Planning Application Status

PL2020075




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2020075
Summit Church - parking lot addition
Commercial Final Development Plan
Commercial Final Development Plan
Approved
03/20/2020
THE UNITED METHODIST CHURCH OF LEES SUMM
Locations
Contacts
THE UNITED METHODIST CHURCH OF LEES SUMM, Address:3381 NW CHIPMAN RD  
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review No Comments 08/28/2020 08/27/2020
Sue Pyles, P.E.
DE C&O #11 Pavement Thickness
Corrective Action Required
08/26/2020

Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
DE Contact Field Eng. Inspector
Corrective Action Required
08/26/2020

Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
DE Engineers Estimate
Corrective Action Required
08/26/2020

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $2,098.49
Planning Review No Comments 04/03/2020 04/03/2020
Hector Soto Jr.
Building Codes Review Approved with Conditions 04/03/2020 04/02/2020
Dawn Bell
Traffic Review No Comments 04/03/2020 04/02/2020
Dawn Bell
Fire Review No Comments 04/03/2020 04/02/2020
Dawn Bell
Engineering Review Approved with Conditions 04/03/2020 04/02/2020
Dawn Bell
DE C&O #11 Pavement Thickness
Corrective Action Required
04/02/2020

Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
DE Contact Field Eng. Inspector
Corrective Action Required
04/02/2020

Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
DE Engineers Estimate
Corrective Action Required
04/02/2020

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $2,098.49
Building Codes Review Approved with Conditions 04/03/2020 03/26/2020
Joe Frogge
Corrective Action Required
03/26/2020

If lighting is added to project it will require a building permit.
Traffic Review No Comments 04/03/2020 03/26/2020
Michael Park
Planning Review Corrections 04/03/2020 03/26/2020
Hector Soto Jr.
Corrective Action Required
03/26/2020

SITE DATA TABLE. Add the proposed number and total number of parking spaces to Sheet C.001.
Corrective Action Required
03/26/2020

PHASING. The site data table on Sheet C.001 labels the proposed improvements as Phase 3. But the leader at the southwest corner of the parking lot on Sheet C.100 labels this as Phase 2 parking lot improvements. Reconcile.
Corrective Action Required
03/26/2020

CURBING. Standard curb details are provided on Sheet C.600, but the site plan does not call out the curb type proposed for the parking lot expansion. CG-1 curbing shall be used, except that temporary asphalt curbing may be used where future parking lot expansion will occur.
Fire Review No Comments 04/03/2020 03/24/2020
Jim Eden
Engineering Review Approved with Conditions 04/03/2020 03/23/2020
Sue Pyles, P.E.
DE C&O #11 Pavement Thickness
Corrective Action Required
03/23/2020

Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
DE Contact Field Eng. Inspector
Corrective Action Required
03/23/2020

Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
DE Engineers Estimate
Corrective Action Required
03/23/2020

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $2,098.49
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $600.00 $600.00 Paid 03/31/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
03/20/2020 C.200
03/20/2020 C.001
03/20/2020 C.201
03/20/2020 C.100
03/20/2020 C.600
03/20/2020 L.100
03/23/2020 FDP APPLICATION
03/23/2020 Activity Document Fees PL2020075 The Summit Church Parking Lot Addition FDP
03/23/2020 Activity Document PL2020 Summit Church Lot Estimate
03/26/2020 Letter Applicant Letter - FDP (DFDP)
03/27/2020 FDP 2020075
03/31/2020 Receipt Receipt for transaction:2020-001337
04/02/2020 Letter Applicant Letter - FDP (DFDP)
04/03/2020 Letter Applicant Letter - FDP (DFDP)
04/03/2020 Approved Set FDP Summit Church Parking Lot addition 4.3.2020
08/26/2020 8.26.20 OFFSITE SWALE GRADES
08/27/2020 Approved Plans Summit Church Parking Lot Expansion - Sheet C.010 Offsite Swale Grading Approved 8.27.20
09/16/2020 Approved - summit church sheet C.010 9.16.20
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home