Review Type |
Outcome |
Est. Completion Date |
Completed |
Fire Review
|
Approved with Conditions
|
09/25/2019
|
09/26/2019
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Imposed Loads
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Fire lanes shall be capable of supporting 75,000- pounds. Confirm heavy duty asphalt locations.
|
|
|
Engineering Review
|
Approved with Conditions
|
09/25/2019
|
09/25/2019
|
|
Gene Williams, P.E.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs is required prior to formal approval. The Engineering Plan Review and Inspection Fee is based on the approved estimate, and must be paid prior to formal approval of the Final Development Plan.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact Field Engineering Inspections at (816) 969-1200 at least 48 hours prior to the onset of construction.
|
|
DE Contact ROW Inspector
Corrective Action Required
Prior to any activities within the right-of-way that are not directly associated with a specific infrastructure or building permit, a separate right-of-way permit may be required. Contact a Right-of-Way Inspector at (816) 969-1800 to obtain the required permit.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
DE C&O #12 Cut & Fill
Corrective Action Required
Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
|
|
|
Building Codes Review
|
No Comments
|
09/25/2019
|
09/20/2019
|
|
Mike Weisenborn
|
|
|
Traffic Review
|
No Comments
|
09/25/2019
|
09/19/2019
|
|
Michael Park
|
|
|
Planning Review
|
No Comments
|
09/25/2019
|
09/19/2019
|
|
Hector Soto Jr.
|
|
|
Engineering Review
|
Corrections
|
09/13/2019
|
09/13/2019
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
No connection of the "future domestic water line" can be made at this time. When the future building expansion is desired, the connection can be made at that time. Please delete the connection on Sheet CE3.
|
|
Corrective Action Required
Comments concerning the public water main extension shall be sent to you separate from these comments. Please ensure those comments are incorporated into the Final Development Plan, in particular, Sheet CE3.
|
|
|
Traffic Review
|
No Comments
|
09/13/2019
|
09/11/2019
|
|
Michael Park
|
|
|
Building Codes Review
|
No Comments
|
09/13/2019
|
09/09/2019
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Note E on Sheet CE3 indicates that a 1.5 inch water line is to be installed. I assume that a 1.5 inch water meter is to be installed. This meter is installed on a 2inch corp on the main and requires the use of 2" Type K copper piping. Please make clearifications on the plans.
|
|
Miscellaneous Correction
Corrective Action Required
Not G on Sheet CE3 does not indicate the size of meter assembly to be used for the irrigation system. Please provide additiona information on the plans note.
|
|
|
Planning Review
|
No Comments
|
09/13/2019
|
09/06/2019
|
|
Hector Soto Jr.
|
|
|
Fire Review
|
Corrections
|
09/13/2019
|
09/06/2019
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Fire lanes shall be capable of supporting 75,000- pounds. Confirm heavy duty asphalt locations.
|
|
|
Building Codes Review
|
Corrections
|
08/27/2019
|
08/27/2019
|
|
Mike Weisenborn
|
|
Miscellaneous Correction
Corrective Action Required
Note E on Sheet CE3 indicates that a 1.5 inch water line is to be installed. I assume that a 1.5 inch water meter is to be installed. This meter is installed on a 2inch corp on the main and requires the use of 2" Type K copper piping. Please make clearifications on the plans.
|
|
Miscellaneous Correction
Corrective Action Required
Not G on Sheet CE3 does not indicate the size of meter assembly to be used for the irrigation system. Please provide additional information on the plans note.
|
|
|
Engineering Review
|
Corrections
|
08/26/2019
|
08/26/2019
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Please provide a separate plan set for the public water main extension. Provide sufficient reference notes on the Final Development Plan which direct the contractor and inspector to the separate set of public water main extension plans.
|
|
Corrective Action Required
Please move the backflow vault outside the limits of the easement. It appears to slightly encroach upon the easement.
|
|
Corrective Action Required
Please indicate the sizing of the domestic and irrigation water meters.
|
|
Corrective Action Required
Service lines (i.e., domestic or irrigation lines) from the water main to the meter must be either 3/4", 1", 2", or 3". 1.5 inch service lines are not allowed.
|
|
Corrective Action Required
It is not clear what is meant by "future expansion". A separate water meter is shown serving this future expansion, and this is typically not done until a future Final Development Plan is submitted for the future building expansion.
|
|
Corrective Action Required
Please reference standard drawing WAT-11 contained elsewhere in the plan set on the Utility Plan sheet.
|
|
Corrective Action Required
Please show how the backflow vault will be drained. There are several ways this can be done. Either by providing a hole in the sump and daylighting, connection to a storm sewer box, or construction of an infiltration trench. Otherwise, the backflow vault will fill with water.
|
|
Corrective Action Required
Sheet CE6: Please show the extension of MoDOT Type 5 aggregate base beneath the pavement, a minimum of one (1) foot beyond the back of curb.
|
|
Corrective Action Required
An itemized and sealed Engineer's Estimate of Probable Construction Costs should accompany your final submittal drawings. Items to include in the estimate are: 1) storm lines greater than 6 inches diameter, 2) storm boxes and connections to existing storm boxes, 3) water lines, 4) backflow vaults, 4) fire hydrants, 5) valves, valve boxes, fittings, elbows, tees, 6) sanitary sewer service lines, 7) pavement and sawcutting, 8) curb and gutter, 9) subgrade including the aggregate base extended a minimum of one (1) foot beyond the back of curb, 10) grading to achieve proper drainage, 11) grading for parking lot, 12) erosion and sediment control devices and measures, and 13) final restoration, including sodding, seeding, fertilizer, mulch, and topsoil.
|
|
|
Planning Review
|
Corrections
|
08/26/2019
|
08/26/2019
|
|
Hector Soto Jr.
|
|
Corrective Action Required
PARKING SPACES. Revise the calculated number of parking spaces for the future building expansion listed in the Calculation table on Sheet CE 5 from 10 to 12.
|
|
Corrective Action Required
PARKING LOT CURBING. Either CG-1 curbing or temporary asphalt curbing shall be installed along the south boundary of the parking lot/access drive where the pavement will be extended in the future for the development of the property to the south.
|
|
Corrective Action Required
TRASH ENCLOSURE. Trash enclosure areas shall be improved with a Portland cement concrete pad and a Portland cement concrete approach 30 feet in length, measured from the enclosure opening. The pad and approach shall be improved with a minimum six inches of full depth unreinforced Portland cement concrete constructed on a sub-grade of four inches of granular base course. The plans currently show a concrete approach 20 feet in length.
|
|
Corrective Action Required
ACCESSIBLE PARKING SIGN. Revise the detail on Sheet CE9 to show a minimum sign mounting height of 5'-0" above grade, measured to the bottom of the sign.
|
|
Corrective Action Required
LANDSCAPE PLAN. Revise the last general note on the plan to read, "Open areas not covered with other materials shall be covered with sod." Seeding of open areas is not allowed in this case.
|
|
Corrective Action Required
ARCHITECTURE.
- Label all of the proposed exterior material colors on Sheet A-201.
- It isn't clear on the building elevations if any vertical and/or horitzontal offsets or projections are proposed for the building walls. The City's Unified Development Ordinance requires these types of features in order to break up the large wall planes.
|
|
Corrective Action Required
MONUMENT SIGN. For your information, approval of the final development plan does not constitute approval of the monument sign that is included in the architectural drawings. The monument sign goes through a separate sign permit approval process. As currently depicted on the architectural drawings, the monument sign exceeds the maximum allowable overall structure size of 96 sq. ft.; the monument has an overall structure size exceeding 100 sq. ft.
|
|
|
Traffic Review
|
Approved with Conditions
|
08/26/2019
|
08/21/2019
|
|
Michael Park
|
|
Corrective Action Required
Although a private roadway/driveway intersection, stop signs are recommended either north-south approaches or east-west approaches (two-way stop) to establish traffic control.
|
|
|
Fire Review
|
Approved with Conditions
|
08/26/2019
|
08/16/2019
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Fire lanes shall be capable of supporting 75,000- pounds. Confirm heavy duty asphalt locations.
|
|
|