| Review Type |
Outcome |
Est. Completion Date |
Completed |
|
Planning Review
|
Corrections
|
03/23/2026
|
03/23/2026
|
|
|
Marlene Pardo
|
|
|
Corrective Action Required
Parking spaces in the southwest can be reduced to 17 feet depth to minimize the overhang.
|
|
|
Corrective Action Required
The minimum parking lot drive aisle width for two-way traffic is 24 feet of actual pavement and must be measured exclusive of curbs and gutters. In areas where the aisles are flanked by islands and other curbs. Revise the plans by pulling the curbed areas back to provide a total of 24 feet of actual pavement width
|
|
|
Corrective Action Required
Detail MTL-4 on sheet A-2.2 needs to label the opacity of the material and its intended use.
|
|
|
Corrective Action Required
Please clarify if the parking spaces adjacent to the dumpster is employee only.
|
|
|
|
|
Engineering Review
|
Corrections
|
03/23/2026
|
03/23/2026
|
|
|
Gene Williams, P.E.
|
|
|
Corrective Action Required
See previous applicant letter. There are questions about the existing water main entering the property. Are you planning on installing a private fire hydrant on this line? If so, a backflow vault and backflow assembly is required on the property. Otherwise, this line should be abandoned. If a fire hydrant and backflow assembly is being installed, a tap is required just prior to the backflow vault and valve. If no fire hydrant is desired or required, a tap should be provided at the main beneath the private drive, and the 8 inch line entering the property should be properly abandoned.
|
|
|
Corrective Action Required
Recommend a Teams meeting with Water Utilities and Development Engineering to discuss the above issue with the water line.
|
|
|
|
|
Building Codes Review
|
No Comments
|
03/23/2026
|
03/19/2026
|
|
|
Joe Frogge
|
|
|
Miscellaneous Correction
Water piping serving 1" meter must be 1" copper from connection to 8" C900 stub to 10' past meter.
|
|
|
|
|
Fire Review
|
Corrections
|
03/23/2026
|
03/18/2026
|
|
|
Jim Eden
|
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Hydrants
Corrective Action Required
IFC 507.5.1 - Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official.
The accessible hydrant location does not meet the 300 foot requirement.
Show the location of nearby hydrants.
|
|
|
|
|
Planning Review
|
Corrections
|
02/17/2026
|
02/18/2026
|
|
|
Marlene Pardo
|
|
|
Miscellaneous Correction
Corrective Action Required
Submission of a fully executed application, bearing the signature of the property owner, is required.
|
|
|
Corrective Action Required
Please label the depth of the proposed parking stall along the southwest property line.
|
|
|
Corrective Action Required
Please label the dimension of the drive lanes.
|
|
|
Corrective Action Required
Identify and label the location of all oil and/or gas wells located on the subject property. If no wells are present, add a note to the plans explicitly stating this and cite the source used to verify that no wells exist.
|
|
|
Corrective Action Required
Please provide details on the heigh of all proposed building and parking lot lighting. If a base is to be included for the pole mounted lighting please include details for such.
|
|
|
Corrective Action Required
Please indicate whether any ground-mounted mechanical equipment is proposed. If so, provide the location, size, and screening material details for all such equipment on the plans. Additionally, submit the manufacturer’s specification sheets for all proposed mechanical equipment.
|
|
|
Corrective Action Required
Will there be a free standing or monument sign with this building? If so please show the location, size, and type of material of all proposed monument or freestanding signs.
|
|
|
Corrective Action Required
Please show the location, size and materials to be used in all screening of rooftop mechanical equipment. Additionally, a dashed line indicating the roof line and rooftop mechanical shall be shown on the elevations as well.
|
|
|
Corrective Action Required
Sheets A-2.2 and A-7.1 should be in color.
|
|
|
Corrective Action Required
Trash and recycling enclosures shall be constructed of permanent materials, such as textured block, split-faced concrete block, brick, or stone. The colors, materials, and design of the enclosure shall match or be compatible with the dominant architectural materials and design of the principal building on the site. The proposed wood gate does not meet the requirements of this section. Please revise the plans to incorporate a compliant alternative material.
|
|
|
Corrective Action Required
Parking stalls shall measure 9 feet in width by 19 feet in depth, or 9 feet in width by 17 feet in depth when the parking space abuts a 6-foot-wide sidewalk or a curbed open green/landscaped area. These dimensions are exclusive of the curb and gutter. Please revise the plans to ensure that parking stall measurements do not include the curb and gutter.
|
|
|
Corrective Action Required
CG-1 concrete curbing required around all parking areas and access drives in office, commercial and industrial districts. Please label the proposed curb type to ensure compliance with the UDO.
|
|
|
Corrective Action Required
The Finish Schedule on sheets A-2.1 and A-2.2 should include the material class for each proposed exterior material.
|
|
|
Corrective Action Required
Per Sec. 8.080, Commercial/Retail Buildings are required to be no less than 18 feet in height, as indicated in Table 8.I-3. Please revise the proposed building height to comply with the minimum UDO standards. Any deviation from this standard will require a modification granted by the City Council through the Preliminary Development Plan process.
|
|
|
Corrective Action Required
Drive-through restaurants are required to provide a minimum queueing capacity of four vehicles at the order board and an additional four vehicles at the first service window. Based on the submitted plans, it does not appear that this requirement is being met. Please revise the plans to ensure compliance with the minimum queuing standards as specified in Table 8.2 of the UDO. Any deviation from this standard will require a modification granted by the City Council through the Preliminary Development Plan process.
|
|
|
Corrective Action Required
All accessible parking shall comply with the requirements of the federal Americans with Disabilities Act.
|
|
|
Corrective Action Required
All signs must comply with the sign requirements as outlined in the sign section of the UDO and will be permitted by separate application.
|
|
|
Corrective Action Required
To enhance the pedestrian-oriented character of the site and further promote walkability, staff recommends incorporating a customer bench seating area at the pedestrian entrance on the east side of the building. Providing seating in this location would create a more welcoming and functional entry point, support pedestrian activity, and contribute to a more inviting streetscape environment.
|
|
|
|
|
Traffic Review
|
No Comments
|
02/17/2026
|
02/17/2026
|
|
|
Erin Ralovo
|
|
|
|
|
Building Codes Review
|
Corrections
|
02/17/2026
|
02/17/2026
|
|
|
Joe Frogge
|
|
|
Miscellaneous Correction
Corrective Action Required
Water piping serving 1" meter must be 1" copper from connection to 8" C900 stub to 10' past meter.
|
|
|
|
|
Engineering Review
|
Corrections
|
02/17/2026
|
02/17/2026
|
|
|
Gene Williams, P.E.
|
|
|
Corrective Action Required
A stormwater memorandum discussing the regional detention was missing. Please provide a short stormwater memorandum discussing why on-site stormwater detention is not required due to regional detention being provided.
|
|
|
Corrective Action Required
Sheet C101: a. Finish the note sections with references denoted by "xxxx". b. Provide a note stating the contractor to supply a jointing pattern for the concrete, or alternatively, provide a site-specific jointing pattern for the pavement.
|
|
|
Corrective Action Required
Sheet C300: a. Label the existing City manhole number. In this instance, the City manhole number is #21-137. b. The 6 inch private sanitary lateral shall be connected to the public sanitary sewer line via a wye connection, not a direct-connect to the manhole. As an alternative, an 8 inch line may be allowed to direct-connect to the manhole, provided the drop is no more than 2 feet. c. Domestic water service is not shown in a normal manner. Typical installation would show a tap at the 8 inch line during construction phase rather than prior. Is this domestic water line already existing? If so, what materials and size? d. The water meter should be placed near the sidewalk to facilitate access to Water Utilities personnel. e. Our GIS records indicate the existence of a pre-existing sanitary sewer lateral to the northwest. Have you explored this? If so, please use the existing sanitary sewer lateral, or properly abandon the existing lateral. f. Note for W2 should be revised to include "...a minimum distance of 10 feet copper line is required from the meter to the HDPE transition."
|
|
|
Corrective Action Required
Sheet C500: a. The City of Lee's Summit requires the use of KCMMB mix for all pavement whether public or private. Please revise.
|
|
|
Corrective Action Required
A cost estimate is required prior to formal approval. The estimate shall be itemized and sealed by a design professional licensed in the State of Missouri.
|
|
|
Corrective Action Required
A SWPPP is required if the disturbed area is greater than 1 acre.
|
|
|
|
|
Fire Review
|
Corrections
|
02/17/2026
|
02/03/2026
|
|
|
Jim Eden
|
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Hydrants
Corrective Action Required
IFC 507.5.1 - Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official.
Show the location of nearby hydrants.
|
|
|
|