Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Underground Electrical Inspection - Commercial
|
Partial
|
12/20/2016
|
12/20/2016
|
12/20/2016
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
12/29/2016
|
12/30/2016
|
12/30/2016
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
|
1/3/2017
|
01/03/2017
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
1/6/2017
|
1/6/2017
|
01/06/2017
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
|
1/10/2017
|
01/10/2017
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Not Ready
|
1/13/2017
|
1/13/2017
|
01/13/2017
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Not Ready
|
1/17/2017
|
1/17/2017
|
01/17/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rough Framing Inspection - Commercial
|
Not Ready
|
1/19/2017
|
1/19/2017
|
01/19/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rough Framing Inspection - Commercial
|
Not Ready
|
1/20/2017
|
1/20/2017
|
01/20/2017
|
Rough Framing Inspection - Commercial
|
Failed
|
1/23/2017
|
1/23/2017
|
01/23/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rough Framing Inspection - Commercial
|
Partial
|
|
1/25/2017
|
01/25/2017
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
1/10/2017
|
1/25/2017
|
01/25/2017
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
1/27/2017
|
01/27/2017
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
1/31/2017
|
1/31/2017
|
01/31/2017
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
1/31/2017
|
01/31/2017
|
|
Misc
|
Above Ceiling Inspection
|
Not Ready
|
1/31/2017
|
1/31/2017
|
01/31/2017
|
Above Ceiling Inspection
|
Not Ready
|
2/1/2017
|
2/1/2017
|
02/01/2017
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
2/3/2017
|
02/03/2017
|
|
Misc
|
|
Misc
|
Gas Piping Inspection - Commercial
|
Partial
|
|
2/6/2017
|
02/06/2017
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
2/6/2017
|
2/6/2017
|
02/06/2017
|
|
Misc
|
|
Misc
|
Gas Piping Inspection - Commercial
|
Partial
|
|
2/7/2017
|
02/07/2017
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
2/8/2017
|
2/8/2017
|
02/08/2017
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
2/9/2017
|
2/9/2017
|
02/09/2017
|
|
Misc
|
|
|
All Rough Inspection - Commercial
|
Partial
|
2/14/2017
|
2/13/2017
|
02/13/2017
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
2/13/2017
|
2/13/2017
|
02/13/2017
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
2/14/2017
|
02/14/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
Gas Piping Inspection - Commercial
|
Partial
|
|
2/14/2017
|
02/14/2017
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
2/16/2017
|
2/16/2017
|
02/16/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
2/16/2017
|
2/16/2017
|
02/16/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
2/17/2017
|
2/17/2017
|
02/17/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
2/21/2017
|
2/21/2017
|
02/21/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
2/23/2017
|
2/23/2017
|
02/23/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
2/23/2017
|
2/23/2017
|
02/23/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
2/24/2017
|
02/24/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
2/27/2017
|
02/27/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
Foundation Inspection - Commercial
|
Passed
|
2/27/2017 (1:00)
|
2/27/2017
|
02/27/2017
|
Rated Assembly Inspection
|
Partial
|
2/28/2017
|
2/28/2017
|
02/28/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
2/28/2017
|
02/28/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
Electrical Service Inspection
|
Partial
|
3/1/2017
|
3/1/2017
|
03/01/2017
|
|
|
All Rough Inspection - Commercial
|
Partial
|
3/1/2017
|
3/1/2017
|
03/01/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Not Ready
|
3/1/2017
|
3/1/2017
|
03/01/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
3/3/2017
|
03/03/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
3/2/2017
|
3/3/2017
|
03/03/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
3/8/2017
|
3/8/2017
|
03/08/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
3/14/2017
|
3/14/2017
|
03/14/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Gas Piping Inspection - Commercial
|
Partial
|
3/14/2017
|
3/14/2017
|
03/14/2017
|
|
Misc
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
3/29/2017
|
3/29/2017
|
03/29/2017
|
|
Misc
|
|
Misc
|
Rough Electrical Inspection - Commercial
|
Partial
|
|
3/31/2017
|
03/31/2017
|
|
Misc
|
|
Misc
|
In-wall Inspection
|
Partial
|
5/1/2017
|
5/1/2017
|
05/01/2017
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
5/2/2017
|
5/2/2017
|
05/02/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
Electrical Service Inspection
|
Failed
|
5/2/2017
|
5/2/2017
|
05/02/2017
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
5/3/2017
|
5/3/2017
|
05/03/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
Corrective Action Required
|
Electrical Service Inspection
|
Passed
|
5/3/2017
|
5/3/2017
|
05/03/2017
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
5/4/2017
|
05/04/2017
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
5/5/2017
|
5/5/2017
|
05/05/2017
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
|
5/5/2017
|
05/05/2017
|
|
Misc
|
Above Ceiling Inspection
|
Passed
|
|
5/2/2017
|
05/19/2017
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Passed
|
|
3/3/2017
|
05/19/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Gas Piping Inspection - Commercial
|
Passed
|
|
3/14/2017
|
05/19/2017
|
|
Misc
|
|
Misc
|
In-wall Inspection
|
Passed
|
|
5/1/2017
|
05/19/2017
|
|
Misc
|
Rated Assembly Inspection
|
Passed
|
|
5/5/2017
|
05/19/2017
|
|
Misc
|
Rough Electrical Inspection - Commercial
|
Passed
|
|
3/31/2017
|
05/19/2017
|
|
Misc
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Passed
|
|
5/5/2017
|
05/19/2017
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Passed
|
5/10/2017
|
12/20/2016
|
05/19/2017
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
5/23/2017
|
5/23/2017
|
05/23/2017
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
5/24/2017
|
5/24/2017
|
05/24/2017
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
5/25/2017
|
5/25/2017
|
05/25/2017
|
|
Misc
|
Above Ceiling Inspection
|
Not Ready
|
5/26/2017
|
5/26/2017
|
05/26/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Partial
|
|
5/31/2017
|
05/31/2017
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
6/2/2017
|
6/2/2017
|
06/02/2017
|
|
Misc
|
Occupancy Inspection - Water Utilities
|
Passed
|
|
6/14/2017
|
06/05/2017
|
Sprinkler - Hydrostatic Test
|
Failed
|
|
6/9/2017
|
06/09/2017
|
Above Ceiling Inspection
|
Passed
|
6/9/2017
|
6/9/2017
|
06/09/2017
|
|
Misc
|
Rated Assembly Inspection
|
Passed
|
|
5/25/2017
|
06/09/2017
|
|
Misc
|
Sprinkler - Hydrostatic Test
|
Passed
|
|
6/12/2017
|
06/12/2017
|
Sprinkler - Flow Test
|
Passed
|
|
6/13/2017
|
06/13/2017
|
Alarm Test
|
Passed
|
|
6/13/2017
|
06/13/2017
|
Occupancy Inspection - Fire
|
Not Ready
|
|
6/14/2017
|
06/14/2017
|
Occupancy Inspection - Planning
|
Temporary C of O
|
|
6/14/2017
|
06/14/2017
|
|
Corrective Action Required
|
|
Corrective Action Required
|
|
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Failed
|
6/14/2017
|
6/14/2017
|
06/14/2017
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Fire
|
Temporary C of O
|
|
6/15/2017
|
06/15/2017
|
Occupancy Inspection - Codes Commercial
|
Temporary C of O
|
|
6/15/2017
|
06/15/2017
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Partial
|
|
6/16/2017
|
06/16/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Partial
|
6/30/2017
|
6/30/2017
|
06/30/2017
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Not Ready
|
|
7/5/2017
|
07/05/2017
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Not Ready
|
7/14/2017
|
7/14/2017
|
07/14/2017
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Temporary C of O
|
|
7/18/2017
|
07/18/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Partial
|
|
9/7/2017 at 2:50 PM
|
09/07/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Full C of O
|
|
9/11/2017 at 9:40 AM
|
09/11/2017
|
|
Misc
|
Occupancy Inspection - Fire
|
Passed
|
|
9/11/2017
|
09/18/2017
|