Summary
PRCOM20215274
Building Permit - Commercial
Certificate of Occupancy
CHAPEL RIDGE TOWNHOMES LLC
NEW MULTI-FAMILY
NEW 4PLEX
10/08/2021
01/21/2022
06/23/2023
Locations
Contacts
CAPITAL CONSTRUCTION SERVICES LLC, Address:2642 NE HAGAN RD, Phone:(816) 875-0018  
DROTHFUSS@CAPITALCONST.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
INHOME SYSTEMS LLC, Address:510 MISSION RD SW, Phone:(816) 372-0483  
A BRIGHT PLUMBING LLC, Address:201 NE WOODBURY DR, Phone:(816) 867-4540  
DAVIDSON ARCHITECTURE & ENGINEERING, Address:4301 INDIAN CREEK PKWY, Phone:(913) 451-9390  
CHAPEL RIDGE TOWNHOMES LLC, Address:3701 NE AKIN DR  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 01/07/2022
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
8331506-EFHB Maybrook, Full $1,874.84 $1,874.84 Paid 01/20/2022
8331507-Sewer Connection Fee $1,320.00 $1,320.00 Paid 01/20/2022
7232302-Residential Excise Tax Fee $2,437.12 $2,437.12 Paid 01/20/2022
9110078-Valuation Fee for New 3 or 4 Family $2,349.12 $2,349.12 Paid 01/20/2022
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 06/02/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Passed 5/10/2022 (1:00) 5/10/2022 05/10/2022
Underslab Plumbing Inspection - Commercial Passed 5/23/2022 5/23/2022 05/23/2022
Rated Assembly Inspection Partial 7/21/2022 7/21/2022 07/21/2022
Misc
Informational
07/21/2022
Attic firewall-1st layer ok
Gas Service Inspection - Commercial Failed 8/31/2022 8/31/2022 08/31/2022
Misc
Corrective Action Required
08/31/2022
-Gas piping test pressure less than ten psi
All Rough Inspection - Commercial Failed 8/31/2022 8/31/2022 08/31/2022
Misc
Corrective Action Required
08/31/2022
-Cannot use s-tee fitting for vertical to horizontal drain connections above half bathroom UNIT A: -Fb garage wall; half bathroom wall -Anchor sill plate at entry door -Cannot use s-tee fitting for vertical to horizontal drain connections above half bathroom -Lower the master shower trap down so that the trap weir is not above the connection to the vented horizontal drain -Protect wiring within six ft of attic access -Fb all wall plate penetrations throughout -Vent master bathroom fan to outside -Fasten girder truss to wall with 2 screws -Insulation shield for b-vent must be min above insulation level. Min 1” space around b-vent UNIT B: -Tighten ledge board nut to garage I beam -Cannot use s-tee fitting for vertical to horizontal drain connections above half bathroom -Master shower S trap not allowed -Support plumbing above kitchen and dining area per code -Nail brace strap near refrigerator -Install roof flashing at vent penetrations -Vent bathroom fan to outside -Support plumbing vent in attic per code -Protect roof deck within 4 ft of firewall with fire-resistant sheathing -Insulation shield for b-vent must be min above insulation level. Min 1” space around b-vent UNIT C: -Fb garage wall -Cannot use s-tee fitting for vertical to horizontal drain connections above half bathroom -Master shower S trap not allowed -Support plumbing above kitchen per code; make sure it’s sloped per code -Nail brace strap near refrigerator; at closet/stair wall -Fb all wall plate penetrations throughout ; Fb opening at laundry/bathroom wall -Protect wiring at rear bedroom and bathroom wall corner; at laundry bottom wall plate -Install roof flashing at vent penetration -Vent bathroom fan to outside -B-vent shall slope upward min 1/4” per ft -Insulation shield for b-vent must be min above insulation level. Min 1” space around b-vent UNIT D: -Fb half bathroom wall -Cannot use s-tee fitting for vertical to horizontal drain connections above half bathroom -Protect wiring at stair wall above switch -Fb all wall plate penetrations throughout -Protect wiring within six ft of attic access; at inside corner of rear bedroom closet; at bottom wall plate in bathroom -Vent bathroom fan to outside -Insulation shield for b-vent must be min above insulation level. Min 1” space around b-vent -Protect water line in master closet **OK TO INSULATE
Electrical Service Inspection Failed 8/31/2022 8/31/2022 08/31/2022
Misc
Corrective Action Required
08/31/2022
-Fully tighten the main bonding screw within the enclosure
All Rough Inspection - Commercial Failed 9/7/2022 9/7/2022 09/07/2022
Misc
Corrective Action Required
08/31/2022
UNIT A: -Insulation shield for b-vent must be min above insulation level. Min 1” space around b-vent UNIT B: -Support plumbing above kitchen and dining area per code -Nail brace strap near refrigerator -Support plumbing vent in attic per code -Protect roof deck within 4 ft of firewall with fire-resistant sheathing -Insulation shield for b-vent must be min above insulation level. Min 1” space around b-vent UNIT C: -Nail brace strap near refrigerator; at closet/stair wall -B-vent shall slope upward min 1/4” per ft -Insulation shield for b-vent must be min above insulation level. Min 1” space around b-vent UNIT D: -Protect wiring at inside corner of rear bedroom closet; at bottom wall plate in bathroom -Vent bathroom fan to outside -Insulation shield for b-vent must be min above insulation level. Min 1” space around b-vent -Protect water line in master closet **OK TO INSULATE
Electrical Service Inspection Passed 9/7/2022 9/7/2022 09/07/2022
Misc
Resolved
09/07/2022
-Fully tighten the main bonding screw within the enclosure
Rated Assembly Inspection Partial 9/8/2022 9/8/2022 09/08/2022
Misc
Informational
07/21/2022
Attic firewall-OK Dwelling separation-1st layer ok
Gas Service Inspection - Commercial Failed 9/13/2022 9/13/2022 09/13/2022
Misc
Corrective Action Required
08/31/2022
-Gas piping test pressure less than ten psi at units A and C. Unit B&D ok
Rated Assembly Inspection Failed 9/13/2022 9/13/2022 09/13/2022
Misc
Informational
09/08/2022
Attic firewall-OK Dwelling separation-Fire caulk wall penetrations at I beam
Rated Assembly Inspection Passed 9/15/2022 9/15/2022 09/14/2022
Misc
Resolved
09/14/2022
Attic firewall-OK Dwelling separation-Fire caulk wall penetrations at I beam
All Rough Inspection - Commercial Passed 9/14/2022 9/14/2022 09/14/2022
Misc
Resolved
09/14/2022
UNIT A-OK UNIT B: -Support plumbing above kitchen and dining area per code UNIT C-OK UNIT D: -Protect wiring at bottom wall plate in bathroom
Gas Service Inspection - Commercial Passed 9/15/2022 9/15/2022 09/15/2022
Misc
Resolved
09/15/2022
-Gas piping test pressure less than ten psi at units A and C. Unit B&D ok
Occupancy Inspection - Codes Commercial Failed 2/23/2023 2/23/2023 02/23/2023
Misc
Corrective Action Required
02/23/2023
**Approval required from: Planning, Water, Field Service EXTERIOR: -Final grade, sod, splash blocks at downspout -Flash and seal above service equipment -Seal exterior lights, wall penetrations, etc -Fix AC whip connections to disconnects and flood light -Secure AC whips within 12” of disconnects UNIT A -Tighten D/D and dishwasher receptacle to box -Adjust garage door closers to fully close -Install anti-hammering arrestors at washer water outlet UNIT B: -Install switch cover plate under kitchen sink -Correctly relabel breaker serving kitchen countertop receptacles -Master bedroom smoke alarm not interconnected -Install anti-hammering arrestors at washer water outlet UNIT C: -Install anti-hammering arrestors at washer water outlet UNIT D: -Close off opening at panel cover -Install anti-hammering arrestors at washer water outlet
Occupancy Inspection - Codes Commercial Ready for Temp CO 2/27/2023 2/27/2023 02/27/2023
Misc
Corrective Action Required
02/23/2023
**Approval required from: Planning, Water, Field Service EXTERIOR: -Final grade, sod, splash blocks at downspout -Flash and seal above service equipment -Seal exterior lights, wall penetrations, etc **TCO APPROVED FOR ALL UNITS
Occupancy Inspection - Codes Commercial Failed 6/21/2023 06/21/2023
Misc
Corrective Action Required
02/27/2023
**Approval required from: Planning, Water, Field Service -Lot drainage issue-standing water -Complete outdoor receptacle outside unit D
Occupancy Inspection - Codes Commercial Full C of O 6/23/2023 06/23/2023
Misc
Resolved
06/23/2023
-Underground raceway to be min 18" below grade -Install tamperproof AC caps
Documents & Images
Date Uploaded File Type Document Name
01/20/2022 Receipt Receipt for transaction:2022-000334
05/10/2022 Letter INSPECTION SUMMARY
05/23/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
08/31/2022 Letter INSPECTION SUMMARY
08/31/2022 Letter INSPECTION SUMMARY
08/31/2022 Letter INSPECTION SUMMARY
09/07/2022 Letter INSPECTION SUMMARY
09/07/2022 Letter INSPECTION SUMMARY
09/08/2022 Letter INSPECTION SUMMARY
09/13/2022 Letter INSPECTION SUMMARY
09/13/2022 Letter INSPECTION SUMMARY
09/14/2022 Letter INSPECTION SUMMARY
09/14/2022 Letter INSPECTION SUMMARY
09/15/2022 Letter INSPECTION SUMMARY
02/23/2023 Letter INSPECTION SUMMARY
06/02/2023 Certificate/License Codes Temporary Certificate of Occupancy
06/02/2023 Receipt Receipt for transaction:2023-003915
06/21/2023 Letter INSPECTION SUMMARY
06/23/2023 Letter DS Building Permit
06/23/2023 Letter Codes Final Certificate of Occupancy
06/23/2023 Letter Field Certificate of Occupancy
12/20/2023 Codes Temporary Certificate of Occupancy215
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home