Planning Application Status

PL2021114




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2021114
East Trails Middle School - Off-site 15" Sanitary Sewer Main Extension No. 1 - Segment #1
Engineering Plan Review
Engineering Plan Review
Complete
03/30/2021
SCHOOL DISTRICT 7 REORGANIZED
This is the first segment of the off-site sanitary sewer line. Second segment to be submitted separate.
Locations
Contacts
SCHOOL DISTRICT 7 REORGANIZED, Address:301 NE TUDOR RD  
OLSSON ASSOCIATES, Address:7301 W 133RD ST #200, Phone:(913) 634-0903  
Brad Sonner, Address:Olsson Associates, Vice President, Phone:(913) 748-2516  
Reviews
Review Type Outcome Est. Completion Date Completed
Record Drawings Review No Comments 03/06/2023 03/06/2023
Gene Williams, P.E.
Engineering Review No Comments 09/21/2021 09/21/2021
Gene Williams, P.E.
Engineering Review Corrections 09/07/2021 09/07/2021
Gene Williams, P.E.
Corrective Action Required
09/07/2021

A "flowline in" elevation from the northeast is still shown for manhole A7, which implies a stub. It is also not the correct diameter. Please remove reference to the northeast "flowline in" elevation.
Corrective Action Required
09/07/2021

The future sanitary sewer extension estimate did not appear to show core-drilling of the manhole to install the 12 inch line, and was also missing the engineering costs (i.e., plans, as-builts, USACE permitting).
Engineering Review Corrections 08/24/2021 08/24/2021
Gene Williams, P.E.
Corrective Action Required
08/24/2021

Proposed alignment looks acceptable, but why was the 18 inch line shown between A7 and A8? The new alignment makes this unneccessary and not desired by the City.
Corrective Action Required
08/24/2021

Provide sufficient notes that make it clear the future connection to the northeast at A7 shall be core-drilled. No temporary stub-outs are allowed.
Corrective Action Required
08/24/2021

The additional easement (sanitary) shall be provided prior to approval of the plans. This easement should be 30 feet wide, with the sanitary sewer line centered within the easement. Please provide a review copy prior to execution and recording.
Corrective Action Required
08/24/2021

Please provide the document number of easements already executed and recorded.
Corrective Action Required
08/24/2021

A cost estimate (itemized) shall be provided prior to approval of the plans. There should be a separate cost estimate for the future 12 inch sanitary sewer to the northeast in order to facilitate an escrow agreement. This estimate should not only include cost of installation, but should also include some engineering costs associated with the scope of work.
Engineering Review Corrections 08/02/2021 08/02/2021
Gene Williams, P.E.
Corrective Action Required
08/02/2021

After revising the road alignment, there are now issues with the geometry of the sanitary sewer extension. It would appear a far better and more maintainable solution would be to extend the sanitary sewer service from manhole A7, crossing the creek just north of the confluence of the east/west tributary, and then terminate the sanitary sewer within the middle of the extended Cape Dr.
Corrective Action Required
08/02/2021

Please provide a profile view how the above alignment will work for the extension.
Corrective Action Required
08/02/2021

An off-site easement would also be needed in addition to the other easement(s) needed.
Engineering Review Corrections 06/18/2021 06/17/2021
Gene Williams, P.E.
Corrective Action Required
06/17/2021

As discussed in the Jun. 9, 2021 email, plans should be updated as appropriate.
Traffic Review No Comments 06/18/2021 06/04/2021
Mike Weisenborn
Engineering Review Corrections 05/18/2021 05/18/2021
Gene Williams, P.E.
Corrective Action Required
05/18/2021

Coordination between Olsson and Schlagel in regard to the Cape Dr. extension continues to be an issue. This will have a direct bearing on the sanitary sewer plans. According to the Bailey Farms preliminary plans, the Cape Dr. right of way is not abutting the Whitnance property to the south, but rather, is offset by approximately 29 feet. This will have a bearing on the design of the public manhole location. In this instance, the manhole should be located outside the limits of the roadway so the future connection from Bailey Farms subdivision to the east can be made without being installed beneath the box culvert.
Corrective Action Required
05/18/2021

Future connection to Bailey Farms shows a 12 inch pipe. Please remove reference to "8 to 12 inch pipe".
Corrective Action Required
05/18/2021

Future connection to Bailey Farms is showing inadequate drop across this high deflection manhole. Minimum drop is 0.5 feet, but recommend 0.6 to account for tolerance.
Corrective Action Required
05/18/2021

Ductile iron pipe is required from manhole to manhole beneath stream crossings. It must be epoxy coated, and include restrained joints.
Corrective Action Required
05/18/2021

Concrete encasement is required beneath stream crossings. Encasement should be shown "bank to bank".
Corrective Action Required
05/18/2021

Depth of bury beneath the stream channel is too shallow. A minimum depth of 3 feet is required.
Corrective Action Required
05/18/2021

We are assuming the additional manhole at the downstream connection point is being proposed to accommodate the incoming pipe diameters?
Corrective Action Required
05/18/2021

Approval of these plans is contingent upon the submittal and approval of the additional downstream sanitary sewer improvements.
Engineering Review Corrections 04/16/2021 04/16/2021
Gene Williams, P.E.
Corrective Action Required
04/15/2021

Off-site easements (from the Whistance property to the south) in a form acceptable to the City shall be obtained prior to approval of plans. They should be twice the depth of the sewer, rounded to the next 5 feet. Please submit a review copy prior to execution and recording. A document number should be provided to the City following recording for verfication.
Corrective Action Required
04/15/2021

Manhole A8 shall be a outside drop manhole due to the excessive drop greater than 2 feet at this point. Please provide notation, along with the standard detail for the outside drop manhole (i.e., SAN-4).
Corrective Action Required
04/15/2021

Recommend increasing the drop across manholes to allow for construction tolerance (i.e., additional 0.1 feet?). As shown, the minimum drop is shown.
Corrective Action Required
04/15/2021

Manhole A5 is too close to the stream bank. Please move the manhole to achieve a minimum distance of 15 feet from the top of bank to the outside of the manhole.
Corrective Action Required
04/15/2021

What is the calculated 100 water surface elevation of the stream? A conservative approach to determining these elevations in relation to the flowline of the stream should be calculated along key points, assuming full build-out upstream, and upstream detention basins being fully clogged and zero available storage (i.e., assume no detention). Tops of manholes shall extend a minimum 1'-0" above the calculated 100-year floodwater elevation, provided that such extension shall not exceed 4 feet above final finish grade. Where these requirements result in a manhole with a rim at or below the 100-year floodwater elevation, the manhole shall be equipped with watertight ring and bolt-down cover assembly with neoprene gaskets.
Corrective Action Required
04/15/2021

Label the existing tie-in point as City manhole #47-019.
Corrective Action Required
04/15/2021

It is very difficult to determine what is shown at the connection point. It appears two (2) new manholes are being installed, and it is unclear why.
Corrective Action Required
04/15/2021

The private forcemain was not located on the plans. What is the plan for managing the private forcemain? This forcemain serves the school district, and will need to be considered during the design. The location of the line should also be shown, rather than assumed based on the easement.
Corrective Action Required
04/15/2021

Portions of the sanitary sewer improvements are shown in red, and would appear to be separate from these plans. Please provide sufficient notation that these lines are not part of the project, to be installed by others (or equivalent language).
Corrective Action Required
04/15/2021

Recommend coordination with David Rinne at Schlagel and Associates concerning the connection point for Bailey Farms. You are showing a manhole in the southeast corner of the school project, which will likely become a drop manhole. Will this drop manhole be able to service the Bailey Farm project? A large diameter sewer line will be connected presumably at this location, and the manhole size may not work with a standard drawing for a drop manhole.
Corrective Action Required
04/15/2021

Concerning the coordination comment above, a plan and profile view of the intended route to serve the Bailey Farm site is required. A cost estimate shall be required for this portion, even if not built until the Bailey Farm project proceeds (see next comment).
Corrective Action Required
04/15/2021

Public sanitary sewer shall be extended to the plat boundary (i.e., to the east to serve Bailey Farms). An off-site easement may suffice after coordination with David Rinne at Schlagel and Associates for this extension. The City would consider an easement be dedicated to the plat boundary in lieu of construction of said improvements, but construction costs would need to be provided by the school district. Coordination between David Rinne would also be required to minimize any future disruption of the sanitary sewer line, and to minimize any re-design at the connection point.
Corrective Action Required
04/15/2021

Trenching and backfill detail shall include 12 inches of aggregate on top of pipe rather than 6 inches shown. This standard changed in the Design and Construction Manual in 2020.
Corrective Action Required
04/15/2021

Design flow calculations were not shown. Typically this is provided in the form of a table. It should include the ultimate condition including the Bailey Farm property.
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
04/05/2021 Engineer Report/Study 20201117-19-227-Bailey Farms Memorandum
04/15/2021 Engineer Report/Study Accepted Sanitary Sewer Study Aug 2020
04/16/2021 Letter DE-Comment Letter (Engineering Plans)
05/03/2021 Letter 21-04-30_LSR7 Middle School #4_Comment Responses
05/18/2021 Letter DE-Comment Letter (Engineering Plans)
06/17/2021 Letter DE-Comment Letter (Engineering Plans)
08/02/2021 Letter DE-Comment Letter (Engineering Plans)
08/17/2021 Letter DE-Comment Letter Response
08/24/2021 Letter DE-Comment Letter (Engineering Plans)
08/30/2021 Letter 21_08_27 Comment Response Table
08/30/2021 Engineers Estimate 21_08_27 Public Main Extension Estimate
09/07/2021 Letter DE-Comment Letter (Engineering Plans)
09/13/2021 Letter DE-Comment Letter Response
09/13/2021 Engineers Estimate Public Sanitary Estimate
09/21/2021 Activity Document FeeWorksheetOffSiteSanSegmentOne
09/21/2021 Email STKY APPROVAL
09/24/2021 Activity Document MDNR Concurrence San Signed DL
11/15/2021 Activity Document MDNR Permit
04/04/2022 Approved Plans East Trails Middle School Offsite Sanitary Extension - Segment #1 Approved 4.4.22
04/05/2022 Letter DE-Engineering Plans Approval Letter
06/16/2022 Activity Document Offsite Easement
02/27/2023 Plans 21_09_22 LSMS SS EXTENSION ASI33-AS-BUILT-SURVEY MU
02/27/2023 Plans 2023_02_21 AS-BUILT 020_0103 LSMS
03/07/2023 Accepted Record Drawings ACCEPTED RECORD DWG MAR2023
03/07/2023 Email EMAIL ACCEPTED RECORD DWG
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home