Permit Application Status

PRCOM20211738


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20211738
Building Permit - Commercial
Certificate of Occupancy
CITY OF LEES SUMMIT
NEW COMMERCIAL
NEW RESTAURANT
04/12/2021
06/02/2021
10/11/2021
05/20/2022
Locations
Contacts
CENTRIC SPECIAL OPS, LLC, Address:520 WEST PENNWAY ST, Phone:(816) 808-8166  
TEMP-CON LLC, Address:15670 S KEELER ST, Phone:(913) 768-4888  
MD ELECTRIC INC, Address:24625 JINGO RD, Phone:(913) 533-4076  
ACCURATE MECHANICAL LLC, Address:205 E 13TH AVE, Phone:(816) 471-2272  
URBAN PRAIRIE ARCHITECTRUAL COLLABRORATIVE - PALU MINTO, Address:4523 MERCIER ST, Phone:(816) 304-7416  
brian.kendrick@centric.build, Address:brian.kendrick@centric.build  
CITY OF LEES SUMMIT, Address:220 SE GREEN ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Sprinkler Plan Review Released for Construction 08/18/2021 08/18/2021
Michael Weissenbach
Installation acceptance testing
Corrective Action Required
08/18/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule a hydrostatic and a water flow test.
Alarm Plan Review Released for Construction 07/07/2021 07/07/2021
Michael Weissenbach
Installation acceptance testing
Corrective Action Required
07/07/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Miscellaneous Correction
Corrective Action Required
07/07/2021

(Action Required) 1. Remove outside horn/strobes in patio areas. The only outside horn/strobe needs to be placed by the FDC.
Alarm Plan Review Rejected 06/18/2021 06/18/2021
Michael Weissenbach
Installation acceptance testing
Corrective Action Required
06/18/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Miscellaneous Correction
Corrective Action Required
06/18/2021

(Action Required) 1. Outside horn/strobe to be located by FDC 2. Add notification devices throughout building.
Building Plan Review Approved with Conditions 05/18/2021 06/02/2021
Joe Frogge
Final Development Plan
Resolved
06/02/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 5/12/21 - acknowledged in letter
Health Dept Inspection
Corrective Action Required
05/11/2021

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 847-7070. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is for informational purposes. 5/12/21 - acknowledged in letter
Misc
Corrective Action Required
05/11/2021

Unable to locate where water service enters building. Action required: Clarify. We need to see backflow and pressure reducing devices as well as a floor drain (or daylight location) for RPZ. 5/12/21 - RPZ shown. Field verify PRV.
NEC Article 110.26 (C)(2) Large equipment
Resolved
05/12/2021

2017 NEC Article 110.26 (C)(3) Personnel Doors. Where equipment rated 800 A or more that contains overcurrent devices, switching devices, or control devices is installed and there is a personnel door(s) intended for entrance to and egress from the working space less than 25 feet from the nearest edge of the working space, the door(s) shall open in the direction of egress and be equipped with panic hardware. Action required: Provide panic hardware at door out of mechanical room 113.
Licensed Contractors Approved 05/18/2021 06/02/2021
Dawn Bell
LC - General Contractor
Resolved
05/20/2021

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact. 5/12/21 - acknowledged in letter
LC - MEP Subs
Resolved
06/02/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 5/12/21 - acknowledged in letter
Final Development Plan Review Approved 06/01/2021
Dawn Bell
Fire Plan Review Approved with Conditions 05/18/2021 05/12/2021
Michael Weissenbach
Posting of occupant load
Corrective Action Required
05/11/2021

2018 IFC 1004.3- Posting of occupant load. Every room or space that is an assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent. (Verified At Inspection) Post occupant load sign for the interior at 225. Post occupant load sign in the exterior patio at 56.
Construction documents for fire alarm systems
Corrective Action Required
05/11/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings for the fire alarm system to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
05/11/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Knox box required
Corrective Action Required
05/11/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knox Box from knoxbox.com. Placement to be made by FDC. 5/12/2021 (Verified At Inspection)
Construction documents - Fire protection systems
Corrective Action Required
05/11/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings for the fire sprinkler system to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
05/11/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Miscellaneous Correction
Resolved
05/12/2021

(Action Required) Provide specs on CO2 tank. More than 100 pounds of carbon dioxide will be required to have a gas detection system. 2018 IFC 5307.3
Panic and fire exit hardware
Resolved
05/12/2021

2018 IFC 1010.1.10 Panic and fire exit hardware. Doors serving a Group H occupancy and doors serving rooms or spaces with an occupant load of 50 or more in a Group A or E occupancy shall not be provided with a latch or lock unless it is a panic hardware or fire exit hardware. (Action Required) Provide panic hardware on doors 126-1 and 127-1 (Upper and lower patio doors)
Illumination required
Resolved
05/12/2021

2018 IFC 1008.1 Illumination required. The means of egress, shall be illuminated at all times the building space served by the means of egress is occupied. (Action Required) Provide exit/emergency lighting at doors 126-1 and 127-1 (Upper and lower patio doors)
Health Department Review Approved 05/11/2021
Joe Frogge
Building Plan Review Rejected 04/26/2021 04/14/2021
Joe Frogge
Final Development Plan
Corrective Action Required
04/14/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Health Dept Review
Resolved
05/11/2021

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 847-7070. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is for informational purposes.
Health Dept Inspection
Corrective Action Required
04/14/2021

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 847-7070. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is for informational purposes.
Misc
Corrective Action Required
04/14/2021

Unable to locate where water service enters building. Action required: Clarify. We need to see backflow and pressure reducing devices as well as a floor drain (or daylight location) for RPZ.
NEC Article 110.26 (C)(2) Large equipment
Corrective Action Required
04/14/2021

2017 NEC Article 110.26 (C)(3) Personnel Doors. Where equipment rated 800 A or more that contains overcurrent devices, switching devices, or control devices is installed and there is a personnel door(s) intended for entrance to and egress from the working space less than 25 feet from the nearest edge of the working space, the door(s) shall open in the direction of egress and be equipped with panic hardware. Action required: Provide panic hardware at door out of mechanical room 113.
Licensed Contractors Rejected 04/26/2021 04/14/2021
Joe Frogge
LC - General Contractor
Corrective Action Required
04/14/2021

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact.
LC - MEP Subs
Corrective Action Required
04/14/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fire Plan Review Rejected 04/26/2021 04/13/2021
Michael Weissenbach
Posting of occupant load
Corrective Action Required
04/13/2021

2018 IFC 1004.3- Posting of occupant load. Every room or space that is an assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent. (Verified At Inspection) Post occupant load sign for the interior at 225. Post occupant load sign in the exterior patio at 56.
Construction documents for fire alarm systems
Corrective Action Required
04/13/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings for the fire alarm system to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
04/13/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Knox box required
Corrective Action Required
04/13/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knox Box from knoxbox.com. Placement to be made by FDC.
Construction documents - Fire protection systems
Corrective Action Required
04/13/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings for the fire sprinkler system to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
04/13/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Miscellaneous Correction
Corrective Action Required
04/13/2021

(Action Required) Provide specs on CO2 tank. More than 100 pounds of carbon dioxide will be required to have a gas detection system. 2018 IFC 5307.3
Panic and fire exit hardware
Corrective Action Required
04/13/2021

2018 IFC 1010.1.10 Panic and fire exit hardware. Doors serving a Group H occupancy and doors serving rooms or spaces with an occupant load of 50 or more in a Group A or E occupancy shall not be provided with a latch or lock unless it is a panic hardware or fire exit hardware. (Action Required) Provide panic hardware on doors 126-1 and 127-1 (Upper and lower patio doors)
Illumination required
Corrective Action Required
04/13/2021

2018 IFC 1008.1 Illumination required. The means of egress, shall be illuminated at all times the building space served by the means of egress is occupied. (Action Required) Provide exit/emergency lighting at doors 126-1 and 127-1 (Upper and lower patio doors)
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Commercial $11,166.00 $11,166.00 Paid 05/28/2021
8331507-Sewer Connection Fee $600.00 $600.00 Paid 05/28/2021
7232302-Commercial License Tax Fee $23,895.00 $23,895.00 Paid 05/28/2021
91100C8-Sanitary Sewer Insp Fees $142.83 $142.83 Paid 05/28/2021
91100C9-Water Insp Fee $2,943.60 $2,943.60 Paid 05/28/2021
9110068-Storm Fee $363.00 $363.00 Paid 05/28/2021
9110081-Paved Surface Inspection Fee $5,896.44 $5,896.44 Paid 05/28/2021
9110071-Site Grading Fee $1,107.83 $1,107.83 Paid 05/28/2021
9110072-Water Test Fee $200.00 $200.00 Paid 05/28/2021
8350015-Water Meter Fee $3,456.47 $3,456.47 Paid 05/28/2021
8331401-Water Tap Fee $21,486.00 $21,486.00 Paid 05/28/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 05/28/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 7/7/2021 (2:30) 7/8/2021 07/08/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/08/2021
- LINE H 2 TO 7, LINE 7 H TO D, LINE 2 H TO D -
Footing Inspection - Commercial Partial 7/9/2021 (11:30) 7/9/2021 07/09/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/08/2021
- LINE H 2 TO 7, LINE 7 H TO D, LINE 2 H TO D - - LINE D 2 TO LINE A 2 , LINE 6 TO A LINE, UFER LOCATED MIDDLE WEST WALL -
Footing Inspection - Commercial Partial 7/12/2021 7/12/2021 07/12/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/09/2021
- LINE H 2 TO 7, LINE 7 H TO D, LINE 2 H TO D - - LINE D 2 TO LINE A 2 , LINE 6 TO A LINE, UFER LOCATED MIDDLE WEST WALL - - LINE 7 A TO H -
Footing Inspection - Commercial Partial 7/14/2021 (1:00) 7/14/2021 07/14/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/12/2021
- LINE H 2 TO 7, LINE 7 H TO D, LINE 2 H TO D - - LINE D 2 TO LINE A 2 , LINE 6 TO A LINE, UFER LOCATED MIDDLE WEST WALL - - LINE 7 A TO H - - (3) COLUMN PADS C LINE WEST END -
Footing Inspection - Commercial Partial 7/16/2021 07/16/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/14/2021
- LINE H 2 TO 7, LINE 7 H TO D, LINE 2 H TO D - - LINE D 2 TO LINE A 2 , LINE 6 TO A LINE, UFER LOCATED MIDDLE WEST WALL - - LINE 7 A TO H - - (3) COLUMN PADS C LINE WEST END - - (3) COLUMN PADS EAST SIDE, (3) PIERS SW CORNER W/ (6) # 5 VERT W/ # 4 WRAP @ 8" OC -
Footing Inspection - Commercial Partial 7/19/2021 (1:00) 7/19/2021 07/19/2021
Misc
Corrective Action Required
07/19/2021
- LINE H 2 TO 7, LINE 7 H TO D, LINE 2 H TO D - - LINE D 2 TO LINE A 2 , LINE 6 TO A LINE, UFER LOCATED MIDDLE WEST WALL - - LINE 7 A TO H - - (3) COLUMN PADS C LINE WEST END - - (3) COLUMN PADS EAST SIDE, (3) PIERS SW CORNER - - (4) PIERS SW CORNER -
Water Line - Construction Inspection Partial 7/20/2021 07/20/2021
Misc
Informational
07/20/2021
7-20-21 11:05am Bair has installed the 6” fire line and ran the 2” copper line for the under slab plumbing. They will be pouring the thrust blocks at approximately 1pm. Mike Harkins will look at this as well.
Footing Inspection - Commercial Partial 7/20/2021 (1:00) 7/20/2021 07/20/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/19/2021
- LINE H 2 TO 7, LINE 7 H TO D, LINE 2 H TO D - - LINE D 2 TO LINE A 2 , LINE 6 TO A LINE, UFER LOCATED MIDDLE WEST WALL - - LINE 7 A TO H - - (3) COLUMN PADS C LINE WEST END - - (3) COLUMN PADS EAST SIDE, (3) PIERS SW CORNER W/ (6) # 5 VERT W/ # 4 WRAP @ 8" OC - - PATIO FIREPLACE FOOTING -
Piers/Caissons Inspection - Commercial Partial 7/20/2021 (1:00) 7/20/2021 07/20/2021
Misc
Informational
07/20/2021
- (3) PIERS SW CORNER - - (4) PIERS SW CORNER - - (1) 24" X 88" PIER SE CORNER -
Underslab Plumbing Inspection - Commercial Partial 7/20/2021 7/20/2021 07/20/2021
Misc
Informational
07/20/2021
- FIRE LINE WEST WALL TO NORTH WALL EXITING BLDG ( JOE S ALSO INSPECTED) -
Piers/Caissons Inspection - Commercial Partial 7/21/2021 07/21/2021
Misc
Informational
07/20/2021
- (3) PIERS SW CORNER - - (4) PIERS SW CORNER - - (1) 24" X 88" PIER SE CORNER - - (1) SW CORNER, (3) NE CORNER -
Underground Electrical Inspection - Commercial Partial 7/23/2021 07/23/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/23/2021
- UNDERGROUND CONDUIT TRANSFORMER SE OF BLDG TO SW CORNER OF BLDG -
Underslab Plumbing Inspection - Commercial Partial 7/27/2021 7/27/2021 07/27/2021
Misc
Informational
07/20/2021
- FIRE LINE WEST WALL TO NORTH WALL EXITING BLDG ( JOE S ALSO INSPECTED) - - PARTIAL MAIN TRUCK LINES EXTERIOR OF BLDG TO RESTROOMS -
Site Visit Partial 7/29/2021 07/29/2021
Misc
Informational
07/29/2021
7-29-21 1:48pm There are no inspections needed from me at this time.
Underslab Plumbing Inspection - Commercial Partial 7/30/2021 7/30/2021 07/30/2021
Misc
Informational
07/27/2021
- FIRE LINE WEST WALL TO NORTH WALL EXITING BLDG ( JOE S ALSO INSPECTED) - - PARTIAL MAIN TRUCK LINES EXTERIOR OF BLDG TO RESTROOMS - - KITCHEN SANITARY LINES -
Underslab Plumbing Inspection - Commercial Partial 8/2/2021 8/2/2021 08/02/2021
Misc
Informational
07/30/2021
- FIRE LINE WEST WALL TO NORTH WALL EXITING BLDG ( JOE S ALSO INSPECTED) - - PARTIAL MAIN TRUCK LINES EXTERIOR OF BLDG TO RESTROOMS - - KITCHEN SANITARY LINES - - KITCHEN GREASE LINES, KITCHEN AREA COMPLETE -
Underslab Plumbing Inspection - Commercial Passed 8/4/2021 8/4/2021 08/04/2021
Misc
Informational
08/02/2021
- FIRE LINE WEST WALL TO NORTH WALL EXITING BLDG ( JOE S ALSO INSPECTED) - - PARTIAL MAIN TRUCK LINES EXTERIOR OF BLDG TO RESTROOMS - - KITCHEN SANITARY LINES - - KITCHEN GREASE LINES, KITCHEN AREA COMPLETE - - RESTROOMS & BAR AREA -
Site Visit Partial 8/4/2021 8/4/2021 08/04/2021
Misc
Informational
07/29/2021
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Underslab Electrical Inspection - Commercial Passed 8/6/2021 08/06/2021
Site Visit Partial 8/12/2021 08/12/2021
Misc
Informational
08/04/2021
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
08/12/2021
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Water Line - Construction Inspection Partial 8/16/2021 8/16/2021 08/17/2021
Misc
Informational
07/20/2021
7-20-21 11:05am Bair has installed the 6” fire line and ran the 2” copper line for the under slab plumbing. They will be pouring the thrust blocks at approximately 1pm. Mike Harkins will look at this as well.
Misc
Informational
08/17/2021
Don’s crew from Larry Bair Excavating laid 80 feet of 6 inch C 900 for. The fire line. RP 8-16-21
Misc
Informational
08/17/2021
They laid another 80 feet of 6 inch C 900 for the fire line. RP 8-17-21
Water Line - Construction Inspection Partial 8/18/2021 8/18/2021 08/18/2021
Misc
Informational
08/17/2021
7-20-21 11:05am Bair has installed the 6” fire line and ran the 2” copper line for the under slab plumbing. They will be pouring the thrust blocks at approximately 1pm. Mike Harkins will look at this as well.
Misc
Informational
08/17/2021
Don’s crew from Larry Bair Excavating laid 80 feet of 6 inch C 900 for. The fire line. RP 8-16-21
Misc
Informational
08/17/2021
They laid another 80 feet of 6 inch C 900 for the fire line. RP 8-17-21
Misc
Informational
08/18/2021
Don’s crew tied in the 6 inch fire line to the building. Still waiting on a fire hydrant. They poured thrust blocks for the 90 degree bend and the 6 inch tee. RP 8-18-21
Water Line - Construction Inspection Partial 8/19/2021 8/19/2021 08/19/2021
Misc
Informational
08/18/2021
7-20-21 11:05am Bair has installed the 6” fire line and ran the 2” copper line for the under slab plumbing. They will be pouring the thrust blocks at approximately 1pm. Mike Harkins will look at this as well.
Misc
Informational
08/18/2021
Don’s crew from Larry Bair Excavating laid 80 feet of 6 inch C 900 for. The fire line. RP 8-16-21
Misc
Informational
08/18/2021
They laid another 80 feet of 6 inch C 900 for the fire line. RP 8-17-21
Misc
Informational
08/18/2021
Don’s crew tied in the 6 inch fire line to the building. Still waiting on a fire hydrant. They poured thrust blocks for the 90 degree bend and the 6 inch tee. RP 8-18-21
Misc
Informational
08/19/2021
Fire hydrant was delivered to the job site and connected to the 6 inch fire line. Informed Don that the top will need to be painted silver since they are private hydrants. RP 8-19-21
Water Line - Construction Inspection Partial 8/20/2021 8/20/2021 08/23/2021
Misc
Informational
08/19/2021
7-20-21 11:05am Bair has installed the 6” fire line and ran the 2” copper line for the under slab plumbing. They will be pouring the thrust blocks at approximately 1pm. Mike Harkins will look at this as well.
Misc
Informational
08/19/2021
Don’s crew from Larry Bair Excavating laid 80 feet of 6 inch C 900 for. The fire line. RP 8-16-21
Misc
Informational
08/19/2021
They laid another 80 feet of 6 inch C 900 for the fire line. RP 8-17-21
Misc
Informational
08/19/2021
Don’s crew tied in the 6 inch fire line to the building. Still waiting on a fire hydrant. They poured thrust blocks for the 90 degree bend and the 6 inch tee. RP 8-18-21
Misc
Informational
08/19/2021
Fire hydrant was delivered to the job site and connected to the 6 inch fire line. Informed Don that the top will need to be painted silver since they are private hydrants. RP 8-19-21
Misc
Informational
08/23/2021
Fire hydrant was set and thrust blocks were poured. RP 8-20-21
Sanitary Sewer Construction Inspection Partial 8/23/2021 8/23/2021 08/23/2021
Misc
Informational
08/23/2021
Sanitary connections coming out of the building and grease interceptor are connected with hard back Fernco’s. RP 8-23-21
Sanitary Sewer Construction Inspection Partial 8/24/2021 8/24/2021 08/24/2021
Misc
Informational
08/23/2021
Sanitary connections coming out of the building and grease interceptor are connected with hard back Fernco’s. RP 8-23-21
Misc
Informational
08/24/2021
They tied into the sanitary main line with a Max Adapter coupler. They are closer to the manhole than the design calls for. RP 8-24-21
Storm Sewer Construction Inspection Partial 8/25/2021 8/25/2021 08/25/2021
Misc
Informational
08/25/2021
They set curb inlet, 20 feet of 18 inch HDPE storm pipe with a 22 1/2 degree bend to tie into Shake Shack field inlet. RP 8-25-21
Underground Plumbing Inspection - Commercial Partial 8/26/2021 8/26/2021 08/26/2021
Misc
Informational
08/26/2021
GREASE INTERCEPTOR NORTH OF BLDG OK TO COVER
Roof Drain Passed 8/27/2021 8/27/2021 08/27/2021
Misc
Informational
08/27/2021
8 inch roof drain is connected from building to curb inlet. They also installed 2 clean outs. RP 8-27-21
Site Visit Partial 8/30/2021 8/30/2021 08/30/2021
Misc
Informational
08/12/2021
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
08/12/2021
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
08/30/2021
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Water Line - Construction Inspection Partial 8/30/2021 8/30/2021 08/30/2021
Misc
Informational
08/23/2021
7-20-21 11:05am Bair has installed the 6” fire line and ran the 2” copper line for the under slab plumbing. They will be pouring the thrust blocks at approximately 1pm. Mike Harkins will look at this as well.
Misc
Informational
08/23/2021
Don’s crew from Larry Bair Excavating laid 80 feet of 6 inch C 900 for. The fire line. RP 8-16-21
Misc
Informational
08/23/2021
They laid another 80 feet of 6 inch C 900 for the fire line. RP 8-17-21
Misc
Informational
08/23/2021
Don’s crew tied in the 6 inch fire line to the building. Still waiting on a fire hydrant. They poured thrust blocks for the 90 degree bend and the 6 inch tee. RP 8-18-21
Misc
Informational
08/23/2021
Fire hydrant was delivered to the job site and connected to the 6 inch fire line. Informed Don that the top will need to be painted silver since they are private hydrants. RP 8-19-21
Misc
Informational
08/23/2021
Fire hydrant was set and thrust blocks were poured. RP 8-20-21
Misc
Informational
08/30/2021
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Water Line - Construction Inspection Partial 9/1/2021 9/1/2021 09/01/2021
Misc
Informational
08/30/2021
7-20-21 11:05am Bair has installed the 6” fire line and ran the 2” copper line for the under slab plumbing. They will be pouring the thrust blocks at approximately 1pm. Mike Harkins will look at this as well.
Misc
Informational
08/30/2021
Don’s crew from Larry Bair Excavating laid 80 feet of 6 inch C 900 for. The fire line. RP 8-16-21
Misc
Informational
08/30/2021
They laid another 80 feet of 6 inch C 900 for the fire line. RP 8-17-21
Misc
Informational
08/30/2021
Don’s crew tied in the 6 inch fire line to the building. Still waiting on a fire hydrant. They poured thrust blocks for the 90 degree bend and the 6 inch tee. RP 8-18-21
Misc
Informational
08/30/2021
Fire hydrant was delivered to the job site and connected to the 6 inch fire line. Informed Don that the top will need to be painted silver since they are private hydrants. RP 8-19-21
Misc
Informational
08/30/2021
Fire hydrant was set and thrust blocks were poured. RP 8-20-21
Misc
Informational
08/30/2021
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
09/01/2021
They poured the floor for the back flow vault. They also poured thrust and straddle blocks for the water line going into the vault. RP 9-1-21
Water Line - Construction Inspection Partial 9/2/2021 9/2/2021 09/02/2021
Misc
Informational
09/01/2021
7-20-21 11:05am Bair has installed the 6” fire line and ran the 2” copper line for the under slab plumbing. They will be pouring the thrust blocks at approximately 1pm. Mike Harkins will look at this as well.
Misc
Informational
09/01/2021
Don’s crew from Larry Bair Excavating laid 80 feet of 6 inch C 900 for. The fire line. RP 8-16-21
Misc
Informational
09/01/2021
They laid another 80 feet of 6 inch C 900 for the fire line. RP 8-17-21
Misc
Informational
09/01/2021
Don’s crew tied in the 6 inch fire line to the building. Still waiting on a fire hydrant. They poured thrust blocks for the 90 degree bend and the 6 inch tee. RP 8-18-21
Misc
Informational
09/01/2021
Fire hydrant was delivered to the job site and connected to the 6 inch fire line. Informed Don that the top will need to be painted silver since they are private hydrants. RP 8-19-21
Misc
Informational
09/01/2021
Fire hydrant was set and thrust blocks were poured. RP 8-20-21
Misc
Informational
09/01/2021
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
09/01/2021
They poured the floor for the back flow vault. They also poured thrust and straddle blocks for the water line going into the vault. RP 9-1-21
Misc
Informational
09/02/2021
They got the back-flow vault set today. RP 9-2-21
Site Visit Partial 9/3/2021 9/3/2021 09/03/2021
Misc
Informational
08/30/2021
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
08/30/2021
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
08/30/2021
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
09/03/2021
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Site Visit Partial 9/7/2021 9/7/2021 09/07/2021
Misc
Informational
09/03/2021
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
09/03/2021
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
09/03/2021
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
09/03/2021
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
09/07/2021
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Underground Electrical Inspection - Commercial Partial 9/10/2021 09/10/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/23/2021
- UNDERGROUND CONDUIT TRANSFORMER SE OF BLDG TO SW CORNER OF BLDG - - UNDERGROUND CONDUIT FOR 8 LIGHT POLE BASES -
Fire Line - Hydrostatic Test Passed 9/13/2021 9/13/2021 09/13/2021
Misc
Informational
09/13/2021
Fire line held over 200 psi for 2 hours. RP 9-13-21
Site Visit Partial 9/17/2021 9/17/2021 09/17/2021
Misc
Informational
09/07/2021
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
09/07/2021
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
09/07/2021
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
09/07/2021
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
09/07/2021
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
09/17/2021
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
In-wall Inspection Partial 10/11/2021 10/11/2021 10/11/2021
Misc
Informational
10/11/2021
- OSB PARAPET WALLS ROOF SIDE, DENSROCK EXTERIOR WALLS -
Site Visit Partial 11/4/2021 11/4/2021 11/04/2021
Misc
Informational
09/17/2021
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
09/17/2021
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
09/17/2021
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
09/17/2021
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
09/17/2021
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
09/17/2021
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
11/04/2021
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Pavement-Aggregate Base Partial 11/5/2021 11/5/2021 11/09/2021
Misc
Informational
11/09/2021
KAW Valley rolled out Tenax 302 geo grid and covered it with 6 inches of APWA Type 3 rock. So far they’ve laid out 115 tons of AB3. RP 11-9-21
In-wall Inspection Failed 11/16/2021 11/16/2021 11/16/2021
Misc
Informational
10/11/2021
- OSB PARAPET WALLS ROOF SIDE, DENSROCK EXTERIOR WALLS -
Miscellaneous Correction
Corrective Action Required
11/16/2021
Provide mid point support vertical 2" & smaller DWV Provide boca plate that extends 2" above & below top & bottom plates where required Complete Electrical in loft
In-wall Inspection Partial 11/17/2021 11/17/2021 11/17/2021
Misc
Informational
11/16/2021
- OSB PARAPET WALLS ROOF SIDE, DENSROCK EXTERIOR WALLS -
Miscellaneous Correction
Corrective Action Required
11/16/2021
: BAR AREA NOT READY FOR INSPECTION 11/17/21: OK TO COVER WALLS EXCEPT BAR
Pavement-Aggregate Base Partial 11/10/2021 11/10/2021 11/17/2021
Misc
Informational
11/09/2021
KAW Valley rolled out Tenax 302 geo grid and covered it with 6 inches of APWA Type 3 rock. So far they’ve laid out 115 tons of AB3. RP 11-9-21
Misc
Informational
11/17/2021
Kaw Valley rolled out more Tenax 302 and covered it with more AB3 rock. RP 11-17-21
Pavement-Proof Roll Partial 11/19/2021 11/19/2021 11/19/2021
Misc
Corrective Action Required
11/19/2021
Kaw Valley had a tandem dump truck with a 20.77 ton load. We proof rolled the curb line. Numerous sections failed the test. RP 11-19-21
Piers/Caissons Inspection - Commercial Partial 11/30/2021 (9:00) 11/30/2021 11/30/2021
Misc
Informational
07/21/2021
- (3) PIERS SW CORNER - - (4) PIERS SW CORNER - - (1) 24" X 88" PIER SE CORNER - - (1) SW CORNER, (3) NE CORNER - - 11/30/21 (8) LIGHT POLE BASES NORTH OF BLDG PER PLAN DRIVEN GROUND ROD AT EACH BASE -
Pavement-Proof Roll Partial 11/30/2021 11/30/2021 11/30/2021
Misc
Corrective Action Required
11/19/2021
Kaw Valley had a tandem dump truck with a 20.77 ton load. We proof rolled the curb line. Numerous sections failed the test. RP 11-19-21
Misc
Informational
11/30/2021
Kaw Valley had a tandem dump truck with a 21.9 ton load. The curb line passed the proof roll today. RP 11-29-21
Above Ceiling Inspection Partial 12/2/2021 12/02/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/02/2021
- 12/1/21 NORTH PATIO LIGHT FIXTURES -
Above Ceiling Inspection Partial 12/6/2021 12/06/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/02/2021
- 12/1/21 NORTH PATIO LIGHT FIXTURES - - 12/6/21 SOUTH PATIO LIGHT FIXTURES -
All Rough Inspection - Commercial Partial 12/6/2021 12/6/2021 12/06/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/06/2021
- NORTH & SOUTH PATIO LIGHT FIXTURES -
Above Ceiling Inspection Partial 12/7/2021 12/7/2021 12/07/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/06/2021
- 12/1/21 NORTH PATIO LIGHT FIXTURES - - 12/6/21 SOUTH PATIO LIGHT FIXTURES - - 12/7/21 HARD LIDS RESTROOMS & REAR ENTRY AT RESTROOMS OK TO COVER -
In-wall Inspection Failed 12/9/2021 12/9/2021 12/09/2021
Misc
Informational
11/17/2021
- OSB PARAPET WALLS ROOF SIDE, DENSROCK EXTERIOR WALLS -
Miscellaneous Correction
Corrective Action Required
11/17/2021
: BAR AREA NOT READY FOR INSPECTION 11/17/21: OK TO COVER WALLS EXCEPT BAR - 12/9/21 BAR AREA PROVIDE BONDING SCREW METAL BOXES PROVIDE BOCA PLATES DWV & PEX WATER LINES
Gas Service Inspection - Commercial Passed 12/10/2021 12/10/2021 12/10/2021
In-wall Inspection Partial 12/10/2021 12/10/2021 12/10/2021
Misc
Informational
12/09/2021
- OSB PARAPET WALLS ROOF SIDE, DENSROCK EXTERIOR WALLS -
Misc
Resolved
12/10/2021
OK TO COVER WALLS, INCLUDING BAR AREA
Pavement-Curb Construction Partial 12/13/2021 12/13/2021 12/13/2021
Misc
Informational
12/13/2021
Bedrock Concrete formed and poured the remaining curbing for the exterior of the parking lot. RP 12-13-21
Pavement-Proof Roll Partial 12/20/2021 12/20/2021 12/21/2021
Misc
Corrective Action Required
11/30/2021
Kaw Valley had a tandem dump truck with a 20.77 ton load. We proof rolled the curb line. Numerous sections failed the test. RP 11-19-21
Misc
Informational
11/30/2021
Kaw Valley had a tandem dump truck with a 21.9 ton load. The curb line passed the proof roll today. RP 11-29-21
Misc
Informational
12/21/2021
They had a tandem dump truck with a 23.7 ton load. We proof rolled the curb line in front of the building. The curb line passed the proof roll. RP 12-20-21
Above Ceiling Inspection Partial 12/21/2021 12/21/2021 12/21/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/07/2021
- 12/1/21 NORTH PATIO LIGHT FIXTURES - - 12/6/21 SOUTH PATIO LIGHT FIXTURES - - 12/7/21 HARD LIDS RESTROOMS & REAR ENTRY AT RESTROOMS OK TO COVER - -12/21/21 HARD LIDS UNDER STAIRWAY, ENTRY VESTIBULE. OK TO COVER -
Electrical Service Inspection Passed 12/22/2021 12/22/2021 12/22/2021
Hood/Duct Inspection Failed 1/14/2022 1/14/2022 01/14/2022
Miscellaneous Correction
Corrective Action Required
01/14/2022
BIG DOUBLE HOOD REPAIR MARKED PINHOLES IN WEST DUCT & EAST DUCT, COMPLETE ELBOWS TO ROOF EAST DUCT. DROP 100 WATT LIGHT FROM ROOF ALL 4 GREASE DUCTS
Hood/Duct Inspection Partial 1/18/2022 01/18/2022
Misc
Corrective Action Required
01/18/2022
WELDS APPROVED FOR 1ST LAYER WRAP
Hood/Duct Inspection Failed 1/19/2022 01/19/2022
Misc
Corrective Action Required
01/19/2022
WELDS APPROVED FOR 1ST LAYER WRAP 1ST LAYER FAIL PROVIDE CLEARANCES OR CONTINUOSLY COVER ON ALL SIDES WITH LISTED & LABELED FIELD APPLIED GREASE DUCT ENCLOSURE MATERIAL ( 2018 IMC 506.3.6 )
Hood/Duct Inspection Partial 1/21/2022 1/21/2022 01/21/2022
Misc
Corrective Action Required
01/19/2022
WELDS APPROVED FOR 1ST LAYER WRAP 1ST LAYER WRAP APPROVED FOR 2ND LAYER
Hood/Duct Inspection Passed 1/24/2022 1/24/2022 01/24/2022
Misc
Corrective Action Required
01/21/2022
WELDS APPROVED FOR 1ST LAYER WRAP 1ST LAYER WRAP APPROVED FOR 2ND LAYER 2ND LAYER WRAP APPROVED ALL 4 GREASE DUCTS
Site Visit Partial 2/9/2022 02/09/2022
Misc
Informational
11/04/2021
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
11/04/2021
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
11/04/2021
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
11/04/2021
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
11/04/2021
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
11/04/2021
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
11/04/2021
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
02/09/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Sanitary Sewer Construction Inspection Passed 2/15/2022 02/15/2022
Misc
Informational
08/24/2021
Sanitary connections coming out of the building and grease interceptor are connected with hard back Fernco’s. RP 8-23-21
Misc
Informational
08/24/2021
They tied into the sanitary main line with a Max Adapter coupler. They are closer to the manhole than the design calls for. RP 8-24-21
Water Line - Construction Inspection Partial 2/15/2022 02/15/2022
Misc
Informational
09/02/2021
7-20-21 11:05am Bair has installed the 6” fire line and ran the 2” copper line for the under slab plumbing. They will be pouring the thrust blocks at approximately 1pm. Mike Harkins will look at this as well.
Misc
Informational
09/02/2021
Don’s crew from Larry Bair Excavating laid 80 feet of 6 inch C 900 for. The fire line. RP 8-16-21
Misc
Informational
09/02/2021
They laid another 80 feet of 6 inch C 900 for the fire line. RP 8-17-21
Misc
Informational
09/02/2021
Don’s crew tied in the 6 inch fire line to the building. Still waiting on a fire hydrant. They poured thrust blocks for the 90 degree bend and the 6 inch tee. RP 8-18-21
Misc
Informational
09/02/2021
Fire hydrant was delivered to the job site and connected to the 6 inch fire line. Informed Don that the top will need to be painted silver since they are private hydrants. RP 8-19-21
Misc
Informational
09/02/2021
Fire hydrant was set and thrust blocks were poured. RP 8-20-21
Misc
Informational
09/02/2021
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
09/02/2021
They poured the floor for the back flow vault. They also poured thrust and straddle blocks for the water line going into the vault. RP 9-1-21
Misc
Informational
09/02/2021
They got the back-flow vault set today. RP 9-2-21
Misc
Corrective Action Required
02/15/2022
Still need to mark fire hydrant as private (silver top). RP 2-15-22
Sidewalk Inspection Partial 2/15/2022 02/15/2022
Misc
Informational
02/15/2022
Forms were placed and aggregate was present and compacted. Had Bedrock Concrete adjust forms to match fountain patio. RP 2-15-22
Pavement-Aggregate Base Partial 12/14/2021 12/14/2021 02/15/2022
Misc
Informational
11/17/2021
KAW Valley rolled out Tenax 302 geo grid and covered it with 6 inches of APWA Type 3 rock. So far they’ve laid out 115 tons of AB3. RP 11-9-21
Misc
Informational
11/17/2021
Kaw Valley rolled out more Tenax 302 and covered it with more AB3 rock. RP 11-17-21
Misc
Informational
02/15/2022
Kaw Valley still rolling on geogrid and laying down AB3 for the parking lot subgrade. RP 2-15-22
Sprinkler - Hydrostatic Test Passed 2/17/2022 02/17/2022
Above Ceiling Inspection Passed 2/18/2022 2/18/2022 02/18/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/21/2021
- 12/1/21 NORTH PATIO LIGHT FIXTURES - - 12/6/21 SOUTH PATIO LIGHT FIXTURES - - 12/7/21 HARD LIDS RESTROOMS & REAR ENTRY AT RESTROOMS OK TO COVER - -12/21/21 HARD LIDS UNDER STAIRWAY, ENTRY VESTIBULE. OK TO COVER - - OK TO INSTALL CEILING TILES -
Site Visit Partial 2/10/2022 2/10/2022 02/21/2022
Misc
Informational
02/09/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
02/09/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
02/09/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
02/09/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
02/09/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
02/09/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
02/09/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
02/09/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
02/21/2022
No work being done due to the snow storm. RP 2-17-22
Site Visit Partial 2/22/2022 2/22/2022 02/22/2022
Misc
Informational
02/21/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
02/21/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
02/21/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
02/21/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
02/21/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
02/21/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
02/21/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
02/21/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
02/21/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/22/2022
No utility or exterior work being done today. RP 2-22-22
Site Visit Partial 2/24/2022 2/24/2022 02/24/2022
Misc
Informational
02/22/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
02/22/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
02/22/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
02/22/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
02/22/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
02/22/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
02/22/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
02/22/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
02/22/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/22/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
02/24/2022
No exterior work being done today due to snow. RP 2-24-22
Site Visit Partial 2/25/2022 2/25/2022 02/25/2022
Misc
Informational
02/24/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
02/24/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
02/24/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
02/24/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
02/24/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
02/24/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
02/24/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
02/24/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
02/24/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/24/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
02/24/2022
No exterior work being done today due to snow. RP 2-24-22
Misc
Informational
02/25/2022
No work being done today that needs inspection. RP 2-25-22
Site Visit Partial 2/28/2022 2/28/2022 02/28/2022
Misc
Informational
02/25/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
02/25/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
02/25/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
02/25/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
02/25/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
02/25/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
02/25/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
02/25/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
02/25/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/25/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
02/25/2022
No exterior work being done today due to snow. RP 2-24-22
Misc
Informational
02/25/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
02/28/2022
Talked with Brian about asphalt specs for the parking lot. Kaw Valley was grading and laying rock down for the parking lot. RP 2-28-22
Sidewalk Inspection Passed 2/25/2022 2/25/2022 03/01/2022
Misc
Informational
02/15/2022
Forms were placed and aggregate was present and compacted. Had Bedrock Concrete adjust forms to match fountain patio. RP 2-15-22
Misc
Informational
03/01/2022
The shared use path around the building and fountain meets LS and ADA specs. RP 3-1-22
Pavement-Curb Construction Passed 12/22/2021 1/3/2022 03/01/2022
Misc
Informational
12/13/2021
Bedrock Concrete formed and poured the remaining curbing for the exterior of the parking lot. RP 12-13-21
Misc
Informational
01/03/2022
Bedrock concrete poured curbs around building exterior. Had framing up, and blankets to protect sub grade prior to removing today to pour. Blankets on-site to cover new curb. 1/3/22 ES
Misc
Informational
03/01/2022
Site Visit Partial 3/2/2022 3/2/2022 03/03/2022
Misc
Informational
02/28/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
02/28/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
02/28/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
02/28/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
02/28/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
02/28/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
02/28/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
02/28/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
02/28/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/28/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
02/28/2022
No exterior work being done today due to snow. RP 2-24-22
Misc
Informational
02/28/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
02/28/2022
Talked with Brian about asphalt specs for the parking lot. Kaw Valley was grading and laying rock down for the parking lot. RP 2-28-22
Misc
Informational
03/03/2022
Talked with Brian from Centric. We are planning on a proof roll next Monday depending incoming weather this weekend. RP 3-3-22
Site Visit Partial 3/4/2022 3/4/2022 03/14/2022
Misc
Informational
03/03/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
03/03/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
03/03/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
03/03/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
03/03/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
03/03/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
03/03/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
03/03/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
03/03/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/03/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/03/2022
No exterior work being done today due to snow. RP 2-24-22
Misc
Informational
03/03/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/03/2022
Talked with Brian about asphalt specs for the parking lot. Kaw Valley was grading and laying rock down for the parking lot. RP 2-28-22
Misc
Informational
03/03/2022
Talked with Brian from Centric. We are planning on a proof roll next Monday depending incoming weather this weekend. RP 3-3-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Site Visit Partial 3/14/2022 03/14/2022
Misc
Informational
03/14/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
03/14/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
03/14/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
03/14/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
03/14/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
03/14/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
03/14/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
03/14/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
03/14/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/14/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/14/2022
No exterior work being done today due to snow. RP 2-24-22
Misc
Informational
03/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/14/2022
Talked with Brian about asphalt specs for the parking lot. Kaw Valley was grading and laying rock down for the parking lot. RP 2-28-22
Misc
Informational
03/14/2022
Talked with Brian from Centric. We are planning on a proof roll next Monday depending incoming weather this weekend. RP 3-3-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/14/2022
KAW Valley was on site compacting and preparing the subgrade for it’s proof roll tomorrow. RP 3-14-22
Pavement-Proof Roll Passed 3/15/2022 3/15/2022 03/15/2022
Misc
Corrective Action Required
12/21/2021
Kaw Valley had a tandem dump truck with a 20.77 ton load. We proof rolled the curb line. Numerous sections failed the test. RP 11-19-21
Misc
Informational
12/21/2021
Kaw Valley had a tandem dump truck with a 21.9 ton load. The curb line passed the proof roll today. RP 11-29-21
Misc
Informational
12/21/2021
They had a tandem dump truck with a 23.7 ton load. We proof rolled the curb line in front of the building. The curb line passed the proof roll. RP 12-20-21
Misc
Informational
03/15/2022
They had a tandem dump truck with a 20.88 ton load. There was just one small spot next to the clean out in front of the building that had some deflection. They had excess material on site and will rework that section. RP 3-15-22
Pavement-Surface Partial 3/16/2022 3/16/2022 03/21/2022
Misc
Informational
03/21/2022
Shawn’s crew put in ~800 tons of base, doing single lift on parking areas and two lifts on drive lanes. Intertek PSI was on site doing compaction testing. 3/16/22 ES
Pavement-Surface Partial 3/21/2022 03/21/2022
Misc
Informational
03/21/2022
Shawn’s crew put in ~800 tons of base, doing single lift on parking areas and two lifts on drive lanes. Intertek PSI was on site doing compaction testing. 3/16/22 ES
Misc
Informational
03/21/2022
Shawn’s crew put down ~320 tons of type 3 surface. Intertek PSI was on site doing compaction testing. 3/17/22 ES
Site Visit Partial 3/21/2022 3/21/2022 03/21/2022
Misc
Informational
03/14/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
03/14/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
03/14/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
03/14/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
03/14/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
03/14/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
03/14/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
03/14/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
03/14/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/14/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/14/2022
No exterior work being done today due to snow. RP 2-24-22
Misc
Informational
03/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/14/2022
Talked with Brian about asphalt specs for the parking lot. Kaw Valley was grading and laying rock down for the parking lot. RP 2-28-22
Misc
Informational
03/14/2022
Talked with Brian from Centric. We are planning on a proof roll next Monday depending incoming weather this weekend. RP 3-3-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/14/2022
KAW Valley was on site compacting and preparing the subgrade for it’s proof roll tomorrow. RP 3-14-22
Misc
Informational
03/21/2022
Stopped by and talked with Brian about the upcoming TCO inspection. RP 3-21-22
Water Line - Construction Inspection Passed 3/17/2022 3/17/2022 03/21/2022
Misc
Informational
02/15/2022
7-20-21 11:05am Bair has installed the 6” fire line and ran the 2” copper line for the under slab plumbing. They will be pouring the thrust blocks at approximately 1pm. Mike Harkins will look at this as well.
Misc
Informational
02/15/2022
Don’s crew from Larry Bair Excavating laid 80 feet of 6 inch C 900 for. The fire line. RP 8-16-21
Misc
Informational
02/15/2022
They laid another 80 feet of 6 inch C 900 for the fire line. RP 8-17-21
Misc
Informational
02/15/2022
Don’s crew tied in the 6 inch fire line to the building. Still waiting on a fire hydrant. They poured thrust blocks for the 90 degree bend and the 6 inch tee. RP 8-18-21
Misc
Informational
02/15/2022
Fire hydrant was delivered to the job site and connected to the 6 inch fire line. Informed Don that the top will need to be painted silver since they are private hydrants. RP 8-19-21
Misc
Informational
02/15/2022
Fire hydrant was set and thrust blocks were poured. RP 8-20-21
Misc
Informational
02/15/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
02/15/2022
They poured the floor for the back flow vault. They also poured thrust and straddle blocks for the water line going into the vault. RP 9-1-21
Misc
Informational
02/15/2022
They got the back-flow vault set today. RP 9-2-21
Misc
Corrective Action Required
02/15/2022
Still need to mark fire hydrant as private (silver top). RP 2-15-22
Misc
Informational
03/21/2022
Fire hydrant has been marked as private. RP 3-21-22
Water Line - Hydrostatic Test Passed 3/21/2022 03/21/2022
Misc
Informational
03/21/2022
Already passed testing on 9-13-21. RP 3-21-22
Storm Sewer Construction Inspection Passed 3/21/2022 03/21/2022
Misc
Informational
08/25/2021
They set curb inlet, 20 feet of 18 inch HDPE storm pipe with a 22 1/2 degree bend to tie into Shake Shack field inlet. RP 8-25-21
Pavement-Aggregate Base Passed 3/21/2022 03/21/2022
Misc
Informational
02/15/2022
KAW Valley rolled out Tenax 302 geo grid and covered it with 6 inches of APWA Type 3 rock. So far they’ve laid out 115 tons of AB3. RP 11-9-21
Misc
Informational
02/15/2022
Kaw Valley rolled out more Tenax 302 and covered it with more AB3 rock. RP 11-17-21
Misc
Informational
02/15/2022
Kaw Valley still rolling on geogrid and laying down AB3 for the parking lot subgrade. RP 2-15-22
Pavement-Surface Passed 3/21/2022 03/21/2022
Misc
Informational
03/21/2022
Shawn’s crew put in ~800 tons of base, doing single lift on parking areas and two lifts on drive lanes. Intertek PSI was on site doing compaction testing. 3/16/22 ES
Misc
Informational
03/21/2022
Shawn’s crew put down ~320 tons of type 3 surface. Intertek PSI was on site doing compaction testing. 3/17/22 ES
Site Visit Partial 3/22/2022 3/22/2022 03/22/2022
Misc
Informational
03/21/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
03/21/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
03/21/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
03/21/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
03/21/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
03/21/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
03/21/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
03/21/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
03/21/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/21/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/21/2022
No exterior work being done today due to snow. RP 2-24-22
Misc
Informational
03/21/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/21/2022
Talked with Brian about asphalt specs for the parking lot. Kaw Valley was grading and laying rock down for the parking lot. RP 2-28-22
Misc
Informational
03/21/2022
Talked with Brian from Centric. We are planning on a proof roll next Monday depending incoming weather this weekend. RP 3-3-22
Misc
Informational
03/21/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/21/2022
KAW Valley was on site compacting and preparing the subgrade for it’s proof roll tomorrow. RP 3-14-22
Misc
Informational
03/21/2022
Stopped by and talked with Brian about the upcoming TCO inspection. RP 3-21-22
Misc
Informational
03/22/2022
Problems with the sprinkler system, so they canceled the TCO inspection. RP 3-22-22
Occupancy Inspection - Engineering Temporary C of O 3/22/2022 03/22/2022
Misc
Informational
03/22/2022
TCO is granted on our end Needed to have Final Occupancy 1. Grading needs to be completed on-site 2. Vegetation needs to be established at 70% 3. All trash and debris needs to be cleaned up and removed from the site.
Occupancy Inspection - Planning Failed 3/22/2022 03/22/2022
Corrective Action Required
03/22/2022
The trash enclosure gate was not installed at time of inspection.
Corrective Action Required
03/22/2022
The exterior lighting was not installed at time of inspection.
Corrective Action Required
03/22/2022
The landscaping had not been installed at time of inspection.
Corrective Action Required
03/22/2022
General site clean up is needed (roll-offs) in the parking lot blocking spaces, etc. This would prevent a TCO to be issued.
Corrective Action Required
03/22/2022
There are 9 spaces that are not striped on the north portion of the lot, east of the driveway and adjacent to the trash enclosure.
Occupancy Inspection - Planning Failed 3/23/2022 03/23/2022
Erosion Control Inspection Residential Partial 3/23/2022 03/23/2022
Misc
Informational
03/23/2022
No erosion issues on the job site. RP 3-23-22
Alarm Test Passed 3/23/2022 03/23/2022
Sprinkler - Flow Test Passed 3/23/2022 03/23/2022
Erosion Control Inspection Partial 3/24/2022 03/24/2022
Misc
Informational
03/24/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Occupancy Inspection - Water Utilities Passed 3/24/2022 03/24/2022
Underground Plumbing Inspection - Commercial Passed 3/24/2022 03/25/2022
Misc
Resolved
03/25/2022
GREASE INTERCEPTOR NORTH OF BLDG OK TO COVER
In-wall Inspection Passed 3/25/2022 03/25/2022
Misc
Resolved
03/25/2022
- OSB PARAPET WALLS ROOF SIDE, DENSROCK EXTERIOR WALLS -
Piers/Caissons Inspection - Commercial Passed 3/24/2022 03/25/2022
Misc
Resolved
03/25/2022
- (3) PIERS SW CORNER - - (4) PIERS SW CORNER - - (1) 24" X 88" PIER SE CORNER - - (1) SW CORNER, (3) NE CORNER - - 11/30/21 (8) LIGHT POLE BASES NORTH OF BLDG PER PLAN DRIVEN GROUND ROD AT EACH BASE -
Footing Inspection - Commercial Passed 3/24/2022 03/25/2022
THE FOLLOWING AREAS ARE APPROVED
Resolved
03/25/2022
- LINE H 2 TO 7, LINE 7 H TO D, LINE 2 H TO D - - LINE D 2 TO LINE A 2 , LINE 6 TO A LINE, UFER LOCATED MIDDLE WEST WALL - - LINE 7 A TO H - - (3) COLUMN PADS C LINE WEST END - - (3) COLUMN PADS EAST SIDE, (3) PIERS SW CORNER W/ (6) # 5 VERT W/ # 4 WRAP @ 8" OC - - PATIO FIREPLACE FOOTING -
All Rough Inspection - Commercial Passed 3/24/2022 03/25/2022
THE FOLLOWING AREAS ARE APPROVED
Resolved
03/25/2022
- NORTH & SOUTH PATIO LIGHT FIXTURES -
Underground Electrical Inspection - Commercial Passed 3/24/2022 03/25/2022
THE FOLLOWING AREAS ARE APPROVED
Resolved
03/25/2022
- UNDERGROUND CONDUIT TRANSFORMER SE OF BLDG TO SW CORNER OF BLDG - - UNDERGROUND CONDUIT FOR 8 LIGHT POLE BASES -
Alternate Protection Systems Inspection Failed 3/24/2022 03/25/2022
Misc
Corrective Action Required
03/25/2022
Gas on hood system did not terminate e when remote pull as activated.
Occupancy Inspection - Engineering Temporary C of O 3/25/2022 03/25/2022
Misc
Informational
03/22/2022
TCO is granted on our end Needed to have Final Occupancy 1. Grading needs to be completed on-site 2. Vegetation needs to be established at 70% 3. All trash and debris needs to be cleaned up and removed from the site.
Misc
Informational
03/25/2022
TCO is granted on our end Needed to have for Final Occupancy 1. Grading needs to be completed on-site 2. Vegetation needs to be established at 70% 3. All trash and debris needs to be cleaned up and removed from the site. 4. Will will check back in 30 days on April 25.
Water Service Inspection Passed 3/25/2022 03/25/2022
Misc
Informational
03/25/2022
Meter well has wrong lid. RP 3-25-22
Occupancy Inspection - Codes Commercial Failed 3/25/2022 3/25/2022 03/25/2022
Misc
Corrective Action Required
03/25/2022
-Approval required from: Fire, Field Service Engineer, Planning, Water, Jackson County Health -Open light box above outdoor walk-in cooler area; complete all outdoor electrical -Outdoor eating area: exit door threshold not meeting ANSI/ADA requirement. Top of the threshold must be no more than 1/2” above floor; Provide landing at both sides of door -Install restroom signage -Install sprinkler plate in men restroom ADA room -Install listed handle ties for breakers -Bond around valves from water service line to building copper water supply w/ conductor sized per NEC 250.66 -Verify with Michael Harkins about service grounding to water -Close open electrical gutter box in electrical room 113 -All receptacles in kitchen area must be gfci-protected per NEC 210.8(B) -Return ramp handrail to wall or floor -Provide maximum 90 amp breaker for RTU-4 -Provide a receptacle within 25 ft of the rooftop units -Complete vestibule 101; all seatings in dining areas -Provide EM lighting at outdoor eating area and inside per plan -Provide performance test report for kitchen hood system as required per IMC 507.6. Smoke test will be performed when ready **OK FOR STOCKING AND TRAINING
Occupancy Inspection - Fire Temporary C of O 3/25/2022 3/25/2022 03/25/2022
Misc
Corrective Action Required
03/25/2022
TCO for stocking only. NO cooking Need a Ash dumpster Spark arrester filter for wood grill ansul hood Add K class extinguisher next to wood grill 704 placard for gate leading to carbon dioxide tank Add a 2A10BC extinguisher in kitchen area
Alternate Protection Systems Inspection Passed 3/28/2022 03/28/2022
03/28/2022
Site Visit Partial 3/23/2022 3/23/2022 04/01/2022
Misc
Informational
03/22/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
03/22/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
03/22/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
03/22/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
03/22/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
03/22/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
03/22/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
03/22/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
03/22/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/22/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/22/2022
No exterior work being done today due to snow. RP 2-24-22
Misc
Informational
03/22/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/22/2022
Talked with Brian about asphalt specs for the parking lot. Kaw Valley was grading and laying rock down for the parking lot. RP 2-28-22
Misc
Informational
03/22/2022
Talked with Brian from Centric. We are planning on a proof roll next Monday depending incoming weather this weekend. RP 3-3-22
Misc
Informational
03/22/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/22/2022
KAW Valley was on site compacting and preparing the subgrade for it’s proof roll tomorrow. RP 3-14-22
Misc
Informational
03/22/2022
Stopped by and talked with Brian about the upcoming TCO inspection. RP 3-21-22
Misc
Informational
03/22/2022
Problems with the sprinkler system, so they canceled the TCO inspection. RP 3-22-22
Misc
Informational
04/01/2022
Bedrock Concrete formed up a walkway from the patio to the walking trail behind the building. Forms were placed and aggregate was present and compacted. RP 4-1-22
Occupancy Inspection - Planning Temporary C of O 4/5/2022 4/5/2022 04/05/2022
Corrective Action Required
04/05/2022
General site clean-up is needed within the parking lot.
Occupancy Inspection - Codes Commercial Failed 4/5/2022 4/5/2022 04/05/2022
Misc
Corrective Action Required
03/25/2022
-Approval required from: Fire, Field Service Engineer, Planning, Water, Jackson County Health -Install restroom signage -All receptacles in kitchen area must be gfci-protected per NEC 210.8(B) ( BREAD WARMER ) -Return ramp handrail to wall or floor patio -Complete vestibule 101; all seatings in dining areas -Provide performance test report for kitchen hood system as required per IMC 507.6. Smoke test will be performed when ready **OK FOR STOCKING AND TRAINING
Occupancy Inspection - Engineering Passed 4/5/2022 4/5/2022 04/05/2022
Misc
Informational
03/25/2022
TCO is granted on our end Needed to have Final Occupancy 1. Grading needs to be completed on-site 2. Vegetation needs to be established at 70% 3. All trash and debris needs to be cleaned up and removed from the site.
Misc
Informational
03/25/2022
TCO is granted on our end Needed to have for Final Occupancy 1. Grading needs to be completed on-site 2. Vegetation needs to be established at 70% 3. All trash and debris needs to be cleaned up and removed from the site. 4. Will will check back in 30 days on April 25.
Misc
Informational
04/05/2022
Site has been sodded, gutter buddies have been removed and trash / debris around the site is being picked up. All work in the field is complete. RP 4-5-22
Erosion Control Inspection Passed 4/5/2022 04/05/2022
Misc
Informational
03/24/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Misc
Informational
04/05/2022
Site has been sodded and gutter buddies have been removed. RP 4-5-22
Site Visit Complete 4/4/2022 4/4/2022 04/05/2022
Misc
Informational
04/01/2022
7-29-21 1:48pm There are no inspections needed from me at this time. 8-4-21 10:38am There is no work that requires inspections at this time.
Misc
Informational
04/01/2022
Met with Brian from Centric and talked about the project. Don’s crew from Larry Bair Excavating was digging trenches for the domestic water line and the fire water line. RP 8-12-21
Misc
Informational
04/01/2022
Don’s crew from Bair dug up and formed the floor for the back flow vault. RP 8-30-21
Misc
Informational
04/01/2022
Back-flow vault has been set, thrust blocks have been poured and back filled. RP 9-3-21
Misc
Informational
04/01/2022
Don’s crew is sealing and grouting the back-flow vault. RP 9-7-21
Misc
Informational
04/01/2022
Don’s crew set water and irrigation meters after water tapped the service line. RP 9-17-21
Misc
Informational
04/01/2022
Met with Brian to discuss parking lot sub-grade. They have the right geo grid on site (Tenax 302). They are cutting the parking lot down to grade. RP 11-4-21
Misc
Informational
04/01/2022
Met with Brian on site. Discussed the requirements concerning the shared-used path behind the building. No exterior work being done today that needed inspection. RP 2-9-22
Misc
Informational
04/01/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
04/01/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
04/01/2022
No exterior work being done today due to snow. RP 2-24-22
Misc
Informational
04/01/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
04/01/2022
Talked with Brian about asphalt specs for the parking lot. Kaw Valley was grading and laying rock down for the parking lot. RP 2-28-22
Misc
Informational
04/01/2022
Talked with Brian from Centric. We are planning on a proof roll next Monday depending incoming weather this weekend. RP 3-3-22
Misc
Informational
04/01/2022
No work being done on site today. RP 3-10-22
Misc
Informational
04/01/2022
KAW Valley was on site compacting and preparing the subgrade for it’s proof roll tomorrow. RP 3-14-22
Misc
Informational
04/01/2022
Stopped by and talked with Brian about the upcoming TCO inspection. RP 3-21-22
Misc
Informational
04/01/2022
Problems with the sprinkler system, so they canceled the TCO inspection. RP 3-22-22
Misc
Informational
04/01/2022
Bedrock Concrete formed up a walkway from the patio to the walking trail behind the building. Forms were placed and aggregate was present and compacted. RP 4-1-22
Misc
Informational
04/05/2022
All work in the field has been completed. No further site visits are required for field engineering. RP 4-5-22
Occupancy Inspection - Fire Passed 4/5/2022 4/5/2022 04/06/2022
Misc
Corrective Action Required
04/01/2022
Occupancy Inspection - Codes Commercial Temporary C of O 4/6/2022 4/6/2022 04/06/2022
Misc
Corrective Action Required
04/05/2022
-Approval for C of O required from: Field Service Engineer, Planning, - Provide permanent handrail patio ramp -Complete vestibule 101; - Upload to permit performance test report for kitchen hood system as required per IMC 507.6. ** TCO expires 4/29/2022
Occupancy Inspection - Codes Commercial Temporary C of O 4/21/2022 04/21/2022
Misc
Corrective Action Required
04/06/2022
-Approval for C of O required from: Field Service Engineer, Planning, - Provide permanent handrail patio ramp -Complete vestibule 101; ** TCO expires 5/27/2022
Occupancy Inspection - Planning Passed 4/25/2022 04/25/2022
Occupancy Inspection - Codes Commercial Full C of O 5/20/2022 5/20/2022 05/20/2022
Misc
Resolved
05/20/2022
Documents & Images
Date Uploaded File Type Document Name
04/12/2021 Application Form Commercial Permit Application_signed
04/12/2021 Application Form License Tax_signed
04/13/2021 Specifications 20210412_RDG Lees Summit_Project Manual
04/13/2021 Plans 20210412_RDG Lees Summit_Permit Set
04/13/2021 Engineer Report/Study 20210412_RDG Lees Summit_Struct Calcs
04/13/2021 Letter Fire Building Plan Review
04/14/2021 Letter DS P/R Corrections Document
05/11/2021 Email New Food Establishment Plan Review - Approved FTG 0001683
05/11/2021 Letter 2021 05-12 Plan Review Response Letter
05/11/2021 Letter CO2_Mk90_Sensors_BaseSET_2090_en_db_LogiCO2_r2_0
05/11/2021 Plans 20210512_RDG Lees Summit_Rev 03 Plan Review Comments
05/28/2021 Receipt Receipt for transaction:2021-003630
06/02/2021 Letter License Tax Bill
06/02/2021 Letter DS Building Permit
06/02/2021 Approved Plans Approved plan set
06/18/2021 Letter Fire (Alarm) Plan Review Notice
07/08/2021 Letter INSPECTION SUMMARY
07/08/2021 Letter INSPECTION SUMMARY
07/09/2021 Letter INSPECTION SUMMARY
07/12/2021 Letter INSPECTION SUMMARY
07/14/2021 Letter INSPECTION SUMMARY
07/16/2021 Letter INSPECTION SUMMARY
07/19/2021 Letter INSPECTION SUMMARY
07/20/2021 Letter INSPECTION SUMMARY
07/20/2021 Letter INSPECTION SUMMARY
07/20/2021 Letter INSPECTION SUMMARY
07/21/2021 Letter INSPECTION SUMMARY
07/23/2021 Letter INSPECTION SUMMARY
07/27/2021 Letter INSPECTION SUMMARY
07/29/2021 Letter INSPECTION SUMMARY
08/02/2021 Letter INSPECTION SUMMARY
08/04/2021 Letter INSPECTION SUMMARY
08/04/2021 Letter INSPECTION SUMMARY
08/06/2021 Letter INSPECTION SUMMARY
08/12/2021 Letter INSPECTION SUMMARY
08/18/2021 Letter Fire (Sprinkler) Plan Review
08/18/2021 Letter INSPECTION SUMMARY
08/19/2021 Letter INSPECTION SUMMARY
08/23/2021 Letter INSPECTION SUMMARY
08/23/2021 Letter INSPECTION SUMMARY
08/24/2021 Letter INSPECTION SUMMARY
08/26/2021 Letter INSPECTION SUMMARY
08/27/2021 Letter INSPECTION SUMMARY
08/30/2021 Letter INSPECTION SUMMARY
08/30/2021 Letter INSPECTION SUMMARY
09/01/2021 Letter INSPECTION SUMMARY
09/02/2021 Letter INSPECTION SUMMARY
09/03/2021 Letter INSPECTION SUMMARY
09/10/2021 Letter INSPECTION SUMMARY
09/13/2021 Letter INSPECTION SUMMARY
09/17/2021 Letter INSPECTION SUMMARY
10/11/2021 Letter INSPECTION SUMMARY
11/09/2021 Letter INSPECTION SUMMARY
11/16/2021 Letter INSPECTION SUMMARY
11/17/2021 Letter INSPECTION SUMMARY
11/17/2021 Letter INSPECTION SUMMARY
11/19/2021 Letter INSPECTION SUMMARY
11/30/2021 Letter INSPECTION SUMMARY
11/30/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/09/2021 Letter INSPECTION SUMMARY
12/10/2021 Letter INSPECTION SUMMARY
12/10/2021 Letter INSPECTION SUMMARY
12/14/2021 Letter INSPECTION SUMMARY
12/21/2021 Letter INSPECTION SUMMARY
12/21/2021 Letter INSPECTION SUMMARY
12/22/2021 Letter INSPECTION SUMMARY
01/14/2022 Letter INSPECTION SUMMARY
01/18/2022 Letter INSPECTION SUMMARY
01/21/2022 Letter INSPECTION SUMMARY
01/24/2022 Letter INSPECTION SUMMARY
02/09/2022 Letter INSPECTION SUMMARY
02/18/2022 Letter INSPECTION SUMMARY
02/21/2022 Letter INSPECTION SUMMARY
02/22/2022 Letter INSPECTION SUMMARY
02/24/2022 Letter INSPECTION SUMMARY
02/25/2022 Letter INSPECTION SUMMARY
02/28/2022 Letter INSPECTION SUMMARY
03/14/2022 Letter INSPECTION SUMMARY
03/14/2022 Letter INSPECTION SUMMARY
03/15/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/21/2022 RedDoor final base asphalt ticket
03/21/2022 Red Door final surface asphalt ticket
03/21/2022 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/06/2021 Letter INSPECTION SUMMARY
12/06/2021 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
11/04/2021 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter Fire Loss Reduction Form
03/23/2022 Letter Fire Loss Reduction Form
03/24/2022 Letter Fire Loss Reduction Form
03/24/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter Fire Loss Reduction Form
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter Fire Loss Reduction Form
03/25/2022 Letter Fire Loss Reduction Form
09/07/2021 Letter INSPECTION SUMMARY
04/01/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Health Inspection
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/06/2022 Letter Codes Temporary Certificate of Occupancy
04/06/2022 Letter Codes Temporary Certificate of Occupancy
04/07/2022 3RD Party Insp Report Red Door Grill - LS MO - Exhaust Hoods TAB Report
08/25/2021 Letter INSPECTION SUMMARY
08/17/2021 Letter INSPECTION SUMMARY
07/30/2021 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
07/20/2021 Letter INSPECTION SUMMARY
07/07/2021 Letter Fire (Alarm) Plan Review Notice
06/01/2021 Approved 6.1.2021 SWP Lot 1 FDP Red Door
05/12/2021 Letter Fire Building Plan Review
03/21/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/03/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
02/15/2022 Letter INSPECTION SUMMARY
02/15/2022 Letter INSPECTION SUMMARY
02/15/2022 Letter INSPECTION SUMMARY
02/15/2022 Letter INSPECTION SUMMARY
01/19/2022 Letter INSPECTION SUMMARY
01/19/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/28/2022 Letter Fire Loss Reduction Form
04/06/2022 Letter Fire Loss Reduction Form
05/20/2022 Letter Field Certificate of Occupancy
05/20/2022 Letter Codes Final Certificate of Occupancy
04/21/2022 Red Door Grill TCO Extension request 4.20.22
04/21/2022 Letter Codes Temporary Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home