Permit Application Status

PRCOM20253573


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20253573
Building Permit - Commercial
In Plan Review
OLDHAM INVESTORS LLC
NEW COMMERCIAL
CLUB CAR WASH - NEW DRIVE THROUGH CAR WASH
08/22/2025
03/03/2026
Locations
Property
61500036400000000

Address
1031 SW JEFFERSON ST, LEES SUMMIT, MO 64081

1021 SW JEFFERSON CROSSING
Contacts
  
  
  
  
OLDHAM INVESTORS LLC, Address:7200 W 132ND ST STE 150  
Finkle + Williams Architecture, Address:8787 Renner Blvd. Suite 100, Phone:(913) 498-1550  
  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Rejected 09/04/2025 09/04/2025
Joe Frogge
License Tax - Payment
Corrective Action Required
09/04/2025

A one-time impact fee in the form of an excise tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process. Action required: Comment is informational. The fee will be $27,843.75
IBC 1209.2 Finish materials
Corrective Action Required
09/04/2025

2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4. 2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches. 2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) Action required: Specify compliant material at water closets. If paint is used it must be epoxy based.
IBC 1015.7 Roof access - roof hatch guard
Corrective Action Required
09/04/2025

2018 IBC 1015.7 Roof access. Guards shall be provided where the roof hatch opening is located within 10 feet of a roof edge or open side of a walking surface and such edge or open side is located more than 30 inches above the floor, roof or grade below. The guard shall be constructed so as to prevent the passage of a sphere 21 inches in diameter. (see code for exception) Action required: Provide guard at parapet near roof hatch.
Misc
Corrective Action Required
09/04/2025

Inadequate information to complete review. Provide the following: - Complete designs for cashier booth. - Complete designs for Trellis.
NEC Article 210.63 Heating, air-conditioning and refrigeration outlet
Corrective Action Required
09/04/2025

2017 NEC Article 210.63 Heating, Air-Conditioning, and Refrigeration Equipment Outlet. A 125-volt, single-phase, 15- or 20-ampere-rated receptacle outlet shall be installed at an accessible location for the servicing of heating, air-conditioning, and refrigeration equipment. The receptacle shall be located on the same level and within 25 feet of the heating, air-conditioning, and refrigeration equipment. The receptacle outlet shall not be connected to the load side of the equipment disconnecting means. Action required: Provide receptacle(s) on roof near hvac equipment.
Licensed Contractors Rejected 09/04/2025 09/04/2025
Joe Frogge
LC - General Contractor
Corrective Action Required
09/04/2025

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and the name, email address & phone number for the on-site contact.
LC - MEP Subs
Corrective Action Required
09/04/2025

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fire Plan Review Approved 09/04/2025 09/04/2025
Craig Hill
Final Development Plan Review Pending 09/19/2025
Grant White
Fire Plan Review Pending 09/24/2025
Craig Hill
Building Plan Review Pending 09/24/2025
Joe Frogge
License Tax - Payment
Corrective Action Required
09/17/2025

A one-time impact fee in the form of an excise tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process. Action required: Comment is informational. The fee will be $27,843.75
IBC 1209.2 Finish materials
Corrective Action Required
09/17/2025

2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4. 2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches. 2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) Action required: Specify compliant material at water closets. If paint is used it must be epoxy based.
IBC 1015.7 Roof access - roof hatch guard
Corrective Action Required
09/17/2025

2018 IBC 1015.7 Roof access. Guards shall be provided where the roof hatch opening is located within 10 feet of a roof edge or open side of a walking surface and such edge or open side is located more than 30 inches above the floor, roof or grade below. The guard shall be constructed so as to prevent the passage of a sphere 21 inches in diameter. (see code for exception) Action required: Provide guard at parapet near roof hatch.
Misc
Corrective Action Required
09/17/2025

Inadequate information to complete review. Provide the following: - Complete designs for cashier booth. - Complete designs for Trellis.
NEC Article 210.63 Heating, air-conditioning and refrigeration outlet
Corrective Action Required
09/17/2025

2017 NEC Article 210.63 Heating, Air-Conditioning, and Refrigeration Equipment Outlet. A 125-volt, single-phase, 15- or 20-ampere-rated receptacle outlet shall be installed at an accessible location for the servicing of heating, air-conditioning, and refrigeration equipment. The receptacle shall be located on the same level and within 25 feet of the heating, air-conditioning, and refrigeration equipment. The receptacle outlet shall not be connected to the load side of the equipment disconnecting means. Action required: Provide receptacle(s) on roof near hvac equipment.
Licensed Contractors Pending 09/24/2025
Joe Frogge
LC - General Contractor
Corrective Action Required
09/17/2025

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and the name, email address & phone number for the on-site contact.
LC - MEP Subs
Corrective Action Required
09/17/2025

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Commercial $5,800.00 $5,800.00 Paid 09/10/2025
Commercial Excise Tax Fee $27,843.75 $27,843.75 Paid 09/10/2025
Parks Impact Fee Non-Residential - Zone 4 $1,031.60 $1,031.60 Paid 09/10/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections

There are no inspections for this permit application.

Documents & Images
Date Uploaded File Type Document Name
08/22/2025 Application Form APPLICATION
08/22/2025 Plans Construction Plans
08/22/2025 Engineer Report/Study Envelope COMcheck
08/22/2025 Engineer Report/Study Geotechnical Report
08/22/2025 Engineer Report/Study Lighting & Mechanical COMcheck
08/22/2025 Engineer Report/Study Storm Report
08/22/2025 Engineer Report/Study Structural Calculations
08/26/2025 Letter License Tax Bill
09/04/2025 Letter DS P/R Corrections Document
09/10/2025 Receipt Receipt for transaction:2025-007022
09/17/2025 Letter 25-0917_CCW Lee's Summit, MO_City Response Letter
09/17/2025 Plans Trellis Construction Plans Sealed_6-6-2025
09/17/2025 Engineer Report/Study Trellis_Structural Calculations_Dig_ Sealed_6-6-2025
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: