Summary
PL2022397
Arcade Alley - Outdoor Space
Commercial Final Development Plan
Commercial Final Development Plan
Expired
11/09/2022
HIBE HOLDINGS LLC
Locations
Contacts
HIBE HOLDINGS LLC, Address:2601 W 68TH ST  
Phillip Henning, Address:11827 W. 112th St., Phone:(913) 317-9390  
SAM COLLINS, Address:COLLINS WEBB ARCHITECTURE, Phone:(816) 249-2270  
Pat Maloney, Address:316 SE Dougas St., Phone:(913) 219-9049  
Reviews
Review Type Outcome Est. Completion Date Completed
Planning Review No Comments 05/31/2024 05/30/2024
Shannon McGuire
Engineering Review No Comments 05/17/2023 05/16/2023
Sue Pyles, P.E.
Misc.
Corrective Action Required
05/16/2023

Submit Engineer's Estimate of Probable Construction Costs. Revisions to estimate required: Please revise the estimate to include a breakdown that includes quantity, units, unit price, and total for each line item. Only site related items should be included. That would include pavers, sidewalk, curb and gutter, retaining wall, earthwork, erosion and sediment control, sanitary sewer pipe and cleanouts, and all storm sewer related items. Expected storm sewer items would include pipe, tees, bends, drainage basins, and flume. Please note that these may not be all site related items, but should be most if not all.
DE Contact Field Eng. Inspector
Corrective Action Required
05/16/2023

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
DE Engineers Estimate
Corrective Action Required
05/16/2023

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $xxx.xx
DE Future Repair Work
Corrective Action Required
05/16/2023

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
Fire Review No Comments 05/23/2023 05/16/2023
Scott Ready
Code Statement
Corrective Action Required
05/16/2023

d All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code. Egress from the outdoor area to be assessed during building permit review. Access to the FDC shall be maintained at all times.
Traffic Review No Comments 05/23/2023 05/16/2023
Scott Ready
Building Codes Review No Comments 05/23/2023 05/16/2023
Scott Ready
Planning Review No Comments 05/23/2023 05/16/2023
Scott Ready
Engineering Review Corrections 04/21/2023 04/20/2023
Sue Pyles, P.E.
Misc.
Corrective Action Required
04/17/2023

Submit Engineer's Estimate of Probable Construction Costs. Revisions to estimate required: Please revise the estimate to include a breakdown that includes quantity, units, unit price, and total for each line item. Only site related items should be included. That would include pavers, sidewalk, curb and gutter, retaining wall, earthwork, erosion and sediment control, sanitary sewer pipe and cleanouts, and all storm sewer related items. Expected storm sewer items would include pipe, tees, bends, drainage basins, and flume. Please note that these may not be all site related items, but should be most if not all.
DE Contact Field Eng. Inspector
Corrective Action Required
04/17/2023

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
DE Engineers Estimate
Corrective Action Required
04/17/2023

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $xxx.xx
DE Future Repair Work
Corrective Action Required
04/17/2023

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
Engineering Review Approved with Conditions 02/24/2023 02/24/2023
Sue Pyles, P.E.
Misc.
Resolved
05/16/2023

Submit Engineer's Estimate of Probable Construction Costs.
DE Contact Field Eng. Inspector
Corrective Action Required
02/24/2023

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
DE Engineers Estimate
Corrective Action Required
02/24/2023

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee of $3,144.55 (which is based on 3% of the total infrastructure cost) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit.
DE Future Repair Work
Corrective Action Required
02/24/2023

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
Building Codes Review No Comments 02/24/2023 02/24/2023
Joe Frogge
Miscellaneous Correction
Resolved
02/24/2023

Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section.
Planning Review No Comments 02/24/2023 02/24/2023
Shannon McGuire
Traffic Review No Comments 02/24/2023 02/16/2023
Scott Ready
Fire Review Approved with Conditions 02/24/2023 02/16/2023
Scott Ready
Code Statement
Corrective Action Required
02/16/2023

d All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code. Egress from the outdoor area to be assessed during building permit review. Access to the FDC shall be maintained at all times.
Planning Review Corrections 01/30/2023 01/31/2023
Shannon McGuire
Corrective Action Required
01/31/2023

Please provide details of what fence materials and style are being proposed.
Corrective Action Required
01/31/2023

Please provide details for the proposed artificial turf.
Corrective Action Required
01/31/2023

Will there be any new RTU’s or ground mounted mechanical equipment? If so how will they be screened?
Corrective Action Required
01/31/2023

Please cite your source of information regarding the location of oil and gas wells.
Corrective Action Required
01/31/2023

Please provide confirmation that the shared parking agreement is still in place.
Corrective Action Required
01/31/2023

Please provide a photometric diagram indicating the foot candle levels throughout the site and at the property lines.
Corrective Action Required
01/31/2023

Please provide the manufacturer’s specification sheets for proposed exterior lighting to include both pole mounted and wall mounted fixtures. The specification sheets shall indicate the exact fixture to be used.
Engineering Review Corrections 01/30/2023 01/30/2023
Nikia Chapman-Freiberger
Corrective Action Required
01/30/2023

General: A) Submit an Engineer’s Estimate of Probably Construction Costs. B) Please submit the final Stormwater Report. C) Include an erosion control plan sheet.
Corrective Action Required
01/30/2023

COVER SHEET: A) Plans must be stamped and signed by a Professional Engineer licensed in the state of Missouri. B) Include a list of drawings. C) Include utility contact information. D) Include note that all construction shall follow the LS Design and Construction Manual.
Corrective Action Required
01/30/2023

C102 SITE PLAN: A) Note 1 does not match the reference to Note 1 in the curb detail. Please review and revise appropriately.
Corrective Action Required
01/30/2023

C103 UTILITY PLAN: A) Consider creating a detail sheet. B) Include turf detail in the plan set. C) Include sidewalk detail/concrete pavement detail. D) Include detail for concrete flume. Flume must be covered/enclosed. E) Provide stormwater/underdrain system plan. Elevations, cleanouts, etc.
Corrective Action Required
01/30/2023

FD201 EXTERIOR ELEVATIONS: A) Please review elevation titles. I believe E7 and A5 should be labeled as north rather than south as it is the north side of the building. This aligns with how the other elevations are titled.
Building Codes Review Corrections 01/30/2023 01/30/2023
Joe Frogge
Miscellaneous Correction
Corrective Action Required
01/30/2023

Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section.
Traffic Review No Comments 01/30/2023 01/18/2023
Brad Cooley, P.E., RSPI
Fire Review Approved with Conditions 01/30/2023 01/17/2023
Jim Eden
Code Statement
Corrective Action Required
01/17/2023

d All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code. Egress from the outdoor area to be assessed during building permit review. Access to the FDC shall be maintained at all times.
Fees
Paid Fees Amount Paid Owing Date Paid
Final Development Plan fee $725.00 $725.00 Paid 02/21/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
City Council Public Hearing 06/18/2024 6:00 PM Council Chambers 06/18/2024 06:00 PM
Agenda Item
Approved
06/18/2024
Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home