Permit Application Status

PRRES20210734


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20210734
Building Permit - Residential
Certificate of Occupancy
ABERDEEN PARTNERS LLC
NEW SINGLE FAMILY
NEW HOUSE - FINISHED AND UNFINISHED BASEMENT - COVERED DECK
02/23/2021
07/21/2021
11/03/2021
06/14/2023
Locations
Contacts
ABERDEEN PARTNERS LLC, Address:9101 W 110TH ST STE 200  
Mill Creek Builders Incorporated, Address:21203 W 81st Terrace, Phone:(816) 349-7209  
TRACY.F@MILLCREEKBUILDERSKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
PRIDE SERVICES INC, Address:3842 GEORGIA TERR, Phone:(785) 242-9700  
MILLER PLUMBING CO, Address:PO BOX 393 , Phone:(913) 851-1333  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 05/11/2021 05/07/2021
Brandon Kalwei
Residential Plan Review Approved 05/11/2021 05/07/2021
Brandon Kalwei
14 Identify roof covering material (IRC Section R905)
Corrective Action Required
05/07/2021

Identify roof covering material (IRC Section R905)
Misc
Corrective Action Required
05/07/2021

still need to address planning comments for stucco exterior
Planning Review (RES) Approved 05/07/2021 05/07/2021
Hector Soto Jr.
Misc
Corrective Action Required
03/12/2021

MATERIAL LABELING. Label all proposed exterior wall and roofing materials on Sheet S-0.1.
Miscellaneous Correction
Corrective Action Required
03/12/2021

EXTERIOR WALL MATERIALS. All exterior walls shall at a minimum have a stucco finish. The use of stone (as depicted on the front elevation), manufactured stone and brick may also be used on the elevations.
Residential Plan Review Rejected 05/04/2021 04/30/2021
Brandon Kalwei
14 Identify roof covering material (IRC Section R905)
Corrective Action Required
04/30/2021

Identify roof covering material (IRC Section R905)
Misc
Corrective Action Required
04/30/2021

still need to address planning comments for stucco exterior
Plot Plan Review Approved 05/04/2021 04/30/2021
Brandon Kalwei
Curb elevation
Corrective Action Required
04/30/2021

The elevation at top of curb at end of driveway and at lot corners adjacent to street must be provided on the plot plan.
Basement elevation
Corrective Action Required
04/30/2021

The Basement floor elevation and basement type (e.g. full/standard, daylight, walk-out, etc.) need to verify with MDP
Contours, spot elevations and arrows
Corrective Action Required
04/30/2021

Contours, spot elevations and drainage flow arrows (as required) shall be provided on the lot. drainage flow arrows needed
Basement egress
Corrective Action Required
04/30/2021

Basement egress location(s) and elevation of the lowest adjacent grade must be provided on the plot plan. egress wells need to be shown
Basement opening elevations
Corrective Action Required
04/30/2021

Minimum Building Opening Elevation (MBOE) and location on structure must be provided on the plot plan. need to verify with MDP
Planning Review (RES) Rejected 03/12/2021 03/12/2021
Hector Soto Jr.
Misc
Corrective Action Required
03/10/2021

MATERIAL LABELING. Label all proposed exterior wall and roofing materials on Sheet S-0.1.
Miscellaneous Correction
Corrective Action Required
03/10/2021

EXTERIOR WALL MATERIALS. All exterior walls shall at a minimum have a stucco finish. The use of stone (as depicted on the front elevation), manufactured stone and brick may also be used on the elevations.
Plot Plan Review Rejected 02/25/2021 02/24/2021
Brandon Kalwei
Curb elevation
Corrective Action Required
02/24/2021

The elevation at top of curb at end of driveway and at lot corners adjacent to street must be provided on the plot plan.
Basement elevation
Corrective Action Required
02/24/2021

The Basement floor elevation and basement type (e.g. full/standard, daylight, walk-out, etc.) need to verify with MDP
Contours, spot elevations and arrows
Corrective Action Required
02/24/2021

Contours, spot elevations and drainage flow arrows (as required) shall be provided on the lot. drainage flow arrows needed
Basement egress
Corrective Action Required
02/24/2021

Basement egress location(s) and elevation of the lowest adjacent grade must be provided on the plot plan. egress wells need to be shown
Basement opening elevations
Corrective Action Required
02/24/2021

Minimum Building Opening Elevation (MBOE) and location on structure must be provided on the plot plan. need to verify with MDP
Residential Plan Review Rejected 02/25/2021 02/23/2021
Brandon Kalwei
06 Designate use of each room or space
Corrective Action Required
02/23/2021

Designate use of each room or space including but not limited to; basement storage, garages, and attic areas intended for storage space. Basement areas need to be labeled.
14 Identify roof covering material (IRC Section R905)
Corrective Action Required
02/23/2021

Identify roof covering material (IRC Section R905)
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,029.69 $1,029.69 Paid 07/21/2021
8331507-Sewer Connection Fee $360.00 $360.00 Paid 07/21/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 07/21/2021
7232302-Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 07/21/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 07/21/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 07/21/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Failed 8/30/2021 8/30/2021 08/30/2021
Misc
Corrective Action Required
08/30/2021
THIRD PARTY FOOTING REPORT REJECTED AS IT IS INCOMPLETE. FOOTING INSPECTION NOT COMPLETED DUE TO LACK OF EROSION CONTROL ON LOT AT TIME OF INSPECTION AS REQUIRED
Erosion Control Inspection Residential Failed 8/30/2021 8/30/2021 08/30/2021
DCM5 ESC INSP DENIED
Corrective Action Required
08/30/2021
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL EROSION CONTROL IS IN COMPLIANCE
Underslab Plumbing Inspection - Residential Passed 9/20/2021 9/20/2021 09/20/2021
Misc
Corrective Action Required
09/20/2021
Maintain stilt fence at side of lot.
Suspended Slab Inspection Passed 10/13/2021 10/12/2021 10/12/2021
Erosion Control Inspection Residential Partial 12/27/2021 12/27/2021
DCM5 ESC INSP DENIED
Resolved
12/27/2021
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL EROSION CONTROL IS IN COMPLIANCE
Misc
Corrective Action Required
12/27/2021
Trash and debris complaint -contacted the builder and he will be on site and abate the issues.
Sewer Service Inspection - R Failed 3/7/2022 03/07/2022
Miscellaneous Correction
Corrective Action Required
03/07/2022
It appears that the MH (4511) in the back of the lot has been hit, there is also debris in the line. Contractor needs to make corrections to the MH.
Gas Service Inspection - Residential Failed 5/25/2022 5/25/2022 05/25/2022
Misc
Corrective Action Required
05/25/2022
-Complete gas line at fireplace, identify metallic pipe bondiing conductor at both ends
Electrical Service Inspection Failed 5/25/2022 5/25/2022 05/25/2022
Misc
Corrective Action Required
05/25/2022
-Use proper, listed clamp at ufer connection -Identify ufer conductor at both ends
All Rough Inspection - Residential Failed 5/25/2022 5/25/2022 05/25/2022
Misc
Corrective Action Required
05/25/2022
-Unable to verify nailing pattern at exterior braced walls -Land exterior electrical at garage -Install electrical for lights at garage door -Provide 2 rows 16d sinkers 3” oc at plate to header at PFH -Strap top plates overlapping less than 24” at beam-both sides -Provide anchor bolt at end of plate north wall -Provide lateral restraint for joists above beam -Protect nm within 6’ of attic access -Address hip strut bearing in ceiling joist in single car bay -Identity metallic gas line bonding conductor at both ends-clamp needs to be accessible after finish -Provide anchor bolt at plate break and at end of plate at south wall behind box out -Corner stud at SW corner over notched for gas line -Protect nm less than 1.25” to face of stud at exterior garage/pantry corner -Address exterior walls not connected at top plate in pantry -Protect electrical for 6” at island floor penetrations -Provide collar ties at back porch/dining rafters -Fireblock top of fur out wall at stairwell -Provide lateral bracing for upset beam in great room -Provide collar ties at front porch rafters -Complete gas at fireplace-secure ward flex, protect and connect -Complete fireblocking at fireplace vent-maintain proper clearance to combustibles-this also needs fireblocking in dead space behind header -Protect dryer duct 2” below top plate on both sides -Nail corner and intersecting wall studs at master, master bath, master closet, front bed etc. -Protect nm within 6’ of attic access in laundry -Provide security blocking at back door -Provide angle brackets at end joists of deck -Provide (2) 1/2” through bolts at all post to beam deck connections -Complete electrical at stairwell -Seal plate penetration at stairwell wall sconce -Protect nm at top plate above switch at bottom of stairs -Seal penetration in return air above soffit-See hole drilled in blocking above beam -Address locations where joists are bored with multiple holes closer than 2” -Min (3) studs in exterior corners-see back basement bed -Fireblock dead space at basement shower -Provide vertical fireblocking 10’ oc at fur out walls -Provide (2) anchor bolts at short plate by egress window in back bed -Sister over notched stud in exterior wall at back corner of back bed -Use listed clamp at ufer -Identity ufer conductor at both ends -Anchor column base near furnace, under suspended slab, and stairway -Fireblock stair landing -Strap top plates lapped less than 24” at beam on south wall -Anchor bolts to be in middle third of plate south wall -Provide plate and stud at exterior corner Southwest wall -Sister over notched stud in exterior wall near SW corner -Tighten anchor bolts in basement -Address over bored stud at SE cable -Protect SE cable -Secure SE cable within 12” -Complete electrical for island -Missing joist at south exterior wall entire length last joist is 21” oc **DO NOT INSULATE, TOO MANY DEFICIENCIES
Sewer Service Inspection - R Passed 7/14/2022 07/14/2022
Miscellaneous Correction
Corrective Action Required
03/07/2022
It appears that the MH (4511) in the back of the lot has been hit, there is also debris in the line. Contractor needs to make corrections to the MH.
Water Service Inspection - R Passed 7/15/2022 (1:00) 7/15/2022 07/15/2022
All Rough Inspection - Residential Failed 7/21/2022 7/21/2022 07/21/2022
Misc
Corrective Action Required
05/25/2022
-Provide 2 rows 16d sinkers 3” oc at plate to header at PFH -Identity metallic gas line bonding conductor at both ends-clamp needs to be accessible after finish. -Provide angle brackets at end joists of deck -Provide (2) 1/2” through bolts at all post to beam deck connections -Anchor column base near furnace, under suspended slab, and stairway OK to insulate
Gas Service Inspection - Residential Passed 7/26/2022 7/26/2022 07/26/2022
Misc
Resolved
07/26/2022
Electrical Service Inspection Passed 7/26/2022 7/26/2022 07/26/2022
Misc
Resolved
07/26/2022
All Rough Inspection - Residential Passed 7/26/2022 7/26/2022 07/26/2022
Misc
Informational
07/26/2022
-Provide angle brackets at end joists of deck -Provide (2) 1/2” through bolts at all post to beam deck connections
Driveway Inspection Passed 9/7/2022 9/7/2022 09/07/2022
Misc
Informational
09/07/2022
On Wednesday, 9-07-2022 I performed and passed a driveway for concrete placement.
Miscellaneous Inspection Passed 2/6/2023 2/6/2023 02/06/2023
Misc
Informational
02/06/2023
PERMIT HOLDER HAS REQUESTED AN EXTENSION TO COMPLETE TO PROJECT. WILL BE READY FOR FINAL IWITHIN 2 WEEKS
Footing Inspection - Residential Passed 04/25/2023
Misc
Resolved
04/25/2023
THIRD PARTY FOOTING REPORT REJECTED AS IT IS INCOMPLETE. FOOTING INSPECTION NOT COMPLETED DUE TO LACK OF EROSION CONTROL ON LOT AT TIME OF INSPECTION AS REQUIRED
Piers/Caissons Inspection - Residential Passed 04/25/2023
Plot Plan Inspection Passed 04/25/2023
Occupancy Inspection - Codes Residential Failed 4/25/2023 4/25/2023 04/25/2023
Misc
Corrective Action Required
04/25/2023
-GFCI at kitchen not working -Garage door needs self closing hinges -Label non GFCI's in garage -Laundry room needs to have GFCI -Spark ring missing at Fireplace outlet -Spark ring missing at kitchen outlets -Secondary lock missing at sliding glass door -Missing filler plate in breaker box -Ensure all Arc fault required in breaker panel E3902.16 of the 2018 IRC -Label non GFCI's in basement -secure whip to water heater -need lock out for all hardwired appliances -address post to beam connection at 1st to 2nd floor connection -paint gas pipe -connect sump pump discharge -splash blocks to discharge 36inches from foundation -secure whip at AC within 12 inches of disconnect box -obtained issued lawn irrigation permit
Erosion Control Inspection Residential Passed 5/11/2023 05/11/2023
Misc
Resolved
05/11/2023
Trash and debris complaint -contacted the builder and he will be on site and abate the issues.
Occupancy Inspection - Codes Residential Failed 5/11/2023 5/11/2023 05/11/2023
Misc
Corrective Action Required
04/25/2023
-Ensure all Arc fault required in breaker panel E3902.16 of the 2018 IRC -Label non GFCI's in basement -need lock out for all hardwired appliances -address post to beam connection at deck - ledger bolts missing at deck -paint gas pipe -obtain an lawn irrigation permit
Occupancy Inspection - Codes Residential Failed 5/12/2023 5/12/2023 05/12/2023
Misc
Corrective Action Required
05/11/2023
-Ensure all Arc fault required in breaker panel E3902.16 of the 2018 IRC missing on disposal and microwave -address post to beam connection at deck -address siding from grade at rear of lot - ledger bolts missing at deck -paint gas pipe -obtain an lawn irrigation permit
Occupancy Inspection - Codes Residential Full C of O 6/13/2023 6/14/2023 06/14/2023
Misc
Resolved
06/14/2023
Documents & Images
Date Uploaded File Type Document Name
02/23/2021 Application Form APPLICATION
02/23/2021 Application Form excise tax
02/23/2021 2021_02_11-20-199 LOT 2 PLOT PLAN REV1 SIGNED
02/23/2021 DW Permit Plan Villa Verona 1514 SW Heartwood Dr
02/24/2021 Letter Codes Residential Plan Review
03/10/2021 Letter Codes Residential Plan Review
04/29/2021 2021_04_22-20-199 LOT 2 PLOT PLAN REV2 CITY COMMENTS SIGNED
04/29/2021 DW Permit Plan Villa Verona 1514 SW Heartwood Dr 4_26_21
04/30/2021 Plot Plan APPROVED PLOT PLAN
04/30/2021 Letter Codes Residential Plan Review
05/05/2021 DW Permit Plan Villa Verona 1514 SW Heartwood Dr 5_5_21
05/07/2021 Plans APPROVED PLANS with materials call-out
07/21/2021 Permit DS Building Permit
07/21/2021 Receipt Receipt for transaction: 2021-005845
07/21/2021 Permit DS Building Permit
08/30/2021 1514 SW Heartwood Dr LSMO Woodland Glen Lot 2 3rd Party Footing Inspection Report 8-27-21
08/30/2021 Letter INSPECTION SUMMARY
08/30/2021 Letter INSPECTION SUMMARY
09/20/2021 Letter INSPECTION SUMMARY
10/12/2021 Letter INSPECTION SUMMARY
12/27/2021 Letter INSPECTION SUMMARY
03/07/2022 Letter Inspection Summary
03/22/2022 Letter INSPECTION SUMMARY
05/25/2022 Letter INSPECTION SUMMARY
05/25/2022 Letter INSPECTION SUMMARY
05/25/2022 Letter INSPECTION SUMMARY
07/14/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
09/07/2022 Letter INSPECTION SUMMARY
09/09/2022 Mill Creek Builders 1514 1518 SW Heartwood Dr LSMO Deck Support Post Pier Inspection Report 9-6-22 (002)
09/20/2022 Mill Creek Builders 1514 SW Heartwood Dr LSMO Deck Support Post Pier Inspection Report 9-6-22
01/25/2023 Letter Codes 140 Day Letter
02/06/2023 Letter INSPECTION SUMMARY
04/25/2023 Letter INSPECTION SUMMARY
04/25/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
05/12/2023 Letter INSPECTION SUMMARY
05/12/2023 Letter INSPECTION SUMMARY
05/12/2023 Letter INSPECTION SUMMARY
05/12/2023 Letter INSPECTION SUMMARY
06/14/2023 Letter Field Certificate of Occupancy
06/14/2023 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: