PL2022415




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2022415
Residences at Blackwell - Public Water
Engineering Plan Review
Engineering Plan Review
Approved
11/29/2022
RESIDENCES AT BLACKWELL LLC
Locations
Contacts
RESIDENCES AT BLACKWELL LLC, Address:21 SE 29TH TER  
GRIFFIN RILEY PROPERTY GROUP, Address:21 SE 29TH TER, Phone:(816) 366-7900  
SCHLAGEL & ASSOCIATES, Address:14920 W 107TH ST, Phone:(913) 492-5158  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 08/21/2024 08/21/2024
Gene Williams, P.E.
Redesign Review Corrections 06/26/2024 06/26/2024
Gene Williams, P.E.
Engineering Review No Comments 07/31/2023 07/31/2023
Gene Williams, P.E.
Engineering Review Corrections 06/26/2023 06/26/2023
Gene Williams, P.E.
Engineering Review Corrections 05/24/2023 05/31/2023
Gene Williams, P.E.
Corrective Action Required
05/16/2023

Water modeling by Water Utilities staff shows that a 12 inch water main is required along Shenandoah Dr. This is due to the fire flow requirements for the apartments and the necessity of reducing water velocities to 10 feet per second or less. The 12 inch main shall be installed to the east plat boundary along Shenandoah Dr. Please revise as appropriate.
Corrective Action Required
05/16/2023

The private fire line connection is shown connecting to the main at the location where it is not practical to make the connection (i.e., a 90 degree bend). Please revise and show the connection at a point prior to the 90 degree bend.
Water Utilities has been trying to model the needed water main sizes, and the review had to slip a bit.
Engineering Review Corrections 04/17/2023 04/17/2023
Gene Williams, P.E.
Corrective Action Required
04/18/2023

There are discrepancies in the location and sizing of the existing main along Blue Pkwy. I have attached a separate sheet showing the location of where we are showing the as-built location of the existing 16 inch main (i.e., not a 12 inch main as shown on the plans). Please revise the plans as appropriate.
Corrective Action Required
04/18/2023

I have attached a separate markup showing how the connection to the new 12 inch water main should be made in relation to the existing 16 inch main. Please see the separate attachment and adjust and revise as appropriate.
Engineering Review Corrections 02/07/2023 03/03/2023
Gene Williams, P.E.
Corrective Action Required
03/03/2023

The 3 inch sanitary force main is shown on the plans as requested in comment #1 within the previous applicant letter, but there are instances where the force main is shown beneath pavement or at the edge of pavement. This will present a maintenance issue for the utility owner. Please contact the owner of this utility (Lee's Summit R-7 School District) and determine what they require in terms of movement of this line outside of paved areas. It is likely that MoDOT will also have input on this, as the force main appears to be shown beneath the proposed roundabout (separate plans not yet resubmitted). Please coordinate and revise as necessary.
Corrective Action Required
03/03/2023

A copy of any correspondence with Lee's Summit R-7 School District shall be required prior to approval of the plans. Please see previous comment concerning this requirement.
late review due to inquiry with other Departments concerning the Hays University Foundation future sanitary sewer service
Engineering Review Corrections 12/16/2022 12/16/2022
Gene Williams, P.E.
Corrective Action Required
12/16/2022

A 3 inch sanitary sewer force main was installed along Blue Pkwy. along the north side, but does not appear to be shown on the plans. Please locate this line, and show on the plans. Please ensure there are no conflicts with this line in terms of distance requrements or clearance issues.
Corrective Action Required
12/16/2022

The proposed interior private line is shown in bold on the general overview sheet, but is not being constructed with these improvements. Wouldn't it be better to show this in a lighter lineweight to distinguish between features to be constructed with these plans? Please revise if appropriate.
Corrective Action Required
12/16/2022

Line C is shown beneath Heritage St., and it appears to be shown as a public rather than a private line. This line should be private. Please ensure the plans reflect the private nature of this line, and revise the notes as appropriate.
Corrective Action Required
12/16/2022

The overview sheet shows the location of the north loop towards Summit Mill subdivision. The City is not reviewing at this time, and will determine the best method of future water main looping at a later date. For purposes of these plans, it may be acceptable to use a lighter lineweight with the words "possible loop location" or equivalent language.
Corrective Action Required
12/16/2022

It appears there are several instances where the pipe is shown where the radius of curvature is less than the threshold of approximately 1200 feet radius. Water main is not designed to be deflected within the pipe itself, but rather, only 1 degree per joint is allowed (i.e., within the joint itself, not the pipe wall). This equates to approximately 1200 feet. Please evaluate, and provide the location of all bends, including the magnitude of the bend.
Corrective Action Required
12/16/2022

Butterfly valves are specified for the 12 inch line, but this specification has recently changed to allow for gate valves in lieu of butterfly valves. Please revise as appropriate wherever a butterfly valve is specified.
Corrective Action Required
12/16/2022

Sheet 5: Water line C is shown as public. Please revise, as this line is private. Please see previous comments related to the lineweight, as this may confuse the contractor and/or the inspector during construction, as well as our GIS technicians who are entering data into our GIS system.
Corrective Action Required
12/16/2022

Trenching and backfill detail should be updated to include the new 12 inch aggregate requirement over the top of pipe.
Corrective Action Required
12/16/2022

Sheet 5: Maximum depth of cover over water mains is 7 feet. There are instances where this has been exceeded slightly, and it appears the 7 foot rule can be achieved. Please revise.
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
11/29/2022 Application Form Application and Affidavit_Rev 0_PL2022413
11/30/2022 Plans 22-102 PUBLIC WATER LINES - REV0 - 2022_11_30
12/16/2022 Letter DE-Comment Letter (Engineering Plans)
01/24/2023 Letter Response to Comments
01/24/2023 Plans 22-102 PUBLIC WATER - REV1 - 2023_01_23
03/03/2023 Letter DE-Comment Letter (Engineering Plans)
04/03/2023 Engineers Estimate 22-102 - COST EST - 2023_01_23
04/03/2023 Plans 22-102 - RESIDENCES AT BLACKWELL - PUBLIC WATER - REV2 - 2023_03_24
04/03/2023 Engineer Report/Study 22-102 - swp2
04/03/2023 Letter Response to Comments - Residences at Blackwell - Public Water DATED 3-3-2023
04/18/2023 Letter DE-Comment Letter (Engineering Plans)
04/18/2023 Email EMAIL SUPPLEMENTAL APR2023
05/09/2023 Plans 22-102 PUBLIC WATER - REV3 - 2023_05_05
05/09/2023 Letter Response to Comments dated 4-18-2023 - Water Line - Residences of Blackwell
05/31/2023 Letter DE-Comment Letter (Engineering Plans)
06/12/2023 Plans 22-102 PUBLIC WATER - REV4 - 2023_06_08
06/12/2023 Letter Response to Comments - Engineering Plan Review - Public Water dated 5-31-2023
06/12/2023 Engineers Estimate 22-102 - COST EST - 2023_06_12
06/26/2023 Email EMAIL COMMENTS JUN2023
07/24/2023 Plans APPROVABLE WATER PLANS JUL2023
08/01/2023 Email STKY APPROVAL CONDITIONS
08/01/2023 Email EMAIL TO WU
08/03/2023 Activity Document Residences At Blackwell Public Main
08/03/2023 Letter MDNR Concurrence Letter - waterLBCPlatS (002)
08/03/2023 Email MDNR CONC LETTER
10/13/2023 3rd Party Permit/Approval MDNR - Residences Waterline Extention Permit
10/18/2023 Approved Plans STAMPED CONSTRUCTION PLANS
06/18/2024 Plans 22-102 - PUBLIC WAT - PP-4 WATER LINE A - PUBLIC
06/26/2024 Email EMAIL COMMENTS
08/14/2024 Plans 22-102 - PUBLIC WAT - PP-4 WATER LINE A - PUBLIC - REV8 - 2024_08-14
08/14/2024 Letter Response to Comments - Water Utilities Plan Review - Public Water dated 6-26-2024
08/22/2024 APPROVED REVISION WATER LINE CONNECTION TO 16 INCH AUG 2024
08/22/2024 APPROVAL LETTER REVISION 16CONNECTIONAUG2024
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home