter DS Building Permit
06/07/2021 Letter INSPECTION SUMMARY
06/07/2021 Letter INSPECTION SUMMARY
06/07/2021 Lot 102 Reserve at Stoney Creek Footing Inspection
06/08/2021 Letter INSPECTION SUMMARY
06/08/2021 Letter INSPECTION SUMMARY
08/03/2021 Letter INSPECTION SUMMARY
10/08/2021 Letter INSPECTION SUMMARY
10/08/2021 Letter INSPECTION SUMMARY
10/08/2021 Letter INSPECTION SUMMARY
10/15/2021 Letter INSPECTION SUMMARY
10/15/2021 Letter INSPECTION SUMMARY
10/15/2021 Letter INSPECTION SUMMARY
10/19/2021 102 Reserve at Stoney Creek bored floor joists
10/20/2021 Letter INSPECTION SUMMARY
10/26/2021 210331 1ST FLOOR LAYOUT x
10/26/2021 102 RESERVE AT STONEY CREEK 1ST FLOOR LAYOUT revised 10-26-21
10/26/2021 Approved Plans APPROVED TRUSS LAYOUT
10/28/2021 Letter INSPECTION SUMMARY
10/28/2021 Letter INSPECTION SUMMARY
10/29/2021 Letter INSPECTION SUMMARY
11/02/2021 Letter INSPECTION SUMMARY
11/03/2021 Letter INSPECTION SUMMARY
11/03/2021 102 Reserve at Stoney Creek Braced Wall Panel Letter
12/01/2021 Letter INSPECTION SUMMARY
12/16/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
12/16/2021 Letter INSPECTION SUMMARY
01/11/2022 Receipt Receipt for transaction:2022-000200
01/20/2022 Letter Codes Temporary Certificate of Occupancy
02/14/2022 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/15/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter Field Certificate of Occupancy
02/16/2022 Letter Codes Final Certificate of Occupancy
02/23/2022 Letter INSPECTION SUMMARY
04/28/2022 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home