Permit Application Status

PRRES20211043


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20211043
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - COVERED DECK
03/10/2021
03/16/2021
09/06/2021
06/01/2022
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
DUSTIN@SUMMITHOMESKC.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 03/18/2021 03/16/2021
Kim Brennan
Sidewalks
Corrective Action Required
03/16/2021

Sidewalks with dimensions must be provided on the plot plan.
Residential Plan Review Approved 03/18/2021 03/16/2021
Kim Brennan
Residential Plan Review Approved 03/12/2021 03/11/2021
Kim Brennan
08 Designate locations of smoke detectors and carbon monoxide detectors
Corrective Action Required
03/10/2021

Designate locations of smoke detectors and carbon monoxide detectors. (IRC Section R314 and R315) Not shown in unfinished basement
Plot Plan Review Rejected 03/12/2021 03/10/2021
Kim Brennan
Sidewalks
Corrective Action Required
03/10/2021

Sidewalks with dimensions must be provided on the plot plan.
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,505.94 $1,505.94 Paid 03/16/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 03/16/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 03/16/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 03/16/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 03/16/2021
8331504-EFHB Middle Big Creek, Full $669.60 $669.60 Paid 03/16/2021
8331507-Sewer Connection Fee $600.00 $600.00 Paid 03/16/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 05/27/2022
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 05/27/2022
9110080-3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 05/27/2022
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 05/27/2022
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 05/27/2022
9110080-3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 05/27/2022
9110080-3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 05/27/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 4/19/2021 04/19/2021
Underslab Plumbing Inspection - Residential Passed 4/30/2021 4/30/2021 04/30/2021
Sewer Service Inspection - R Passed 11/3/2021 (10:00) 11/3/2021 11/03/2021
Water Service Inspection - R Partial 11/3/2021 11/3/2021 11/03/2021
Water Service Inspection - R Passed 11/5/2021 (1:00) 11/5/2021 11/05/2021
All Rough Inspection - Residential Not Ready 12/13/2021 12/13/2021 12/13/2021
Misc
Corrective Action Required
12/13/2021
INSPECTION DENIED NO CITY APPROVED PLANS ON SITE AT TIME OF INSPECTION
Erosion Control Inspection Residential Failed 12/15/2021 12/15/2021 12/15/2021
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
12/15/2021
*12-15-21 EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL IN COMPLIANCE -PROVIDE GRAVEL FILTER AT FRONT OF LOT, RESTORE SILT FENCE AT PERIMETER, CLEAN TRASH AND DEBRIS FROM LOT, STREET AND ADJACENT PROPERTY
All Rough Inspection - Residential Not Ready 12/15/2021 12/15/2021 12/15/2021
Misc
Corrective Action Required
12/13/2021
INSPECTION DENIED NO CITY APPROVED PLANS ON SITE AT TIME OF INSPECTION
Misc
Corrective Action Required
12/15/2021
Misc
Corrective Action Required
12/15/2021
*12-15-21 -INSPECTION DENIED: EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL IN COMPLIANCE -PROVIDE GRAVEL FILTER AT FRONT OF LOT, RESTORE SILT FENCE AT PERIMETER, CLEAN TRASH AND DEBRIS FROM LOT, STREET AND ADJACENT PROPERTY
Electrical Service Inspection Passed 12/15/2021 12/15/2021 12/20/2021
Gas Service Inspection - Residential Failed 12/15/2021 12/15/2021 12/20/2021
Misc
Corrective Action Required
12/20/2021
-complete all gas lines, pressure test required
All Rough Inspection - Residential Failed 12/20/2021 12/20/2021 12/20/2021
Misc
Resolved
12/20/2021
INSPECTION DENIED NO CITY APPROVED PLANS ON SITE AT TIME OF INSPECTION
Misc
Resolved
12/20/2021
Misc
Corrective Action Required
12/15/2021
-No city approved truss plans on site, unable to verify truss, have on site at reinspect, corrections list subject to change, approved truss plans required on site for all rough same as house plans -fireblock vertical to horizontal at furred down soffit ends garage -fireblock DWV chase garage -bump out garage wall to allow for insulation at HVAC -connect HVAC duct at garage furred down, (3) screws -fireblock deadspace at tub, 1st floor west bath -vent all bath exhaust fans to exterior -connect HVAC duct at 1st floor west bath ceiling, (3) screws -add dbl joist hanger, joist to lvl connection mud room -joist hanger required at triple lvl to lvl connection 1st floor west bath -solid block between joists at cantilevers -fireblock HVAC chase mud room -Install back door at deck -Fireblock HVAC/Plumbing/electrical chases at great room -fireblock fireplace lid -seal low volt plate penetration great room, garage -Address modified joist hanger, triple lvl great room -joist hanger required at dbl joist beam connection kitchen -12” oc nailing at intersecting corners -30” vertical clearance at attic access garage -dbl 2 x 10 joists at all locations shown on plans at garage -(4) 2x4 stud pack at tpl lvl bearing end per plans 1st floor west bath -exterior bracing CS-PF at dining room per plans, unable to inspect exterior nailing pattern with siding cover -fireblock deadspace, 2nd floor bed#2 entry -protection plate DWV bath#2 2nd floor, less than 1 1/4” from end of stud -attic access required at 2nd floor -fireblock deadspace master bed/closet -seal top plate penetration for NM master bed -address top plate connections at 2x6 to 2x4 walls 2nd floor -nail all H2.5 truss clips at 2nd floor -set and anchor all SCH 40 steel columns to floor at basement -add joist hangers at all joists 4’ or more at basement for 1st floor fireplace cantilever -complete all gas lines -(3) 2x10 joists at fireplace cantilever basement per plans -(3) 2x10 header at basement daylight window per plans -3.5” SCH 40 steel column at pier pad location “E” per plans -solid block between joists every 48” oc for kitchen island per plans -properly support stair landings, joists 4’ or more require joist hangers -full height 6x6 cedar posts at covered deck per plans -Nail all exterior sheathing per plans
All Rough Inspection - Residential Failed 1/11/2022 1/11/2022 01/11/2022
Misc
Corrective Action Required
12/20/2021
-Unable to confirm truss hangers installed per plans at covered deck with lid installed -fireblock DWV chase garage, seal annular space around DWV, block between studs on bath wall side -bump out garage wall to allow for insulation at HVAC -protection plate at DWV furred down soffit end, 1st floor bath -fireblock deadspace at tub, 1st floor west bath -fireblock HVAC chase mud room -Install back door at deck -Fireblock HVAC/Plumbing/electrical chases at great room, fireblock at annular space around DWV, HVAC and electrical -seal low volt plate penetration great room -solid block between joists at cantilever- see dining room, fireplace cantilever -joist hanger required at dbl joist beam connection kitchen -exterior bracing CS-PF at dining room per plans, 3” oc grid nail pattern sheathing to header -fireblock deadspace, 2nd floor bed#2 entry, fireblock where open to attic space on hall side -seal top plate penetration for NM master bed and low volt, seal low floor penetration at mechanical chase -address top plate connections at 2x6 to 2x4 walls 2nd floor, (have engineer address) -protect NM within 6’ of attic entry 2nd floor -Truss hanger per plans at J14 hip truss 2nd floor -sheathing nailed to both sides of E7 truss above 2nd floor hall, if truss was damaged upload engineer letter from mitek on field fix -complete all gas lines -properly support stair landings, joists 4’ or more require joist hangers -full height 6x6 cedar posts at covered deck per plans
Gas Service Inspection - Residential Failed 1/24/2022 1/24/2022 01/24/2022
Misc
Corrective Action Required
12/20/2021
-complete all gas lines, pressure test required
All Rough Inspection - Residential Failed 1/24/2022 1/24/2022 01/24/2022
Misc
Corrective Action Required
01/11/2022
-clean all construction debris along rear of lot at tree line -fireblock DWV chase garage, seal annular space around DWV -protection plate at DWV furred down soffit end, 1st floor bath -Install back door at deck -Fireblock HVAC/Plumbing/electrical chase at great room, fireblock at annular space around DWV -seal low volt plate penetration great room -seal top plate penetration for NM master bed and low volt, seal low floor penetration at mechanical chase -address top plate connections at 2x6 to 2x4 walls 2nd floor, make field repair as outlined in the engineer letter that has been uploaded to permit -complete all gas lines -full height 6x6 cedar posts at covered deck per plans, make field repair as outlined in engineer letter uploaded (5) ALL ROUGH INSPECTIONS, FEES ADDED
All Rough Inspection - Residential Not Ready 1/25/2022 1/25/2022 01/25/2022
Misc
Corrective Action Required
01/24/2022
-Clean all construction trash and debris along rear of lot at tree line <---GET THIS ADDRESSED BEFORE SCHEDULING REINSPECTION -protection plate at DWV furred down soffit end, 1st floor bath -Install back door at deck -seal the unused bore through floor at mechanical chase master bedroom -address top plate connections at 2x6 to 2x4 walls 2nd floor, make field repair as outlined in the engineer letter that has been uploaded to permit -complete all gas lines -full height 6x6 cedar posts at covered deck per plans, make field repair as outlined in engineer letter uploaded THIS IS THE 6TH ALL ROUGH INSPECTION, FEES ADDED, ALL ISSUES SHOULD BE ADDRESSED BEFORE SCHEDULING INSPECTION, HAVE RESPECT FOR THE INSPECTORS TIME
All Rough Inspection - Residential Not Ready 1/27/2022 1/27/2022 01/27/2022
Misc
Corrective Action Required
01/25/2022
-Clean all construction trash and debris along rear of lot at tree line <---GET THIS ADDRESSED BEFORE SCHEDULING REINSPECTION -protection plate at DWV furred down soffit end, 1st floor bath -Install back door at deck -address top plate connections at 2x6 to 2x4 walls 2nd floor, make field repair as outlined in the engineer letter that has been uploaded to permit -complete all gas lines -full height 6x6 cedar posts at covered deck per plans, make field repair as outlined in engineer letter uploaded THIS IS THE 6TH ALL ROUGH INSPECTION, FEES ADDED, ALL ISSUES SHOULD BE ADDRESSED BEFORE SCHEDULING INSPECTION, HAVE RESPECT FOR THE INSPECTORS TIME 1/27/22-NOT READY FEE ASSESSED
All Rough Inspection - Residential Failed 2/3/2022 2/3/2022 02/03/2022
Misc
Corrective Action Required
01/27/2022
-Install back door at deck 8TH ALL ROUGH INSPECTION, FEES ADDED **OK TO INSULATE**
Gas Service Inspection - Residential Passed 2/3/2022 02/03/2022
Misc
Resolved
02/03/2022
Erosion Control Inspection Residential Failed 2/11/2022 2/11/2022 02/11/2022
DCM3 ESC REQUIRED 2 DAY
Resolved
02/11/2022
Misc
Corrective Action Required
02/11/2022
CLEAN ALL MUD AND GRAVEL FROM STREET AT FRONT OF LOT
All Rough Inspection - Residential Passed 2/11/2022 2/11/2022 02/11/2022
Misc
Resolved
02/11/2022
Driveway Inspection Partial 4/5/2022 4/5/2022 04/05/2022
Misc
Informational
04/05/2022
Driveway was framed up with aggregate in and compacted. 4/5/22 ES
Sidewalk Inspection Partial 4/5/2022 4/5/2022 04/05/2022
Misc
Informational
04/05/2022
Sidewalk was framed up with aggregate in and compacted. 4/5/22
Sidewalk Inspection Failed 4/15/2022 4/15/2022 04/15/2022
Misc
Informational
04/05/2022
Sidewalk was framed up with aggregate in and compacted. 4/5/22
Misc
Corrective Action Required
04/15/2022
There is one panel directly east of driveway that needs replaced due to being busted. The rest of sidewalk meets LS and Ada specs. 4/15/22 ES
Driveway Inspection Passed 4/15/2022 4/15/2022 04/15/2022
Misc
Informational
04/05/2022
Driveway was framed up with aggregate in and compacted. 4/5/22 ES
Misc
Informational
04/15/2022
Driveway meets LS and Ada specs. 4/15/22 ES
Occupancy Inspection - Codes Residential Failed 5/24/2022 5/24/2022 05/24/2022
Misc
Corrective Action Required
05/24/2022
Tempered glazing required at windows master bath jacuzzi tub Tempered glazing required at 2nd floor stairs landing Provide gravel at water meter pit Final sidewalk inspection required, contact development services to schedule resolve outstanding inspection fees
Erosion Control Inspection Residential Passed 05/24/2022
Misc
Resolved
05/24/2022
CLEAN ALL MUD AND GRAVEL FROM STREET AT FRONT OF LOT
Sidewalk Inspection Passed 5/27/2022 5/27/2022 05/27/2022
Misc
Informational
04/15/2022
Sidewalk was framed up with aggregate in and compacted. 4/5/22
Misc
Corrective Action Required
04/15/2022
There is one panel directly east of driveway that needs replaced due to being busted. The rest of sidewalk meets LS and Ada specs. 4/15/22 ES
Plot Plan Inspection Passed 06/01/2022
Occupancy Inspection - Codes Residential Full C of O 6/1/2022 6/1/2022 06/01/2022
Miscellaneous Correction
Resolved
06/01/2022
Documents & Images
Date Uploaded File Type Document Name
03/10/2021 Application Form Permit Application and License Tax Form
03/10/2021 Letter Codes Residential Plan Review
03/11/2021 Approved Plans Approved Drawings
03/11/2021 Approved Plans Approved Truss Layout
03/11/2021 Approved Plans Approved Truss Package
03/16/2021 Plot Plan Approved Plot Plan
03/16/2021 Receipt Receipt for transaction:2021-001304
03/16/2021 Letter DS Building Permit
04/16/2021 Lot 80 Stoney Creek Footing Inspection
04/19/2021 Letter INSPECTION SUMMARY
04/30/2021 Letter INSPECTION SUMMARY
11/03/2021 Letter INSPECTION SUMMARY
11/03/2021 Letter INSPECTION SUMMARY
11/05/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
12/15/2021 12-15-21 Erosion control .jpeg
12/15/2021 12-15-21 Erosion control .jpeg0
12/15/2021 12-15-21 Erosion control .jpeg1
12/15/2021 Letter INSPECTION SUMMARY
12/15/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
01/11/2022 Letter INSPECTION SUMMARY
01/21/2022 RR80TRUSSrepair
01/21/2022 80 reserve at stoney creek spliced deck column and top plate letter
01/24/2022 Letter INSPECTION SUMMARY
01/24/2022 Letter INSPECTION SUMMARY
01/25/2022 Letter INSPECTION SUMMARY
01/27/2022 Letter INSPECTION SUMMARY
02/03/2022 Letter INSPECTION SUMMARY
02/03/2022 Letter INSPECTION SUMMARY
02/11/2022 Letter INSPECTION SUMMARY
02/11/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/15/2022 Letter INSPECTION SUMMARY
04/15/2022 Busted sidewalk panel
04/15/2022 Letter INSPECTION SUMMARY
05/24/2022 Letter INSPECTION SUMMARY
05/24/2022 Letter INSPECTION SUMMARY
05/24/2022 Letter INSPECTION SUMMARY
05/24/2022 Plot Plan Approved As Graded Plot Plan
05/25/2022 Letter Codes Temporary Certificate of Occupancy
05/27/2022 Letter INSPECTION SUMMARY
05/27/2022 Receipt Receipt for transaction:2022-004026
06/01/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter Field Certificate of Occupancy
06/01/2022 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home