Review Type |
Outcome |
Est. Completion Date |
Completed |
Planning Review
|
No Comments
|
05/31/2024
|
05/30/2024
|
|
Shannon McGuire
|
|
|
Engineering Review
|
No Comments
|
05/17/2023
|
05/16/2023
|
|
Sue Pyles, P.E.
|
|
Misc.
Corrective Action Required
Submit Engineer's Estimate of Probable Construction Costs.
Revisions to estimate required:
Please revise the estimate to include a breakdown that includes quantity, units, unit price, and total for each line item. Only site related items should be included. That would include pavers, sidewalk, curb and gutter, retaining wall, earthwork, erosion and sediment control, sanitary sewer pipe and cleanouts, and all storm sewer related items. Expected storm sewer items would include pipe, tees, bends, drainage basins, and flume.
Please note that these may not be all site related items, but should be most if not all.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $xxx.xx
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Fire Review
|
No Comments
|
05/23/2023
|
05/16/2023
|
|
Scott Ready
|
|
Code Statement
Corrective Action Required
d All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Egress from the outdoor area to be assessed during building permit review. Access to the FDC shall be maintained at all times.
|
|
|
Traffic Review
|
No Comments
|
05/23/2023
|
05/16/2023
|
|
Scott Ready
|
|
|
Building Codes Review
|
No Comments
|
05/23/2023
|
05/16/2023
|
|
Scott Ready
|
|
|
Planning Review
|
No Comments
|
05/23/2023
|
05/16/2023
|
|
Scott Ready
|
|
|
Engineering Review
|
Corrections
|
04/21/2023
|
04/20/2023
|
|
Sue Pyles, P.E.
|
|
Misc.
Corrective Action Required
Submit Engineer's Estimate of Probable Construction Costs.
Revisions to estimate required:
Please revise the estimate to include a breakdown that includes quantity, units, unit price, and total for each line item. Only site related items should be included. That would include pavers, sidewalk, curb and gutter, retaining wall, earthwork, erosion and sediment control, sanitary sewer pipe and cleanouts, and all storm sewer related items. Expected storm sewer items would include pipe, tees, bends, drainage basins, and flume.
Please note that these may not be all site related items, but should be most if not all.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $xxx.xx
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Engineering Review
|
Approved with Conditions
|
02/24/2023
|
02/24/2023
|
|
Sue Pyles, P.E.
|
|
Misc.
Submit Engineer's Estimate of Probable Construction Costs.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee of $3,144.55 (which is based on 3% of the total infrastructure cost) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Building Codes Review
|
No Comments
|
02/24/2023
|
02/24/2023
|
|
Joe Frogge
|
|
Miscellaneous Correction
Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director.
Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section.
|
|
|
Planning Review
|
No Comments
|
02/24/2023
|
02/24/2023
|
|
Shannon McGuire
|
|
|
Traffic Review
|
No Comments
|
02/24/2023
|
02/16/2023
|
|
Scott Ready
|
|
|
Fire Review
|
Approved with Conditions
|
02/24/2023
|
02/16/2023
|
|
Scott Ready
|
|
Code Statement
Corrective Action Required
d All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Egress from the outdoor area to be assessed during building permit review. Access to the FDC shall be maintained at all times.
|
|
|
Planning Review
|
Corrections
|
01/30/2023
|
01/31/2023
|
|
Shannon McGuire
|
|
Corrective Action Required
Please provide details of what fence materials and style are being proposed.
|
|
Corrective Action Required
Please provide details for the proposed artificial turf.
|
|
Corrective Action Required
Will there be any new RTU’s or ground mounted mechanical equipment? If so how will they be screened?
|
|
Corrective Action Required
Please cite your source of information regarding the location of oil and gas wells.
|
|
Corrective Action Required
Please provide confirmation that the shared parking agreement is still in place.
|
|
Corrective Action Required
Please provide a photometric diagram indicating the foot candle levels throughout the site and at the property lines.
|
|
Corrective Action Required
Please provide the manufacturer’s specification sheets for proposed exterior lighting to include both pole mounted and wall mounted fixtures. The specification sheets shall indicate the exact fixture to be used.
|
|
|
Engineering Review
|
Corrections
|
01/30/2023
|
01/30/2023
|
|
Nikia Chapman-Freiberger
|
|
Corrective Action Required
General:
A) Submit an Engineer’s Estimate of Probably Construction Costs.
B) Please submit the final Stormwater Report.
C) Include an erosion control plan sheet.
|
|
Corrective Action Required
COVER SHEET:
A) Plans must be stamped and signed by a Professional Engineer licensed in the state of Missouri.
B) Include a list of drawings.
C) Include utility contact information.
D) Include note that all construction shall follow the LS Design and Construction Manual.
|
|
Corrective Action Required
C102 SITE PLAN:
A) Note 1 does not match the reference to Note 1 in the curb detail. Please review and revise appropriately.
|
|
Corrective Action Required
C103 UTILITY PLAN:
A) Consider creating a detail sheet.
B) Include turf detail in the plan set.
C) Include sidewalk detail/concrete pavement detail.
D) Include detail for concrete flume. Flume must be covered/enclosed.
E) Provide stormwater/underdrain system plan. Elevations, cleanouts, etc.
|
|
Corrective Action Required
FD201 EXTERIOR ELEVATIONS:
A) Please review elevation titles. I believe E7 and A5 should be labeled as north rather than south as it is the north side of the building. This aligns with how the other elevations are titled.
|
|
|
Building Codes Review
|
Corrections
|
01/30/2023
|
01/30/2023
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director.
Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section.
|
|
|
Traffic Review
|
No Comments
|
01/30/2023
|
01/18/2023
|
|
Brad Cooley, P.E., RSPI
|
|
|
Fire Review
|
Approved with Conditions
|
01/30/2023
|
01/17/2023
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
d All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Egress from the outdoor area to be assessed during building permit review. Access to the FDC shall be maintained at all times.
|
|
|